COUNTY ADMINISTRATOR’S MONTHLY REPORT DECEMBER 7, 2016 BOARD OF COUNTY COMMISSIONERS MARTIN COUNTY, FLORIDA
Transcript
Page 1: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

C O U N T Y A D M I N I S T R ATO R ’ S

M O N T H LY R E P O RT

D E C E M B E R 7 , 2 0 1 6

B O A R D O F C O U N T Y C O M M I S S I O N E R S

M A R T I N C O U N T Y , F L O R I D A

Page 2: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

M O N T H LY R E P O RT DECEMBER 7, 2016

AN INTRODUCTION TO THIS REPORT

This monthly report by the County Administrator to the Board of County Commissioners provides information about the progress and successes of County activities. The report details projects by Commission District and also contains progress updates on activities of interest to all Districts and Commissioners. If you have any questions regarding this report, please direct them to the Office of the County Administrator by calling (772) 288-5677 or e-mail [email protected].

TABLE OF CONTENTS

District 1 ..........................................................................................D1-1

Florida Department of Transportation Projects ................................... D1-1

Engineering/Utilities Projects ............................................................. D1-1

Development Applications in Review .................................................. D1-2

Jensen Beach CRA Project Highlights ................................................ D1-3

Rio CRA Project Highlights .............................................................. D1-3

Upcoming Meetings & Events in District 1 ....................................... D1-4

District 2 ..........................................................................................D2-5

Florida Department of Transportation Projects ................................... D2-1

Engineering/Utilities Projects ............................................................. D2-1

Development Applications in Review .................................................. D2-2

Golden Gate CRA Project Highlights ................................................ D2-3

Upcoming Meetings & Events in District 2 ....................................... D2-4

District 3 .......................................................................................... D3-1

Florida Department of Transportation Projects ................................... D3-1

Engineering/Utilities Projects ............................................................. D3-1

Development Applications in Review .................................................. D3-1

Hobe Sound CRA Project Highlights ................................................ D3-3

Indiantown CRA Project Highlights .................................................. D3-4

Upcoming Meetings & Events in District 3 ....................................... D3-4

District 4 ..........................................................................................D4-1

Florida Department of Transportation Projects ................................... D4-1

Engineering/Utilities Projects ............................................................. D4-1

Development Applications in Review .................................................. D4-2

Port Salerno CRA Project Highlights ................................................ D4-3

Upcoming Meetings & Events in District 4 ....................................... D4-4

District 5 ..........................................................................................D5-1

Florida Department of Transportation Projects ................................... D5-1

Engineering/Utilities Projects ............................................................. D5-1

Development Applications in Review .................................................. D5-2

Old Palm City CRA Project Highlights............................................. D5-4

Upcoming Meetings & Events in District 5 ....................................... D5-4

Fiscal Year Budget Status Report .............................................. MC-1

Page 3: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR’S MONTHLY REPORT

C O M M I S S I O N D I S T R I C T

R E P O RT S

DISTR ICT 1 Honorable Doug Smith, Commissioner District 1 Includes Northeast Martin County: Hutchinson Island, Jensen Beach, North River Shores, Ocean Breeze Park, Rio, Sewall's Point and sections of the City of Stuart.

DISTRICT 1: FLORIDA DEPT. OF TRANSPORTATION PROJECTS

NE Causeway Boulevard – Sidewalk closure along the north side of NW Causeway Boulevard. Status: The sidewalk is closed through spring of 2017. Pedestrians should use the sidewalk on the south side of the roadway. Contact: FDOT, 489-7064

DISTRICT 1: ENGINEERING/UTILITIES PROJECTS AND ROAD CLOSURES

Britt Road Bridge Replacement – Removal and replacement of the bridge on Britt Road over Britt Creek. Status: Design is 98% complete. Construction is scheduled to start in spring 2017. Contact: Paul Bangs, Engineering, 288-5927 Hilltop Water Quality Improvement Project – This project consists of the design and installation of exfiltration trench in the area of NE Hilltop Street and NE Highland Avenue. This area historically experiences prolonged roadway flooding and standing water. The project will provide water quality benefits to assist the County in meeting TMDL/BMAP requirements. Status: Final design and construction plans, cost estimate, specifications and bidding documents are all complete and finalized. Contact: Greg Nolte, Engineering, 288-5927 Indian River Drive – Resurfacing of Indian River Drive from Jensen Beach Boulevard to Palmer Street. The project work will also include traffic calming and sidewalks at Ocean Breeze. Status: This project is on hold pending completion of the NE Indian River Drive stormwater quality retrofit roadway and drainage improvements project which will be going out to bid in January 2017. Contact: Ken Vreeland, Engineering, 288-5927 Jensen Park Estates – Removal and replacement of failing CMP pipes under roadways and asphalt resurfacing at replaced pipes. Status: Pipe replacement construction began on December 5 and will be completed by mid-January. Road resurfacing will be bid in December. Contact: Paul Bangs, Engineering, 288-5927

Page 4: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast concrete bridge over Warner Creek on Bayberry Lane. Status: Design is approximately 80% complete. Construction is scheduled to start in January of 2017. Contact: Paul Bangs, Engineering, 288-5927

DISTRICT 1: DEVELOPMENT APPLICATIONS IN REVIEW

Bathtub Beach – Request for minor final site plan approval to construct a restroom facility with an added space for storage of ocean rescue gear. The 24’x42’ restroom will be placed at the southwest corner of Bathtub Beach. Status: Application entered 8/26/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495 CarMax Jensen Beach – Request for major final site plan approval for a proposed CarMax automobile dealership and associated infrastructure. The subject property is located at the northwest intersection of Jensen Beach Boulevard and Main Avenue on approximately 9 acres of partially developed commercial property. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 15/15/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Jensen Dunes Residential Care Facility – Request for approval of the 2nd amendment to the PUD zoning agreement and revised master site plan and phasing plan. The 34.3-acre property is located on the north side of Cedar St. between the FEC Railroad and Savannah Rd. and south and west of the Town of Ocean Breeze. Status: Application entered 8/12/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Just Believe Recovery Center – Request for approval of a zoning district change from R-3A to Limited Commercial. The property is located on the east side of the Indian River, approximately ¼ mile north of the Jensen Beach Causeway. Status: Application entered 7/12/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495 Mulligan’s Beach House – Request for approval of a minor final site plan for proposed patio expansion and addition of a roof-top dining area. The developed subject property is approximately 1.23 acres located at the northwest corner of Jensen Beach Boulevard and Indian River Drive in the Jensen Beach CRA. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 9/21/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Savanna Key – Requesting minor final site plan approval for 8, two-story apartment units on a 1.05-acre site for a density of 7.62 units per acre. The project is located on Savanna Road north of the Savanna Animal Hospital and south and east of the Jensen Park Villas community. Status: Application entered 7/28/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Savanna Oaks – Request for an administrative amendment to the approved final site plan to extend the retaining wall to incorporate 205 lf of vinyl sheet pile at the rear of lots 1-3, 100 lf of concrete cast in place at the rear of lots 9 and 10. In addition, 145 lf of concrete block wall along the side and rear of lot 11 and 240 lf of FDOT concrete gravity wall behind lots 19-21. The subject subdivision is approximately 9.86 acres located on the west side of Savannah Road, approximately 900 feet north of Jensen Beach Boulevard. Status: Application entered 4/27/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

