Date post: | 10-Apr-2015 |
Category: |
Documents |
Upload: | pushpendraanurag17 |
View: | 529 times |
Download: | 1 times |
AAGC January 19-23, 2010
Cost Estimation & payback analysis
Towards Rain Cities -- Mainstreaming urban rainwater harvesting in cities
Module 7: Estimating cost and payback analysis
A. How to calculate the quantities and costs? B. Which is more economical storage or
recharge?C. What is the pay back period?D. Running and maintenance costsE. Parameters affecting the cost of RWH
A. How to calculate the quantities and costs?
ExcavationPlain Concrete CementMasonry (Brickwork) WallsReinforced Concrete CementCement PlasteringFilters Pipe work and manholes
Calculate separately for each item:
1. Assess topography of site
2. Level the required site area
3. Excavate required volume - Length x Breadth x Depth (m3)
Cost of excavation= Volume (m3) x rate (Rs per m3)
`
A. How to calculate quantities and costs? A1.Excavation
2.00
0.23
0.23
0.05
0.05
Note: When the required volume is 5 cu m, it means the inner area multiplied by depth
Brick wall
Hollow
A. How to calculate quantities and costs?A1. Excavation
Tank size (inner)-2 mX2 mX 2m
Volume of PCC of depth 10 cm
Length
(2+0.23+0.05+0.23+0.05)
Breadth
(2+0.23+0.05+0.23+0.05)
Height
(0.10)
2.00
0.23
0.23
0.05
0.05
0.10
A2. Plain Cement Concrete
A. How to calculate quantities and costs?
2.00
0.23
0.23
0.05
0.05
Section
Plan
`
A3. Masonry (Brickwork) WallsA. How to calculate quantities and costs?
Tank size (inner)-2 mX2 mX 2m
Volume of brick wall 23cm thick
Length
(2+0.23+2+0.23) x 2
Breadth
(0.23)
Height
(2)
2.00
0.23
0.23
0.05
0.05
Section
A3. Masonry (Brickwork) Walls
A. How to calculate quantities and costs?
Plan
Tank size (inner)-2 mX2 mX 2m
Volume
Length
(2+0.23+0.10)
Breadth
(2+0.23+0.10)
Height
(0.10)
2.00
0.23
0.23
0.05
0.05
Section
A4. Reinforced cement concrete cover slab
A. How to calculate quantities and costs?
Plan
Tank size (inner)-2 mX2 mX 2m
Volume
Length
(2)
Breadth
(2)
Thickness
(2)
Filter volume is 30 % of total volume= 0.3 x (2x2x2)
2.00
0.23
0.23
0.05
0.05
Section
A5. Filter
A. How to calculate quantities and costs?
Plan
Cost of pipe = total length (m) x unit rate
Calculate the length of interconnecting pipe
A6. Interconnecting pipe and manholes
A. How to calculate quantities and costs?
And number of collection chambers if required
Cost of chambers = total no of chambers x unit rate
B1. Storage - Ferro cement tanksApx Rs. 2/litre
5,000 6,000 7,000 9,000 10,000Total cost inrupees 12,430 12,975 13,970 14,380 15,800
Source: Action for food Production and United Nations Children's Fund,Rooftop rainw ater harvesting systems
Capacity of rooftop water harvesting system in litres
B. Which is more economical storage or recharge?
B1. Storage -PVC tanks
Brand name
Unit cost (Rs. Per
litre)Hindustan, Jindal 1.8Storex, Ganga 2.75
B. Which is more economical storage or recharge?
B1. Storage – Brick Masonry tank
Suitable for small size underground or ground storage tanksCosts anywhere between Rs 2.5-3.5 per litre (varies as per the size of tank)
B. Which is more economical storage or recharge?
B1. Storage - RCC tanks
Suitable for underground storage tanksCosts anywhere
between Rs 3-5 per litre (varies as per the size of tank)
B. Which is more economical storage or recharge?
B1. Storage - Metal tank
Very economical for smaller size tanks
Costs anywhere between Rs 1- 1.5 per litre
B. Which is more economical storage or recharge?
How to calculate costs?S.n. Item of work Quantity Unit Rate (Rs) Amount (Rs)
1 Excavation Cu.m 902 PCC Cu m 27003 Brick work (23 cm) Cu.m 2250
Brick work (10 cm) Cu.m 25004 Plastering sq m 1005 RCC slab (100 mm thk) Cu m 5500
6 Drain pipes*M 250
7Brickbats Pebbles, sand and coir packing (filter)
L.S.
8 Interconnection pipe* M 250
9 Collection Chambers Each 500
10Drilling a recharge bore (specify size and mode of drilling)
M 250 (hand)/500
Contingency charges At 10 % Rs.Total Rs.
