Date post: | 24-Dec-2015 |
Category: |
Documents |
Upload: | sherman-holt |
View: | 223 times |
Download: | 2 times |
Solar Plant Performance Assessment
Copyright © 2013 Mahindra EPC. All rights reserved.
Copyright © 2013 Mahindra EPC. All rights reserved.
Analysis Team Project Developer
EPC
Panel Cleaning
String Monitoring Inverter & LT Panel
Transformer & HT Switchgear
Control Room, SCADA, HT Panels, Auxiliary
Power
Weather Monitoring Station
General PV Plant Layout
Evacuation Structure
The solar asset management post commissioing is generally done by a dedicated Operations & Maintenance (O&M) team.
Prime Objectives of O&M team is to operate plant safely with minimum impact to environment & occupational health, while maximizing generation of the plant and minimizing downtime.
Solar Asset Management
Environmental Impact Analysis
Occupational Health & Safety Equipment Safety
Safety Trainings
Hazard Identification and Risk Analysis
Emergency Management Plan
Water Conservation
Minimize Downtime• Plant Monitoring
• Predictive Maintenance• Breakdown Maintenance
• Spares Management
Maximize Generation• Soiling Impact Analysis• Module Cleaning• Periodic Reporting • Benchmarking
Layout Processes for Plant, Personnel and Planet safety
Maximize Return on Investment
4
Maximizing Generation
Maximize Generation
Plant overview as seen through a PV Monitoring
solution
The current values should be within prescribed deviations. For e.g. 10% of max
•Cables to be checked for any fault / loose connection.•The string modules to be cleaned if dust layer is found
DC combiner
box output
Should be as per individual installed DC capacity
Module cleaning to be initiated if dust is found on the serving PV field
Equipment Standards & Limits Action plan in case of deviations
Transformer
parameters
Should not exceed standard design capacity
• Load to be monitored.• Shutdown to be taken for further checking
Plant Performance of individual cluster(s) may be affected due to underperforming string/combiner box
Impact
Due to deviation in parameters transformer will trip & lead to higher generation losses
Maximize Generation
Track Actual V/s Predicted values and take corrective action as per triggers
Summary of instantaneous power and cumulative energy generated at a single glance
Hourly performance ratio reporting for better generation tracking w.r.t peak hours
Power evacuation status
Monitoring of all relevant data in single window
Parameters Action Plan in case of deviation
Should be according to the prescribed performance ratio
Data from inverter and irradiation sensors to be checked.; In case of abnormality, individual equipments to be checked
Generation v/s actual Irradiation
Cluster wise PR values
Should be identical for all the clusters
Individual inverters and combiner boxes to checked for abnormalities if any
Standards & Limits
Impact
Performance of individual cluster(s) may be affected due to underperforming equipment
Maximize Generation
Summary of equipment parameters
Device Health
Real Time Monitoring of energy flow as per AC SLD
Parameters Action Plan in case of deviation
Energy Flow
Voltage & current should be balanced and normal.
Individual equipment to be checked for any abnormality.
Standards & Limits
Impact
•Abnormal values may lead to major breakdown of the respective equipment.•Warranties of the equipments will be at risk
Maximize GenerationReal Time Monitoring of graphs
Historical analysis of collected data. Plant performance evaluation. User-defined formulas to calculate efficiencies, trends, performance ratios,
estimation of losses and alarm notifications. Analysis tool to explore and detect errors and energy production losses. Fast and reliable access to large amounts of captured data. Remote monitoring and control enabled.
Performance Analysis
Case Study : Soiling LossCurent and Power Deviation for the Month plotted
Shows module o/p power losses by ≈ 7.5% in eleven days due to dust accumulation on PV module surface
Module power drop by 0.7% per day due to dust/soil accumulation on PV module surface
Performance Analysis
Case Study : Soiling LossCurent and Power Deviation for the Month plotted
Shows module o/p power losses by ≈ 7.5% in eleven days due to dust accumulation on PV module surface
Module power drop by 0.7% per day due to dust/soil accumulation on PV module surface
Performance Analysis
11
Minimizing Downtime
Activity Frequency
Impact Action Plan
•Oil filtration to be carried out.