Page 5: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Treasure Coast Square Mall PUD – Requesting revised zoning and master site plan approval to recommission a 10,429sf space and 1,828sf space that would increase the mall's maximum square footage to 901,837sf. Also a request to amend the PUD Agreement to bifurcate all future mall and peripheral applications. Status: Application entered 1/14/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 West Jensen PUD Ph 1B – Request for approval of the 11th amendment to the PUD zoning agreement and revised master and final site plan for Phase 1B, Parcels 10.2, 17.1, 17.2 and 17.3, West Jensen PUD/DRI. The proposed change is to decrease the number of previously approved residential units from 247 units to a total of 130 single-family units. Included in this application is a request for a certificate of public facilities exemption. The 61.52 subject site is located on the east side of NW Federal Highway adjacent to the county line. Status: Application entered 3/5/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

DISTRICT 1: JENSEN BEACH CRA HIGHLIGHTS

Community Redevelopment Agency At the November 22, 2016 meeting, the Board of County Commissioners requested staff bring back several capital projects for consideration. Among the projects was the Jensen Beach Mooring Field project. Staff will be presenting information about these projects at the January 10, 2017 BOCC meeting. At this meeting, the Board also directed that staff begin the process of reconstituting the Community Redevelopment Agency as a separate body, to be comprised of each of the chairmen (or their designee) of the Neighborhood Advisory Committees (NACs). Staff was directed to prepare the appropriate ordinance to facilitate this direction, and that ordinance will be heard on December 13.

Jensen Beach Neighborhood Advisory Committee Update The existing Community Redevelopment Plan for Jensen Beach has not been updated since 2009. Changes to the Redevelopment Plan will be explored, in depth, at future advertised workshops. As requested by the Board of County Commissioners, the NAC has had ongoing discussion about the disposition of the former Jensen Beach Library Building. At the November 30 meeting the NAC requested that the Board of County Commissioners not surplus the property without first determining the condition of the building and further analysis in order to explore options for redevelopment. NAC members expressed a desire to revisit the idea of a waterfront boardwalk. The agenda also included a workshop on recommendations by Growth Management staff to correct the “glitches” in the land development code and zoning overlay in the Jensen Beach CRA.

The public is welcome to attend any meetings of the Jensen Beach Neighborhood Advisory Committee. Information on the next regular meeting is provided below under Upcoming Meetings & Events. If you have a question or need more information about the CRA program, please do not hesitate to contact the Office of Community & Strategic Partnerships at (772) 463-3253 or visit our website at www.martin.fl.us/cra, or sign up to receive agendas or announcements here and select the list Community Development/CRA.

DISTRICT 1: RIO CRA HIGHLIGHTS

Community Redevelopment Agency At the November 22, 2016 meeting, the Board of County Commissioners directed that staff begin the process of reconstituting the Community Redevelopment Agency as a separate body, to be comprised of each of the chairmen (or their designee) of the Neighborhood Advisory Committees (NACs). Staff was directed to prepare the appropriate ordinance to facilitate this direction, and that ordinance will be heard on December 13.

Page 6: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Rio Neighborhood Advisory Committee Update The Rio NAC met on November 10. The agenda included a presentation by Habitat for Humanity of a potential mixed use project being considered for the property formerly occupied by Rio Mobile Home Village. Sidewalk connection options were also discussed at the meeting. The public is welcome to attend any meetings of the Rio Neighborhood Advisory Committee. Information on the next regular meeting is provided

below under Upcoming Meetings & Events. If you have a question or need more information about the CRA program, please do not hesitate to contact the Office of Community & Strategic Partnerships at (772) 463-3253 or visit our website at www.martin.fl.us/cra, or sign up to receive agendas or announcements here and select the list Community Development/CRA. Project Updates Sewer Line Extension Plans are being developed to extend infill sewer lines to Haven Lane and Francis, Olive and Railroad Streets.

UPCOMING MEETINGS & EVENTS IN DISTRICT 1

Jensen Beach Neighborhood Advisory Committee Meeting There are two openings for members on the Jensen Beach NAC. If you are interested in becoming involved in your community’s future, please contact Donna Gordon at 221-2352. Date: Wednesday, January 4 at 5:00 pm Location: Jensen Beach Community Center, 1912 NE Jensen Beach Boulevard, Jensen Beach Contact: Community and Strategic Partnerships, 463-3253 Rio Neighborhood Advisory Committee Meeting Date: Thursday, January 19 at 6:00 pm Location: Rio Civic Center, 1255 NE Dixie Highway, Jensen Beach Contact: Community and Strategic Partnerships, 463-3253

Page 7: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

DISTR ICT 2 Honorable Ed Fielding, Commissioner

District 2 Includes: East Martin County, Stuart and East Stuart.

DISTRICT 2: FLORIDA DEPT. OF TRANSPORTATION PROJECTS

I-95 Interchange – This .745-mile project includes widening Kanner Highway (SR 76) at the I-95 interchange, reconstructing the I-95 entrance and exit ramps, drainage, milling and resurfacing, signing and pavement markings, and signalization. Construction cost is $5.79 million and completion is expected in early 2017. Status: Lanes on either direction of Kanner Highway will be closed intermittently. Contact: Terry Rauth, Engineering, 288-5927 Kanner Highway/SR 76 – 4.3 miles of Kanner Highway, from Lost River Road to south of Monterey Road, is being widened to a six-lane divided highway. Additional work on this project includes widening the bridge over the south fork of the St. Lucie River; drainage improvements, including construction of five retention ponds; guardrail improvements; signalization upgrades; and turn lane and bicycle lane improvements. Construction cost is $20.8 million and completion is expected in spring of 2019. Status: One lane in either direction of Kanner Highway may be closed weekdays from 9:00 am and 4:00 pm. Sidewalks may also experience intermittent closures. Contact: FDOT, 489-7064

DISTRICT 2: ENGINEERING/UTILITIES PROJECTS AND ROAD CLOSURES

Cove Road Resurfacing – Resurfacing of Cove Road from Kanner Highway to US 1. The project work will also include repairs of failing drainage pipes. Status: Design Survey work and engineering will start in November 2016. Construction is scheduled for October 2019. This is an FDOT grant-funded project. Contact: Paul Bangs, Engineering, 288-5927 Kindred/Johnson Sidewalks and Streetscape – City of Stuart project including sidewalks, bike lanes and streetscaping. This is an FDOT grant funded project. Status: Design is in progress. Contact: Paul Bangs, Engineering, 288-5927 SE Dixie Highway – Sidewalk and crosswalk construction along SE Dixie Highway between SE Florida Street and SE 6th Street. Status: Construction is complete. Contact: Logan Huber, 288-5932 SE Dixie Highway – Florida Power and Light is replacing 18 power poles along SE Dixie Highway between SE 5th Street and SE Cutoff Road. Status: The project is underway and is anticipated to be complete by January 18. Work will necessitate intermittent lane closures on SE Dixie Highway between 9:00 am and 3:30 pm. Contact: Jana Cox, Engineering, 288-5927

