www.coromandel.biz1
Coromandel – Visakhapatnam – At a Glance
Commissioned in 1967
1.0 / 0.185 / 0.6 / 0.025 MMTPA Complex
Fertiliser / Phos Acid / Sulf Acid /
Speciality Nutrients Plants respectively
5 MW Turbo Generator from Waste Steam
20 LIGPD Max Water from Tatipudi &
Meghadrigedda Reservoirs
Connected Load 14.3 MVA
Energy cost 2.19% of Mfg Cost
Turnover 2496 Crore Rupees 2016-17
Employees incl Contract Tech – 1567
Brand – Gromor
An ISO9001, ISO 14001 & OHSAS 18001 Certified & PSMS Compliant Company
www.coromandel.biz2
Manufacturing Process
Sulphuric acid Plant – I
DCDA Process - 1400 MTPD
Sulphuric acid Plant – II
DCDA Process - 300 MTPD
Sulphur SulphurWater Air Water Air
Sulphuric Acid
Phosphoric acid Plant
Dihydrate Process - 600 MTPD
Water
Rock
Phosphate
By Product Gypsum
Evaporation
& Fluorine Recovery
NP/NPK
Preneutraliser & Pipe
Reactor Process
Granulation Plant
1050 MTPD x 2
1800 MTPD X 1
By Product
Hydrofluorosilicic
Acid
28-28-0
14-35-14
10-26-26
18-46-0
28% P2O5 Acid
48% P2O5 Acid
20-20-0-13
Products
Steam
Steam
Steam
Ammonia
Urea
Potash
24-24-0-8SBought out Sulf Acid
Auxillary Boiler
48 MTPH
LSHS
Diesel Generators
2 nos x 4 MW
1 nos X 6 MW
LSHS
Turbo Generator
1 nos X 5 MW
Bought out Phos Acid 20-20-0-13S
www.coromandel.biz3
Major Energy Saving Measures Implemented-2014-15
S. No Title of Project
Annual
Electrical
Saving (kWh)
Annual
Electrical
Cost Saving
(Rs million)
Investment
Made (Rs
million)
Payback
(Months)
1Modernization of 11 KV
Circuit Breakers243769 1.19 12.5 126
2
Optimization of
Mechanical design of
Plate Heat Exchanger -
Sulphuric acid Plant - I
258467 1.27 8 76
3
Optimisation of Thermal
Design of Turbo
Generator Surface
Condenser
2142857 10.5 37.25 43
4
Deployment of Low
pressure steam
Extraction from Turbo
Generator
106931 0.52 0.01 0
www.coromandel.biz4
Major Energy Saving Measures Implemented 2015-16
S.No Title of Project
Annual
Electrical
Saving
(kWh)
Annual
Savings
(million
INR)
Investment
(million
INR)
Payback
(Months)
1 LED Retrofit of HPSV Street Lighting 91265 0.49 3.11 76
2Installation of Variable Frequency
Drives on variable power loads119516 0.64 1.4 26
3Conversion of Mercury Vapor Lamps
to Metal Halide Lamps297292 1.60 8.78 66
4
Reducing precooling time by design
change in Ammonia pre-cooling
pipeline (5.2km) from wharf to AAST
17600 0.09 10.58 -
5
Separation of variable and
common lighting loads in
Bagging Plant
35186 0.19 0.1 6
6Replacement of old rewound motors
by modern energy efficient motors150912 0.81 6.7 99
7
Stoppage of Building air-
conditioning power loads during
night time in winter season
70000 0.38 0.01 1
www.coromandel.biz5
Major Energy Saving Measures Implemented 2015-16
S.No Title of Project
Annual
Electrical
Saving
(kWh)
Annual
Savings
(million
INR)
Investment
(million
INR)
Payback
(Months)
8
Power Tie up with Rain CII Carbon
(Vizag) Ltd for avoiding high cost
fuel oil fired diesel generator power
0 0.51 0.05 1
9Renewable Energy Power Tie up
with Sagar Power Limited0 1.19 0.05 1
10Optimization of HP steam
consumption in Dryer of C Train1838994 9.90 0.1 1
11Integrated pumping system for
