Cordillera Administrative Region
Transcript
Page 1: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

Cordillera Administrative Region

Page 2: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

2:

THE DILG CAR IN FY 2017: Sustaining a development-oriented local

government through SUCCESS 2017

I. Introduction

To impress the change that the administration promised to the Filipino people, the

DILG CAR recognized the need to usher LGUs to be development oriented. To realize such task, the DILG CAR devised a guidepost coined SUCESS 2017 or “Stepping-Up to

Challenges and Changes thru Excellent and Sustainable Strategies” to make DILG CAR

more effective, relevant and responsive to the needs of the LGUs.

II. Significant Accomplishments

LOCAL GOVERNMENT SECTOR

A. PEACEFUL, ORDERLY AND SAFE LGUs

a. Mamamayang Ayaw Sa Anomalya, Mamamayang Ayaw Sa Ilegal na Droga (MASA MASID)

1. Community watch and volunteerism through MASA MASID was observed by the 686 barangays with MASA MASID teams organized

throughout this region while 12 municipalities have organized their

Community Rehabilitation Network as of March 31, 2017. For 2nd Qtr, MM

teams were organized in 471 barangays. In total, 1157 barangays have

organized MMTs EO 2nd Semester.

2. 21 municipalities have organized CRN for 2nd Qtr. In total, as of EO

2nd semester, there were 33 CRNs organized in this region.

3. As of 2nd Semester, 2383 from the five provinces and 1 HUC of CAR

registered as MM volunteers.

Page 3: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

3:

b. Payapa at Masaganang Pamayanan (PAMANA-DILG Fund) Pillar 3

Continuing

1. Two remaining PAMANA 2015 projects were on-going as of 2nd Semester t wit, Benguet Province; Concreting Of Dangadangan-Copcopit Road

(Bakun)Tinglayan, Kalinga; Concreting Of Bugnay-Butbut Road

2. For PAMANA 2016, there were a total of 24 SPs under. 4 SPs were already

completed on FY 2016. For this year, 20 remaining SPs were monitored as to

status as shown in the table below:

Province Municipality PROJECT_TITLE AMOUNT STATUS

ABRA Province CONCRETING AND IMPROVEMENT OF ACCESS ROAD OF BARANGAY DALIMAG CABAYUGAN-OLO TO LAPTING, ILOCOS SUR

P 48,000,000.00 On-going

APAYAO Province CONCRETING AND IMPROVEMENT OF MARAG-CALAYUCAY ROAD

P 20,000,000.00 Completed

APAYAO Province IMPROVEMENT OF GUINAMGAMAN ILI LOCAL ACCESS ROAD

P 20,000,000.00 Completed

BENGUET Province IMPROVEMENT OF TALABING-TINOC (KABAYAN) P 12,000,000.00 On-going

BENGUET Province ROAD OPENING FROM BOKES SADDLE TO LASILAS, TAWANG TOWARDS BADEO (KIBUNGAN)

P 10,000,000.00 On-going

BENGUET Province CONCRETING OF CABITEN-KAMTAKKI ROAD (MANKAYAN)

P 20,000,000.00 On-going

BENGUET Province CONSTRUCTION OF MANPEY-AS CONCRETE CANAL AND FLOOD CONTROL (MANKAYAN)

P 3,000,000.00 Completed

IFUGAO Asipulo OPENING AND IMPROVEMENT OF LIWON AMDUNTONG ASIPULO-INDALMOGAN KIANGAN ACCESS

P 24,000,000.00 Completed

IFUGAO Tinoc IMPROVEMENT OF DANGGO ROAD P 24,000,000.00 On-going

IFUGAO Alfonso Lista IMPROVEMENT OF POTABLE WATER SYSTEM/CONSTRUCTION OF DEEPWELL AND RESERVOIR

P 4,000,000.00 On-going

IFUGAO Alfonso Lista CONCRETING OF JUNCTION TO CARAGASAN ACCESS ROAD

P 20,000,000.00 On-going

KALINGA Province CONCRETING AND IMPROVEMENT OF ALLAGUIA-ASIBANGLAN ROAD (PINUKPUK)

P 32,000,000.00 On-going

MASA MASID

Teams of the 303

barangays

of Abra

were oriented by

their

MLGOOS,

Community Facilitator

Jesus

Fernan

Alagao and PFP LGOO II

JR Tenebro.