Page 8: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

DISTRICT 2: DEVELOPMENT APPLICATIONS IN REVIEW

Bayley Products Inc. – Request for a zoning change from Category “C” R-3A zoning district to a Category “A” Waterfront Resort Commercial (WRC) zoning district. Status: Application entered 2/4/14. Under review. Contact: Clyde Dulin, Principal Planner, Growth Management, 288-5495 Como Oil Distribution Facility – Request for administrative amendment approval for minor modifications to the approved final site plan and construction plans. The subject property is approximately 2.46 acres located on the east side of Commerce Avenue at the corner of Dominica Terrace in Stuart. Included in this application is a request for a certificate of public facilities exemption. Status: Application entered 6/30/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Cooke’s Plumbing and Septic Service – Submittal of a revised minor final site plan on the proposed construction of a new admin/office building to replace the existing office building and the two (2) trailers located behind the building. The existing building, trailers, and an accessory structure will be removed from the site. The improvements will also include a pumping station. Status: Application entered 10/12/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495 Glades Crossing – Request for minor final site plan approval for a single-family lot layout for 16 lots which represents a gross residential density of 1.13 units per acre. The 14.26-acre subject property is located east of SE Kanner Highway and south of SE Pomeroy Street. Status: Application entered 2/23/15. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Holt Law Enforcement Complex Medical Wing Expansion – Request for revised final site plan approval for a proposed 3,209 sf expansion of the existing medical wing of the jail facility. The subject site is located at 800 SE Monterey Road in Stuart. A request for a certificate of public facilities exemption is included with this application. Status: Application entered 6/13/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Kanner Business Park Lot 1 – Request for Request for minor final site plan approval to construct a single-story, 3,149 sf Popeye’s convenience restaurant with drive-through on Lot 1 of the Kanner Business Park commercial subdivision. The undeveloped subject lot is approximately 1.2 acres located at the NW corner of SW Kanner Highway and SW Gaines Avenue in Stuart. A request for a certificate of public facilities exemption is included with this application. Status: Application entered 6/28/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Osprey Ridge – Request to amend the Osprey Ridge PUD zoning agreement and revise the approved 17-lot PUD master and final site plan by splitting lots 1 and 13 into two additional lots which will increase the number of lots to 19. The development is located on the west side of S Kanner Highway approximately 2,000 feet south of SE Pomeroy Street in Stuart. Status: Application entered 2/10/14. Application withdrawn by applicant. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Sailfish Marina Stealth Communications Tower – Request for approval of a revised major master and final site plan to add a stealth communications tower. Status: Application entered 2/4/14. Under review. Contact: Clyde Dulin, Principal Planner, Growth Management, 288-5495

Page 9: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Stuart Jet Center East and West – Request for revised major final site plan approval for proposed improvements on the Stuart Jet Center East and West campuses. The proposed improvements include hangar and office buildings with associated parking and ramp areas. The project site are is approximately 8.66 acres located on Witham Field property east of SE Dixie Highway between SE Airport Road and SE Thunderbolt Drive. A request for a certificate of public facilities exemption is included with this application. Status: Application entered 6/27/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Willoughby PUD/DRI – Request for administrative amendment approval to amend the vertical datum for the Providence One Assisted Living Facility project which is currently under construction. The property is known as Parcel U and included in Phase 3E of the Willoughby PUD. The property consists of approximately 7.43 acres of land located on the southwest corner of the intersection of Willoughby Boulevard and Pomeroy Street in Stuart. Status: Application entered 3/30/16. In post-approval processing. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Willoughby Vittoria of Stuart – Request for major master and final site plan approval for a proposed residential care facility containing 150 beds and associated infrastructure. The proposal is two phases with a 75-bed, two-story building within each phase. The undeveloped subject property is approximately 10.75 acres and is located on the west side of Willoughby Boulevard approximately 1000 feet north of the Willoughby Boulevard/Cove Road intersection. Included in this application is a request for a certificate of public facilities reservation. Status: Application entered 7/29/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Wright, Rita May and Stuart C. – Request for a variance by Rita May Wright and Stuart C. Wright to reduce the lot area requirements of Article 3, Zoning Districts, Land Development Regulations, Martin County Code for the WE-1, Waterfront Estates District and to reduce the setback requirements to permit the existing encroachments into the side yard setbacks by the single family residential dwelling located at 3868 SE Old St. Lucie Boulevard, Stuart, Florida to remain within the current location. Status: Application entered 9/29/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

DISTRICT 2: GOLDEN GATE CRA HIGHLIGHTS

Community Redevelopment Agency At the November 22, 2016 meeting, the Board of County Commissioners directed that staff begin the process of reconstituting the Community Redevelopment Agency as a separate body, to be comprised of each of the chairmen (or their designee) of the Neighborhood Advisory Committees (NACs). Staff was directed to prepare the appropriate ordinance to facilitate this direction, and that ordinance will be heard on December 13.

Golden Gate Neighborhood Advisory Committee Update The Golden Gate NAC met on October 3 and heard an update on the Golden Gate Building renovations. Presentations were also offered for the Gateway for the Arts project, and Habitat for Humanity’s Brush with Kindness program. NAC members and attendees also reviewed the elements of the Golden Gate Redevelopment Plan and provided comments on which elements remained a priority, and additional priorities.

The public is welcome to attend any meetings of the Golden Gate Neighborhood Advisory Committee. Information on the next regular meeting is provided below under Upcoming Meetings & Events. If you have a question or need more information about the CRA program, please do not hesitate to contact the Office of Community & Strategic Partnerships at (772) 463-3253 or visit our website at www.martin.fl.us/cra, or sign up to receive agendas or announcements here and select the list Community Development/CRA.

Page 10: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Project Updates Golden Gate Building Work is progressing on the Golden Gate Building Restoration project that involves a build out of the interior in order to transform the building into the Golden Gate Center for Community Enrichment. The project, which included contributions from MC District and TIF Funds, grants and private donations, represents a collaborative effort of the House of Hope, United Way Foundation, Habitat for Humanity, Martin County Library System, Indian River State College and Project LIFT.

UPCOMING MEETINGS & EVENTS IN DISTRICT 2

Golden Gate Neighborhood Advisory Committee Meeting Date: Monday, December 12 at 6:00 pm Location: Cassidy Community Center, 2895 Fairmont Street, Stuart Contact: Community and Strategic Partnerships, 463-3253

Page 11: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

DISTR ICT 3 Honorable Harold E. Jenkins II, Commissioner

District 3 Includes Southern Martin County: Hobe Sound, South County, a portion of Tequesta and Indiantown.