effluent recovery in AB Trains72000 0.39 0.2 6
12
Independent pumping system,
for effluent recovery in
Phosphoric acid plant
24143 0.13 0.1 9
13Combining multiple Conveyors
in Bagging Plant29700 0.16 0.1 8
14Reduction of Instrument Air piping
system pressure drop127334 0.69 0.2 4
www.coromandel.biz6
S.No Title of Project
Annual
Electrical
Saving
(kWh)
Annual
Savings
(million
INR)
Investment
(million
INR)
Payback
(Months)
1Higher Capacity SAP Economizer
System4942000 26.1 89 41
2
Reducing the catalyst striking
temperature at 410 deg C in SAP1853250 9.6 - -
3
Reducing ETP Operations in
Acid Plant by implementing best
water balancing practices
113933 0.60 0 -
4
Installing sieve tray condenser
in PAP evaporation section
thereby stopping a 75KW
vacuum pump
483883 2.08 0.5 3
5Installation of New Turbo
Generator Stator60922 0.32 34.2 -
6Installed Steam Driven Ejector
for Open pit dewatering1980 0.01 0.005 6
Major Energy Saving Measures Implemented 2016-17
www.coromandel.biz7
Major Energy Saving Measures Committed
S No Title of Project Year Status
1 Higher Capacity SAP – I Economiser System 2016-2017 Implemented
2 Installation of New Turbo Generator Stator 2016-2017 Implemented
3 Installed Steam Driven Ejector for Open pit dewatering 2016-2017 Implemented
S No Title of Project Year
Annual
Electrical
Saving
kWh
Annual
Thermal
Saving
million kcal
Status
1 Sieve Tray Condenser 2017-18 540000 Implemented
2
Supply Chain – Install 30000 MT
Rock Phosphate storage godown &
avoid diesel fuel oil consumption due
to multiple handling
2017-18 1078Under
construction
3
Supply Chain – Deploy 28 MT
capacity trucks replacing 17 MT
trucks for Sulphuric acid transport &
avoid diesel consumption due to
multiple handling
2017-18 458 Implemented
4 Install Variable frequency drive 2017-18 23900 1078Under
proposal
5 Modernised lighting 2017-18 332412 In progress
www.coromandel.biz8
Road map for energy conservationParameters 2017-18 2018-19 2019-20
Capacity utilisation
100% 105% 110%
Widen base raw material
Establish usage of alternative raw materials
Maximise production run with alternative raw materials
Sustain the improvements
Minimize Unplanned downtime
17% 15% 14%
Encon projects
1) Install sieve tray condenser
2) Install variable frequency drives
3) Supply chain - Install 30000 MT Raw material godown & avoid material handling diesel costs due to multiple handling
4) Supply chain - Deployment of higher capacity trucks for Sulfuric acid transportation
5) Modernise lighting
1) Conversion to energy efficient lighting
2) Replace age old motors by energy efficient motors
3) Install Sulf acid tanks at wharf & transfer via pipeline thereby avoid material handling diesel costs
Incorporate energy efficient plant layout in plant expansion
Monitoring & Reporting
Blueprint of automation
Energy Consumption tracking via INSIS
Centralization of process plant control monitoring & reporting through DCS
Sustain the improvement
www.coromandel.biz9
% Capacity Utilisation
0%
50%
100%
150%
% U
tilisati
on
% Cap Utilisation 82% 88% 90% 88% 100% 105% 110%
Capacity 100% 100% 100% 100% 100% 100% 100%