•If after oil filtration the value of BDV is not improving then it should be completely changed.
•Yearly / Half yearly,
•Samples to be sent to authorised testing agency
•May lead to winding failure of transformer due to degradation of oil.
•This would lead to higher generation losses as transformer need to be sent to factory location for repairs.
CHARACTERISTIC TESTING OF
TRANSFORMER OIL
• BDV : > 60 KV• DENSITY : 0.89 gm / cc • APPEARANCE : Clear and Transparent• ACIDITY : 0.03 mg KOH/ gm (Max)• WATER CONTENT : 20 PPM (Max)
Minimizing Plant Downtime
BDV Test kit
FREQUENCY IMPACTS ACTION PLAN
•Proper connection tightness and cleanliness to be ensured.• preventive maintenance to be carried out in case of abnormalities.
Monthly
• Fire hazards due to overheating of cables due to loose connections if any.
PHYSICAL CHECKING OF COMBINER BOXES
PLOTTING OF I-V CURVES USING HIGH PRECISION ARRAY TESTER TO TRACE PERCENTAGE DEGRADATION
OVER A PERIOD OF TIME
Yearly
The activity helps in keeping the track of performance of modules and its degradation with time.
•If the set of modules found underperforming. Same can be informed to the manufacturers and new modules can be claimed under warranty
ACTIVITY
Minimizing Plant Downtime
ACTIVITY FREQUENCY IMPACTS ACTION PLAN
• Fresh air fan filters to washed for effective air flow.• Fan motors to be checked for free movement.
Fortnightly, Values should be greater
than 4 m/sec.
Under performance (Deration) of inverters subjected to higher temperatures
Monthly, the indicators
should be green in colour.
The inverters may be subjected to heavy voltage surges and would further develop into major fault.
•The surge arrestors should be immediately replaced if ”end of life” indication is ON
Airflow monitoring at inlets of inverter panel
Green Indication
Status of surge arrestors
Minimizing Plant Downtime
Annual PPM Tracker
EQUIPMENT FREQUENCY TO BE DONE BY
Switchyard equipments
HT Panel
Inverters
LT DB’s
UPS
Battery Charger
Motors
Earth Pits
Yearly
Yearly
Quarterly
Quarterly
Quarterly
Quarterly
Quarterly
Yearly
ACTIVITY
• Detailed servicing and checks to be carried out as per annual PPM tracker.
• Periodic testing of equipments to be carried out for proper functioning
Breakers Yearly
MEPC team in consultation with OEM
MEPC team
OEM/MEPC team in consultation with OEM
MEPC team
OEM/MEPC team in consultation with OEM
OEM/MEPC team in consultation with OEM
MEPC team
MEPC team
OEM
The preventive maintenance is carried out periodically and based on feedbacks on predictive maintenance depending on the priority
The equipments to be identified for action to be done onsite or by vendor.
Transformer Yearly
MEPC team in consultation with OEM
MEPC team in consultation with OEM
Combiner boxes Yearly
Annual PPM Tracker
Preventive Maintenance Schedule for minimizing plant downtime
Use of Specialized Testing Equipments for Maximization of Generation & Minimization of plant downtime.
Stocking of critical equipments for minimizing plant downtime
Array Tester Thermal Imager for checking any hot
spot/loose connectionsPower Analyzer for equipment efficiency
measurement
Transformer Oil BDV Test kit
Cable Fault Locator for fast identification & restoration of cable
faults
Cumulative Data
5 MW Rawra (Aug,12-Jul,13) 5 MW Rawra (Aug,13-Dec,13) 2 MW Lucknow (9 Aug,12-8 Aug,13)
2 MW Lucknow (9 Aug,13-Dec,13)-40.00%
-20.00%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
73.1
0%
73.6
0%
79.7
0%
78.5
5%
79.6
0%
75.4
8%
82.4
0%
81.4
2%
-3.7
9%
-3.5
9%
-14.
