+ All Categories
Home > Documents > Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded”...

Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded”...

Date post: 30-May-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
32
FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN Page 1 Core & Shell Outline Design Narrative NuHealth Medical Specialty Center CONFIDENTIAL EXHIBIT E
Transcript
Page 1: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 1

Core & Shell Outline Design Narrative

NuHealth Medical Specialty Center

CONFIDENTIAL

EXHIBIT E

Page 2: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 2

Document Overview

The following information and design criteria presented in this package are intended to establish a consistent level of quality for the design, construction and delivery of a Class�A Medical Office Building. The design information contained within this building design narrative should not be considered final and complete. Accordingly, the project architectural, mechanical, electrical, plumbing, and fire protection systems shall be designed, drawn and stamped by each respective design and engineering entity based upon the specific building location and use requirements. The following document does not include the design and construction scope definition needed to obtain any form of the United States Green Building Council’s (USGBC’s) Leadership in Energy and Environmental Design (LEED) certification.

Page 3: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 3

CONDENSED PROJECT SCOPE DESCRIPTION Introduction The proposed Medical Office Building (MOB) will be built in East Meadow, NY. The MOB is estimated to have three stories, each with a floor plate of 37,630 gsf. The total estimated building area is 112,500 gsf and the tenant usable area will be approximately 90,525 usf. General

• The general parameters upon which this estimate is based are listed below:

o Please include two forms of contingency; 1). Design Contingency & 2). Construction Contingency. The amount and/or percentage of contingency are at your discretion.

o Construction Commencement is anticipated to occur Wednesday, January 01, 2014. Please include a construction schedule depicting construction activities required to construct the MOB (as described within this narrative).

o All applicable State, County, City and Village sales taxes, Use taxes and other taxes pertaining to the construction of the building should be included within the construction budget

o Prevailing wages will be required for this project

o Performance Bonds, Material, and Labor Payment Bonds on general contractor’s work shall be included (as an additional line item) in construction budget

o Insurance costs for general contractor(s) and all sub�contractors for general liability, excess liability, auto, workers compensation, and difference of coverage should be included within the construction budget

o Builder’s risk insurance should be included within the construction budget.

o Building permit for Core & Shell should be included within the construction budget.

o All applicable sewer/water/electric tap fees should be included within the construction budget.

o Special inspections / testing shall be included within the construction budget.

o Include stockpiling of tenant build out materials as indicated in landlord�supplied items. (Attached Exhibit D).

� 1” Horizontal louvered blinds for all tenant windows – supplied, not

installed � Solid surface window sills for all tenant windows – supplied, not

installed

Page 4: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 4

FOUNDATIONS A shallow foundation system consisting of pad footings, wall footings and 12�inch thick frost walls and elevator pit walls/slabs may be included, depending on the design. It is assumed that the soil bearing capacity is approximately 3,500 lbs/sf. The building slab on grade is 5�inch thick over 6�inch of granular base course. Waterproofing will be provided on the elevator pit walls and under the pit slab. A reinforced vapor barrier will be provided under the slab on grade.

STRUCTURE The building structure is a structural steel frame with a weight of 8.5 lbs/sf. The three floors will be constructed with wide flange beams and girders with composite floor deck. The roof will be constructed with wide flange girders, beams, bar joists and metal roof deck. The steel structure will be designed for a live load of 100 lbs/sf. The three floors will have a 6�inch normal weight slab on metal deck. Eight�inch thick pads are to be included at the roof level under the RTU’s for sound and vibration dampening. Concrete fill should be included in the building stair treads and landings. Inclusion of spray fireproofing will be based on the local building codes and the requirements of the building program.

ENCLOSURE The MOB enclosure shall consists of brick veneer on metal stud backup framing, insulated metal panels, aluminum punched windows and aluminum storefront or curtain wall. Aluminum windows and aluminum curtain wall will utilize insulated glass with a low�E coating. Aluminum mullions will be finished with a two�coat standard color Fluor polymer finish. Main entry doors shall be Power Operated Sliding Doors. Aluminum and glass door with auto�operator will be located at the secondary public entries. Other entry�exit doors will be hollow�metal. The perimeter wall will be insulated with 2�inch rigid insulation at the masonry cavities. The perimeter wall will have a 6�inch metal stud partition with dens glass on the exterior. A drywall on the interior face will not be insulated. This will enable tenants to rough�in electrical work along the exterior walls.

ROOF The roof shall be a fully adhered, 60�mil, single ply EPDM or TPO roofing membrane with adhesive and accessories for application to deck. Roof flashings will be galvanized. Walkway pavers will be provided to access all sides of the RTU’s. Screen walls surrounding the RTU’s will not be included unless required by local building codes – Please provide guidance on requirement. Stepped or tiered roof levels to be accessible.

INTERIOR CONSTRUCTION & FINISHES SHELL & CORE

Page 5: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 5

The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board ceilings/soffits and 2x2 acoustical ceiling tiles. Central toilet rooms will be located on each floor. Toilet room floors will have ceramic floor tile. Wet walls will have full height ceramic tile and all other walls will have vinyl wall covering. Suspended toilet partitions will be metal with a baked enamel finish. The ceilings will be painted drywall. Elevator lobbies and all central corridors will have carpeting, carpet base, vinyl wall covering, 2x2 acoustical ceiling tiles and gypsum board soffits. Central corridors will be 6’� 0” wide. Assume upgraded finish level for main elevator lobby. Electrical closets, mechanical rooms and janitor’s closets will have sealed concrete floors with vinyl base, painted walls and exposed structure ceilings. Stairwells will have painted walls and sealed concrete treads and landings. Stair stringers, risers and railings will be painted.

CONVEYING The MOB will have 3 elevator(s). The first being a 4,500 lb. gurney�size hydraulic OR traction/MRL type elevator and the second being a 3,500 lb. hydraulic OR traction/MRL type passenger elevator � both with standard cab finishes. Please provide price for both the hydraulic and MRL style elevators – we will consider further. As stated below in more detailed section, please include traveler cables within estimate – to allow for easier key�card access adaption.

FIRE PROTECTION The MOB will have a wet sprinkler system in accordance with local building codes. Sprinkler heads will be quick response type with recessed heads located in center of tile. FM certification is not required. Not knowing the local water pressure conditions, please include a Fire Pump to supply fire suppression system.

PLUMBING Plumbing systems will be designed and installed in accordance with the current plumbing code(s). Domestic water, sanitary sewer, and storm sewer piping will be connected to local utility services. Domestic water piping will be Type�L hard copper with Sweat Joint fittings. Hot water will be provided to all base building fixtures via most economical hot water heater. Tenants are required to heat their own hot water. Above ground, sanitary waste and vent piping will be service�weight, cast iron pipe with no hub couplings. Underground sanitary waste and vent piping will be schedule�40 PVC pipe. Floor drains will be provided in each toilet room. Above ground storm piping will be service�weight cast iron pipe with no hub couplings. Underground storm and vent piping will be Schedule 40 PVC pipe. Roof drains will be cast iron with dome strainers. Scuppers on the exterior parapet wall will provide roof rainwater overflow.

Page 6: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 6

Plumbing fixtures will be commercial quality. Water closets will be floor mount, utilizing auto flush valves. Urinals will be wall�hung units with auto flush valves. Lavatories will be wall�hung fixtures with auto faucets. Electric water coolers will be located outside each toilet room. Wall hydrants (hose bibs) will be located on each side of the building, and on the roof of the building. Janitor service sinks will be provided in the janitor’s closets on each floor. A Water Softener shall be provided if the hardness is above 120 PPM.