2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20
% Rock Phosphate utilisation
0%
20%
40%
60%
80%%
Uti
lisati
on
Hi grade 54% 60% 67% 51% 36% 35% 35%
Low grade 46% 40% 33% 49% 64% 65% 65%
2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20
Machine Downtime % Breakdown
0%
10%
20%
30%
40%
% D
ow
nti
me
% Unplanned BD 29% 19% 19% 17% 17% 15% 14%
2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20
Roadmap on Strategy
• Reduce unplanned stoppages by improving equipment reliability
• Under Long Term Strategy, we operate various sources of rock phosphates (Low & medium grades)
www.coromandel.biz10
Excellence in Energy ManagementParameters
2013 -2014
2014 -2015
2015 -2016
2016 -2017
Annual Electrical Energy Consumption million kWh 85 86 93 90
Annual Cost of Electricity Consumed million INR 336 406 393 379
Annual Consumption of Fuel LSHS Metric Ton 501 426 452 484
Annual Consumption of Fuel Light Diesel Oil Kilo Litres 1.5 2.3
Annual Consumption of Kerosene oil (SKO) Kilo Litres 86 71 87 54
Annual Total Cost of Fuel million INR 31 24 19 18
Thermal Energy Consumption million kcal / Year 5716 4840 5217 5250
Production MT 862795 921592 949236 925056
Specific Electrical Energy Consumption , kWh / Ton of production 99.00 93.08 97.72 97.0
Specific Thermal Energy Consumption, kJ / kg of Production 27.74 21.99 23.01 23.76
13
13.5
14
14.5
15
15.5
16
16.5
Sp Power Consumption, KWh / MT - SAP - I
KWh/MT 16.1 14.2 14.3
2014-15 2015-16 2016-1770
75
80
85
90
95
Sp Power Consumption, KWh / MT - Evap acid
KWh/MT 92.6 88.2 80.3
2014-15 2015-16 2016-1735
35.5
36
36.5
37
37.5
Sp Power Consumption, KWh / MT - Complex
KWh/MT 37.1 36.7 35.8
2014-15 2015-16 2016-17
www.coromandel.biz11
Unit wise Power consumption & Operation trends
Imported Vs Evap Acid, MT
20000
40000
60000
80000
100000
0%
10%
20%
30%
40%
Evap Acid 59975 53131 73011 80134
Imported 55754 79820 58908 56655
% Imported 27% 35% 26% 26%
2014-15 2015-16 2016-17 2017-18
% Consumption on overall Power consumed
SAP-1, 8%SAP-2, 8%
PAP, 37%
Complex A,
15%
Complex B,
13%
Complex C,
19%
• PAP (Phosphoric Acid Plant contributes 37% on the total power consumption
• Captive generation of Acid increasing against reducing imports which consumes additional power
www.coromandel.biz12
Energy Benchmarking- Detailed Roadmap
Parameter BenchmarkActuals 2016-
17Action Plan Target
Phosphoric acid (kWh/MT P2O5)
150 161
Improve the evaporation efficiency by 6th
Evaporator2017-18
Capacity enhancement of PA Plant thereby improve the SEC
2019-20
Complex (kWh/MT) 32 36
Increase Capacity utilisation of Complex A & B train by 30%
2017-18
Overall Unit (kWh/MT Complex) 93 97.4
Maximising capacity utilisation & improve onstream hours of all units
2017-18
As we are an integrated manufacturing facility, Plant units’ capacity, products vary from industry to industry hence benchmark not comparable with other manufacturing units
www.coromandel.biz14
Innovation Project- SAP Economizer system
Brief Description: Replacement of old economizers by higher capacity economizers, cooling Inter Absorption tower inlet gases up to 165 degC from earlier 200 degC.
