Copyright Course Technology 1999
1
TOPIC 3Project Scope ManagementChapter 4
Copyright Course Technology 1999
2
Importance of Good Project Scope Management1995 CHAOS study cited user
involvement, a clear project mission, a clear statement of requirements, and proper planning as being important for project success
The program manager of Keller Graduate School of Management cites proper project definition and scope as the main reasons projects fail
Copyright Course Technology 1999
3
What is Project Scope Management?Scope refers to all the work involved in
creating the products of the project and the processes used to create them
Project scope management includes the processes involved in defining and controlling what is or is not included in the project
The project team and stakeholders must have the same understanding of what products will be produced as a result of a project and what processes will be used in producing them
Copyright Course Technology 1999
4
Project Scope Management Processes
Initiation: beginning a project or continuing to the next phase
Scope planning: developing documents to provide the basis for future project decisions
Scope definition: subdividing the major project deliverables into smaller, more manageable components
Scope verification: formalizing acceptance of the project scope
Scope change control: controlling changes to project scope
Copyright Course Technology 1999
5
Project Initiation: Strategic Planning and Project SelectionThe first step in initiating projects is to
look at the big picture or strategic plan of an organization
Strategic planning involves determining long-term business objectives
IT projects should support strategic and financial business objectives
Copyright Course Technology 1999
6
Table 4-1. Why Firms Invest in Information Technology
Reason for Investing in IT Projects Rank Based on Overall Value of ProjectsSupports explicit business objectives 1Has good Internal Rate of Return (IRR) 2Supports implicit business objectives 3Has good Net Present Value (NPV) 4Has reasonable payback period 5Used in response to competitive systems 6Supports management decision making 7Meets budgetary constraints 8High probability of achieving benefits 9Good accounting rate of return 10High probability of completing project 11Meets technical/system requirements 12Supports legal/government requirement 13Good profitability index 14Introduces new technology 15
Copyright Course Technology 1999
7
Identifying Potential ProjectsMany organizations follow a planning
process for selecting IT projectsFirst develop an IT strategic plan
based on the organization’s overall strategic plan
Then perform a business area analysisThen define potential projectsThen select IT projects and assign
resources
Copyright Course Technology 1999
8
Figure 4-1. Information Technology Planning Process
Copyright Course Technology 1999
9
Methods for Selecting Projects
There are usually more projects than available time and resources to implement them
It is important to follow a logical process for selecting IT projects to work on
Methods include focusing on broad needs, categorizing projects, financial methods, and weighted scoring models
Copyright Course Technology 1999
10
Focusing on Broad Organizational NeedsIt is often difficult to provide strong
justification for many IT projects, but everyone agrees they have a high value
“It is better to measure gold roughly than to count pennies precisely”
Three important criteria for projects:– There is a need for the project– There are funds available– There’s a strong will to make the project
succeed
Copyright Course Technology 1999
11
Categorizing IT Projects
One categorization is whether the project addresses– a problem– an opportunity– a directive
Another categorization is how long it will take to do and when it is needed
Another is the overall priority of the project
Copyright Course Technology 1999
12
Financial Analysis of Projects
Financial considerations are often an important consideration in selecting projects
Three primary methods for determining the projected financial value of projects:– Net present value (NPV) analysis– Return on investment (ROI)– Payback analysis
Copyright Course Technology 1999
13
Net Present Value AnalysisNet present value (NPV) analysis is a
method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time
Projects with a positive NPV should be considered if financial value is a key criterion
The higher the NPV, the better
Copyright Course Technology 1999
14
Figure 4-2. Net Present Value Example
Excel file
Copyright Course Technology 1999
15
Return on Investment
Return on investment (ROI) is income divided by investment ROI = (total discounted benefits - total
discounted costs) / discounted costs
The higher the ROI, the betterMany organizations have a required
rate of return or minimum acceptable rate of return on investment for projects
Copyright Course Technology 1999
16
Payback Analysis
Another important financial consideration is payback analysis
The payback period is the amount of time it will take to recoup, in the form of net cash inflows, the net dollars invested in a project
Payback occurs when the cumulative discounted benefits and costs are greater than zero
Many organizations want IT projects to have a fairly short payback period
Copyright Course Technology 1999
17
Figure 4-3. NPV, ROI, and Payback Analysis for Project 1
Excel file
Copyright Course Technology 1999
18