HVAC The HVAC system will be designed to provide a comfortable working environment for normal medical office use (based on regional climatic conditions). The MOB will be conditioned by using the appropriate CFM – VAV type packaged roof top units. For purposes of this estimate, unless contractor believes otherwise, please include (3) RTUs to supply air to building. The units will have DX cooling and gas fire heating capability. The MOB will have a dedicated exhaust system for the toilet rooms. General MOB exhaust shall be sized for normal medical office use, and will be stubbed to each floor. Building supply ductwork will extend down to the tenant floors through vertical shafts. Supply ductwork shall be designed and fabricated per SMACNA duct construction standards for 2�inch pressure classification and Class�A duct sealing. Supply ducts will be insulated with external fiberglass duct insulation and a foil�scrim�kraft vapor barrier jacket covering. VAV boxes will be provided for each zone within the shell and core. Perimeter VAV boxes shall be Fan Powered type. VAV boxes will have electric reheat coils. Return air risers will be stubbed into the tenant spaces on each floor. DISCUSS DUCT LOOP THEORY The HVAC system will be controlled by a DDC system. The system is to be non proprietary, open interoperability framework accepting all legacy communications protocol, i.e. Mod Bus, Lon, and BacNet. Tridium/Niagra AX based using Native BacNet communications between devices. The system will also be fully Web Accessible with the capability of sending out Critical Alarms via Email and Text Messaging. The system will include all necessary components including, but not be limited to, CPU, monitor, modem or Ethernet card. Testing and balancing will be completed by a certified AABC or NEBB testing firm.

ELECTRICAL The local utility will provide the transformer, primary conductors and primary terminations. The contractor will provide the transformer pad and conduits needed between the transformer and switchboard. The building electrical service will be a minimum 2000A or as required, 480V, 3�phase main switchboard. Ideally, Frauenshuh would like to provide tenants with 15 watts/square foot – this calculation is based off of total power available, less Core & Shell HVAC loads. Please provide recommendation on service size. Lighting installations will be designed to meet local energy code requirements. Interior lighting will meet the following requirements: Corridors: 20 fc, Toilets: 20 fc and Janitor’s Closets: 20 fc. Emergency exit lights will be battery back�up units and emergency lighting will be located within the fluorescent fixtures. The fire alarm system will be designed and installed in accordance with local codes.

Page 7: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 7

Each floor will have a common electrical closet, where the core and shell will provide breakers for tenants to tie�into the 277/480v feed. It is, therefore, the tenant’s responsibility to run the 277/480 feed back to their space (within conduit supplied by them), step down their power to 120/208 and meter their specific usage. The base building 277/480 feed is required to supply core and shell lighting and VAVs. Tenants are required to supply their own VAVs with the 277/480v power they’ve pulled to their space. Each floor will have a data closet with the common telephone / data connections. Please include cost for Fiber Optic. The MOB will have four (4) 4�inch telephone / data conduits serving the building from local utility firm(s).

SITE Storm water, sanitary sewer, domestic water, and site electrical connections are included in the shell MOB budget. Access roads and parking lot(s) are included within in budget and will remain consistent with the surrounding site plan. Please include a trash enclosure to accommodate the requirements of the MOB within construction estimate. Landscaping and irrigation system(s) will be provided and will meet all local codes / ordinances.

GENERAL

Please identify any items in the above outline scope that are not consistent with the local market and propose an alternate.

Page 8: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 8

FRAUENSHUH STANDARD DESIGN INFORMATION

PART 1: STRUCTURAL SYSTEMS

1.1 Overview

A. The structure shall consist of a slab�on�grade first floor with three occupied levels and roof above. Floor to floor heights shall be approximately 15’�6” on the first floor and 14’�6” on any additional floors.

1.2 Design Criteria

A. Codes and Standards: Design criteria for the structural and design of this building shall be based upon local codes and standards and are, therefore, the responsibility of the Engineer of Record.

B. Design Loads: 1. Live Loads:

Typical Floors 80 PSF Public Areas 100 PSF Corridors and Stairs 100 PSF Roofs 30 PSF (plus drifting snow) Partitions 20 PSF

1.3 Lateral System

A. Composite deck systems shall act as a diaphragm to transmit lateral loads to steel braces or steel moment frames at required locations.

B. Beam to column connections at the steel moment frames shall be full moment welded connections.

1.4 Foundation System

A. Overview: The foundation system design and construction shall be based on the recommendations and analyses in the final Geotechnical Investigation.

1.5 Slab On Grade

A. Standard Slab on Grade: Five�inch thick, 4,000�psi concrete slab with welded wire fabric shall be placed on compacted granular fill.

1. A reinforced polyethylene vapor barrier shall be placed over compacted granular fill

1.6 Structural Framing System

A. Overall Structural Concept: 1. Structural steel framing, with approximately 30’ x 30’ bay spacing 2. Composite beams and slabs at floors and portion of roof

B. Floor and Roof Construction: Typical system to be 3.5" lightweight concrete on 3" x 18 gauge composite steel deck with composite steel beams and girders with 3/4" x 5 1/2" shear connectors.

Page 9: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 9

PART 2: EXTERIOR ENCLOSURE

2.1 Exterior Masonry Wall Construction

A. The exterior wall consists of the assemblies outlined below. It is expected that each of these systems will be revised and variations of each be explored for cost efficiencies during the design phases of the project.

1. Masonry Wall Assemblies with punched window units. 2. Storefront Wall Assemblies.

B. Masonry Wall Assembly at Typical Solid Wall Conditions: The exterior wall assembly shall consist of a combination of brick and architectural precast concrete sills, placed over 16 gauge metal stud wall system:

1. Face brick: Jumbo face brick, running bond with standard Portland /lime mortar raked horizontal joints at wall � standard joints at vertical and other wall types

2. Two�inch air space

3. Minimum two�inch extruded polystyrene insulation conforming to ASTM C578, Type�IV

4. Through�wall flashing: Asphalt coated copper flashing

5. Damp proofing applied over concrete block foundation walls. In areas within the MOB with special environmental requirements of high relative humidity, a special moisture barrier�building wrap will be used. Special attention and detailing will be required at transitions between wall, floors, ceilings and roof areas

6. Sealants within brick and stone veneer: Low modulus polyurethane sealant with 50% movement (extension and compression)

2.2 Exterior Doors and Frame

A. Major Entrance Doors: Entry pair, complete assembly with aluminum sub;frame. All doors shall have aluminum door leafs and sidelight panels, threshold, and automatic door operator and related controls.

1. Configuration: Entry pair (3’�0” x 7’�6” each)

2. Operation: Electro�hydraulic operator with push plates, hardwired

B. Power Operated Sliding Doors: Sliding, low�energy, power operated pedestrian doors.

1. Locations to be determined during Schematic Design Phase

2. Hardwired electro�mechanical unit, DC motor powered with positive pulley and cog belt drive in both opening and closing cycles.

3. Standard for quality and design: Stanley Manufacturing Company, Dura�Glide 3000

4. Factory electric locking hardware to be included

Exterior Metal Doors:

5. 1�3/4 inch 16 gauge hollow metal doors complying with SDI Type II, extra�heavy duty, Model 1 full flush design with polyurethane core and 14 gauge hollow metal frames

6. Galvanized steel (A60 Coating) with field painted finish

Page 10: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 10

2.3 Exterior Window Systems

A. Punched Window System: Aluminum windows with prefinished metal clad exterior (anodized aluminum)

1. Standard break metal profile series

2. Typical units shall be fixed

3. Exterior finish: Anodized aluminum

4. Glass type: 1�inch tinted insulated glass with a high transmittance Low�E coating

5. Spandrel Glass: Color of spandrel coating shall be as recommended by the manufacturer to match vision glass color

PART 3: WATERPROOFING AND ROOFING SYSTEMS

3.1 ROOFING SYSTEMS

A. Single;ply Membrane: Fully adhered, minimum 60�mil, single ply EPDM or TPO roofing membrane with adhesive and accessories for application to roof deck.

1. Poly�isosyanurate rigid insulation

2. Roof pavers or adhered walking pads leading from roof access to all sides of RTU’s are to be provided

3. Minimum 20�year Roof Warranty

3.2 Roof Openings ; Roof Access

A. Roof Access: Typical roof access hatches shall be located within a stair shaft and serviced via means of a 60 degree angled interior ships�ladder. Multi�level or tiered roof areas are to have accessibility i.e. ladder or window opening.