Page 4: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

4:

KALINGA Province WAREHOUSE AND MULTI-PURPOSE PAVEMENT (GIMMA, TANUDAN)

P 600,000.00 Completed

KALINGA Province WAREHOUSE AND MULTI-PURPOSE PAVEMENT (PORAY, TANUDAN)

P 600,000.00 Completed

KALINGA Province CONSTRUCTION OF 60 LM WAGUD BUAYA BRIDGE (BALBALAN)

P 40,000,000.00 On-going

KALINGA Pasil LANAS CEMENTED PATHWAY P 600,000.00 Completed

KALINGA Pasil LEVEL II WATERWORKS SYSTEM P 1,600,000.00 On-going

MT. PROVINCE

Province IMPROVEMENT OF BETWAGAN ACCESS ROAD P 20,000,000.00 On-going

MT. PROVINCE

Province COMPLETION OF CONSTRUCTION OF EVACUATION CENTER IN BARANGAY AMBAGIW

P 1,500,000.00 Completed

MT. PROVINCE

Tadian IMPROVEMENT OF WATERWORKS IN KAYAN WEST AND LUBON

P 6,000,000.00 On-going

PHOTO DOCUMENTATION of PAMANA 2016 project entitled: Concreting of Junction to Caragasan Access Road in Alfonso Lista, Ifugao

Start of the Road project Materials used for the construction of slope protection

Construction of slope protection

Remaining concreting works of the road network (materials for slope protection

works are still stockpiled in the area)

End of the Road network

Page 5: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

5:

c. Payapa at Masaganang Pamayanan (PAMANA-DILG Fund) Pillar 1

Continuing

All 15 PAMANA LGUs in this region successfully drafted their POPS plan.

d. Provision of Secretariat Services to the Peace and Order Council

All 65 NON PAMANA LGUs in this region successfully drafted their POPS plan while Abra municipalities of Bucay and Penarrubia have approved POPs plan.

As of 2nd semester, additional 10 LGUs have approved POPs plan. LGUs were

Kalinga Province, Tanudan, Rizal, Balbalan, Tinglayan, Apayao Province,

Calanasan, Pudtol, Conner, and Luna.

e. Comprehensive Local Integration Program (CLIP) – Continuing

For 1st Qtr, 100% or 10 surfacing former rebels from Boliney, Bucay, Lacub, Licuan-Baay, Malibcong and Sallapadan, Abra were provided with financial

assistance. Six FRs surfaced in Abra, Kalinga and Mt. Province for the 2nd Qtr

were provided with financial assistance.

f. Others:

1. In support to the Comprehensive Social Benefits Program for the

AFP and PNP (CSBP) which attempts to provide the necessary assistance to uniformed officers and soldiers of the police and armed service who are

killed and wounded while in action (KIA-WIA), employees (1) attended the

CSBP Roll out conducted on March 23-25, 2017 in Pasay City. Along this

line, one KIA WIA beneficiary was hired by this region.

2.

B. SOCIALLY PROTECTIVE LGUs

a. BUB Other Infra FY 2015

One (1) remaining project for this program, which is the Purchase of Rescue

Equipment for Baguio City, targeted to be completed for the 4th quarter this year was successfully completed 1st quarter. 100% of projects for this

program was already complete.

b. BUB Others FY 2016

A total of 5 projects were under this program, however one project was

completed in 2016. The status of implementation of the four remaining

project this year are as follows:

Province Municipality PROJECT_TITLE AMOUNT STATUS

IFUGAO Hingyon EVACUATION FACILITY (CABABUYAN SOUTH) P 1,500,000.00 On-going

IFUGAO Hingyon EVACUATION FACILITY (NORTH CABABUYAN) P 500,000.00 Procurement

KALINGA Rizal EVACUATION FACILITY P 5,000,000.00 Completed

MT. PROVINCE

Sadanga EVACUATION FACILITY P 5,000,000.00 On-going

c. BUB-Provision of Potable Water Supply (PWS) FY 2014

Out of the total 118 projects under this PWS 2014, only five projects are left for completion this year. Status as of EO 2nd semester are as follows:

Province Municipality PROJECT_TITLE AMOUNT STATUS

ABRA Bangued PROPOSED LEVEL I WATER SYSTEM - BAÑACAO P 1,471,000.00 Completed

ABRA La Paz PROVISION OF WATER SUPPLY P 4,560,000.00 On-going

ABRA Licuan-Baay REHABILITATION OF CAGUYEN WATER SYSTEM P 300,000.00 Completed

ABRA Licuan-Baay REHABILITATION OF BAQUERO WATER SYSTEM P 1,000,000.00 Completed

IFUGAO Aguinaldo PROVISION OF WATER SYSTEM FOR MALELEMPFOB-POBLACION

P 4,000,000.00 On-going

Page 6: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

6:

d. BUB-Provision of Potable Water Supply (PWS) FY 2015

Under this program, 91 sub-projects were spread over 38 LGUs. There are 16 remaining project for completion this year while one project was

cancelled. Three SPs were completed for the 2nd Quarter. The table below

reflects the status of implementation as of reporting date:

Province Municipality PROJECT_TITLE AMOUNT STATUS

ABRA Danglas SALINTUBIG P 12,500,000.00 On-going

ABRA Lagayan SALINTUBIG (PHASE I) P 11,000,000.00 On-going

ABRA San Quintin SAGANA AT LIGTAS NA TUBIG SA LAHAT( SALINTUBIG)

P 5,000,000.00 Completed 1st Q

ABRA Lacub TALIPUGO POTABLE WATER SYSTEM P 1,200,000.00 Completed 2nd Q

ABRA Malibcong CONSTRUCTION OF BAYABAS LEVEL 1 DOMESTIC WATER SYSTEM

P 1,000,000.00 Completed 1st Q

ABRA Malibcong IMPROVEMENT OF PACGUED DOMESTIC WATER SYSTEM

P 1,000,000.00 On-going

ABRA Malibcong CONSTRUCTION OF ADUGAO (UMNAP) DOMESTIC WATER SYSTEM

P 1,000,000.00 Completed 1st Q

ABRA Tubo CONSTRUCTION OF TABACDA WATER SYSTEM P 1,407,640.60 Completed 2nd Q

APAYAO Sta. Marcela EXPANSION AND UPGRADING OF WATER SYSTEM (LEVEL 2 TO LEVEL 3)

P 4,475,000.00 Completed 1st Q

BENGUET Atok CONSTRUCTION OF POTABLE WATER SUPPLY AT SALIDET-SAYET

P 500,000.00 CANCELLED

BENGUET Atok CONSTRUCTION OF POTABLE WATER SUPPLY AT UPPER AND LOWER ENGLANDAD

P 500,000.00 Completed 1st Q

IFUGAO Kiangan SALINTUBIG FOR KIANGAN URBAN AREA P 5,000,000.00 Completed 1st Q

IFUGAO Banaue CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM (5 PROJECTS)

P 3,500,000.00 Completed 2nd Q

IFUGAO Hungduan DAYANDI-TINANGAAN WS P 500,000.00 Completed 1st Q

KALINGA Tanudan LAY-ASAN WWS P 3,000,000.00 On-going

KALINGA Balbalan REHAB OF MADALAAG-BOTOD WWS P 600,000.00 On-going

MT. PROVINCE

Sadanga COMPLETION OF DEMANG WATER SYSTEM P 2,000,000.00 On-going

Completed 2015 BUB Potable Water Supply Construction at Upper and Lower Englandad, Atok, Benguet Under CY 2015 BUB-GPP. Photos taken during the final joint inspection of the project on March 7, 2017.