Figure 4-4. NPV, ROI, and Payback Analysis for Project 2
Excel file
Copyright Course Technology 1999
19
Weighted Scoring ModelA weighted scoring model is a tool that provides a
systematic process for selecting projects based on many criteria– First identify criteria important to the project selection process
– Then assign weights (percentages) to each criterion so they add up to 100%
– Then assign scores to each criterion for each project
– Multiply the scores by the weights and get the total weighted scores
The higher the weighted score, the betterSee “What Went Right?” on pg. 87 for a description of
how a mortgage finance agency uses a weighted scoring model for IT projects
Copyright Course Technology 1999
20
Figure 4-5. Sample Weighted Scoring Model for Project Selection
Excel file
Copyright Course Technology 1999
21
Project ChartersAfter deciding what project to work on, it
is important to formalize projectsA project charter is a document that
formally recognizes the existence of a project and provides direction on the project’s objectives and management
Key project stakeholders should sign a project charter to acknowledge agreement on the need and intent of the project
Copyright Course Technology 1999
22
Table 4-2. Sample Project Charter Project Title: Information Technology (IT) Upgrade Project Project Start Date: March 4, 1999 Projected Finish Date:
December 4, 1999 Project Manager: Kim Nguyen, 691-2784, [email protected] Project Objectives: Upgrade hardware and software for all employees
(approximately 2,000) within 9 months based on new corporate standards. See attached sheet describing the new standards. Upgrades may affect servers and midrange computers as well as network hardware and software. Budgeted $1,000,000 for hardware and software costs and $500,000 for labor costs.
Approach: Update the IT inventory database to determine upgrade needs Develop detailed cost estimate for project and report to CIO Issue a request for quotes to obtain hardware and software
Use internal staff as much as possible to do the planning, analysis, and installation
Copyright Course Technology 1999
23
Table 4-2. Sample Project Charter (continued)
Name Role ResponsibilityWalter Schmidt, CEO Project Sponsor Monitor projectMike Zwack CIO Monitor project, provide
staffKim Nguyen Project Manager Plan and execute projectJeff Johnson Director of IT Operations Mentor KimNancy Reynolds VP, Human Resources Provide staff, issue memo
to all employees aboutproject
Steve McCann Director of Purchasing Assist in purchasinghardware and software
Sign-off: (Signatures of all above stakeholders)
Comments: (Handwritten comments from above stakeholders, if applicable)This project must be done within ten months at the absolute latest. Mike Zwack, CIOWe are assuming that adequate staff will be available and committed to supporting thisproject. Some work must be done after hours to avoid work disruptions, and overtimewill be provided. Jeff Johnson and Kim Nguyen, Information Technology Department
Roles and Responsibilities:
Copyright Course Technology 1999
24
Scope Planning and the Scope StatementA scope statement is a document used
to develop and confirm a common understanding of the project scope. It should include– a project justification– a brief description of the project’s
products– a summary of all project deliverables– a statement of what determines project
success
Copyright Course Technology 1999
25
Scope Planning and the Work Breakdown StructureAfter completing scope planning, the
next step is to further define the work by breaking it into manageable pieces
Good scope definition– helps improve the accuracy of time, cost,
and resource estimates– defines a baseline for performance
measurement and project control– aids in communicating clear work
responsibilities
Copyright Course Technology 1999
26
The Work Breakdown Structure
A work breakdown structure (WBS) is an outcome-oriented analysis of the work involved in a project that defines the total scope of the project
It is a foundation document in project management because it provides the basis for planning and managing project schedules, costs, and changes
Copyright Course Technology 1999
27
Figure 4-6a. Sample Intranet WBS Organized by Product
Copyright Course Technology 1999
28
Figure 4-6b. Sample Intranet WBS Organized by Phase
Copyright Course Technology 1999
29
Table 4-3. Intranet WBS in Tabular Form1.0 Concept
1.1 Evaluate current systems1.2 Define Requirements
1.2.1 Define user requirements1.2.2 Define content requirements1.2.3 Define system requirements1.2.4 Define server owner requirements
1.3 Define specific functionality1.4 Define risks and risk management approach1.5 Develop project plan1.6 Brief web development team
2.0 Web Site Design3.0 Web Site Development4.0 Roll Out5.0 Support
Copyright Course Technology 1999
30
Figure 4-7. Intranet WBS and Gantt Chart in Project 98WBS Gantt Chart
Project 98 file
Copyright Course Technology 1999
31
Approaches to Developing WBSsUsing guidelines: Some organizations,
like the U.S. Department of Defense, provide guidelines for preparing WBSs
The analogy approach: It often helps to review WBSs of similar projects
The top-down approach: Start with the largest items of the project and keep breaking them down
The bottoms-up approach: Start with the detailed tasks and roll them up
Copyright Course Technology 1999
32
Basic Principles for Creating WBSs1. A unit of work should appear at only one place in the WBS.