B. Roof Hatch Designed for Industrial Stairs (Ships Ladder): Hatch curbs and covers shall be fabricated by using, not less than, 14�gauge prime coated galvanized steel. Minimum Size 2’�6” by 8’�0”.

C. Roof Davit/Safety Tie;Offs: Provide roof davits for window washing tie�downs for buildings 4 stories or higher. Project location/access may necessitate installation on shorter projects.

PART 4: INTERIOR CONSTRUCTION

4.1 Fireproofing and Firestopping

A. Sprayed Cementitious Fireproofing: Thickness as required to meet code requirement(s)

4.2 Interior Doors and Frames

A. Door Frames and Borrowed Lights: One piece, fully welded flush faces welded and ground smooth. Blunt stops with tight hairline joints are acceptable.

1. Fully welded frames, including stops

a. Exterior Frame Material: 14�gauge galvanized sheet steel painted b. Interior Frame Material: 16 gauge cold�rolled sheet painted

Page 11: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 11

B. Double Egress Doors and Frames: Hollow metal doors and frames with concealed vertical rod exit devices, closers and electric hold�opens.

1. Ratings to be determined during design development phase

C. Interior Metal Doors: 1�3/4 inch, 16 gauge hollow metal doors complying with SDI Type II, heavy duty, Model 1 full flush design doors with hourly rating indicated.

D. Doors in Public Areas: Provide AWI rated and nonrated doorframes at high design public areas. 1�3/4 inch flush wood doors with Premium Select Grade (TBD) veneer. Door Height 8’�0”.

1. Lifetime warranty

2. Finish: Prefinished, color (TBD)

E. Access Panels:

1. Flush stainless steel at public areas

2. Flush gypsum board surface with concealed hinges at Non�Public areas

4.3 Hardware

A. The overall quality and standard for building hardware shall comply with Owner’s Specification Guidelines.

B. Hardware shall be specified to comply with ADA Requirements throughout the project. 1. Finishes: For all items unless otherwise indicated: (dull chrome), or (satin

stainless steel).

2. Locksets and Latchsets: Preferred Schlage D�Series Lever or similar. Heavy duty mortise locksets with screwless shank and anti�friction latch bolts.

3. Lock Cylinders and Keying: Preferred Schlage D�Series or similar.

4.4 Ceramic Tile (TBD DURING DESIGN)

4.5 Acoustical Ceilings

A. Ceiling System at Public Areas (ACT;1):

1. Suspension system: Exposed 15/16�inch wide narrow grid

2. Acoustical ceiling board: 24�inches by 24�inches by 3/4 inch thick integral colored cast board with revealed edges

4.6 Resilient Flooring

A. Vinyl Composition Tile (RF;1): 12�inches by 12�inches by 1/8�inch thick.

4.7 Carpet (SECTION 09680)

A. Carpet (CPT;1): Carpet Tiles in public areas.

1. Colors: (TBD DURING DESIGN)

4.8 Painting

A. Exterior Painting: All exposed materials to be prefinished. Provide Intercept antimicrobial and mildew deterrent additive for exterior products.

1. Steel beams: Polyurethane finish with epoxy primer

2. Traffic striping at entrance and other areas as required

B. Interior Painting: Paint surfaces with primer and two finish coats, unless otherwise indicated.

1. Paint the following items and surfaces:

Page 12: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 12

a. Ceilings: Satin latex

b. Walls � Gypsum wallboard: Satin latex

c. Walls � Concrete block: Semi�gloss latex with block filler

d. Walls to receive wall coverings: Prime paint with latex sizing

4.9 Wall Coverings

A. WC;1: Typical vinyl wall covering, Type II not less than 20 ounces per 54�inch linear yard.

1. Wall coverings shall not be installed on building exterior walls

4.10 Finish Schedule

A. The development of materials, finishes, special features and accent lighting for interior areas has been subdivided into two basic categories: 1). Public Areas, and 2). Service Areas. A detailed finish schedule will be developed through the course of design.

B. PUBLIC AREAS: General MOB areas directly accessible to the public will include vestibules, main lobby areas, elevator lobbies, corridors, and public toilets. Basic finishes and materials shall include:

1. Main Lobby Areas:

a. Floor Finishes: Tile and CPT

b. Base Material: Wood/Tile/Carpet base

c. Wall Materials and Finishes: Upgraded wall finish at selected locations & wall covering (wood, stone, etc)

d. Ceiling Materials and Finishes: Gypsum board detail, ACT

e. Special lighting design or accents

2. Public Corridors:

a. Floor Finishes: CPT

b. Base Material: Carpet base

c. Wall Materials and Finishes: WC over gypsum wallboard

d. Ceiling Materials and Finishes: ACT�1 with gypsum board soffits at tenant entries (painted)

3. Vestibules:

a. Floor Finishes: Recessed floor mat with tile surround. Rubber backed walk�off carpet squares

b. Base Material: Tile or Wood

c. Wall Materials and Finishes: Storefront aluminum window system or Lobby finishes at solid walls

d. Ceiling Materials and Finishes: ACT�1 with hold down clips

4. Public Toilets:

a. Floor Finishes: Thin set CT with final grout sealer.

b. Base Material: Thin set CT over gypsum wallboard

c. Wall Materials and Finishes: Thin set full height CT at wet wall, vinyl over gypsum wallboard at other walls

d. Ceiling Materials and Finishes: Gypsum wall board soffits and ACT�1

Page 13: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 13

C. SERVICE AREAS: Building areas provided for the internal use of staff and solely for of the operation of the building. Service areas include mechanical, electrical areas, and service areas. Typical materials and finishes are described below.

1. Loading/Receiving Area

a. Floor Finishes: Sealed concrete

b. Base Material: Resilient Base

c. Wall Materials and Finishes: Painted gypsum wall board or concrete block

d. Ceiling Materials and Finishes: Painted

2. Trash Holding:

a. Floor Finishes: Resilient Flooring

b. Base Material: Resilient Base

c. Wall Materials and Finishes: Gypsum wallboard with epoxy paint

d. Ceiling Materials and Finishes: Gypsum wallboard with epoxy paint

3. Mechanical, Electrical and Data Areas:

a. Floor Finishes: Sealed concrete

b. Base Material: Resilient Base

c. Wall Materials and Finishes: Painted gypsum wallboard

d. Ceiling Materials and Finishes: None � exposed structure

4. Janitors/Housekeeping Closets:

a. Floor Finishes: Sealed concrete

b. Base Material: Resilient Base

c. Wall Materials and Finishes: Rigid wall protection up to 4’�6”, epoxy paint above. 0.060�inch thick semi�rigid vinyl protective wall covering, complete with trim and accessories to terminate material at corners and exposed edges.

d. Ceiling Materials and Finishes: Exposed

5. Stairwells a. Floor Finishes: Sealed concrete b. Base Material: Resilient Base c. Wall Materials and Finishes: Painted gypsum wall board or concrete block d. Ceiling Materials and Finishes: Painted e. Painted raises and handrail

6. Bldg. Eng. Office/Storage Area

a. Floor Finishes: Resilient Flooring

b. Base Material: Resilient Base

c. Wall Materials and Finishes: Painted gypsum wall board or concrete block

d. Ceiling Materials and Finishes: Painted

7. Mail Room/Specimen Sample Closet & Wheelchair Alcove a. Details are project specific.

PART 5: SPECIALTIES, EQUIPMENT, AND FURNISHINGS

5.1 Toilet Compartments

A. Ceiling Mounted Partitions: Painted metal stainless steel ceiling connection and chrome plated hardware, including the following:

Page 14: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 14

1. Door hinges and latch hardware designed for ADA requirements.

2. Color: To be determined.

5.2 Identifying Devices

A. Exterior Signage:

1. Primary exterior building signage for building name / monument (dollar allowance stated in this document)

2. Match existing campus design standard

B. Interior Signage: Interior signage required by code, suite/tenant identification signs and required way�finding signs will be provided.