Page 7: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

7:

e. SALINTUBIG FY 2013

A total of eight projects were lined-up for this program. However, the one

remaining project which is the CONSTRUCTION OF PANTIKIAN WATER

SYSTEM in Balbalan, Kalinga amounting to P1,696,000.00 was successfully

completed this quarter. All or 100% of the projects were completed.

f. SALINTUBIG FY 2014

There were three remaining on-going projects last FY 2016 for completion

this year. Out of the three projects, two were already completed while one is still on-going as of 1st quarter. 1 SP was completed for the 2nd Qtr, causing

the completion of all SPs under this program.

Province Municipality PROJECT_TITLE AMOUNT STATUS

ABRA Bangued MACARCARMAY SHALLOW WELL PROJECT (2 WELLS)

P 461,538.46 Completed 1st Q

ABRA Bangued MALITA SHALLOW WELL PROJECT P 230,769.24 Completed 1st Q

BENGUET Kibungan REHABILITATION OF WATER SYSTEM DERIVED FROM TOPINAO (SAGPAT)

P 1,000,000.00 On-going 2nd Q

Distribution tank at Upper Englandad, Atok, Benguet

RD Marlo L. Iringan turned-over the BUB 2015 SALINTUBIG project in San Quintin, Abra on May 26, 2017

Page 8: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

8:

g. SALINTUBIG FY 2015

Status of the remaining 25 subprojects under this program is shown below:

Province Municipality PROJECT_TITLE AMOUNT STATUS

ABRA Bangued CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM AT SAPPAAC, MAOAY, SAO-ATAN, PALAO

P 5,000,000.00 Completed 2nd Q

ABRA La Paz CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM AT BENBEN

P 3,000,000.00 Procurement

ABRA Pidigan CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM (IMMULI)

P 1,000,000.00 Completed

ABRA Pidigan CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM (ARAB)

P 1,000,000.00 On-going

ABRA Pidigan CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM (SAN DIEGO)

P 1,000,000.00 Completed 1st Q

ABRA Villaviciosa CONSTRUCTION OF TAMAC LEVEL II WATER SYSTEM

P 2,000,000.00 Completed 2nd Q

ABRA Bucay CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM AT MADALIPAY/LAYUGAN

P 2,000,000.00 Completed 1st Q

APAYAO Luna WATER DISTRIBUTION SYSTEM (TUROD) P 2,000,000.00 on-going

APAYAO Luna SPRING DEVELOPMENT AND WATER DISTRIBUTION (CAGANDUNGAN)

P 2,000,000.00 on-going

APAYAO Luna SPRING DEVELOPMENT AND WATER DISTRIBTION SYSTEM (CALABIGAN)

P 3,000,000.00 on-going

APAYAO Luna WATER DISTRIBUTION SYSTEM (LUYON) P 1,000,000.00 on-going

APAYAO Luna WATER DISTRIBUTION SYSTEM (SAN ISIDRO NORTE)

P 1,000,000.00 on-going

APAYAO Conner IMPROVEMENT AND EXTENSION OF WATER SYSTEM (GUINAMGAMAN)

P 1,000,000.00 On-going

APAYAO Conner IMPROVEMENT OF WATER SYSTEM (DAGA) P 1,000,000.00 on-going

APAYAO Conner CONSTRUCTION OF WATER SYSTEM PHASE II (ALLANGIGAN)

P 1,000,000.00 on-going

APAYAO Conner CONSTRUCTION OF WATER SYSTEM (RIPANG) P 1,000,000.00 On-going

APAYAO Conner IMPROVEMENT OF WATER SYSTEM (CALAFUG) P 1,000,000.00 on-going

APAYAO Conner CONSTRUCTION OF KARIKITAN WATER SYSTEM P 1,000,000.00 Completed 1st Q

APAYAO Conner CONSTRUCTION OF CAGLAYAN WATER SYSTEM P 3,000,000.00 on-going

APAYAO Flora CONSTRUCTION OF WATER SUPPLY SYSTEM LEVEL 2 (MALAYUGAN, BALLUYAN)