Type of Innovation – New concept
(risks taken/self driven/beyond OEM)
New EconomizersOld Economizers
Increased surface area & Duct redesigning
Trend of Gas Temperature before & after modification
0
50
100
150
200
250
300
6.Feb 12.Feb 18.Feb 24.Feb 6.May 12.May18.May24.MayBefore & After SD
Gas T
em
pera
ture
Inlet temperature
Outlet TemperatureBefore After
Trend of Gas Temperature before & after modification
0.0
100.0
200.0
300.0
400.0
500.0
6.Feb 12.Feb 18.Feb 24.Feb 6.May 12.May18.May24.May
Before & After SD
Gas T
em
pera
ture
Eco II inlet
Outlet Temperature
BeforeAfter
SAP-1 Economizer-1 SAP-1 Economizer-2
www.coromandel.biz15
Cost Benefit Analysis:
Specific Steam Generation
1.04
1.08
1.18
1.21
1.171.19 1.19
1.20
0.95
1.00
1.05
1.10
1.15
1.20
1.25
2014-15 2015-16 2016-17 2017-18
MT st
eam
/MT
of H
2SO4
SAP 1
SAP 2
Benefits:
• Additional Turbo Power generation
from additional steam generated
• Reduction in heat lost to cooling
tower & water makeup
• Acid coolers cooling water outlet
temperature limited to 50oC max
minimizing water side scaling
InvestmentRs. 891 Lakhs INR
Annual Power saving 4941603 KWH
Annual savingsRs. 261 Lakhs INR
Pay Back 41 Months
Innovation Project- SAP Economizer system
www.coromandel.biz16
Weak
washReturn
acid
Product
TankProductWASH
TANK
WASH
WATER
ETP Operations
Spillages &
waste water
Clean water
separation via
sumps
Separation of low quality
water in ETP storage
&treat
Reuse back to
the Process
Shutdown water
due to non-
operations
Innovation Project- ETP Operations Optimization
www.coromandel.biz17
Innovation Project- ETP Operations Optimization
Type of Innovation : Elimination/Substitution of an activity by making
changes in the process
Brief Description: Effluent Treatment Plant (ETP) operates with the
effluent generated from the process, during maintenance, scrubbing &
breakdowns.
The treated water is taken back to the process
Break through Innovation:
The generation of effluent was identified to be inversely proportional
to the operating hours of the plant. Also at higher utilization of the plant,
system requires more water due to the process conditions.
Operations team brainstormed & worked on this phenomena &
analyzed the complete water balance of the process, arrived at conclusions
on reducing the power consumption from ETP sector by reducing its
operating hours.
www.coromandel.biz18
Innovation Project- ETP Operations Optimization
Steps taken:
1. Consistent operation of plant above
85% of the max load always
2. Segregation of effluent based on its
impurities
3. Reuse into the process as per the
quality of water
Benefits:
1. Lesser operation of ETP plant thereby saving power (as illustrated
above)
2. Reduced water consumption due to reuse of the process water
www.coromandel.biz19
Innovation Project- Evaporator operations
Type of Innovation – Elimination/Substitution of an activity by making
changes in the process
Brief Description of Process: Strong Phosphoric acid is produced from
the Evaporators by evaporating the water from the weak phosphoric acid
produced from the process & enriching its concentration from 26% to 48%
levels. Evaporation is by process of heat through Heat exchangers &
steam under Vacuum
Break through Innovation:
The overall power consumption of the unit PMT of complex was
identified to be increasing based on captive generation of Phosphoric acid
(Strong Acid). Team was focusing on reducing the power consumption
from the Evaporator sector by either increasing the throughput or by
reducing the operation of equipment or both.
Benchmarking was one of the tool used to identify the gap where
team worked on reducing the power consumed in the vacuum section by
redesigning the vacuum pump to Sieve tray condensor model.
www.coromandel.biz20
Innovation Project- Evaporator operations
Description of Change– Earlier the
vacuum pump (75 KW motor driven) was
used to apply vacuum in the condenser.
Instead of normal open condenser, sieve
tray has been installed in the condenser to
give additional surface area for the vapors
to condense.