C. Electronic Building Directory: 1. Standard for design and quality: Mirada Wall Mount TouchSource Directory – Items to Include:

a. 32�inch flat panel LCD touch monitor b. Intel/Windows�based processor c. Ability to network multiple directories d. TouchSource Software e. "DIRECTORY" lettering in raised black acrylic f. Mirada semi�recessed wall mount cabinet g. Fully Web Accessible

5.3 Toilet Accessories

A. Acceptable Manufacturers for Toilet Accessories:

1. Bobrick Washroom Equipment, Inc.

2. Bradley Corporation

3. McKinney/Parker Company

4. American Specialties, Inc.

B. Toilet Paper Holder, Multi;Roll (TPH;5): Surface mounted, double roll type with non�restrictive delivery operation; cast aluminum, satin finish.

1. Standard for design and quality: Bobrick Washroom Equipment, Inc.: No. B�2740

C. Sanitary Napkin Disposal (SND;1): Recessed mounted, feminine napkin disposal, 18�gauge door and disposal panel, 22�gauge cabinet, 304 stainless steel satin finish all exposed surfaces; full length stainless steel piano hinge on self closing door and disposal panel; approximately 13�inches wide by 19�inches high by 4�inches deep. Hem all exposed edges.

1. Standard for design and quality: Bobrick Washroom Equipment, Inc.: No. B�353

D. Sanitary Napkin and Tampon Vendor (SNC;1): Surface mounted feminine large capacity with two dispensing mechanisms, each with $.25 single coin operation. 22 gauge cabinet, 18 gauge door, all of 304 stainless steel, satin finish all exposed surfaces; full length stainless steel piano hinge on door approximately 28�inches high by 12�inches wide by 8�inches deep. Hem all exposed edges.

1. Standard for design and quality: Bobrick Washroom Equipment, Inc.: No. B�2800

E. Paper Towel Cabinet (PTC;1): Semi�recessed mounted; Tri�Fold with trash disposal.

1. Standard for design and quality: (TBD DURING DESIGN)

Page 15: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 15

F. Soap Dispenser (SDISP;1): Lavatory mounted soap dispenser with 4�inch spout and 32�ounce plastic container mounted below countertop.

1. Standard for design and quality: Bobrick Washroom Equipment, Inc.: No. B�822.

2. Mount soap dispenser so that spout is over the sink.

G. Baby Changing Station: Vertical style semi�recessed mounted.

1. Standard for design and quality: Bobrick Washroom Equipment, Inc.: No. B�239 x 34

5.4 General Access

A. Mail Station: The typical mailbox is the Standard Horizontal Mailbox from Salsbury Industries�3715D�16 16MB1 Doors and two (2) Parcel Lockers (PL6) 31�1/8” W x 55” H x 17�inch D 160 lbs (15 Doors High). Specifications will be reviewed per project and adjustments made as needed.

B. Mop and Broom Holder with Shelf: 304 stainless steel, satin finish, not less than 22 gauge; 8�inch wide shelf, length as indicated.

C. Wire Shelving – Heavy�Duty wire shelving in each Janitor Closet, three (3) shelves; 3’ wide.

PART 6: CONVEYING SYSTEMS

NOTE: AN ELEVATOR STUDY SHALL BE CONDUCTED, BASED ON BUILDING SIZE AND ANTICIPATED OCCUPANT LOADS, TO DETERMINE TYPE, QUANTITY, SIZE AND SPEED OF ELEVATOR(S)

6.1 Elevators

A. Elevator No. 1 (Gurney Size): electric traction/MRL Gurney Size elevator as indicated with the following characteristics:

1. Capacity: 5000 pounds

2. Speed: 150 feet per minute

3. Clear Inside Dimensions (W x D): 5'�6 13/16" x 8'�9 3/16"

4. Travel: As indicated

5. Number of stops: 1 per floor

6. Entrance Width & Type: 4' & Left Opening

7. Door operation: Single speed, center opening

8. Hoistway frame: Stainless steel

9. Hoistway door: Standard stainless steel panels

10. Operation: Simplex

11. Control: Variable voltage, 2 way leveling

12. Car enclosure: Standard hospital cab

13. Rear Entry Door (Option TBD): 3’�6” wide by 7’�0” high

14. Power Supply: 480 Volts + 5%, three�phase

B. Elevator No. 2: electric traction/MRL fully automatic passenger elevators as indicated with the following characteristics:

1. Capacity: 3,500 pounds

2. Speed: 150 feet per minute

Page 16: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 16

3. Clear Inside Dimensions (W x D): 6'�6" x 5'�6 3/16"

4. Travel: As indicated

5. Number of stops: 1 per floor

6. Entrance Width & Type: 3'�6" & Center Opening

7. Door operation: Single speed, center opening

8. Hoistway frame: Stainless steel

9. Hoistway door: Custom etched stainless steel panels

10. Operation: Simplex

11. Control: Variable voltage, 2�way leveling

12. Power Supply: 480 Volts + 5%, three�phase

C. Control System: Non�proprietary, solid state, modular microprocessor to control car movements in a regulated sequence in response to hall calls, with automatic response of system to changes in demand. (Standard of Quality: Motion Control Engineering, Rancho Cordova, CA).

1. Provide traveler cables for future (optional) card access in elevator cabs

2. MRL applications that utilize a belt�type conveyance system are to include the factory pulse testing device.

3. Provide Emergency Loss of Power Lowering device on each car.

4. Machine Room location shall be inside the hoist way mounted on car guide rail.

5. Control equipment shall be located in an integral closet at the top floor landing

D. Car Enclosure: Manufacturer’s standard pre�engineered car enclosure with standard finishes as indicated. Include ventilation, lighting, ceiling finish, wall finish, access doors, cab doors, power door operators, sill, trim, accessories and sub�floor.

1. Sill shell: Steel construction with full height removable panels

2. Front and transom: Flush stainless steel

3. Side panels: High pressure plastic laminate, color, texture, and pattern to be determined during design development phase

4. Aluminum sills: Cast or extruded aluminum, with grooved surface, ¼ inch thickness, mill finish

5. Custom ceiling with fully accessible indirect lighting as indicated

a. Manufacturer’s standard mounting height

b. Florescent or LED light fixtures

6. Handrails: Continuous 2�inch satin stainless steel cylindrical on back and side walls

7. Accessories:

a. Protection pad buttons and pads with pad mounting devices for all cars.

E. MANUFACTURER � Standard for design and quality: 1. Provide AC gearless machine room�less elevator systems subject to compliance

with the design and performance requirements of this specification. Elevator manufacturers may include but are not limited to one of the following:

a. Basis of Design: EcoSpace™ traction elevators by KONE, Inc. (www.kone.com).

b. Other acceptable machine room�less products:

1) Otis Elevator Co. � Gen2L™ Product 2) Schindler Elevator Corp. � 400A Product 3) TKE Synergy 85S

Page 17: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 17

PART 7: HEATING, VENTILATING & AIR CONDITIONING

7.1 Heating, Ventilating and Air Conditioning

A. The proposed MOB will be conditioned via roof�mounted, RTUs. The load calculations (minimum) will be 1 ton per 350 gross square feet required. Equipment will be variable air volume (VAV) systems, electric DX cooling, fully modulating gas heat, and variable speed drives on supply, return, and exhaust fans, stainless steel condensate pans & heat exchanger (10 yr. extended warranty), compressors (5 yr. extended warranty), hail guards, hot�gas bypass, enthalpy control, Traq dampers/airflow monitoring station and 3�phase compressor protection. Condensate drains are to be piped to roof drain locations.

B. General exhaust shall be sized for no less than 0.15 cfm/sq.ft.

C. Controls shall be direct digital control (DDC). The system is to be non�proprietary with open interoperability framework accepting all legacy communications protocol, i.e. Modbus, Lon, and BacNet. Software is to be Tridium/Niagara AX based using Native BacNet communications between devices. The system will contain a full graphics package and be fully Web Accessible with the capability of sending out Critical Alarms via Email and Text Messaging. The system shall be capable of communicating with third party software service data analysis systems/hosted systems utilizing JACE devices containing an Obix driver. System shall include all necessary components, but not be limited to, CPU, monitor, modem or Ethernet card. Any/all device level programming software is to be provided as well. A data/communications trunk loop is to be run on each floor for future tie�in.