P 12,000,000.00 On-going

APAYAO Kabugao REHABILITATION AND UPGRADING OF LEVEL 2 WATER SYSTEM

P 12,000,000.00 On-going

BENGUET Kibungan REHABILITATION OF NAPSONG WATER SYSTEM (MADAYMEN)

P 1,000,000.00 Completed 1st Q

IFUGAO Banaue BANAO WATER SYSTEM P 2,000,000.00 On-going

KALINGA Pinukpuk CONSTRUCTION OF PAKAWIT WATERWORKS SYSTEM

P 2,000,000.00 On-going

KALINGA Lubuagan CONSTRUCTION OF ANTONIO CANAO WATERWORKS SYSTEM

P 1,000,000.00 Procurement

h. SALINTUBIG FY 2016

Projects were already identified during the 2nd Quarter. Four SPs were

identified over 4 LGUs. Status as of 2nd semester is shown below:

Province Municipality PROJECT_TITLE AMOUNT STATUS

ABRA La Paz CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM AT MALABBAGA

P 2,000,000.00 Document Preparation

ABRA Villaviciosa CONSTRUCTION OF TAMAC LEVEL II WATER SYSTEM P 1,000,000.00 Procurement

ABRA Tineg CONSTRUCTION OF POTABLE WATER SUPPLY SYSTEM P 12,000,000.00 On-going (61.31%)

Page 9: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

9:

MT. PROVINCE

Bauko PROVISION OF MT. DATA POTABLE WATER SUPPLY P 2,000,000.00 Completed 2nd Q

The potable water project in Naglicaban, Tineg, Abra. The completed intake tank (upper left), reservoir (upper right), the tap stand (left) as potable water is being enjoyed by the beneficiaries.

A beneficiary experiencing the benefits of the Potable Water Supply project in Barangay Anayan, Tineg, Abra (left). A view of Sitio Baking in Barangay Anayan (right) – one of the beneficiary barangay of the water project.

Page 10: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

10:

g. Sustainable Development Goals- Family-based Actions for Children and

Their Environs in the Slums (SDG-FACES)

a. RD M. Iringan together with the SDG-FACES RFP attended the National

Orientation and MOA Signing April 26, 2017

b. Conducted SDG FACES Regional Roll Out on May 24, 2017

h. Assistance to Disadvantaged Municipalities

357 ADM projects were spread over 75 municipalities of CAR.

Table 1: Summary of Projects

Province

Core Local

Access Road

Amount Water

Systems Projects

Amount Evacuation

Facility Amount

Small Water Impounding

Project

Total No. of

Projects

Total Amount

Abra 42 251,398,907 6 20,255,000 8 25,267,000 1 3,000,000 57 299,920,907

Apayao 22 75,738,000 0 2 9,356,000 0 24 85,094,000

Benguet 109 151,171,000 3 9,156,000 6 19,208,000 1 1,500,000 119 181,035,000

Ifugao 58 101,011,000 9 19,184,000 2 8,138,000 0 69 128,333,000

Kalinga 12 52,778,000 8 18,443,000 1 2,000,000 0 21 73,221,000

Mt. Province

53 121,605,628 12 32,508,000 2 6,000,000 0 67 160,113,628

Total No. of Projecs

296 38 21 2 357

Total Amount

753,702,535 99,546,000 69,969,000 4,500,000 927,717,535

The Tapayen Level II Water System project in Brgy, Tapayen, Tineg, Abra. The reservoir (top) and beneficiaries using the water system.