DISTRICT 3: FLORIDA DEPT. OF TRANSPORTATION PROJECTS

Kanner Highway/SR 76 – Work on Kanner Highway from Connors Highway (SR 15) to west of SW Lake Point Circle. This 1.8 mile project includes milling and resurfacing of Kanner Highway, signing and pavement markings including rumble striping, shoulder widening, intersection and driveway paving, new guardrail and guardrail repair. Project cost is $1.31 million and completion is expected in spring of 2017. Status: Work on the project is anticipated to begin on Monday, December 12. Construction will necessitate travel lane closures at various times. When closures occur, two way traffic will be maintained by flag crews. Contact: FDOT, 489-7064 State Road 441/US 98 – Work on SR 441 north of Wood Street in western Martin County. Status: The northbound lane of SR 441, approximately one mile north of Wood Street, will be closed intermittently Monday through Friday between 7:30 am and 5:00 pm. A flag crew will maintain traffic. Contact: FDOT, 489-7064

DISTRICT 3: ENGINEERING/UTILITIES PROJECTS AND ROAD CLOSURES

Bridge Road Bike Lanes and Resurfacing – Add bike lanes and resurface Bridge Road from Kanner Highway to Pratt Whitney Road. Status: Construction is underway. The work is approximately 85% complete. This is an FDOT grant-funded project. Contact: Paul Bangs, Engineering, 288-5927 Bridge Road Sidewalk – Sidewalk project on Bridge Road from Flora Avenue to Plandome Drive. Status: Construction Drawings are 90% complete. The County has prepared an FDOT TDAP grant application for funding the project and the TAP grant application has been approved. Design will resume in late 2016 and construction is anticipated to occur in 2017. Contact: Paul Bangs, Engineering, 288-5927 Christmas Parade Closures – On Saturday, December 10, the Indiantown Chamber of Commerce will host their annual Christmas Parade. Status: The parade will begin at Big Mound Park and the following roads will be closed to traffic from 3:00 to 7:00 pm: SW Yalaha Street from SW Indianmound Drive to SW Jackson Avenue; SW Jackson Avenue from SW Yalaha Street to SW Osceola Street; SW Osceola Street from SW Jackson Avenue to SW Washington Avenue; SW Washington Avenue from SW Osceola Street to Post Family Park. Contact: Sue Trovato, Engineering, 288-5927 CR A1A (SE Dixie Highway) and CR 708 (SE Bridge Road) – Project will reconfigure parking, drainage, curbs and sidewalks on the SW corner of CR 708 and CR A1A. Work includes clearing and grubbing, sidewalk removal and construction, utility relocation, signing and pavement markings, milling, resurfacing and sodding. Status: Work is underway and will necessitate intermittent lane closures weekdays between 8:30 am and 5:00 pm, as well as some night work. Lane and sidewalk closures will not occur during school arrival or departure times. This project is anticipated to be complete by February 18. Contact: Renee Fresneda, Engineering, 288-5927

Page 12: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

CR 708/SW Bridge Road – Milling and resurfacing of CR 708 (SW Bridge Road) from SR 76 (Kanner Highway) to CR 711 (SW Pratt Whitney Road). Status: The project is underway and anticipate to be complete by March 13. Work will necessitate intermittent lane closures on weekdays between 7:00 am and 5:00 pm. Contact: Ken Vreeland, Engineering, 288-5927 Heritage Ridge Pipe Replacements and Resurfacing – Removal and replacement of failing CMP pipes under roadways and asphalt resurfacing at replaced pipes. Status: The contract construction began on 4/25/16. Work is approximately 98% complete. Contact: Paul Bangs, Engineering, 288-5927

DISTRICT 3: DEVELOPMENT APPLICATIONS IN REVIEW

Algozzini Place – Request for a zoning district change from the current R-3A, Liberal Multiple Family District and B-1, Business District to the RM-6, Medium Density Residential District or the most appropriate zoning district. The subject property is undeveloped and consists of two tracts totaling approximately 6.43 acres located adjacent to the west of Lares Avenue and Dixie Highway intersection in the Hobe Sound CRA. Included in this application is a request for a Certificate of Public Facilities Exemption. Status: Application entered 10/27/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Christ Fellowship Church – Request for revised final site plan approval for additional paved parking areas to serve the church congregation. The subject site is approximately 321 acres located along the east side of Pratt Whitney Road between Bulldog Way and South Fork High School. A request for a certificate of public facilities exemption is included with this application. Status: Application entered 6/16/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Daystar Storage – Request for an administrative amendment to the approved final site plan. The proposed changes include the extension of the existing open storage area for equipment, business vehicles, RV's and boats and construction of a surface water management system to serve the existing and proposed storage area. The 10.5 acre property is located at the southwest corner of Bridge Road and Flora Avenue in Hobe Sound. Status: Application entered 5/29/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

The Grove Golf Club – Request for major final site plan approval for a proposed project consisting of an 18-hole private golf course, driving range, golf clubhouse and golf maintenance facilities. The 226-acre subject property is located north of the Hobe Sound Polo Club. Status: Application entered 7/25/16. Under review. Contact: Peter Walden, Principal Planner, Growth Management, 288-5495 Hobe Sound Village – Request for major final site plan approval for a 92 unit residential townhome project within the Hobe Sound CRA Boundary. The undeveloped 14.88 acre site is located along the west side SE Federal Hwy and abuts the Banner Lake community to the west and the Pine School campus to the south. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 7/15/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Island Way Auto Spa –Request for major final site plan approval for a proposed automatic carwash facilty and associated infrastructure. The undeveloped 0.62 acre site is located approximately 1300 feet south of Bridge Road at the NE corner of the intersection of SE Federal Highway and Olympus Street in Hobe Sound. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 9/10/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

Page 13: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Jupiter Pointe Resort – Request approval of a revised major master site plan for an expansion to the existing Jupiter Pointe Marina. The proposed expansion is to add a new hotel with 54 units in the main building, a new accessory attached restaurant building and a modification of the previously approved club building. The project is located at 18701 SE Federal Highway in Hobe Sound. Status: Application entered 10/14/15. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Oblivious Holdings LLC – Requesting minor final site plan approval to build a 10,714 sf commercial building. The proposed, two story building will replace and existing two story building. The developed subject property is approximately 0.31 acres and is located at the corner of SE Apollo Street and the SE Dixie Highway (Service Road) in Hobe Sound. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 5/4/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 The Palms at Hobe Sound (FKA Sunset Ridge) – Request for PUD final site plan approval for Phases I, II and III of the approved Palms at Hobe Sound Master Site Plan. The vacant subject property is approximately 12.3 acres located on the west side of Federal Highway (US 1) approximately 1,700 feet north of Bridge Road in Hobe Sound. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 4/18/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Pennock Preserve PUD Phases 2 & 3 – This is an application for final site plan approval for Phase 2 and 3 of Pennock Preserve PUD as per the 3rd PUD amendment and revised master site plan. The Phase 2 and 3 site area is approximately 171.81 acres with 94 Single family lots and associated infrastructure. The subject property is located in Southern Martin County along SE Island Way between Jonathan Dickinson State Park and the Palm Beach County line. Also a plat approval for Phases 2 & 3. Status: Application entered 5/13/15 (Amend) and 4/14/16 (Plat). Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