D. The finished areas of the building in the core and shell will be conditioned by Parallel type fan�powered terminals with electric heat on perimeter zones, and VAV terminals with electric heat in the interior. Where miscellaneous entrance vestibules or exit stairways require heat, electric wall heaters or air curtains shall be included. Electric heat shall be 277/480 volt.

E. The design intent is to locate the units on the roof with roof curbs and a concrete pad coordinated with the structural design. The preliminary floor plan indicates vertical mechanical duct chases. Economizer inlets to be a minimum 36” above roof surface as per regulatory requirements.

F. The base building return air shall utilize the air ceiling plenum for the return path. Supply air shall be fully ducted to include a trunk duct loop on each floor, and installed according to the latest SMACNA guidelines.

G. The following criteria establish the baseline assumptions. Design load considerations shall be adjusted based on regional climate conditions.

Ambient Design Conditions Summer 98°FdB/75°wb

Winter 0°FdB

Inside Design Conditions 75°F dB

Building Assemblies Wall 0.08 U�value

Roof 0.05 U�value

Glass 0.57 U�value, SC of 0.37

Infiltration Rate 0.06 cfm/S.F. perimeter skin

Internal Loads Power 2.75 watts/S.F.

Page 18: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 18

Lights 1.50 watts/S.F

People One per 140 S.F. outside air per code

PART 8: PLUMBING 8.1 Plumbing

A. Above grade sanitary, waste, and vent piping shall be cast iron hub and spigot, or hub�less pipe and fittings, with stainless steel clamps and neoprene gaskets. Within the proposed building, provide minimum of three (3) 4�inch sanitary/waste stacks, along with a 4�inch vent stack, all with capped 4�inch rough�ins for future extension above ceiling line on each floor level.

B. All sanitary/waste piping will be gathered within the outline of the building beneath the ground floor, and extended to on�site sanitary sewers. Future 4�inch capped sanitary rough�ins will be provided below the ground floor slab at appropriate intervals to permit the connection of future plumbing fixtures. Below grade piping will be schedule 40 PVC.

C. Above grade storm piping shall be cast iron hub and spigot or hub�less pipe and fittings with stainless clamps and neoprene gaskets. Internal roof and overflow drains will be furnished; roof drain storm piping will be gathered below the ground floor slab and extended to on�site sewers. Overflow drain storm piping will extend down through the proposed building and daylight through the building exterior wall at finish grade with bronze downspout nozzles. Below grade piping will be schedule 40 PVC.

D. Subsoil drainage piping shall be corrugated and perforated polyethylene piping, or SDR�35 PVC piping. Route piping around all walls below finish grade and connect to storm piping routed to on�site sewers.

E. Should we select a hydraulic�style elevator, provide an oil / water separation type sump pump in the elevator pit, similar to Stancor “Oil Minder”. Pipe discharge to storm system. All sump pumps are to be set up to send “high level” alarms to EMS system.

F. All cold, hot, and hot�water recirculation piping shall be type�L copper tube with wrought or cast copper sweat�type fittings. Provide a new 4�inch cold water service with dual reduced pressure backflow preventer assemblies, located on the ground floor. Confirm available water pressure for the project. Provide dual water pressure regulators to reduce pressure to no more than 80 psig within the building if necessary. Locate the regulators on the ground floor in the same room with the reduced pressure backflow assemblies.

G. A 50�gallon electric water heater with thermal expansion absorber, dielectric fittings, circulation pump, time clock, and return line will serve the core public toilets and janitor sinks only.

H. Water heater shall have an output temperature of 145°F to control bacteriological growth within the system. Provide a thermostatic mixing valve to reduce hot water system temperature to 115°F, downstream of the water heater, for distribution to the core plumbing fixtures.

I. A minimum of three (3) cold water risers with valved and capped rough�ins shall be located above ceiling line on each floor level. Locate the cold water risers adjacent to the sanitary / vent wet columns.

Page 19: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 19

J. Plumbing fixtures shall be commercial grade white vitreous china water closets, wall�hung water closets and lavatories with electronic sensor controls. Design mounting of wall�hung water closets for Bariatric patient use. Mop basins shall be molded stone construction with manual controls, including cross handles, rigid spout, and atmospheric vacuum breaker. Electric water coolers shall be bi�level, ADA compliant, units.

K. Electronic Faucets

a. Standard for design and quality: HyTronic Gooseneck Deck Mounted Single Hole Faucet – DC fed from hard�wired AC power source

L. Four (4) freeze proof hydrants (one on each elevation of the building exterior) shall be provided per floor. Additionally, one (1) hydrant shall be placed on the roof

PART 9: FIRE PROTECTION 9.1 Fire Protection

A. A new 6�inch fire service line shall be installed from the existing underground fire main to the building. As stated previously under the plumbing narrative, confirm water pressure for this building is sufficient – for purposes of this estimate, provide a booster pump on the ground floor. Provide a 6�inch double detector check valve assembly on the 6�nch fire service.

B. If required by code, standpipes shall be provided in stairwells.

C. One (1) 6�inch combined sprinkler / standpipe in the stairwell closest to the fire service entrance. Riser shall be complete with two (2) 1/2” Fire Department valves, electrically supervised valves and flow switches for supervision of sprinkler systems on each floor level. A 4�inch standpipe riser in the remaining stairwell, complete with two (2) 1/2” Fire Department valves shall be provided at each floor level. A roof manifold, post indicator valve and a Fire Department siamese connection shall be also be provided.

D. The building will be fully sprinklered (per code req.), based on an open (unfinished) floor plan, with quick�response sprinkler heads. Upright sprinkler heads shall be furnished in shell areas. For finished areas, recessed sprinkler heads shall be furnished and centered in ceiling tile.

E. Sprinkler / standpipe piping systems shall be schedule 10/40 black steel piping with threaded cast or malleable iron fittings (Schedule 40 only) or roll�grooved piping with Victaulic style clamps.

F. Attic and canopy areas requiring a dry�type system shall be of a pre�action type as to protect against unintentional filling/charging of the system.

PART 10: ELECTRICAL

10.1 Service Distribution

A. Power distribution and equipment will be transmitted underground from a utility�owned pad�mounted transformer, which will be located adjacent to the building. Provide 277/480 volt, three phase, 4 wire electrical service appropriately sized for a medical office load from the pad mounted transformer to the new building. New service conduit(s) from the property line to the transformer will be installed. A concrete transformer pad will be installed adjacent to the facility for the transformer. Transformer and primary service provided by local utility company. Discuss electrical

Page 20: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 20

service redundancy capabilities with local utility provider. All work shall be coordinated through local utility.

B. A secondary cable will be brought into the main electrical room from the pad�mounted transformer, terminating in a main service switchboard. This service will be metered with a single meter with metering provisions as required by the serving utility company.

C. 480 volt feeder risers shall distribute power to each floor for lighting, receptacle and miscellaneous power use. The feeders shall be run as EMT or IMC conduit with THHN/THWN or XHHW copper wire.

D. The main switchboard shall have ground fault protection and phase loss/failure protection. An integral TVSS unit shall be provided in this switchboard. The ground fault protection will be provided as required by the NEC. Two levels of ground fault protection will be provided where required by code. The main service shall be sized to accommodate a minimum of 18 watts per square foot for tenant spaces, core and shell, site lighting and mechanical equipment.

E. Power will be feed out of main distribution panel – up to common electrical closets located on each floor. Each closet shall contain a 277/480 volt sub�panel with a minimum total capacity of 15 watts per square foot, allowing for future tenant single�feed connection. In addition, there shall be a 120/208 3�phase, 4 wire, TP�1 rated, dry type transformer & associated 120/208 volt subpanel per floor to accommodate receptacle and miscellaneous 120/208 volt power needs of each floor common area. The transformer and 120/208 volt panels shall be capable of supporting a minimum of 5 watts per square foot for common area power needs. The watts per square foot above shall be increased accordingly per project. Mechanical equipment larger than ½ HP shall be served from the main switchboard and/or dedicated mechanical panel.