05%
-16.
72%
11.9
6%
5.88
% -4.3
3%
-6.5
1%
6.37
%
0.58
%
-11.
32%
-13.
46%
Cumulative Data for Project Commissioned in 2012
Target PR Actual PR Change in Weather Change In Generation w.r.t. Guaranteed Change In Generation w.r.t. Target
5 MW Gajner (Feb,13-Dec,13) 15 MW Gajner (Feb,13-Dec,13) 10 MW Rawra (May,13-Dec,13) 20 MW Rawra (May,13-Dec,13)0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
82.0
0%
82.0
0%
78.3
4%
78.3
4%
84.1
5%
85.3
6%
84.5
8%
84.1
6%
6.33
%
6.18
%
11.3
3%
11.1
5%
14.8
7%
10.5
3%
26.3
4%
24.8
3%
9.13
%
44.7
1%
20.0
2%
18.5
9%
Cumulative Data for Project Commissioned in 2013
Target PR Actual PR Change in Weather Change In Generation w.r.t. Guaranteed Change In Generation w.r.t. Target
Cumulative data for Plant Up Time & CUF
*Plant Up Time for 5MW Rawra is low due to failure of one 1.25 MVA transformer.
2 MW Lucknow (9th Aug-12 to Dec-13)
5 MW Rawra (Aug-12 to Dec-13)
10 MW Rawra (Oct-13 to Dec-13)
20 MW Rawra (Oct-13 to Dec-13)
5 MW Gajner (April-13 to Dec-13)
15 MW Gajner (April-13 to Dec-13)
98.20%
98.40%
98.60%
98.80%
99.00%
99.20%
99.40%
99.60%
99.80%
100.00%
99.38%
98.78%
99.87%99.68%
99.86% 99.90%
Plant Up Time
15.00%
16.00%
17.00%
18.00%
19.00%
20.00%
21.00%
22.00%
23.00%
24.00%
25.00%
15.72%
20.78%
19.01% 18.73%
20.61% 21.05%
15.84%
20.93%21.63% 21.37%
21.04% 21.30%
CUF CUF with 100% grid availability
20
Intricacies in a typical 20 MW Solar PV Plant
20Copyright © 2013 Mahindra EPC. All rights reserved.
3
250,000 photovoltaic modules
2
Total Surface Area:
140 Acres
4
30 Inverters
Remote area
550 Transformers
6
350 KMs of Cable
7
8
240 Combiner Boxes
6 Km of Plant Perimeter
Remote Monitoring & Control is CRITICAL for solar plants
7,800,000 Data Points stored every day
1
9
Traditional Monitoring &
Control Solutions
Evolution of Monitoring & Control Solutions
21Copyright © 2013 Mahindra EPC. All rights reserved.
Manual Monitoring1 Basic Equipment
Monitoring
2Basic SCADA system
3M
ahin
dra
Sola
r PV
SCA
DA S
oluti
on
Complete Equipment Monitoring (Module to DB) – CB, Inverters, Transformers
Equipment Control Options Integrated Solution – Security & Surveillance, Access Control, Module cleaning, spares management, license management, billing & reporting
Vendor Agnostic – Any equipment, any make
Comprehensive data monitoring -- 150 parameters on inverters
Customizable to user preferences – Trends, Reporting
Scalable – for same plant and across multiple plants
Intuitive User Interfaces
Dynamic Dashboards
Cloud based – Real time data access anytime, any where
Events & Alarms Management – SMS notifications Predictive Analytics –
Real time Generation forecast; early fault detection
Mahindra Solar SCADA Solution
Domestic & International Clientele
Over 8,000,000 data points monitored daily. Consistently being analyzed using advanced analytics to deliver
•Business reporting•KPI evaluation •Plant indexation and
benchmarking •Preventive maintenance•Resource Monitoring •ERP •Operations and
Maintenance
85 MW
MONITORED