Seabranch/US-1 – Requesting plat approval for an approved project known as Seabranch/US-1. The project was approved as a major final site plan with a fifty-lot single family subdivision and three story residential care facility. The subject property is 33.6 acres in size and is located on the east side of Federal Hwy (US 1) at the intersection of Seabranch Blvd and Federal Hwy between Port Salerno and Hobe Sound. Included in this application is a request for a certificate of public facilities exemption. Status: Application entered 8/15/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Seacoast Center – Request for revised final site plan approval to renovate the existing bank building and associated infrastructure on the subject property. The building renovation is to include a convenience restaurant, tenant space for Seacoast Bank and two retail bays. The property is located on the east side on Federal Highway (US 1) approximately 700 feet north of Bridge Road in the Hobe Sound CRA. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 8/31/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Seacoast National Bank (Seacoast Center) – Request for a zoning district change from the current HB-1, Limited Business District, to GC, General Commercial or the most appropriate zoning district. The property is developed with an existing bank building and associated infrastructure on approximately 1.37 acres. The property is located on the east side of Federal Highway (US1) approximately 700 feet north of Bridge Road in the Hobe Sound CRA. Included in this application is a request for a certificate of public facilities exemption. Status: Application entered 7/29/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Weathers, Eleanor – Request to rezone the subject 6.2-acre parcel to RE-1/2A. The rezoning is necessary to allow the property owner to split the subject parcel that is located south of Kanner Highway into two lots in order to build a single-family house on each lot and retain her homestead property north of Kanner. The future land use on the property located south of Kanner Highway is Estate Density and the current zoning district is

Page 14: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

A-2. The rezoning is necessary because the minimum lot size requirement under the current A-2 zoning will not permit a lot split. Status: Application entered 6/28/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495 Village Square Two-Building Three – Requesting revised final site plan approval to construct an additional single-story 2,575 square foot commercial building and infrastructure at the NE corner of the property. The subject property is approximately 1.03 acres and located at 15935 SW Warfield Boulevard in Indiantown. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 9/8/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

DISTRICT 3: HOBE SOUND CRA HIGHLIGHTS

Community Redevelopment Agency At the November 22, 2016 meeting, the Board of County Commissioners directed that staff begin the process of reconstituting the Community Redevelopment Agency as a separate body, to be comprised of each of the chairmen (or their designee) of the Neighborhood Advisory Committees (NACs). Staff was directed to prepare the appropriate ordinance to facilitate this direction, and that ordinance will be heard on December 13.

Hobe Sound Neighborhood Advisory Committee Update At the October 19, 2016 Hobe Sound NAC meeting, residents heard a presentation on the various elements that impact the design and construction within the CRA. Martin County staff is endeavoring to improve the process and clarify the codes to facilitate development in the CRAs. The public is welcome to attend any meetings of the Hobe Sound Neighborhood Advisory Committee. Information on the next regular meeting is provided below under Upcoming Meetings & Events. If you have a question or need more information about the CRA program, please do not hesitate to contact the Office of Community & Strategic Partnerships at (772) 463-3253 or visit our website at www.martin.fl.us/cra, or sign up to receive agendas or announcements here and select the list Community Development/CRA.

Project Updates A1A Service Road Project This work involves relocating the entrance of the service road from Bridge Road to A1A and construction will begin in early December. Lares Avenue Flood Control Project Construction is scheduled to being in January 2017.

DISTRICT 3: INDIANTOWN CRA HIGHLIGHTS

Community Redevelopment Agency At the November 22, 2016 meeting, the Board of County Commissioners directed that staff begin the process of reconstituting the Community Redevelopment Agency as a separate body, to be comprised of each of the chairmen (or their designee) of the Neighborhood Advisory Committees (NACs). Staff was directed to prepare the appropriate ordinance to facilitate this direction, and that ordinance will be heard on December 13.

Page 15: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Indiantown Neighborhood Advisory Committee Update Members of the Indiantown NAC met on November 9. Attendees were provided with an update on the Farm Road project, which is scheduled for 2017. The NAC was also asked to provide input about whether they want to pursue a tourism grant for a museum, which is part of the Indiantown Redevelopment Plan. Florida Community Health Center presented information about the planned expansion of their facility on Warfield Boulevard.

The public is welcome to attend any meetings of the Indiantown Neighborhood Advisory Committee. Information on the next regular meeting is provided below under Upcoming Meetings & Events. If you have a question or need more information about the CRA program, please do not hesitate to contact the Office of Community & Strategic Partnerships at (772) 463-3253 or visit our website at www.martin.fl.us/cra, or sign up to receive agendas or announcements here and select the list Community Development/CRA.

UPCOMING MEETINGS & EVENTS IN DISTRICT 3

Hobe Sound Neighborhood Advisory Committee Meeting Date: Wednesday, January 18 at 6:00 pm Location: Hobe Sound Community Center, 8980 Olympus Street in Hobe Sound Contact: Community and Strategic Partnerships, 463-3253 Indiantown Neighborhood Advisory Committee Meeting Date: Wednesday, December 14 at 6:00 pm Location: Indiantown Civic Center, 15675 SW Osceola Street, Indiantown Contact: Community and Strategic Partnerships, 463-3253

Page 16: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast
Page 17: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADM INISTRATOR’S MONTHLY REPORT

DISTR ICT 4

Honorable Sarah Heard, Commissioner District 4 Includes East, Lower Central Martin County: Port Salerno and

Tropical Farms.

DISTRICT 4: FLORIDA DEPT. OF TRANSPORTATION PROJECTS

I-95 Interchange – This .745-mile project includes widening Kanner Highway (SR 76) at the I-95 interchange, reconstructing the I-95 entrance and exit ramps, drainage, milling and resurfacing, signing and pavement markings, and signalization. Construction cost is $5.79 million and completion is expected in early 2017. Status: Lanes on either direction of Kanner Highway will be closed intermittently. Contact: Terry Rauth, Engineering, 288-5927 Kanner Highway/SR 76 – 4.3 miles of Kanner Highway, from Lost River Road to south of Monterey Road, is being widened to a six-lane divided highway. Additional work on this project includes widening the bridge over the south fork of the St. Lucie River; drainage improvements, including construction of five retention ponds; guardrail improvements; signalization upgrades; and turn lane and bicycle lane improvements. Construction cost is $20.8 million and completion is expected in spring of 2019. Status: One lane in either direction of Kanner Highway may be closed weekdays from 9:00 am and 4:00 pm. Sidewalks may also experience intermittent closures. Contact: FDOT, 489-7064