F. Fault�current and overcurrent protective device coordination studies will be performed using widely used nationally distributed software. All protective devices used in power distribution equipment shall be included in these studies. These studies shall be accompanied with power distribution submittals and shall indicate fault current and coordination compliance with all power distribution components. Arc Flash labeling shall be included on all applicable panels/devices.

G. Housekeeping pads for electrical equipment shall be provided by the electrical contractor

H. Branch circuit panel boards will be quick�make, quick�break circuit breakers

I. Distribution panel boards will be fusible type with quick�make, quick�break switches

J. Fuses will be Bussman or equal, the type will be as required to suit both the interrupting capacity and time delay required. A spare fuse cabinet shall be included.

10.2 Emergency System

A. Egress lighting will be provided via battery powered back�up integral in base fluorescent fixtures, exit signs to utilize LED technology. Quantity and location of all egress and exit units shall be as required to comply with the local Authority Having Jurisdiction.

Page 21: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 21

10.3 Wiring Methods

A. All wiring will be installed as Type “A.C.” cable, “MC” cable, or in conduit (rigid steel, E.M.T., flexible or plastic type) as required by The National Electric Code, state or local codes.

B. Conduit located below grade will be galvanized rigid heavy wall, IMC steel or PVC.

C. Wiring for branch circuits and feeders will be type XHHW, THWN, or THHN 600 volt, #12 AWG minimum, copper.

D. Control wires will generally be No. 14 AWG. Wiring for signaling, alarm, and communication circuits shall be sized as required and in compliance with manufacturer’s recommendations. This wiring will be run without conduit as permitted by code. Conduit will be used in walls, in accessible spaces and where the wiring is subject to physical damage.

E. Low Voltage cabling is not permitted to be hung from any plumbing or mechanical equipment.

F. If electrical work is installed or altered in an exterior wall, the electrical contractor is responsible for repairing or maintaining the integrity of the vapor barrier. Upon completion of work, this is to be verified by building personnel.

G. All breakers shall be properly identified and marked. Panel directories in the panel boards shall be typed.

10.4 Lighting

A. Lighting will generally be recessed (or surface) fluorescent fixtures, using Type T�8, 28 Watt maximum, 4100 K energy saving lamps.

B. All fluorescent lighting will be 277 volts. All light fixtures will be Underwriters’ Laboratories listed.

C. Ballasts for fluorescent fixtures will be electronic type, UL approved, Class P.

D. Lighting fixtures will be as follows:

1. Lobbies, entrance vestibule and elevator lobbies will be fluorescent or LED down lights (PL lamps)

2. Public corridors will be 2’ x 2’ indirect recessed fluorescent

3. Mechanical, electrical, and telephone/data rooms will utilize 4’ fluorescent strips

4. Stairwells will be wall�mounted fluorescents with lens

5. High ceiling areas (15’ or above) will be metal halide or LED type

6. Public restrooms will be indirect fluorescent 2 x 2 with occupancy sensors

7. Light levels shall be in accordance with IES standards

8. Exterior lighted parking areas, roadways, and walkways shall utilize cut�off pole�mounted pulse�start metal halide fixtures with light levels meeting local codes and IES standards. Pole bases are to be provided by the electrical contractor. Control of exterior lighting shall be by means of time clock and photo cell.

9. Lighting and lighting controls shall be provided to meet current energy codes. Occupancy sensors shall be used where customary.

Page 22: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 22

10.5 Wiring Devices and Equipment Connections

A. Provide convenience receptacles in the shell building for housekeeping purposes. One receptacle shall be provided every 50’ of corridor and/or as appropriate for common areas of the MOB. Receptacles shall be specification grade.

B. Provide weatherproof GFCI receptacles at rooftop equipment (25’ minimum distance from outdoor equipment to a weatherproof GFCI outlet).

C. Provide wiring and connections to all automatic door operators. Interlock and program automatic door controls with security system and/or Building Automation System (BAS).

D. Provide power wiring and connections to all mechanical equipment and provide electrical disconnect switches on or adjacent to equipment per code.

E. Provide 480 volt power to elevator equipment. Provide all code required appurtenances (i.e. shunt trip devices, etc.).

F. Provide 120 volt power for fire/smoke dampers.

10.6 Special Systems

A. Fire Alarm:

1. Provide a complete analog addressable fire alarm system complying with all local and state codes. System shall have P.A. capabilities.

2. Devices such as speakers, bells, chimes, pull stations, heat and smoke detectors, ADA compliant visual flashers, duct detectors, fan shutdown, door release, etc. will be provided to the extent required by code. Combination audible and strobe devices shall be ADA compliant.

3. Upgrades of the base building fire alarm system for the tenants use will be provided at cost of the tenant.

4. A U.L. listed digital communicator shall be provided for off�site monitoring.

5. The base fire alarm system shall be capable of being expanded for tenant work.

6. Final zone isolation/programming shall be determined with owner input.

B. Television System:

1. One (1) – 2�inch conduit from the main telephone room to a point 10’ outside the building for cable TV service will be provided.

C. Telephone/Data:

1. Four (4) – 4�inch conduit from the main telephone room to a point outside the building (property line) designated by the service communication utility.

2. Provide two (2) 4’ x 8’ x 3/4” fire retardant plywood backboards for the demarcation point within the building. Locate the backboards in the main telephone room.

3. From the main telephone room, provide a 200 pair, 24 plenum rated, voice grade cable (CAT5) for each satellite telephone room. These cables shall be

Page 23: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 23

terminated on 110 punch down blocks. There shall be two (2) four inch penetrations provided between floors for data/phone line routing.

4. Provide Fiber Optic service to the building. Review Fiber Optic service options with communications provider.

D. Security System:

1. Included is a Security/Card Access system. Base security system will monitor main building entrances, shall be fully Web Accessible, and provide remote alarming functions. An Add�Alternate for cabling/infrastructure for all exterior doors and elevator cabs shall also be included.

E. Lightning Protection:

1. An Add Alternate for installation of a lightning protection system complete with a master cable (U/L Certification).

F. Real;Time Energy Metering System:

1. System

a. This system is designed to be tied to all incoming electrical services for the building

2. Software

a. Be EFT Energy Manager™ or approved equal (www.eft�energy.com) and shall provide for two options; software to provided as a SaaS (software as a service) or as an installed platform; option to be chosen at time of purchase.

b. Support an unlimited number of users and data points coming on the system.

3. Infrastructure

c. Meters and monitoring shall be installed on each load, per the engineering drawings. All equipment shall be installed to meet all local codes and requirements and per the manufacturer’s instructions.

d. All meters and monitors shall be equipped with dry contact type, pulse output (Form A, 2 wire or Form C, 3 wire).

e. Data Collection

f. Data collection device shall be the DataTRAK™ System provided by EFT Energy Inc. or approved equal.

g. For data collection from the meters, DataTRAK™ shall be used to log the pulses in 15 minute intervals (1 or 5 minute intervals are optional) and send the data via the internet EFT Energy.

h. DataTRAK™ devices shall log data for up to 8 pulse meters or up to 31 pulse meters with an optional High Density Pulse Module.

i. DataTRAK™ shall be provided with 120V plug power supply.

j. DataTRAK™ shall be provided with connection to owner’s Ethernet system (DHCP connection preferred).

4. Execution

k. Provide installation of pulse based meters and Gateway in accordance with manufacturer’s instructions.

Page 24: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 24

l. Each pulse based meter or monitor shall be connected to the DataTRAK™ via #18�22 AWG, twisted wire. Maximum length of the wire from the meter to the DataTRAK™ shall be 200 feet or less or per the meter or monitor manufacturer’s instructions, whichever is less.

m. Provide all necessary CAT5 cabling between the LAN connection points and the DataTRAK™ for connection of the data to the EFT server.