2. The work content of a WBS item is the sum of the WBS items below it.
3. A WBS item is the responsibility of only one individual, even though many people may be working on it.
4. The WBS must be consistent with the way in which work is actually going to be performed; it should serve the project team first and other purposes only if practical.
5. Project team members should be involved in developing the WBS to ensure consistency and buy-in.
6. Each WBS item must be documented to ensure accurate understanding of the scope of work included and not included in that item.
7. The WBS must be a flexible tool to accommodate inevitable changes while properly maintaining control of the work content in the project according to the scope statement.
Cleland, David I. Project Management: Strategic Design and Implementation, 1994
Copyright Course Technology 1999
33
Scope Verification and Scope Change ControlIt is very difficult to create a good scope
statement and WBS for a projectIt is even more difficult to verify project
scope and minimize scope changesMany IT projects suffer from scope creep
and poor scope verification– FoxMeyer Drug filed for bankruptcy after
scope creep on a robotic warehouse– Engineers at Grumman called a system
“Naziware” and refused to use it
Copyright Course Technology 1999
34
Table 4-4. Factors Causing IT Project Problems
Factor RankLack of user input 1
Incomplete requirements and specifications 2Changing requirements and specifications 3Lack of executive support 4Technology incompetence 5Lack of resources 6Unrealistic expectations 7Unclear objectives 8Unrealistic time frames 9New Technology 10
Johnson, Jim, "CHAOS: The Dollar Drain of IT Project Failures," Application Development Trends, January 1995, www.stadishgroup.com/chaos.html
Copyright Course Technology 1999
35
Suggestions for Improving User InputInsist that all projects have a sponsor
from the user organizationHave users on the project teamHave regular meetingsDeliver something to project users and
sponsor on a regular basisCo-locate users with the developers
Copyright Course Technology 1999
36
Suggestions for Reducing Incomplete and Changing RequirementsDevelop and follow a requirements management
processEmploy techniques such as prototyping, use case
modeling, and Joint Application Design to thoroughly understand user requirements
Put all requirements in writing and keep them current
Create a requirements management databaseProvide adequate testingUse a process for reviewing requested changes
from a systems perspectiveEmphasize completion dates
Copyright Course Technology 1999
37
Discussion QuestionsGive examples of IT projects and why they
were or were not selected for implementation. What type of project selection process did the organization use?
Discuss the theory and practice behind using project charters, scope statements, and WBSs.
Describe a project that suffered from scope creep. Could it have been avoided? How? Can scope creep be a good thing? When?
Copyright Course Technology 1999
38
Topic 3:Continued
Project Time Management
Chapter 5
Copyright Course Technology 1999
39
Importance of Project SchedulesManagers often cite delivering projects
on time as one of their biggest challenges
Average time overrun from 1995 CHAOS report was 222%
Time has the least amount of flexibility; it passes no matter what
Schedule issues are the main reason for conflicts on projects, especially during the second half of projects
Copyright Course Technology 1999
40
Figure 5-1. Conflict Intensity Over the Life of a Project
0.00
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
ProjectFormation
Early Phases Middle Phases End Phases
Co
nfl
ict
Inte
nsi
ty
Schedules
Priorities
Manpower
Technical opinions
Procedures
Cost
Personality conflicts
AverageTotal Conflict
Copyright Course Technology 1999
41
Project Time Management ProcessesProject time management involves the
processes required to ensure timely completion of a project. Processes include:– Activity definition– Activity sequencing– Activity duration estimating– Schedule development– Schedule control
Copyright Course Technology 1999
42
Where Do Schedules Come From? Defining ActivitiesProject schedules grow out of the
basic documents that initiate a project– Project charter includes start and end
dates and budget information– Scope statement and WBS help define
what will be doneActivity definition involves developing
a more detailed WBS and supporting explanations to understand all the work to be done
Copyright Course Technology 1999
43
Activity SequencingInvolves reviewing activities and
determining dependencies– Mandatory dependencies: inherent in the nature
of the work; hard logic– Discretionary dependencies: defined by the
project team; soft logic– External dependencies: involve relationships
between project and non-project activities
You must determine dependencies in order to use critical path analysis
Copyright Course Technology 1999
44
Project Network Diagrams
Project network diagrams are the preferred technique for showing activity sequencing