DISTRICT 4: ENGINEERING/UTILITIES PROJECTS AND ROAD CLOSURES

Cove Road Resurfacing – Resurfacing of Cove Road from Kanner Highway to US 1. The project work will also include repairs of failing drainage pipes. Status: Design survey work has begun and engineering will start in March 2018. Construction is scheduled for July 2020. This is an FDOT grant-funded project. Contact: Paul Bangs, Engineering, 288-5927 Salerno Road Sewer Enhancement – Sanitary sewer and streetscape project on Salerno Road between Commerce Avenue, and on Railway Avenue between Salerno Road and Seaward Street. The project will include sanitary sewer improvements, on-street parking and landscaping. This project is a CRA project that is being managed by Capital Projects. Status: Construction is underway. Work necessitates a road closure on SE Salerno Road from SE Commerce Avenue to SE Railway Avenue. Thru traffic is detoured. Construction completion is scheduled for April 2017. As of December 6, work is approximately 25% complete. Contact: Paul Bangs, Engineering, 288-5927 Seabranch Boulevard Resurfacing – Resurfacing of Seabranch Boulevard from US 1 to the end of the road. Status: Engineering is complete. Bidding and construction are scheduled for March 2017. This is an FDOT grant-funded project. Contact: Paul Bangs, Engineering, 288-5927

Page 18: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

DISTRICT 4: DEVELOPMENT APPLICATIONS IN REVIEW

Christ Fellowship Church – Request for revised final site plan approval for additional paved parking areas to serve the church congregation. The subject site is approximately 321 acres located along the east side of Pratt Whitney Road between Bulldog Way and South Fork High School. A request for a certificate of public facilities exemption is included with this application. Status: Application entered 6/16/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Coastal Health Park PUD Parcel C&D (Healthsouth) – Requesting approval of an administrative amendment to add a 1,750 sf addition to the existing physical rehabilitation facility. The addition will provide additional workout and rehabilitation facilities to enhance the existing services as well as provide additional storage. A portion of the existing building currently used for storage will be renovated to add ten beds to the facility. The result of this application will be a revised final site plan and revised master site plan. The subject property is approximately 7.96 acres and located on SE Community Drive within the Coastal Health Park PUD. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 8/15/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Coral Reef Rentals, LLC – Request for minor final site plan approval for proposed 14,260 sf manufacturing building on 1.29 acres located on the north side of SE Gran Park Way. The applicant is requesting a certificate of public facilities reservation for the Coral Reef Rentals, LLC. Status: Application entered 1/8/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Driftwood Cay – Application for a residential, minor final development site plan to accommodate a 13-lot, single family subdivision on an existing 14.2 acre property. The site is currently undeveloped and located along the south side of Cove Road between Atlantic Ridge Drive and Grace Lane in Stuart. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 2/26/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Emerald Lakes First Class Self Storage – This is an application requesting approval for a commercial, minor development final site plan proposing a 23,490 square foot two-story building for use as a residential storage facility. The subject property consists of approximately 1.75 acres of undeveloped land located within the Emerald Lakes commercial subdivision on the east side of US-1 approximately 0.6 miles south of Cove Road in Martin County. Status: Application entered 7/6/15. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Gomez Avenue Preserve – Requesting minor final site plan approval for the extension of the East Coast Greenway to include an ADA compatible shell rock pathway with informational kiosks, shelters, exercise stations and osprey platform. The project is located on 10.56 acres of upland on the 33.61 acre FCT property on the Intracoastal Waterway on Peck Lake in Martin County, Florida. Status: Application entered 9/20/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495 Loblolly Bay PUD – Request for revised final site plan approval for Lot 1-A within the Loblolly Bay PUD. The applicant is seeking approval to add approximately 50 feet of the property adjacent to the north by way of purchase from the Loblolly Bay POA. The applicant would then seek to expand the existing residence and add a three-car garage. The subject property is located at 7860 SE Loblolly Bay Drive in Hobe Sound. Status: Application entered 4/14/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

Page 19: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Loblolly Pines PUD – Request for Revised PUD Zoning Agreement and Revised Master Site Plan approval to expand the current PUD boundary to include an undeveloped 20 acre parcel, relocate the existing golf maintenance facility to the 20 acre parcel and add 9 single family units to the former golf maintenance facility site. The Loblolly Pines PUD is located between SE Dixie Highway and SE Gomez Avenue in Hobe Sound. Included in this application is a request for Deferral of Public Facilities Reservation. Status: Application entered 2/18/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Locks Estates – Request for minor final site plan approval for proposed six (6) lot single-family residential subdivision on a vacant 4.677 acre parcel. The lots are one-half acre minimum. The property is located on Locks Road, just north of Queens Park Mobile Home Park and adjacent to Locks Point. Status: Application entered 7/28/15. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Mariner Village Square – Request approval of the 5th amendment to the PUD zoning agreement, revised master site plan and phasing plan. The partially developed property is approximately 20 acres in size and located on the west side of US 1 at the intersection of Mariner Sands Drive and Federal Highway between Port Salerno and Hobe Sound. Status: Application entered 12/15/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Martin Memorial Hospital South – Requesting revised final site plan approval to construct a 5,250 sf, one-story data center building near the southwest corner of the site, located on the south side of Salerno Road and east of Tower Drive. Status: Application entered 2/2/16. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Medalist Building Group LLC – Request for a variance by Medalist Building Group LLC to reduce the setback requirements of Article 3, Zoning Districts, Land Development Regulations, Martin County Code for the RS-3, Residential District and the centerline setback requirements of Section 3.16.C.1.b., to permit the construction of a single family dwelling and appropriate accessory structures on the subject lot located at 5097 SE Schooner Oaks Way, Stuart, Florida. Status: Application entered 6/30/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Phipps Park – Request for major final site plan approval for renovations to Phipps Park. The park is located at 2177 SW Locks Road and contains 67.26 acres, more or less. Status: Application entered 9/2/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495 Stuart Assisted Living Facility – Request for major final site plan approval for a proposed 150-bed assisted living facility on approximately 9.2 acres. The subject property is currently undeveloped and located along the north side of Cove Road, approximately 1,000 feet east of the Willoughby Boulevard intersection in Stuart. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 12/3/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495

WWD Tract 3 LLC – Request for a zoning district change from R-3 to RM-10 for an approximately 8.678-acre undeveloped parcel of land located on the south side of SE Hydrangea Street approximately 400 feet east of US 1. Status: Application entered 7/19/16. Approved by the BCC on 11/22/16. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495

Page 20: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

DISTRICT 4: PORT SALERNO CRA HIGHLIGHTS

Community Redevelopment Agency At the November 22, 2016 meeting, the Board of County Commissioners directed that staff begin the process of reconstituting the Community Redevelopment Agency as a separate body, to be comprised of each of the chairmen (or their designee) of the Neighborhood Advisory Committees (NACs). Staff was directed to prepare the appropriate ordinance to facilitate this direction, and that ordinance will be heard on December 13.

Port Salerno Neighborhood Advisory Committee Update The Port Salerno NAC meeting was held on November 17. The agenda included discussions about parking options for Port Salerno and replacement of the shade structures at the Manatee Pocket Gateway. NAC members asked staff to explore both county owned and private locations for the parking. When presented with the cost of replacing the shade structures at the Manatee Pocket Gateway, the NAC tabled the item for future consideration. Attendees also received an update on the Salerno Sewer Enhancement project.