Page 11: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

11:

Table 2: Summary of LGUs with Released Funds PROVINCE 1ST BATCH 2ND BATCH TOTAL AMOUNT

No. of

Mun

Amount No. of

Mun

Amount No. of Mun Amount

ABRA 8 81,403,000.00 11 128,377,907.00 19 209,780,907.00

APAYAO 1 14,803,000.00 3 38,390,000.00 4 53,193,000.00

BENGUET 11 156,942,000.00 1 14,602,000.00 12 171,544,000.00

IFUGAO 4 49,707,000.00 6 68,772,000.00 10 118,479,000.00

KALINGA 3 36,087,000.00 3 26,807,000.00 6 62,894,000.00

MT. PROVINCE 6 89,778,814.00 4 32,678,000.00 10 122,456,814.00

TOTAL 33 428,720,814.00 28 309,626,907.00 61 738,347,721.00

C. Accountable, Transparent, Participative and Effective Local Governance

a. Transition Towards Federalism

1st Quarter

The DILG CAR is constantly pushing our LGU functionaries to be more active in the drive towards Federalism. The IEC on federalism was a ride-on activity

during the conduct of barangay assemblies of 570 barangays of this region.

Also, Federalism which was presented by ARD Jonathan Paul M. Leusen, Jr.,

was also included as one of the topics in the following activities:

i. MASA MASID orientation in the provinces of Abra and Kalinga

ii. Radio guesting in Radyo Natin, Abra

iii. Turn-over of DILG completed projects in Tubo, Abra attended by

five barangay captains and their kagawads.

iv. BUB stakeholders’ forum in Bontoc, Mt. Province and for the

province of Benguet

v. Autonomy and Federalism conducted by NEDA CAR (together with Atty. Tomas Kiwang, Jr.) in Paracelis, Mt. Province attended by

municipal officials and functionaries, teachers, policemen, barangay

officials and CSOs

MLGOO Julie Malig discusses Federalism during the Barangay Assembly Day at Bagong, Sablan last March 25, 2017

Page 12: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

12:

b. Full Disclosure Policy

The Full Disclosure Policy (FDP) has been seriously observed by all levels of

local governments in the Cordillera. 99.9% of PCMs and 89% of barangays in our

region are fully compliant to FDP while 100% were FDP compliant as of 2nd quarter.

c. Performance Challenge Fund

2015 – There are eight total SPs under PCF 2015. Out of the 8 SPs, 4

projects are for continuing this year. Hereunder table depicts the details:

Province Municipality PROJECT_TITLE AMOUNT STATUS

ABRA San Juan CONSTRUCTION AND REPAIR OF MULTI-PURPOSE AND TOURISM FACILITY

P 3,000,000.00 Completed 1st Q

APAYAO Calanasan CONSTRUCTION OF YMANDAYA ISNAG VILLAGE REPLICA

P 3,500,000.00 on-going

BENGUET Province IMPROVEMENT ALONG PICO-STOCKFARM PROVINCIAL ROAD

P 7,000,000.00 Completed 1st Q

BAGUIO CITY

CONSTRUCTION OF TRANSPORT TERMINAL AT CITY CAMP PROPER

P 5,000,000.00 On-going

2016 – Three projects were completed for the 2nd Qtr. Status of

implementation of 22 LGUs provided with PCF 2016 funds were as follows:

Province Municipality PROJECT_TITLE AMOUNT PRESENT

ABRA La Paz Construction of Pasalubong Center at Bulbulala P 3,000,000.00 Document Preparation

ABRA Dolores Construction of Drainage Canals at Poblacion P 3,000,000.00 On-going

ABRA San Juan Construction of Access Road at Baug P 3,000,000.00 Completed 2nd Q

ABRA Tayum Construction of Stone Masonry at Basbasa P 3,000,000.00 Completed 2nd Q

ABRA Bucay Construction of Multi-Purpose Hall at South Poblacion

P 3,000,000.00 On-going

ABRA Peñarrubia Construction of Access Roads P 3,000,000.00 On-going

APAYAO Luna IMPROVEMENT OF BUYAGAO ROAD P 3,000,000.00 On-going

APAYAO Pudtol CONSTRUCTION/REHABILITATION OF DRAINAGE CANAL LINING

P 3,000,000.00 on-going

(From Left to Right)

MLGOO Soledad M. Bersamin, CCAGG Joel

Barbadillo (CSO),

Mayor Meynardo M.

Bautista Jr., Municipal Staff Twinkle Jane

Bueno, FDP Focal

Person JR A. Tenebro

and Municipal Treasurer Marieta

Rivada during the FDP

monitoring at San

Juan, Municipal Hall on February 17, 2017.

