+ All Categories
Home > Documents > County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight...

County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight...

Date post: 30-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
31
Transcript
Page 1: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 2: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

Page 1 of 7

County of Santa Clara

2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19

Period in Review: This report provides an update on activity regarding the County’s 2016 Measure A Affordable Housing Bond Program and its Citizens’ Oversight Committee from July 1, 2018 through September 30, 2018, the first quarter of Fiscal Year 2018-19.

Summary

We highlight the following observations regarding the financial and operational performance of the Measure A Affordable Housing Bond Program (Program) during this first quarter of 2018-19:

No new housing developments were allocated Program funding during this reporting period. Without new housing developments, there was no increase in the amount of total funding committed to housing developments, nor has there been an adjustment to the housing development goals.

During the first quarter of 2018-19, progress continues as there were several milestones reached for the Program’s housing development projects. These development milestones are outlined in Exhibit 6 of this report.

As summarized in Exhibit 2 below, three projects had expenditures totaling $11.3 million during the quarter. As a result, cumulative project-to-date actual expenditures increased 142 percent from approximately $8 million at the end of June 2018 to $19.3 million as of September 30, 2018.

Activity Reported: Citizens’ Oversight Committee

Oversight Committee Meetings During this reporting period, the Oversight Committee held one meeting on September 6, 2018. Quarterly Report MGO has been coordinating with the Office of Supportive Housing staff to compile statistics on the financial and operational performance of housing developments supported by Measure A. In this quarterly report, we provide statistics outlining how Measure A funds are being used for affordable housing projects, as well as an outline of milestones being monitored for the development projects. Performance Dashboard MGO has been working with the Office of Supportive Housing to source originating documentation that will be used for compiling various performance metrics to be included in the performance dashboard. MGO originally created the performance dashboards through a third party data analytics software, and have now imbedded those graphics onto a landing page located on the Office of Supportive Housing’s website. A snapshot of this web page is attached to this report, and MGO will provide a live demonstration at the January 2019 Oversight Committee meeting. Financial Audit MGO has completed its financial audit of the Program for Fiscal Year 2017-18, of which the final version is attached for consideration by the Oversight Committee.

Page 3: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

Page 2 of 7

Housing Development Financials – Exhibit 1

No housing developments were added to the Program during this reporting period. However, as reported in the June 30, 2018 report, there were 10 housing developments either under construction or in the planning process, that are either already receiving Measure A funds, or have received commitments from the Program. The County has committed $111 million from Measure A proceeds, which are estimated to finance approximately 26 percent of all total development costs, or approximately $135,900 per unit, as presented in Exhibit 1 below.

Exhibit 1 Projected Financials by Housing Development as of September 30, 2018

Project Name No. of Units/ Bedrooms

Estimated Total

Development Cost

Estimated Total

Cost Per Unit

Committed Program Funding

Program Commitment as % of Total

Estimated Cost

Program's Estimated Cost Share Per Unit

Villas on the Park 84/85 $38,947,606 $463,662 $7,200,000 18.49% $85,714

The Veranda 19/20 $11,390,778 $599,515 $1,000,000 8.78% $52,632Gateway Senior Apartments 75/86 $30,413,539 $405,514 $7,500,000 24.66% $100,000Crossings on Monterey 39/87 $22,841,968 $585,691 $5,800,000 25.39% $148,718Quetzal Gardens 71/141 $50,194,787 $706,969 $9,830,000 19.58% $138,451Leigh Avenue Senior Apartments 64/65 $49,947,164 $780,424 $13,500,000 27.03% $210,938

Sango Court 102/129 $72,488,258 $710,669 $16,000,000 22.07% $156,863North San Pedro 135/136 $60,229,610 $446,145 $7,200,000 11.95% $53,333Corvin Apartments 146/147 $56,946,894 $390,047 $29,000,000 50.92% $198,630Page Street Apartments 82/83 $40,716,824 $496,547 $14,000,000 34.38% $170,732

Totals 817*/979 $434,117,428 $111,030,000 25.58% $135,900Source: Financial data queried by the Office of Supportive Housing. * Note: The number of units includes units dedicated for property manager for each development. First Time Home Buyer Loan Program On June 5, 2018, the County Board of Supervisors approved $25 million of Measure A funds to finance a new, first-time homebuyer down payment loan program. The program will be administered through a partnership between the County’s Office of Supportive Housing and Housing Trust Silicon Valley. The funds will assist approximately 235 households over the first five years of the program by providing deferred loans for down payments of up to 17% of a home’s purchase price. The loan will be subordinate to the first mortgage. The program does not require monthly principal or interest payments. Borrowers will repay the principal loan amount plus a share of the appreciation, based on the percentage of the loan borrowed. Payments will be deferred until the earlier of the maturity date of the loan, the sale of the home, or a refinance of the first mortgage. The County anticipated issuing its first loans in September or October 2018, but the program did not officially launch until November 20, 2018. Further information on this housing loan activity will be addressed in the next quarterly report covering October through December 2018.