The public is welcome to attend any meetings of the Port Salerno Neighborhood Advisory Committee. Information on the next regular meeting is provided below under Upcoming Meetings & Events. If you have a question or need more information about the CRA program, please do not hesitate to contact the Office of Community & Strategic Partnerships at (772) 463-3253 or visit our website at www.martin.fl.us/cra, or sign up to receive agendas or announcements here and select the list Community Development/CRA. Project Updates Salerno Road Sewer Construction of a central sewer system along Salerno Road west of the FEC right of way, along with on-street parking and landscaping. Construction started mid-September 2016 and is expected to be completed by March 2017. Letters were sent to 638 property owners in the area to keep them apprised of the schedule. Electronic signs were strategically placed to notify motorists that Salerno Road would be closed October 25 – December 25. Another sign alerted residents that local businesses remain open during the construction. Updates will be provided, as new information becomes available.

UPCOMING MEETINGS & EVENTS IN DISTRICT 4

Port Salerno Neighborhood Advisory Committee Meeting Date: Thursday, December 15 at 6:00 pm Location: Port Salerno Civic Center, 4950 SE Anchor Avenue, Stuart Contact: Community and Strategic Partnerships, 463-3253

Page 21: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

DISTR ICT 5

Honorable Edward V. Ciampi, Commissioner

District 5 Includes Western Martin County: Palm City, and sections of Indiantown.

DISTRICT 5: FLORIDA DEPT. OF TRANSPORTATION PROJECTS

Danforth Creek Bridge/State Road 714 – The Danforth Creek Bridge repair project on SR 714 includes providing slope protection/channel lining to prevent further erosion, repairing the bridge slabs to prevent rotational movements and repairing the existing sidewalk on the south side of the bridge. Construction cost is $1.18 million and completion is expected in early 2017. Status: The speed limit on westbound Martin Downs Boulevard just before Mapp Road has been temporarily reduced from 45 mph to 35 mph. Westbound traffic on Martin Downs Boulevard at the Danforth Creek Bridge has been diverted to the eastbound lane, reducing traffic to one lane in each direction for approximately 900 feet. Contact: FDOT, 489-7064

DISTRICT 5: ENGINEERING/UTILITIES PROJECTS AND ROAD CLOSURES

All American Ditch Stormwater Quality Retrofit Project – This project consists of installing a drainage system and control structures within the older residential area south of CR 714, north of All American Boulevard, and east of Mapp Road, in order to capture and convey stormwater runoff south along Mapp Road to a proposed deep water, wet detention lake and a shallow water stormwater treatment area, configured in a treatment train style system that will provide water quality treatment prior to discharging to the South Fork of the St. Lucie River. Status: Construction is underway. Storm pipe installation throughout the neighborhood will continue in December. Contact: Greg Nolte, Engineering, 288-5927 High Meadows Avenue Bike Lanes and Resurfacing – Add bike lanes and resurface High Meadows Avenue from SR 714 (Martin Highway) to Murphy Road. Status: Design Survey work is complete. The preparation of Engineering Drawings is underway. Construction is scheduled for August 2018. This is an FDOT grant-funded project. Contact: Paul Bangs, Engineering, 288-5927 Mapp Road Town Center Bike Lanes and Resurfacing – Add bike lanes and resurface Mapp Road from SR 714 (Martin Highway) to Martin Highway. Also included is drainage system piping work. Status: Design work is in progress. The project scope has been revised and is now intended to include the backbone drainage system piping to accommodate the future construction of the Town Center project. Construction is scheduled for August of 2017. This project is partially funded by an FDOT grant. FDOT review of the Construction Drawings is in progress. Contact: Paul Bangs, Engineering, 288-5927 Murphy Road Bridge Replacement – Replacement of bridge on Murphy Road at the C-23 Canal. Status: 100% Construction Drawings have been approved. Permitting is complete. Construction has been deferred until funding is available. FDOT grant funding has been programmed for FY 20. Contact: Paul Bangs, Engineering, 288-5927

Page 22: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Murphy Road Resurfacing – Resurfacing of Murphy Road from Mapp Road to the Martin/St. Lucie County Line. The project work will also include repairs of failing drainage pipes and bridge repair work. Status: Design Survey work and preparation of engineering drawings is underway. Construction is scheduled for September 2018. Contact: Paul Bangs, Engineering, 288-5927 SW Murphy Road – Florida Power and Light will be placing concrete poles on SW Murphy Road between NW Gilson Road and SW Bessey Creek Trail. Status: Work is underway and anticipated to be complete by January 16. Work will necessitate intermittent lane closures on SW Murphy Road between 9:00 am and 3:30 pm Monday through Friday. Contact: Jana Cox, Engineering, 288-5927

DISTRICT 5: DEVELOPMENT APPLICATIONS IN REVIEW

Chabad Jewish Center – Requesting minor final site plan approval for a 8,930 square foot place of worship which will include a sanctuary, social hall, classrooms, related support offices, and associated infrastructure.The subject property is 2.54 acres and is currently developed with a single family residence and a variety of accessory structures located on the north side of Sunset Trail approximately 950 feet east of High Meadow Avenue in Palm City. Included in this application is a request for a Certificate of Public Facilities Reservation. Status: Application entered 11/3/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495 Costco – Request for major master and final site plan approval for a new Costco store with gas station, outparcel and associated infrastructure on approximately 28 acres. The undeveloped subject property is approximately 28 acres and located south of Martin Highway (CR 714) between the Turnpike and High Meadow Avenue (CR 713) in Palm City. Included is a request for a Certificate of Public Facilities Reservation. Status: Application entered 10/19/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Florida Superior Sand – Request for final site plan approval for a 47-acre lake with a 7-acre processing and stockpiling area. It also includes a construction trailer/weigh station with potable water and wastewater service via well and septic, along with a 5,160 sf site for a storage shed. Located west of I-95 and south of SR 714. Status: Application entered 7/12/12. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Fort Dawson PUD – Request approval of the First Amendment to the PUD zoning agreement, revised master site plan and phasing plan, revised final site plan for Phase 2. The proposed changes include the expansion of an existing lake known as Lake Annie, the creation of an additional 4-acre habitat island within Phase 2 and the reduction in the number of residential lots by 15, from 109 to 94 lots. The overall project is approximately 552 acres located on the north side of Citrus Blvd east of Indiantown. Status: Application entered 12/17/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Marandy Properties – Requesting a zoning change from A-2 to AG-20A for the 99.81-acred property known as Superior Sand Mine. Status: Application entered 3/30/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 Osprey Ridge – Request to amend the Osprey Ridge PUD zoning agreement and revise the approved 17-lot PUD master and final site plan by splitting lots 1 and 13 into two additional lots which will increase the number of lots to 19. The development is located on the west side of S Kanner Highway approximately 2,000 feet south of SE Pomeroy Street in Stuart. Status: Application entered 2/10/14. Application withdrawn by applicant. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495

