+ All Categories
Home > Documents > Cost Estimate-S1 Module 3

Cost Estimate-S1 Module 3

Date post: 01-Jun-2018
Category:
Upload: herly-fajrie-hermaiita
View: 218 times
Download: 0 times
Share this document with a friend

of 16

Transcript
  • 8/9/2019 Cost Estimate-S1 Module 3

    1/16

    Cost EstimateCost EstimateModule 3Module 3

    Dr. Ari Sandhyavitri

    Engineering Faculty

    UNRI, 2004

  • 8/9/2019 Cost Estimate-S1 Module 3

    2/16

    Cost and PriceCost and Price

    Cost : cost directly attributable to an element ofwork plus overhead.

    Cost = direct costs + overhead (e.g. 5%-10%).

    Price : cost of an element of work plus allowancefor general overhead, insurance, taxes, interest

    charges, and profits (contributions).

    Price = cost estimate+ risk+ overhead+ profit+mark up/mark down.

  • 8/9/2019 Cost Estimate-S1 Module 3

    3/16

    Cost ComponentsCost Components

    Cost (Direct costcomponents):

    Labours

    Materials Equipment

    Sub-contractors

    Price (In-direct cost

    components): Taxes

    Insurances

    Overheads: Offices & adms.

    Sites

    General conditions

    Risks: Contingencies

    Loss & profit

  • 8/9/2019 Cost Estimate-S1 Module 3

    4/16

    Category of EstimationCategory of Estimation

    Abduh, 2004 summarised 4 category ofestimation:

    Order of magnitude estimation

    Budget estimation

    Defined estimation

  • 8/9/2019 Cost Estimate-S1 Module 3

    5/16

  • 8/9/2019 Cost Estimate-S1 Module 3

    6/16

    Terms of PaymentTerms of Payment

    Price based: ls and unit rate submitted by acontractor in tender.

    Cost based: cost reimbursable and target

    costs. The actual cost incurred by the

    contractor are reimbursed plus fee,

    overhead and profits.

  • 8/9/2019 Cost Estimate-S1 Module 3

    7/16

    1a. Lump Sum1a. Lump Sum

    Based on a single tendered price for thewhole works.

    Amount to pay is fixed (or subject to

    change for escalation). Paid after completion a major stage of work

    or a milestone (defined stage of progress)

    a planned payment scheme. Inflexible.

  • 8/9/2019 Cost Estimate-S1 Module 3

    8/16

    1b. Advantages and Disadvantages of Ls1b. Advantages and Disadvantages of Ls

    Advantages: High degree of certainty about the final price.

    Administration is easy.

    Keen pricing.

    The promoters mgt. resources are freed for otherprojects.

    Disadvantages:

    Unsuitable for any changes. The lowest bidder may in the loss situation (bear

    the overall financial and economic risks).

    Minimum involvement of the promoters and design

    org. in the mgt. of construction.

  • 8/9/2019 Cost Estimate-S1 Module 3

    9/16

    2a. Unit Rate2a. Unit Rate((AdmeasurementAdmeasurement))

    Bill of Quantities (BoQ) or Schedule Rates. Items of work are specified with quantities.

    Tender rates against each item of works.

    Payment : monthly or measuring quantities completed

    works or valuing the rates in the tender or new negotiatedrates.

    A scheduled of measured works or rates : total price isfixed rates but it changes if the quantities change (+/-15%).

    Separate organisation structures.

    Completed major design.

    Public sector users.

    E.g. bridges, roads, schools and urban sewerage systems.

  • 8/9/2019 Cost Estimate-S1 Module 3

    10/16

    2b. Advantages and Disadvantages of2b. Advantages and Disadvantages ofBoQBoQ

    Advantages: Widely used. Offer some degree of flexibility for design change.

    May overlap design and construction progress.

    Competitive bidders.

    Indication of final price (change is low).

    Disadvantages: Claims resolution is difficult (Quantity based).

    Limited flexibility (involvement of promoters in the mgt. and to

    add new items). Under disruption and major change emerge, the final price may not

    be determined.

  • 8/9/2019 Cost Estimate-S1 Module 3

    11/16

    3a. Cost Reimbursable3a. Cost Reimbursable Payment of actual cost + fees (for overhead and profits).

    Contractors cost account are open to the promoters (Open-bookaccounting).

    The scope and timing of works are uncertain. Almost impossible to define quantity of works and the

    programmes.

    E.g. installation of pipe works and cables, repairs, services,

    demolition, an emergency project/ rescue of disruption projects,and site clearing.

    Agreed period (terms).

    Monthly or based on an impressed account.

    Promoters pay all satisfactory accepted works (reimburse) andsome rejected works.

    Contractors technical risks are low.

    The contractors profit rate is lower than BoQ.

    Contractor is an extension of promoters organisation.

  • 8/9/2019 Cost Estimate-S1 Module 3

    12/16

    3b. Advantages and Disadvantages of3b. Advantages and Disadvantages ofCost ReimbursableCost Reimbursable

    Advantages: Extremely flexible.

    Fair pay and good control of risks.

    Promoters involvement.

    Joint planning.

    Knowledge of actual costs.

    Disadvantages :

    Little incentives to the contractors efficiency.

    No estimate of the final price at tender.

    Administration procedures are unfamiliar.

  • 8/9/2019 Cost Estimate-S1 Module 3

    13/16

    4a. Target Costs4a. Target Costs

    Promoters and contractors agreed at the start aprobable (target) costs for an uncertain scope ofwork (inadequate definition of work).

    Promoters role are significant.

    Contractors actual cost monitored andreimbursed.

    Final cost Actual cost will be shared (usingincentive mechanism).

    Fee of the contractor covers o/h and cost in thecontract (excluding profit).

  • 8/9/2019 Cost Estimate-S1 Module 3

    14/16

    AC = Actual Cost

    TC = Target cost

  • 8/9/2019 Cost Estimate-S1 Module 3

    15/16

    4b. Advantages and Disadvantages4b. Advantages and Disadvantagesof Target Costof Target Cost

    Advantages: Fair payment and control risks.

    Flexibility of design changes.

    Encourage to be efficient (common interest).

    Promoters involvement.

    Should ensure adequate resources and methods.

    Knowledge improvement.

    Disadvantages: Full promoters involvement and need to change

    attitude from BoQ contract.

    Unfamiliar administration procedures.

  • 8/9/2019 Cost Estimate-S1 Module 3

    16/16

    ReferencesReferences

    Smith, N. J. (Editor), Engineering Project

    Management, Blackwell Science, 1999,

    UK.

    Peurfoy, R, L and Oberlender, G, D, (1989),Estimating Construction Costs, McGraw-

    Hill Book Company,USA.


Recommended