G. ELECTRICAL POWER MONITORING AND CONTROL PART 1 ; GENERAL 1.1 System Description

A. Furnish and install a complete Power Monitoring System (PMS) to record individual tenants and rooftop unit’s energy consumption for the intent of billing purposes. The system is defined to include, but not be limited to, C/TS, meter multi meter housing and built in RS485 communications to the Owner’s EFT data track management system located in the Maintenance Office #4T008 on the fourth floor.

B. XXX meters and C/TS shall be provided in this contract or serving XXX rooftop unit feeders. All meters for rooftop units and future tenants meters will be located in the fourth floor electric room.

C. Tenants will be responsible for providing an E�MON�D�MON meter C/TS and wiring to the fourth floor electric room.

D. The XXX energy meter located on the pad mounted transformer will provide a pulsed output to be wired to Owner’s EFT data tracker located in the Maintenance Office #4T008.

PART 2 – PRODUCTS 2.1 The PMS shall be the Class 3400 Smart meter KWH / Demand meters with

communications by E�MON�D�MON.

A. Meter shall be fully electronic with 4�line display showing kwh, kW demand (with peak date and time), power factor by phase, real�time load in kW, Amps per phase and Volts per phase. The meter shall have communication built in for RS�485, pulse output or Ethernet. Protocols capability built in for EZ7, Modbus RTU, Modbus TCP/IP, BACNET MS/TP, BACNET IP or LON works FT�10.

B. Meter shall utilize 0�2 volt AC output current sensors to allow paralleling and/or mounting up to 500 feet from the meter. Sensors shall be of split�core configuration to allow installation without disconnecting cabling, etc. Sensors shall be available from 100 amp to 3200 amp. Sensors shall be optionally available in solid�core configuration (100 & 200 amp.)

C. Meter shall be field programmable for meter date / time, IP address and ID code for communication.

Page 25: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 25

D. Meter shall provide installation diagnostics on display.

E. Meter shall be UL/CUL listed to latest applicable standards for safety.

F. Meter shall meet or exceed ANSI C12.20 accuracy standards.

G. Meter shall provide non�volatile memory to maintain reading during power outages.

H. Meter shall store interval data for kWh and kVAR for up to 72 days in first�in first�out format. (Standard firmware).

I. Meter shall be capable of daisy�chain or star connection using RS�485 communications in combinations of Class 3400 not to exceed 52 devices. Cabling shall be available terminal block (3�conductor), 18�22AWG, up to 4,000 cable feet total.

J. The Owner has requested the meter be wired for RS�485 communications from the meters to EFT data tracker units. Coordinate cable type with E�MON�D�MON.

PART 3 – EXECUTION 3.1 Installation

A. All control power, CT, PT and data communications wire shall be wired and harnessed within the equipment enclosure.

B. Interconnection wiring requirements shall be clearly identified on the PMS system drawings.

C. All equipment shall be securely mounted in enclosures or special�mounting devices made for the purpose and be clearly, permanently marked.

D. All equipment shall be properly grounded to meet NEC code requirements and to prevent electromagnetic or electrostatic interference.

E. All penetrations in smoke or firewalls shall be sealed with fire stop rated for this purpose.

3.2 Wiring Installation

A. Wiring shall be furnished and installed in accordance with manufacturer’s recommendations, industry standards and in compliance with all Local, City, State and National Codes. All wiring, not inside equipment enclosures, shall be installed in conduit.

Page 26: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 26

B. All wiring entering/leaving switchboards or cabinets shall be properly routed and secured. Wires and cables used in assembling switchgear or cabinets shall be formed into harnesses which are tied and supported for proper strain relief. Harnessed cables shall be combed straight. Each cable that breaks out from the harness for termination shall be provided with an ample service loop and shall not violate the minimum bend radius of the cable.

C. Provide all required control cabling between equipment as required by the manufacturer.

D. All control and signal cable shall be installed continuous and without splices. Provide appropriate connectors or pre�manufactured cables for each application.

3.3 Grounding

A. The installing contractor shall be responsible for ensuring the grounding integrity of all installed equipment to eliminate the potential for equipment or personnel hazards due to improperly or inadequately grounded systems.

B. All grounding and bonding shall be in conformance with the National Electric Code, article 250 and as recommended by EIA/TIA and the vendor.

3.4 Programming

A. It is the vendor’s responsibility to program the system in this section according to the Owner’s wishes. The vendor shall meet with the Owner and Engineer and reach agreement on the programming. This programming agreement shall then be written out in detail and forwarded to the Engineer for approval. After approval is granted, proceed with final programming.

3.5 Identification/Labeling

A. Contractor shall identify and tag all cables with permanent type markers to denote tenant or equipment served. Cables shall be tagged at both ends and at each point where the cable is administered. All control and signal cables shall be installed continuous and without splices. Provide appropriate connectors or pre�manufactured cables for each application.

B. The Contractor shall clearly and logically label all terminal blocks, cables and equipment and ensure that labeling coordinates with the as�built documentation.

3.6 Tests

A. Upon completion of installation and satisfactory testing of system by Contractor in presence of the equipment supplier, the Contractor shall test the system in the presence of the Owner and the Engineer.

Page 27: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 27

B. System shall be tested by and a certificate of inspection shall be furnished by a qualified manufacturer’s representative or equipment vendor; Submit report indicating result to the Engineer.

3.7 System Start�up and Training Requirements

A. The equipment supplier shall provide system integration, set�up and start�up assistance to the Installing Contractor. The proposal shall include complete technical onsite assistance for these activities as required for this system’s size and complexity. After completion of the installation, the supplier shall commission the system and request an initial acceptance test by the Owner and Engineer. A final acceptance test shall then be scheduled after correcting any system deficiencies or functionality issues that are determined in the initial test. Provide training, by a system certified trainer, at the project site as coordinated with the Owner. The training shall include the following elements:

1) Start�up shall include a complete working demonstration of the PMS.

2) Demonstrate adjustment, operation and maintenance of the system including each component and control.

3) A final technical training session, which shall include hands�on training, accompanied by full system documentation and system as�built drawings.

4) Training shall include any documentation and hands�on exercises necessary to enable electrical operations personnel to assume full operating responsibility for the PMS after completion of the training period.

5) Provide a manufacturer’s “Certificate of Completion” that is signed, dated and documented for each trainee.

6) The power monitoring vendor shall offer regularly scheduled factory training to the Owner on all aspects of power monitoring and control, including:

a) Comprehensive software and hardware setup, configuration, and operation

7) The power monitoring manufacturer shall provide a dedicated technical support center for the Owner.

B. This training period shall be scheduled with the Owner after the successful completion of the system.

C. Manufacturer shall have total single point of contact responsibility for all aspects of PMS implementation, including equipment supply, integration, customization, start�up, and on�going systems support.

D. Manufacturer shall employ a service technician within 100 miles of project site that is specially trained and certified to modify and repair the PMS system.

Page 28: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 28

E. Supplier shall provide a follow�up site inspection / training refresher to the Owner 60 days after final acceptance to verify system is operating correctly within programmed parameters and to review operational and training with Owner personnel.

3.8 As�Built Documentation

A. The Contractor shall furnish the Owner two (2) complete bound as�built manuals in an 8.50” x 11” format. Drawings shall be a minimum of 11” x 17” engineering format. These manuals shall be assembled in a loose leaf binder and shall contain:

1) System Operating Instructions

2) System Single Line Diagrams

3) System Detailed Wiring Diagrams

4) Component Technical Operating Manuals

5) Component Service Manuals

3.9 Warranty

A. Provide a one (1) year full warranty of the system, including equipment, wiring and software against defects in material and workmanship from the date of system completion and final acceptance. If any defects are found within the warranty period, the defective system component shall be replaced at no extra cost to the Owner for parts or labor.

3.10 Certification

A. Upon completion of the testing, the manufacturer or representative shall issue to the Owner a letter of certification attesting to the fact that he has tested and adjusted the system, that all components are properly installed and free of defects, and that the system is in compliance with this specification.

Page 29: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

A. PART 11: GENERAL REQUIREMENTS FOR CONSTRUCTION

11.1 Laws, Ordinances, Rules and Regulations

A. All work and equipment shall be installed in accordance with all applicable Federal, State and Local laws, ordinances, rules, regulations and codes; the most stringent applies. All items of labor and material required to meet these regulations shall be included, regardless of their absence in the project documents.