Page 13: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

13:

APAYAO Sta. Marcela IMPROVEMENT AND CONCRETING OF PUBLIC MARKET PERIMETER

P 3,000,000.00 on-going

BAGUIO CITY

P 3,400,000.00 Document Preparation

BENGUET Province Construction of PDRRM Office P 4,000,000.00 Document preparation

BENGUET Itogon Improvement of Antamok-Loacan Brgy. Road P 3,000,000.00 Procurement

BENGUET Kapangan Improvement of Municipal Eco-Tourism Park P 3,000,000.00 On-going

BENGUET La Trinidad Expansion of Cell 3 Engineered Sanitary Landfill (Phase 2)

P 3,000,000.00 On-going

BENGUET Tublay Construction of Multipurpose Building at the Municipal Grounds cum Evacuation Center, Caponga

P 3,000,000.00 Procurement

IFUGAO Lamut CONSTRUCTION OF PUBLIC MARKET BUILDING 4 (2nd Floor Vegetable Section)

P 3,000,000.00 On-going

IFUGAO Banaue CONSTRUCTION OF MULTIPURPOSE PAVEMENT P 3,000,000.00 On-going

KALINGA Province BULANAO-MARKET PROVINCIAL ROAD P 4,000,000.00 Completed 2nd Q

KALINGA City of Tabuk IMPROVEMENT OF ROAD (AGBANNAWAG AND GOBGOB)

P 3,400,000.00 Document Preparation

KALINGA Balbalan POBLACION WATERWORKS SYSTEM P 3,000,000.00 Document Preparation

MT. PROVINCE

Province SADSADAN-BALICANAO-SALIN ROAD P 4,000,000.00 On-going

MT. PROVINCE

Paracelis PARACELIS WATER SYSTEM PHASE III P 3,000,000.00

Suspended pending completion of Phase 2 which is at 90% accomplishment

d. Lupong Tagapamayapa Incentives and Awards (LTIA)

There were a total of nine nominees for all categories assessed on March

23-24, 2017 as follows:

HUC Category – Imelda, Village, Baguio City

CC Category – Dagupan Centro, Tabuk City

1st to 3rd Class Category - Alno, La Trinidad, Benguet

- Poblacion, Bontoc, Mt. Province

- Dagupan, Luna, Apayao

4th to 6th Class Category - Payawan, Lamut, Ifugao

- Poblacion, Sablan, Benguet

- Poblacion, Luba, Abra

- Nueva, Santa Marcela, Apayao

Regional winners and forwarded as regional nominees to the national awards were:

HUC Category – Imelda, Village, Baguio City

CC Category – Dagupan Centro, Tabuk City

1st to 3rd Class Category - Alno, La Trinidad, Benguet

4th to 6th Class Category - Payawan, Lamut, Ifugao

e. Local Governance Performance Management System- Seal of Good Local

Governance (LGPMS-SGLG)

1. LGMED Chief and SGLG RFP and PFPs attended the SGLG National

Orientation at Manila on April 24- 27, 2017

Page 14: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

14:

2. 100% or all of PCMs were assessed by the SGLG Regional

Assessment Team (RATs)

f. CSO- People’s Partnership Participation Program

1. CSIS

a. Attended the briefing for Regional FPs , RDs, PDs for the target municipalities for the 2017 CSIS Implementation at Quezon City on May 3-5, 2017

D. BUSINESS-FRIENDLY AND COMPETITIVE LGUs

a. Regulatory Simplification for Local Governments- ENHANCED BPLS

As of 1st quarter, 88% of CAR LGUs were oriented on JMC- 1-2016 while 29% of LGUs were coached on BPLS standards.

b. Local Investments and Incentives Code (LIIC)

1. RFP attended the LIC ToT in Manila on March 28-31, 2017

E. Environment-Protective, Climate Change Adaptive and Disaster Resilient LGUs

1st Quarter

a. DILG CAR is continuously giving technical assistance and trainings on mainstreaming CSPP and sectoral concerns in the Comprehensive