Page 23: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Sands Commerce Center III – Requesting revised major master and final site plan approval for modifications consisting of the reduction of the size of building #16 from 168,000 sf to 126,000 sf, increase width of pavement between buildings #15 and #16 to allow for more truck maneuvering and relocation of proposed sidewalk along SW Cargo Avenue. The applicant is requesting a certificate of public facilities of reservation. Status: Application entered 6/13/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495 Seven J’s Subdivision Lot 8 (VM Iron Works) – Request for approval of a minor final site plan to construct a pre-manufactured metal building with a concrete foundation on the site. The project is located at 1861 SW Poma Drive in Palm City. Status: Application entered 6/30/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Seven J’s Subdivision Lots 6 and 7 (Waterblasting Technologies) – Requesting final site plan approval to construct a 91,785 square foot manufacturing facility known as Waterblasting Technolgies on approximately 8.32 acres. The properties are located at 1860 SW Poma Drive and 1910 SW Poma Drive. Status: Application entered 11/13/15. Under review. Contact: Paul Schilling, Principal Planner, Growth Management, 288-5495 Seven J’s Subdivision Lots Parcel 16 – Requesting minor site plan approval to obtain a development order for construction of a fence for the purpose of securing outdoor storage on the property. The property is located at 8739 SW Justin Trace, Palm City. Status: Application entered 12/29/15. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 South Florida Shooting Grounds – Requesting approval of a revised major final site plan for the addition of golf cart barns on the project site. The boundary of the project has been increased to 42.72 acres. Status: Application entered 2/22/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 The Floridian Golf Club PUD Phase 1 – Requesting plat approval for The Floridian Golf Club Phase 1. The request is to plat the portion of River’s End Way that has been constructed in Phase 1 from Murphy Road to the intersection of Bessey Creek Way. Status: Application entered 8/12/15. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 The Floridian Golf Club PUD Phase 3 – Requesting plat approval for The Floridian Golf Club Phase 3, which consists of 18 single-family waterfront lots, shoreline protection zone restoration and related infrastructure improvements including the completion of River’s End Way. Status: Application entered 3/29/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 The Floridian Golf Club PUD Phase 4 – Requesting PUD final site plan approval for Phase 4 with a Certificate of Public Facilities Reservation. Phase 4 consists of 18 single-family waterfront lots. Status: Application entered 1/27/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 The Floridian Golf Club PUD Phase 5 – Requesting PUD final site plan approval with a Certificate of Public Facilities Reservation. Phase 5 consists of five single-family lots on the existing island parcel. Status: Application entered 1/28/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495 The Floridian Golf Club PUD Phase 6 – Requesting PUD final site plan approval for The Floridian Golf Club Phase which will consist of 5 cottages on an existing lake. Status: Application entered 5/18/16. Under review. Contact: Catherine Riiska, Principal Planner, Growth Management, 288-5495

Page 24: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Treasure Coast Wildlife Hospital – Requesting approval regarding the previously approved site plan. The 20-acre parcel is located on the west side of Citrus Boulevard, approximately 3/4-mile north of 96th Street. Status: Application entered 9/14/16. Under review. Contact: Peter Walden, Senior Planner, Growth Management, 288-5495

DISTRICT 5: OLD PALM CITY CRA HIGHLIGHTS

Community Redevelopment Agency At the November 22, 2016 meeting, the Board of County Commissioners requested staff bring back several capital projects for consideration. Among the projects was the Mapp Road Town Center project. Staff will be presenting information about these projects at the January 10, 2017 BOCC meeting. At this meeting, the Board also directed that staff begin the process of reconstituting the Community Redevelopment Agency as a separate body, to be comprised of each of the chairmen (or their designee) of the Neighborhood Advisory Committees (NACs). Staff was directed to prepare the appropriate ordinance to facilitate this direction, and that ordinance will be heard on December 13.

Old Palm City Neighborhood Advisory Committee Update The Old Palm City NAC met on October 17 and the agenda included an update from Engineering Department staff on the Mapp Road project, which will replace failing drainage pipe, as well as resurface and stripe the roadway from 714/SW Martin Downs Boulevard to Bridgeway Street. Members and residents also discussed possible future plans for the Mapp Road corridor. An update on the eco art “Ripple” project was also provided at the meeting. A grant was secured from the National Endowment for the Arts (NEA) to assist with conceptual design and a

second grant from the LISC was awarded for technical assistance. Additional funding will be sought for the construction of this innovative project combining stormwater treatment with eco art. The public is welcome to attend any meetings of the Old Palm City Neighborhood Advisory Committee. Information on the next regular meeting is provided below under Upcoming Meetings & Events. If you have a question or need more information about the CRA program, please do not hesitate to contact the Office of Community & Strategic Partnerships at (772) 463-3253 or visit our website at www.martin.fl.us/cra, or sign up to receive agendas or announcements here and select the list Community Development/CRA. Note: See district 3 for Indiantown CRA highlights.

UPCOMING MEETINGS & EVENTS IN DISTRICT 5

Indiantown Neighborhood Advisory Committee Meeting Date: Wednesday, December 14 at 6:00 pm Location: Indiantown Civic Center, 15675 SW Osceola Street, Indiantown Contact: Community and Strategic Partnerships, 463-3253 Old Palm City Neighborhood Advisory Committee Meeting Date: Monday, February 20 at 6:00 pm Location: Palm City Community Center, Leighton Park, 2701 SW Cornell Avenue, Palm City Contact: Community and Strategic Partnerships, 463-3253

Page 25: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

Page 26: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast
Page 27: COUNTY ADMINISTRATOR ’S MONTHLY REPORT · COUNTY ADMINISTRATOR’S MONTHLY REPORT Pinecrest Lakes – Warner Creek Bridge – Removal of culvert pipes and construction of a pre-cast

COUNTY ADMINISTRATOR ’S MONTHLY REPORT

FY 16 BUDGET STATUS REPORT AS OF DECEMBER 6 , 2016

Revenues

Current Adjusted Budget

Current Collections

% of Budget

Ad Valorem, Delinquent & Other Taxes 161,494,492 65,043,013 40.3%

Local Sales & Use Taxes 10,044,000 96,644 1.0%

Communications Tax 1,800,000 137,128 7.6%

Licenses/Permits/Franchise Fees 18,125,229 2,460,778 13.6%

State & Federal Grants 41,692,807 3,160,097 7.6%

Charges for Services 90,297,611 18,155,498 20.1%

Fines and Forfeits 708,500 81,434 11.5%

Interest Earnings & Misc Revenues 11,308,944 982,744 8.7%

Interfund Transfer, Debt Proceeds 10,720,747 377,582 3.5%

Transfers 17,337,366 2,559,660 14.8%

Fund Balance 97,924,904 97,924,904 100.0%

461,454,600 190,979,481

Expenditures

Current Adjusted Budget

Expended/ Committed

% of Budget

Personnel 78,245,289 12,833,276 16.4%

Operating 164,357,698 47,980,085 29.2%

Capital Outlay 69,785,230 24,592,445 35.2%

Transfers & Reserves 149,066,383 20,991,307 14.1%

Total 461,454,600 106,397,114

Components of the various revenues listed above: Includes:

Ad valorem Delinquent taxes and other taxes

Local sales and use taxes Fuel, discretionary and tourist development taxes

Licenses and permits Building permits and occupational licenses

Interest earnings and miscellaneous revenues Rents, royalties, disposition of fixed assets, contributions


Recommended