Benefits:
Elimination of one vacuum pump thereby
reducing the energy consumption by 5.4
Lakh KWhr
Investment:
Negligible(as in-house fabricated sieve tray
installed)
Cold
Well
HOTWELL
1 2
Vacuum
Pump-
600mm
Hg Abs
3
Cold
Well
HOTWELL
1 2
Strong
Acid
Strong
Acid
No
Vacuum
Pump-
600mm
Hg Abs
3
BEFORE
AFTER
1. Flash Chamber
2. Heat Exchanger
3. Condensor
4. Condensor
5. Sieve Tray Condensor
www.coromandel.biz21
Carbon Emission Reductions
Scope Emission Sources Considered
Scope 1 Emissions
LSHS Fuel of for process heating, Diesel for Power Generation, Kerosene oil for furnace firing, Diesel for company owned internal transport & LPG for Ammonia
Tank flare stack
Scope 2 Emissions
Bought out Electrical Power
Scope 3 Emissions
Employees commuting and Business travel
Year Scope 1
emissions
Scope 2
emissions
Scope 3
emissions
Total % Reduction in
emission
CO2e (MT) CO2e (MT) CO2e (MT) CO2e
MT *
intensity since
baseline year
study
2013-14 2287 51777 3177 57241 Baseline year
2014-15 1870 58571 3177 63618 -11.14%
2015-16 1902 54991 3177 60070 -4.94%
2016-17 1915 51494 3221 56630 1.07%
www.coromandel.biz22
Efficiency Improvement & GHG reduction
Rock Efficiency & Rock / MT P2O5
93%
94%
94%
95%
95%
3.05
3.1
3.15
3.2
3.25
3.3
Rock Efficiency 93.63% 94.74% 94.60%
Rock / MT P2O5 3.26 3.17 3.15
2014-15 2015-16 2016-17
Complex P2O5 Efficiency & P2O5 Bought out
reduction / MT P2O5
97%
97%
98%
98%
99%
99%
1
1.01
1.02
1.03
1.04
P2O5 Efficiency 97.25% 97.37% 98.60%
P2O5 / MT P2O5 1.03 1.03 1.01
2014-15 2015-16 2016-17
Phosphoric Acid Plant:
Improved efficiency of the process
thereby reducing the raw materials
purchased & the carbon footprint
Complex Plant:
Improved efficiency of the process
thereby reducing the raw materials
purchased & the carbon footprint
Corporate level Mfg. Plant LevelMCM Review | Operational Review BEST | Core Committee | Process
Facilitation, Resource, R&R Deployment, R&R, Cutomization
23
5S Visual Factory – Management by walk around
IdeaTap creative potential of employees
kaizenSimple why-why Analysis
SGAProblem solving - 7QC Tools
LSSLean & SQC Tools
InnovationEntrepreneurship
Focus AreasCommunication
Outcomes of
• Internal
Performance
levels
• Operational
Imperatives
• Market
Feedbacks
• Sense of
purpose visit
• Service Level
Agreements
Total Employee Involvement (TEI)
Employee Empowerment : Structural | Informational | Knowledge
Training | Hands-on exp. | OPLs | TQM – How to Guide | Best Practices sharing platforms
Mgmt .