A project network diagram is a schematic display of the logical relationships among, or sequencing of, project activities
Copyright Course Technology 1999
45
Figure 5-2. Sample Activity-on-Arrow (AOA) Network Diagram for Project X
Copyright Course Technology 1999
46
Arrow Diagramming Method (ADM)Also called activity-on-arrow (AOA)
project network diagramsActivities are represented by arrowsNodes or circles are the starting and
ending points of activitiesCan only show finish-to-start
dependencies
Copyright Course Technology 1999
47
Process for Creating AOA Diagrams1. Find all of the activities that start at node 1. Draw their
finish nodes and draw arrows between node 1 and those finish nodes. Put the activity letter or name and duration estimate on the associated arrow
2. Continue drawing the network diagram, working from left to right. Look for bursts and merges. Bursts occur when a single node is followed by two or more activities. A merge occurs when two or more nodes precede a single node
3. Continue drawing the project network diagram until all activities are included on the diagram that have dependencies
4. As a rule of thumb, all arrowheads should face toward the right, and no arrows should cross on an AOA network diagram
Copyright Course Technology 1999
48
Precedence Diagramming Method (PDM)Activities are represented by boxesArrows show relationships between
activitiesMore popular than ADM method and
used by project management softwareBetter at showing different types of
dependencies
Copyright Course Technology 1999
49
Figure 5-3. Task Dependency Types
Copyright Course Technology 1999
50
Figure 5-4. Sample Precedence Diagramming Method (PDM) Network Diagram for Project X
Project 98 file
Copyright Course Technology 1999
51
Activity Duration EstimatingAfter defining activities and
determining their sequence, the next step in time management is duration estimating
Duration includes the actual amount of time worked on an activity plus elapsed time
People doing the work should help create estimates, and an expert should review them
Copyright Course Technology 1999
52
Schedule DevelopmentSchedule development uses results of the
other time management processes to determine the start and end date of the project and its activities
Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project
Important tools and techniques include Gantt charts, PERT analysis, and critical path analysis
Copyright Course Technology 1999
53
Gantt ChartsGantt charts provide a standard format for
displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format
Symbols include:– A black diamond: milestones or significant
events on a project with zero duration– Thick black bars: summary tasks– Lighter horizontal bars: tasks– Arrows: dependencies between tasks
Copyright Course Technology 1999
54
Figure 5-5. Gantt Chart for Project X
Project 98 file
Copyright Course Technology 1999
55
Figure 5-6. Gantt Chart for Software Launch Project
Project 98 file
Copyright Course Technology 1999
56
Figure 5-7. Sample Tracking Gantt Chart
Project 98 file
white diamond: slipped milestonetwo bars: planned and actual times
Copyright Course Technology 1999
57
Critical Path Method (CPM)CPM is a project network analysis
technique used to predict total project duration
A critical path for a project is the series of activities that determines the earliest time by which the project can be completed
The critical path is the longest path through the network diagram and has the least amount of slack or float
Copyright Course Technology 1999
58
Finding the Critical Path
First develop a good project network diagram
Add the durations for all activities on each path through the project network diagram
The longest path is the critical path
Copyright Course Technology 1999
59
Figure 5-8. Determining the Critical Path for Project X
Copyright Course Technology 1999
60
More on the Critical PathIf one of more activities on the critical path
takes longer than planned, the whole project schedule will slip unless corrective action is taken
Misconceptions:– The critical path is not the one with all the critical
activities; it only accounts for time– There can be more than one critical path if the
lengths of two or more paths are the same– The critical path can change as the project
progresses
Copyright Course Technology 1999
61
Using Critical Path Analysis to Make Schedule Trade-offsKnowing the critical path helps you
make schedule trade-offsFree slack or free float is the amount of
time an activity can be delayed without delaying the early start of any immediately following activities
Total slack or total float is the amount of time an activity may be delayed from its early start without delaying the planned project finish date
Copyright Course Technology 1999
62
Table 5-1. Free and Total Float or Slack for Project XTask Start Finish Late Start Late Finish Free
SlackTotalSlack
