Wastewater Treatment Capacity ExpansionCouncil Workshop, June 24, 2014
WWTF Expansion
Image Date: 1/15/2014
Future WWTF No. 2 Capacity2.0 MGD., Expandable to 6.0 MGD.
Existing WWTF No.1 Capacity 6.83 MGD
FDEP Requirements
62-600.405 Planning for Wastewater Facilities Expansion.
(8)(b) If the initial capacity analysis report or an update of the capacity analysis report documents that the permitted capacity will be equaled or exceeded within the next four years, the report shall include a statement, signed and sealed by an engineer registered in Florida, that plans and specifications for the necessary expansion are being prepared.
(8)(d) If the initial capacity analysis report or an update of the capacity analysis report documents that the permitted capacity will be equaled or exceeded within the next six months, the permittee shall submit to the Department an application for an operation permit for the expanded facility. The operation permit application shall be submitted no later than the submittal of the initial capacity analysis report or the update of the capacity analysis report.
City 2014 Strategic Action Plan
Strategy 1.2.2: Coordinate facility capacity upgrades to meet the City’s growth needs appropriately
Projected Flow
YearProjected Flow,
MGD2015 6.319
2016 6.528
2017 6.737
2018 6.946
2019 7.155
2020 7.403
2021 7.765
2022 8.127
2023 8.490
2024 8.852
2025 9.196
Projected using State population projections (BEBR) and historical Flow Per Residential Connection / Day
2000 2005 2010 2015 2020 20250.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
Mid Year
Flo
w (
MG
D)
WWTF No.1 Capacity
Histori-cal
Flow
ProjectedFlow
Early2018
Flow vs Capacity
CurrentFlow 6.162mgd
Future WWTF Plan
2015 2020 20250.00
2.00
4.00
6.00
8.00
10.00
12.00
Mid Year
Flo
w (
MG
D)
WWTF No.1, 6.83 MGD
WWTF No.1 + WWTF No.2 = 8.83 MGD
Projected Flow
WWTF No.2, 2.0 MGD
WWTF No.2, 2.0 MGD Expansion
Early 2024
Implementation Schedule
Review Projections and Reevaluate Construction Schedule
WWTF Expansion CIP Budget
Description2014
Budgeted2014
Forecasted2015
Budgeted2015
Revised2016
Budgeted2016
Revised2017
Budgeted 2017
Revised2018
Budgeted 2018
Revised2014-2018 Budgeted
2014-2018 Revised
Water Treatment Plant # 3 1,200,000 1,003,000 380,000 560,000 275,000 225,000 1,725,000 1,500,000 3,530,000 3,338,000
Wellfield and Wells 850,000 300,000 1,800,000 2,350,000 1,750,000 1,750,000 2,000,000 2,000,000 1,850,000 2,050,000 8,250,000 8,450,000
Water Mains 900,000 800,000 1,250,000 200,000 1,050,000 1,400,000 100,000 3,550,000 2,150,000
PEP System 400,000 450,000 400,000 600,000 400,000 850,000 400,000 900,000 400,000 950,000 2,000,000 3,750,000
Wastewater Treatment Plant #1 170,000 118,000 400,000 400,000 500,000 500,000 5,122,000 5,402,000 878,000 878,000 7,070,000 7,298,000
Force Mains 250,000 170,000 1,000,000 1,000,000 350,000 350,000 350,000 350,000 1,950,000 1,870,000
Matanzas Wood Pkwy RCW Main 600,000 600,000 1,700,000 1,700,000 2,300,000 2,300,000
Other Reclaimed Water Mains 100,000 23,000 1,250,000 1,250,000 650,000 650,000 2,000,000 1,923,000
WWTF No.2 Engr. Design & Construction 75,000 110,000 6,000,000 11,000,000 10,000,000 4,000,000 10,000,000 21,185,000
WWTF No.2 RCW Wetlands Discharge 65,000 100,000 300,000 30,000 1,700,000 1,000,000 500,000 1,300,000 2,395,000
Beachside Sewer System 367,000 1,000,000 1,000,000 1,000,000 1,367,000
Water Treatment Plant #1 500,000 500,000 500,000 500,000
Water Treatment Plant #2 9,300,000 9,300,000 650,000 650,000 9,950,000 9,950,000
General Plant R & R - Water 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 2,500,000 2,500,000
Distribution System Improvements 100,000 50,000 100,000 100,000 75,000 75,000 75,000 75,000 100,000 100,000 450,000 400,000
Matanzas Woods MPS 2,000,000 500,000 250,000 500,000 2,250,000
Other Lift Stations and Pump Stations 1,675,000 175,000 405,000 1,630,000 525,000 130,000 255,000 180,000 125,000 130,000 2,985,000 2,245,000
General Plant R & R - Wastewater 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 500,000 2,500,000 2,500,000
Miscellaneous Utility Services 31,000 31,000 44,000 194,000 64,000 64,000 114,000 114,000 45,000 45,000 298,000 448,000
Total 15,976,000 13,927,000 7,929,000 11,244,000 5,564,000 13,774,000 12,491,000 24,721,000 20,673,000 13,153,000 62,633,000 76,819,000
SRF Program
Request for Inclusion • Narrative of Project • Priority Categories • Census Tracts • Population • Cost Estimate • Priority Score • Schedule
Planning Document • Executive Summary • Cost Comparison
• 2 Alternatives • Environmental Effects/Benefits
• Evaluation of: Flora, Fauna, Endangered Species, Water Bodies, Agric. Lands,
Wetlands, & Undisturbed Areas • Selected Alternative Evaluation • Statement on Environmental Justice • Public Participation Process
• Advertise in newspaper; Discuss Alternatives; Provide Minutes • Financial Feasibility
• Dedicated Revenues to Repaying the Loan • Existing/Proposed User Charge System
• Schedule • Adopting Resolution
Agency Reviews of Planning Documents • State Clearing House • US Fish and Wildlife • 60 Day Review Period
Environmental Information Document • 30 Day comment period • DEP drafts and publishes based on information provided in the planning document
SRF Program
Readiness-to-Proceed Requirements • For loans, submit all documentation 30 days Prior to SRF Hearing Date or before June 1st. For Grants, submit all documents by June 30th. All must be deemed complete 15 days before hearing.
• Request for Inclusion • Planning Document, including environmental review
process must be complete Biddable Plans & Specs • Permits • Site Certification
Priority List Meeting • Places Project on Fundable List • Assigns a Priority Score • For grants, assigns a grant percentage • For loans, if funds are not available for all or a portion of the project, this amount goes to contingency list • For grants, if the project does not successfully compete for funds at the list adoption meeting, the sponsor may reapply the next year.
Loan/Grant Application • Must be submitted with 120 days after being placed on the fundable list • Agreement must be executed within 210 days of being placed on the fundable list
Loan Agreement • 20 year terms • Financing rate is a percentage of the market rate • The percentage is based on affordability criteria
Next Steps
July 8, 2014 Council Workshop - Presentation of proposed work order
July 15, 2014 City Council Meeting - Approval of Resolution authorizing Work Order
February/March, 2015 - Public Hearing and approval of the Capital Financing Plan
June 1, 2015 - Request for Inclusion
July 1, 2015 - DEP Hearing
July/August 2015 - Review flow projections and reassess construction schedule
Questions