Review
Breakthrough
Incremental
Small
Continual Improvement
in PQDCSM
Continual Improvement
TQM FrameworkBuilding Culture of Excellence
“Company-wide integrated & quantitative continual improvement of processes, products and services with total empowered employee involvement and aiming at stakeholders’ delight to help improve business results”
www.coromandel.biz24
Employee Involvement
85%
90%
95%
100%
Employee Involvement
Overall 93.78% 100.00% 100.00%
NM 90.40% 100% 100%
Target 100% 100% 100%
2014-15 2015-16 2016-17
82%
84%
86%
88%
90%
92%
%TQM Score Card Achieved
Actual 87.40% 89.20% 90.30%
Target 85% 85% 85%
2014-15 2015-16 2016-17
0
100
200
300
400
TQM Projects Implemented
SGA & Six Sigma 15 18 20
Kaizen 300 305 310
Ideas 61 56 50
2014-15 2015-16 2016-17
0%
1000%
2000%
3000%
4000%
Energy Related Projects
No of Projects 25 30 40
2014-15 2015-16 2016-17
www.coromandel.biz25
Employee InvolvementDescription Project - 1 Project - 2 Project - 3 Project - 4 Project - 5
Source of En-Con Idea Workmen Engineer Middle Management Senior Management Top Management
Name of the Project
Stoppage of Building airconditioning power loads during night time in winter season
Installation of Variable Frequency Drives on variable power loads
Install Sieve Tray Condenser
Power Tie up with Sagar Power Ltd for renewable Hydro power for avoiding high cost fuel oil fired diesel generator power
Installation of Higher Capacity Economiser
Idea Originated in Year 2015 2015 2016 2015 2015
Whether Idea
ImplementedYes Yes Yes Yes Yes
Details of Members in
the Implementation
Team / Core Group
(Nos, & Designation)
Small Group consisting of Plant Technicians - 5 Members
Small Group consisting of Managers, Supervisors and Plant Technicians - 5 Members
5 member team comprising Sr Manager Tech Services, Manager Operations, Manager Maintenance & Technicians
5 member P & I Team comprising GM - P& I, DGM Finance, Manager - Power, DGM - Legal
5 member Senior Management Team comprising Unit Head, AVP, Sr GM P & I, Asst GM Projects & Sr Mgr Tech Services
Expected or Actual
Date of ImplementationApr-2015 Apr-2015 Mar-2017 Apr-2015 Apr-2016
Constraints
encountered during
implementation of idea
Locations of equipment far & wide. Regular visit during night times for checking requirement of air conditioning very low
Replacement requires shutdown of plant
Lack of knowledge on working of Sieve Tray Condenser
Lack of Knowledge on Trade terms to plant teams
Allocation of funds, Lack of techno commercial talent in implementation team
Methodology adopted
to overcome the
constraints
Routine checks on individual equipment performance being practiced
Replaced during planned shutdown
Sharing of Literature
Technical & Legal team Inter department Knowledge sharing
Estimation of replacement, Knowledge sharing, Selection of experienced fabricator
www.coromandel.biz26
Team workOPERATIONS IMPROVEMENT TEAM
Managing
Director
Executive Vice President &
Head - Manufacturing
Vice President -
Manufacturing
Sr Manager
Tech Services
Associate Vice President
Operations
Sr GM
EngineeringSr GM – Power,
Inst. & Projects
Asst GM Safety
& Environment
Section Heads
Process Plants &
Facilities
Section Heads
Engineering Units
Dy GM – Process
Plant Operations
Dy GM –Bagging &
product handlingGM –E & I
DGM / AGM –
Mech Maintenance
www.coromandel.biz27
Employee Team work Monitoring & Reporting format
TQM Score Card 2016-17 as on Mar-17 end
S No.Simpli5
MeasureTarge
tWeight
age Actual ScoreWeighted
Score
15S external audit score (Target: score of lowest scoring zone)
Score (1K points)
600 5 620 100 5
Klic 15
1 Kaizens implemented No./Emp 1 9 0.54 54 5
Sparks 15
1 Overall Ideas implemented in a yearNo./NM Emp
0.5 2 0.14 28 1
2 No Of Ideas received No./Emp 3 2 3.05 100 2
Small Group Activity 10
1No. of projects completed before Dec-16 No.