A Mon 8/3/98 Mon 8/3/98 Wed 8/5/98 Wed 8/5/98 0days 2daysB Mon 8/3/98 Tue 8/4/98 Mon 8/3/98 Tue 8/4/98 0days 0daysC Mon 8/3/98 Wed 8/5/98 Wed 8/5/98 Fri 8/7/98 0days 2daysD Tue 8/4/98 Fri 8/7/98 Thu 8/6/98 Tue 8/11/98 2d 2dE Wed 8/5/98 Tue 8/11/98 Wed 8/5/98 Tue 8/11/98 0d 0dF Wed 8/5/98 Mon 8/10/98 Fri 8/14/98 Wed 8/19/98 7d 7dG Thu 8/6/98 Thu 8/13/98 Mon 8/10/98 Mon 8/17/98 0d 2dH Wed 8/12/98 Wed 8/19/98 Wed 8/12/98 Wed 8/19/98 0d 0dI Fri 8/14/98 Mon 8/17/98 Tue 8/18/98 Wed 8/19/98 2d 2dJ Thu 8/20/98 Mon 8/24/98 Thu 8/20/98 Mon 8/24/98 0d 0d
Copyright Course Technology 1999
63
Techniques for Shortening a Project ScheduleShortening durations of critical tasks
by adding more resources or changing their scope
Crashing tasks by obtaining the greatest amount of schedule compression for the least incremental cost
Fast tracking tasks by doing them in parallel or overlapping them
Copyright Course Technology 1999
64
Shortening Project Schedules
Overlappedtasks
Shortenedduration
Original schedule
Copyright Course Technology 1999
65
Many Horror Stories Related to Project SchedulesSee “What Went Wrong?” example on
pg. 126 about the National Insurance Recording System
Creating realistic schedules and sticking to them is a key challenge of project management
Copyright Course Technology 1999
66
Importance of Updating Critical Path DataIt is important to update project
schedule informationThe critical path may change as you
enter actual start and finish datesIf you know the project completion
date will slip, negotiate with the project sponsor
Copyright Course Technology 1999
67
Program Evaluation and Review Technique (PERT)PERT is a network analysis technique
used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates
PERT uses probabilistic time estimates based on using optimistic, most likely, and pessimistic estimates of activity durations
Copyright Course Technology 1999
68
PERT Formula and Example
PERT weighted average formula: optimistic time + 4X most likely time + pessimistic time
6
Example:
PERT weighted average = 8 workdays + 4 X 10 workdays + 24 workdays = 12
days 6
where 8 = optimistic time, 10 = most likely time, and 24 = pessimistic time
Copyright Course Technology 1999
69
Controlling Changes to the Project SchedulePerform reality checks on schedulesAllow for contingenciesDon’t plan for everyone to work at
100% capacity all the timeHold progress meetings with
stakeholders and be clear and honest in communicating schedule issues
Copyright Course Technology 1999
70
Working with People Issues
Strong leadership helps projects succeed more than good PERT charts
Project managers should use– empowerment– incentives– discipline– negotiation
Copyright Course Technology 1999
71
What Went Right?Chris Higgins used the discipline he learned in the Army to transform project management into a cultural force at Bank of America. Higgins learned that taking time on the front end of a project can save significant time and money on the back end. As a quartermaster in the Army, when Higgins' people had to pack tents, he devised a contest to find the best way to fold a tent and determine the precise spots to place the pegs and equipment for the quickest possible assembly. Higgins used the same approach when he led an interstate banking initiative to integrate incompatible check processing, checking account, and savings account platforms in various states.
Law mandated that the banks solve the problem in one year or less. Higgins' project team was pushing to get to the coding phase of the project quickly, but Higgins held them back. He made the team members analyze, plan, and document requirements for the system in such detail that it took six months just to complete that phase. But the discipline up front enabled the software developers on the team to do all of the coding in only three months, and the project was completed on time.
Copyright Course Technology 1999
72
Using Software to Assist in Time ManagementSoftware for facilitating
communications helps people exchange schedule-related information
Decision support models help analyze trade-offs that can be made
Project management software can help in various time management areas
Copyright Course Technology 1999
73
Table 5-2. Project 98 Features Related to Project Time Management
Reports Views and Table Views Filters Overview reports: critical
tasks and milestones Current activities reports:
unstarted tasks, tasks startingsoon, tasks in progress,completed tasks, should havestarted tasks, and slippingtasks
Assignment reports: whodoes what when
Gantt chart, PERTchart, Tracking Gantt,schedule, tracking,variance, constraintdates, and delay
All tasks,completed tasks,critical tasks,incomplete tasks,and milestonetasks
Copyright Course Technology 1999
74
Words of Caution on Using Project Management SoftwareMany people misuse project
management software because they don’t understand important concepts and have not had good training
You must enter dependencies to have dates adjust automatically and to determine the critical path
You must enter actual schedule information to compare planned and actual progress