Specifications
1. Brick work> Cement mortar (CM) 1:6
2. Half brick> CM 1:3
3. PCC> 1: 4: 8 (40 mm nominal size for footings)
4. RCC> 1:2:4 (20 mm nominal size stone aggregates)
5. Pipe 4 or 6 kg/ cm2 HDPE pipe .
6. Manhole 60 cm x 60 cm for cleaning purpose.
C. What is the pay back period?
Method of harvestingAmount of water harvestedDepends on the city where you live
pricing rainfall patternwater requirements
Age of water harvesting system (esp in recharge)
An industry in Bangalore will effect better cost saving (due to highly priced water and temporally dispersed rainfall) than an industry in Delhi
Tex corpInvestment=Rs 5.50 lakhsRecharge and storageStorage capacity of 1.2 lakh litres at a time. Water used for non potable purposes-at Delhi rate its worth ONLY Rs 1800 but Bangalore rates 7200
And the saving on TANKERSSavings Rs 70000 per year on tankersNet saving: Lets say Rs 70000Pay back period from stored water alone is 8 years
C. What is the pay back period?- Eg case study of storage in Tex Corp Ltd
JamiaInvestment=Rs 6.25 lakhsRecharge only- yield has improved in some wells (indicator water levels)-power savings not quantified but can be doneDirect benefits-saving on TANKERSRs 3 lakhs (in 2001) now reduced by one third (approx a lakh) Net saving: Lets say Rs 2 lakh per year (will depend on rainfall and water demand)Pay back period (as calculated from savings from tankers is nearly 3.5 years)
C. What is the pay back period?- Eg case study of recharge in Jamia Hamdard
Table: Comparison of water rates
minimum charges
Unit cost slab
DomesticBangalore 90 6 0 to 15 klDelhi 40 to 150 (for
6 kl)2 6 to 20 kl
Chennai 50 2.5 0 to 10 klCommercialBangalore 360 36 0 to 10 klDelhi 250 10 0 to 25 klChennai 400 (non water
intensive)/800 water intensive
35 upto 500 kl
Industrial Bangalore not specified 60 not specifiedDelhi 600 15 0 to 25 klChennai
C. What is the pay back period?How does rate of municipal supply affect pay back period?
D. Running (maintenance) costs
You need to factor in running and maintenance costs also:Cleaning and minor repairing required Replacement or cleaning of filtersFlushing of bores (mechanical or manual)
Mechanical for three hour flushing Rs 15000Manual (using hand auger labour charges)
No energy and chemical costs
D. Running (maintenance) costs
Total cost> Number of structures; type of structures Jamia Hamdard
Rs 1.25 lakhs (2005)Rs 20000 (2004)
CSE building(Rs 400) twice a year ~ less than Rs 1000 annually
Water treatment plants-Rs 2-6 per kl depending on technologySewage treatment plants-Rs 0.60 to Rs 5 per KlDesalination- Rs 50-60 per klRO Rs 30-40 per kl
D. Parameters affecting the cost of RWH1. Catchments: Type of catchments and amount of water
harvested 2. Drainage pattern: Flow direction, spreading of rainwater
pipes and flow of storm water drains3. Retrofitting / new construction4. Geology, hydrogeology and meteorological parameters5. Purpose of harvesting6. Availability of unused tanks, dry/abandoned tube wells/
open wells etc7. Material used (PVC or MS pipe)
D. Parameters affecting the cost of RWH
D1.Catchments
Cost of RWH system is generally directly proportional to area of catchmentsFor equal size of catchments, the cost of RWH system varies (increase) from unpaved runoff to paved runoff to rooftop runoff.The RWH systems when done at community level costs less.The cost of RWH systems in clean and maintained catchment’s is less
D. Parameters affecting the cost of RWHD2. Drainage pattern: flow direction
Drainage pattern plays a very important role in over all cost or RWH system.If the rainwater outlets are spread all over the place in smaller buildings, it may require more interconnecting pipe or more structures to harvest maximum runoff, hence more costlier. If site has well defined drainage it may be easier to divert rainwater into recharge structures or storage tanks without much effort, therefore costs less.
D. Parameters affecting the cost of RWH
D3. Retrofitting / new constructionIt costs more to retrofit an existing building with a RWH system.Cost can be considerably reduced if RWH system is incorporated during the planning stage.
D. Parameters affecting the cost of RWH
D4. Geology, hydrogeology and meteorological parameters
The nature of terrain directly affects the cost eg. The cost of excavation and drilling on a hard rock terrain is more expensive. Costs are generally higher where porous strata is available at lower depth. Meteorological conditions also affect cost of storage. If the intensity of rain is high, it requires larger storage and thus increases the cost.
D. Parameters affecting the cost of RWH
D5. Purpose of harvesting
If RWH is done to meet non potable requirements ----less costIf RWH is done to meet potable requirements ---- cost is more as it requires good quality water and treatment also.
D. Parameters affecting the cost of RWH
D6. Availability of unused tanks, dry/abandoned tube wells/ open wells etcUnused tank available at site can be used as storage tanks or can be converted into recharge wells….lot of cost saving.Available dry bore wells can be used for recharging purpose---saving on drilling cost of recharge bore.Dry open wells provide good opportunity and can cater to larger catchments without much investment.