15 6 15 100 6
2 Avg cycle time of projects completion Months 6 2 6.00 100 2
Six Sigma
1 No. of projects completed by Mar 2016 No. 5 5 5 100 5
Take One
1 One Point learning Implemented No / Emp 1.5 7 1.51 100 7
Overall
Employee Involvement % 100 8 100 100 8
Reward & Recognition % 40 8 41.12 100 8
Employee given training % 90 6 90.25 100 6
Others 45
Total Score 100 90.3
www.coromandel.biz28
Management Certifications
Management system Certification Valid Up to
Environmental Management system
ISO 14001:2004 28/Jul/2018
Occupation Health & Safety
OHSAS 18001:2007 28/Jul/2018
Quality Management System
ISO 9001:2008 28/Jul/2018
Process Safety Management
Process Safety Management System
Level 4 / 4
Training ISO 10015+:1999
We have initiated implementation of ISO 50001 in 2017-18
www.coromandel.biz29
Investment in Encon
2014-15 2015-16 2016-17
Investment in Encon Rs Crore
6 4 12
Turnover Rs Crore 2759 2871 2496
% Investment for Encon on Turnover
0.20% 0.13% 0.49%
Savings Rs Million 14 18 26
0
5
10
15
20
25
30
Encon Savings Rs Million
Savings Rs Million 14 18 26
2014-15 2015-16 2016-17
0
2
4
6
8
10
12
Encon Investment Rs Million
Investment Rs
Million
6 4 12
2014-15 2015-16 2016-17
0.00%
0.10%
0.20%
0.30%
0.40%
0.50%
% Investment for Encon on Turnover
% Investment on
Turnover
0.20% 0.13% 0.49%
2014-15 2015-16 2016-17
www.coromandel.biz30
Energy Monitoring & ReportingHourly Monthly
Online Plant DCS & SCADA Report Monthly Plant Performance Report
By Engineers & Managers of Operations & Technical Services
By Top Management
Power variable cost – Rs 5.29/kWh; Fuel – Rs 3003/million kcal
www.coromandel.biz31
Energy Monitoring - Steam / Condensate Balance
All figure in MT/HR
Air Blower
Turbine37
4 Vent
1
27 15
30 0.5 0.5 0 9.5 2 HP to LP 0.5
make up
5 MW
Turbo
Generator Vent
37 30 0 9.5 0 1
0.5 0.5 0.5 1 25 0.5
6 0.5 0.75 0.75
21 21 77 0.75 0.75
Process / Losses 1
Condensate Header
SAP-I WHB
HP generation
68 MT
HP steam Header 32 ata ,350 0 C
Melters &
jacketing
SAP-II WHB
HP generation
15 MT
DM Water
Make up
LP steam Header 3.0 ata , Saturated
Sulphuric Acid Plants- Waste Heat Steam Generation Units
Water Soluble
Fertiliser Plant
Dearator
Fuel Oil
Heater&
Tracing
Vapour
Absorption
Refrigiration
AAST
Ammonia
Heater
Granulation
Plant
Air Preheaters
Sulphur
Bentonite
Plant
Complex Plant
Sparging /
Flushing
Bagging
Air
Handling
CafeteriaWork
shop
Turbo Power
Generation
Complex
Sulphur Pit
Insulation &
Trap Losses
Evaporated
Phos acid
Complex
dedusting
www.coromandel.biz32
Encon Implementation Methodology
Mapping Energy
Consumption
External Energy Audits
Best Practices / Benchmarks
New Technologies
Training
Targets
Achieved
Daily review by HoD’s & Unit
Head & through Daily Prodn
report & Daily Energy Balance
Monthly review by Executive
Vice President & MD through
conversion cost report
No
Identify Thermal &
Power Energy Losses
Formulation of Encon
Projects
Prioritisation of Encon
Projects
Implementation
Check & Reviews
Reward & Recognition
Horizontal Deployment
Updation of Knowledge Management Portal
Training
Yes
www.coromandel.biz33
Environment - Renewable Energy Utilisation
Renewable energy certificates purchase:
Solar – 0.25% of purchased power
Non Solar – 4.75% of purchased power
Renewable Energy Tie-up: Coromandel International Ltd entering into a renewable
energy tie up for around 20 Lakh KWH per annum with Mini Hydel Plant for
meeting its renewable energy obligations
Replacement of
Electrical Energy with
Renewable Energy
Installed
Capacity
Annual
Energy
Generated in
2014-15
%
Share
Annual
Energy
Generate
d in 2015-
16
%
Share
Annual
Energy
Generate
d in
2016-17
%
Share
(Million kWh) (Million
kWh)
(Million
kWh)
Solar Photovoltaic (PV) 0 34000 0.04% 40000 0.04% 39006 0.04%
Small Hydro Plant 0 0 0 871179 0.94% 116802 0.13%
Others 0 641000 0.75% 0 0.00% 606263 0.68%
www.coromandel.biz34
Raising Public awareness
Showing consumers the many ways to conserve energy & water and congratulates them on their energy &
water saving efforts
Reporting to all consumers budgeted and actual monthly / periodic specific energy & water consumptions
Encouraging all plant workmen in generating ideas for energy & water conservation and providing
necessary human and financial resources for effective implementation
An idea mela is conducted once in a year and all plant personnel are encouraged to put up their water and
energy conservation ideas.