Development Plan as well as Mainstreaming DRR-CCA in the Local

Development Plan. As of 1st quarter nine municipalities (i.e. Licuan Baay, Abra;

Asipulo, Ifugao; Alfonso Lista, Ifugao; Tinoc, Ifugao; Tanudan and Tinglayan,

Kalinga; Besa, Bontoc and Paracelis, Mt. Province) were provided with TA on CDP formulation.

b. The Regional Planning for Provincial Preparedness Dialogue and Regional

Disaster Preparedness Planning Workshop was conducted last February 1, 2017 at the Nene Pimentel Hall, DILG-CAR, Upper Session Road, Baguio City.

All provinces of CAR successfully conducted their Provincial Preparedness &

Listo Partnership Dialogue as well. Schedule of said activity were as follows:

1. Abra February 23, 2017

2. Apayao March 7, 2017

3. Benguet March 9, 2017

4. Ifugao March 7, 2017

On June 6-7, 2017, the Provincial Government of Abra was assessed and validated for the

2017 SGLG. ARD Jonathan Paul M. Leusen, Jr., LGMED DC Daisy Amoy and RFP Florinda

Garcia served as the Regional Assessment Team (RAT) together with Stat II Danilo Azarcon

and Engr. Nathaniel Lubrica as members.

Page 15: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

15:

5. Kalinga March 14, 2017

6. Mountain Province March 8, 2017

c. The assessment of the nominees for the Gawad Kalasag Award was effectively

conducted on March 2017.

2nd Quarter

a. LGOO V M. Griba attended the Coaches Training on Post Disaster Recovery

April 17-22 and the initial workshop to develop the Contingency Plan for 7.2M earthquake April 23-26 at Manila

III. Strengthened Internal Organizational Capacity

1st Quarter

a. The 1st Regional Management Conference (RMC) was conducted on January

19, 2017. On February 24, a special RMC was conducted as a venue for the

DILG CAR COA Auditors to present their Audit Observation Memo for FY 2016

as well as to update management on the accomplishments of this year’s PPAs. In addition, the regional management welcomed SILG Ismael Sueno on

February 25. The SILG interfacing activity with DILG CAR family and the PRO-

Cor Regional Director was conducted on the same date.

b. The 13 DILG CAR 50th Batch LGOO II trainees presented their outputs during

the Component 2- Phase II- Field Immersion. Trainees also attended the

Component 3- Part I: Paper and Pen Examination and Part 2: Simulated Exercise and Interview of the said training.

c. The January-February 2017 issue of the Gongs and Drums, which is the official publication of the DILG CAR, was published as of 1st quarter.

d. To continuously learn and be capacitated employees attended various technical trainings called for by Central Office bureaus and other agencies as well as

seminar/workshops relating to stress management.

2nd Quarter

e. Two FAD employees attended the Managing Stress and Experiencing Inner

Peace at Tagaytay on March 29-30, 2017.

f. Competency assessment was administered on all employees at the Regional

office as well as FOUs.

g. Conducted 2nd Quarter RMC on April 24, 2017 in Baguio City and 2nd special RMC cum on-site visit on LFPs in Kalinga province and participation to the

Pagpupugay at Pasasalamat for R2 RD J. Castaneda on May 21-23, 2017.

h. 13 50th Batch LGOO trainees attended the Revalida and Graduation of 50th

Batch on May 14-20, 2017 at LGATC, Los Baňos

Participants from DILG Benguet, PRO-Cor, BJMP Benguet, Municipal Mayors and MDRRMOs from 13 municipalities of Benguet and PDRRMO from Benguet Province during the Operation Listo Partnership Dialogue at the Jewel Igorot Building last March 9, 2017.

Page 16: Cordillera Administrative Region - dilgcar.com 2017... · apayao luna water distribution system (luyon) p 1,000,000.00 on-going apayao luna water distribution system (san isidro norte)

16:

Prepared by:

Fe S. Binay-an

Planning Officer

Approved by:

Engr. Marlo L. Iringan

Regional Director


Recommended