B. The contractor is to obtain and pay for all permits, licenses and fees; make arrangements

for all necessary inspections and pay all fees in connection therewith. The contractor is responsible for all applicable Federal, State and Local taxes.

C. If conflict exists between these guidelines and the drawings, specifications or addenda,

request clarification from architect.

11.2 Design Build Drawings

A. Carefully investigate and coordinate all drawings and the finished conditions of all work and arrange such work accordingly.

B. All changes from the plans necessary to make the work conform to buildings as constructed and to fit work of other trades, or to conform to rules of all governing authorities and regulations, shall be met by each contractor without extra cost to the owner.

C. Design Build contractors shall prepare design documents stamped by a professional

engineer registered in the State of Jurisdiction. All design costs and drawing costs are to be included by the mechanical contractor. Drawings shall be fully coordinated with all other aspects of construction.

1. The documents will be prepared with software compatible with the architect and

will be issued to the architect at the architect’s schedule in electronic form.

2. Construction design documents prepared by the contractors shall include a complete depiction of the systems along with schedules and details.

3. After project completion, an as�built document will be issued to the architect in electronic form and in printed form.

11.3 Quality Assurance

A. Qualifications of contractor: All materials and equipment shall be new and all work shall be executed with the maximum speed consistent with current accepted trade practices. The contractor is to furnish materials and equipment promptly after authorization to proceed, and proceed with work in progress with the other contractors, if any, on the project. The contractor is to perform all work included in the contract in a manner that will not cause interferences or delays to, or interfere with, the progress of other contractors.

B. Workmanship shall be of the best quality with good appearance of finished work of equal

importance as its mechanical efficiency.

1. No makeshift work shall be permitted anywhere; and all portions of work shall be laid out and installed such that as a whole is of uniform quality and appearance. Cracked, damaged or otherwise defective material shall not be installed.

Page 30: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 30

11.4 General Materials

A. Use only new materials, of the best quality of their respective kinds.

11.5 Access Panels

A. Access panels, in walls or ceilings, required for access and maintenance (i.e., automatic or manual damper, fire or smoke damper, coil or control instrument mounted in a duct or pipe, etc.) shall be provided by the respective contractor. Access panels are not required in areas where the ceiling system is lay�in tile; however, sufficient space must be available in and through the ceiling system to allow maintenance and adjustment of dampers, and cleaning of coils as necessary, or a suitable access panel shall be provided for that purpose. Access panels shall be approximately 15�inches by 18�inches wherever possible and shall be provided with flush trim and an allenkey operated camlock fastener.

11.6 Instruction of Owner’s Designated Personnel

A. Contractor will facilitate two (2), eight�hour sessions, one week apart, for instructional periods with the owner’s designated representative. Contractor shall video tape all appropriate portions of training sessions for owner’s future reference.

11.7 Operation and Maintenance Manuals

A. Upon completion of the work, provide the Owner with two (2) copies of electronic/CD’s, and two (2) copies of a hardbound operating manual for all equipment furnished and installed under this work. The manual shall, however, first be approved by the architect/engineer.

B. The manual shall include manufacturer’s lubricating and operating/repair instructions,

parts list and serial numbers for all operating machinery; including drive information, and motor horsepower, amperage, and voltage readings on all phases.

11.8 Final Acceptance

A. When the work, testing, balancing, initial start�up and operation instructions have been completed, contractor will notify architect and arrange for final acceptance.

B. Contractor shall have all necessary test data complete in accordance with specifications and at hand during inspection.

C. Items found to be not in accordance with Contract Documents or items functioning incorrectly will be itemized and submitted in writing to contractor for correction.

D. Contractor shall obtain and turn over to the architect / engineer all certificates of inspection and approval from all city and state authorities having jurisdiction.

11.9 Warranty

A. Contractor, by accepting the plans and specification and signing the contract, will guarantee the following:

1. All equipment, accessories and material furnished by him, for a period of one year from final acceptance, against all defects in material and workmanship.

2. If equipment fails, does not operate satisfactorily or shows undue wear, contractor will be notified and will be required to remedy the defect immediately at his own expense.

B. Warranty shall extend for one (1) year from date of acceptance by the owner except where items of equipment, etc., are guaranteed by manufacturer for periods in excess of this time, manufacturer’s guarantee shall take preference.

Page 31: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 31

C. Provide owner with an individual summary of all warranties and associated timeframes.

PART 12: PROJECT CLOSEOUT PROCEDURES NARRATIVE

12.1 Project Closeout Procedures Narrative

a. Energy Management System/ Controls – Supplier and installation contractor will confirm in writing to the owner upon completion of the installation and before the date of building turn�over, the system installed has been correctly integrated with other building systems, meets the designed specifications and the designed operating specifications and is operating under these specifications as well as adequately marking, labeling and identifying wire and components. The installation contractor is responsible for coordinating operational training with building owner.

b. Commissioning � Please provide pricing for Commissioning specific to the base building mechanical systems along with their integration of the BAS system.

c. HVAC� Rooftop/ Air Handling Equipment – Supplier and installation contractor will confirm in writing to the owner upon completion of the installation and before the date of building turn�over, the unit(s) installed have been correctly integrated with other building systems, meets the designed specifications and the designed operating specifications and are operating under these specifications as well as adequately marking, labeling and identifying equipment and components. A final operational check and filter change are required prior to building turn�over. The installation contractor is responsible for coordinating operational training with building owner.

d. Elevators – Supplier and installation contractor will confirm in writing to the owner upon completion of the installation and before the date of building turn�over, the unit(s) installed is correctly integrated with other building systems, meets the designed specifications and the designed operating specifications and are operating under these specifications. The installation contractor is responsible for coordinating operational training with building owner.

e. Fire/ Life Safety Systems – Supplier and installation contractor will confirm in writing to the owner upon completion of the installation and before the date of building turn�over, the equipment and systems installed are correctly integrated with other building systems, meets the designed specifications and the designed operating specifications and is operating under these specifications as well as adequately marking, labeling and identifying wire and components. The installation contractor is responsible for coordinating operational training with building owner.

Page 32: Core & Shell Outline Design Narrative - NuHealth...The main entry lobby will have an “upgraded” style finish: tile flooring, tile or wood base, vinyl wall covering, gypsum board

FRAUENSHUH HEALTHCARE REAL ESTATE SOLUTIONS 7101 WEST 78TH STREET, SUITE 100 MINNEAPOLIS, MN 952-829-3480 MAIN

Page 32

f. Exhaust Systems – Supplier and installation contractor will confirm in writing to the owner upon completion of the installation and before the date of building turn�over, the unit(s) and equipment installed are correctly integrated with other building systems, meets the designed specifications and the designed operating specifications and is operating under these specifications as well as adequately marking and labeling equipment. The installation contractor is responsible for coordinating operational training with building owner.

g. Metering – The electrical or mechanical contractor will confirm in written form that all meters that were to be installed have been prior to building turn�over and that they are tied into the Energy Management System and the proper commissioning has taken place to ensure accurate calculation of usage. The installation contractor is responsible for coordinating operational training with building owner.

h. Electrical Systems – Electrical contractor will provide adequate training and documentation to building Owner on sequence of operation and operating procedures for components not limited to, but including electronic transfer switches, generators, emergency power inverters, lighting controls, etc.

*The general contractor shall ultimately be responsible for the proper integration between various building systems and collaboration of said installation vendors as well as normal design operation of building systems. The general contractor shall confirm in written form to the building owner. The general contractor shall provide a dedicated, full warranty schedule separate from the “Operation and Maintenance” manual. Please include the following allowances within your preliminary estimate:

Furniture $20,000.00

Artwork $5,000.00

Signage

Exterior $20,000.00

Interior Included in estimate

Mailboxes $5,000.00

Landscaping & Irrigation $20,000.00

Security/Card Access Included in estimate

Digital Directory $10,000.00


Recommended