Sharing knowledge on need to conserve energy & water through handouts, booklets etc in plant,
residential colony and local community
6. Knowledge dissemination to all on a. Where our energy / water comes from; b. How we are utilizing
c. The value of energy & water; d. How much we actually need and how much has gone wasted
e. Necessity to conserve energy & water
World Environment Day Cycling Simhachalam to shirdi
spreading environment awarenesss
World Water day – Walkathon on the beach
www.coromandel.biz35
Utilisation of waste heat-Turbo Power Generation
The heat from the Sulphur Gases after melting is recovered as steam energy, which is used for driving the turbine of SAP blower & Power generation in TG. The remaining steam is reused in process.
Various initiatives been taken to improve the TG performances on availability & full utilisation.
The graph shows significant reduction in the Power consumption from the GRID, contributed by the TG performance & Power
0
200
400
600
800
TG Vs GRID Power, Lakh kWh
TG 150 265 277
GRID 715 671 628
2014-15 2015-16 2016-17
55
60
65
70
75
Grid Power withdrawal trend
Grid Power
KWH/MT of
Complex
74 66 64
2014-15 2015-16 2016-17
www.coromandel.biz36
Green Supply Chain Management
a.Projects
ImplementedProjects Evaluated
We take up green purchase initiatives in all dealings with vendors
1) Constructed Temporary sheds to store product & avoid plant stoppage
b.Supplier
EvaluationSuppliers evaluated based on
1) fuel efficiency of transport
2) Lowest cost
c.Benefits
AchievedBenefits Achieved
1) Lower cost of product
2) Lower specific energy consumption
3) Support to our industry from all stake holders
d. Replication Improvements achieved are replicated at all sister locations within the
business group
www.coromandel.biz37
AccoladesAward Awarded By Year
SAFETY & ENVIRONMENT
“One of the Top 10 Greenest Companies in India” TERI & Business Today 2001
Safety, Health & Environment Performance Award CII - SR 2003, 2004
Environment Protection Award FAI 1996, 2009
5 Star Rating British Safety Council 1999, 2011
Safety Award National Safety Council 1998
WATER & ENERGY CONSERVATION
Excellence in Energy Conservation & Management CII 2000,2001,2002,2014,2015,2016,2017
Certificate of Merit BEE 2002-03, 2003-04, 2005-06 & 2006-07, 2011-12
Excellence in Energy Conservation NREDCAP – Govt of AP 2009-10,2011-12,2012-13
Excellence in Energy Conservation AP Productivity council 2006-07
Excellence in Water Management CII 2009-10, 2010-11, 2011-12
PRODUCTION
Best overall performance of Fertiliser Plant FAI 1994-95
Best Operating Phosphoric Acid Plant FAI 1994-95,1995-96,1996-97,1997-98,2000-
01,2001-02,2003-04,2004-05,2005-06,2006-
07,2009-10, 2011-12,2013-14,2014-15,2015-16
INDUSTRIAL RELATIONS
Best Management Award Labour Dept – AP Govt 2005, 2013, 2015,2016,2017
www.coromandel.biz3838
For further information please contact
Vice President - Manufacturing