Page 4: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

Page 3 of 7

Housing Trust Silicon Valley (HTSV) – Supportive Housing Fund (SHF) There have not been any modifications to this section since the last report which covered activity through June 30, 2018. As additional information becomes available on how the $11.9 million funds are administered, they will be addressed in future quarterly reports. In June 2015, the County Board of Supervisors approved $5 million in lending capital (“County Contribution”) to the SHF to make predevelopment loans for the creation and preservation of permanent housing with supportive services for extremely low-income individuals and families, and those with special needs. In addition, in June 2015, the County Board of Supervisors entered into a memorandum of understanding (MOU) with Housing Trust Silicon Valley to administer SHF to make loans to qualified developers. On April 11, 2017, the County Board of Supervisors entered into an amended MOU with Housing Trust Silicon Valley to augment the County’s contribution to the SHF by an additional $11.9 million to make predevelopment loans in accordance with the 2016 Measure A Affordable Housing Bond. This additional contribution to SHF was initially funded through the County’s general fund, with the intent to be repaid by Measure A bond funds once the bonds were issued. The 2016 Measure A Affordable Housing Bond, which was approved by the voters of Santa Clara County, authorizes the County Board of Supervisors to provide affordable housing for vulnerable populations including veterans, seniors, the disabled, low and moderate income individuals or families, foster youth, victims of abuse, the homeless, and individuals suffering from mental health of substance abuse illness. The amended MOU stipulates that the use of the $11.9 million funded by Measure A shall be used only for the purposes authorized by Measure A. The MOU further states that HTSV will provide the County with an annual summary report on all SHF’s disbursed funds, including demographic information collected. HTSV shall also provide the County with a report showing the amount of funds expended and the status of any project required or authorized to be funded with sufficient detail that is needed for the completion of an annual report and to ensure compliance with Measure A. Upon termination of the MOU, HTSV is to return to the County and County Contributions (including Measure A contributions) funds that have never been committed to a revolving loan through the SHF to the County no later than 30 days from the date of termination, expiration, or cancellation of the MOU. After termination, expiration, or cancellation of the MOU, any loan repayments received by HTSV must continue to be used for the intent and purpose of the SHF. Program Expenditures per Development Project – Exhibit 2 Of the $111 million committed to the 10 housing developments summarized in Exhibit 1, over $19 million, or 17 percent, was expended as of September 30, 2018. This is an increase of 142 percent when compared to the approximately $8 million spent as of June 30, 2018. Exhibit 2 below provides an overview, by project; of the expenditures to-date by cost category (acquisition, pre-development, and construction) reimbursed from Measure A funds.

Page 5: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

Page 4 of 7

Exhibit 2 Program Expenditures by Housing Development as of September 30, 2018

Project Name Program Funds Expended This

Quarter

Total Program Funds

Expended Acquisition Construction

Pre-Development

Villas on the Park $1,963,244 $4,154,948 $0 $2,510,446 $1,644,502

The Veranda $0 $827,479 $68,564 $607,481 $151,434

Gateway Senior Apartments $7,500,000 $7,500,000 $3,600,000 $3,900,000 $0

Crossings on Monterey $1,865,675 $4,772,337 $2,400,000 $1,271,598 $1,100,739

Quetzal Gardens $0 $2,031,928 $2,031,928 $0 $0

Leigh Ave Senior Apartments $0 $0 $0 $0 $0

Sango Court $0 $0 $0 $0 $0

North San Pedro $0 $0 $0 $0 $0

Corvin Apartments $0 $0 $0 $0 $0

Page Street Apartments $0 $0 $0 $0 $0

Totals $11,328,919 $19,286,692 $8,100,492 $8,289,525 $2,896,675Source: Financial data provided by the Office of Supportive Housing.

Public/Private Leveraging Ratio (PPLR) - Exhibit 3

Based on the financial projections provided by the County for the 10 housing developments, we estimate that for every one dollar invested by the Measure A Program, the Program is incentivizing $2.91, on average, from outside investments (Public/Private Leveraging Ratio [PPLR]) into affordable housing projects, as estimated in Exhibit 3 below. For the current 10 projects in the Program, the PPLR ranged from $10.39 for The Veranda to just below $1 for the Corvin Apartments. This average and the information in Exhibit 3 have not changed compared to the last quarter since no new developments were added to the Program.

Exhibit 3 Estimated Ratio of Outside Investment per Development

Project Name Estimated Total

Development Cost

Committed Program Funding

Other Funding

PPLR

Villas on the Park $38,947,606 $7,200,000 $31,747,606 $4.41

The Veranda $11,390,778 $1,000,000 $10,390,778 $10.39

Gateway Senior Apartments $30,413,539 $7,500,000 $22,913,539 $3.06

Crossings on Monterey $22,841,968 $5,800,000 $17,041,968 $2.94

Quetzal Gardens $50,194,787 $9,830,000 $40,364,787 $4.11

Leigh Avenue Senior Apartments $49,947,164 $13,500,000 $36,447,164 $2.70

Sango Court $72,488,258 $16,000,000 $56,488,258 $3.53

North San Pedro $60,229,610 $7,200,000 $53,029,610 $7.37

Corvin Apartments $56,946,894 $29,000,000 $27,946,894 $0.96

Page Street Apartments $40,716,824 $14,000,000 $26,716,824 $1.91

Totals $434,117,428 $111,030,000 $323,087,428 $2.91Source: Financial data provided by the Office of Supportive Housing.

Page 6: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

Page 5 of 7

It is important to note that PPLRs calculated in Exhibit 3 are based on projections and are likely to change over time as individual developments are completed and actual costs are finalized.

Housing Development Goals – Exhibits 4 and 5

In accordance with the Measure A Program Guidelines, Exhibit 4 below outlines the range and volume of the different types of housing units being built with the 10 developments underway. There are currently five categories of housing impacted by Measure A housing developments, of which we provide the following definitions for each type:

Permanent Supportive Housing (PSH): Housing units that provide long-term rental assistance, case management, and supportive services to the most vulnerable chronically homeless individuals and families.

Rapid Rehousing (RRH): Temporary housing units offered to individuals and families to quickly exit homelessness, all while receiving support services such as rental and financial assistance, case management, and support in identifying and securing permanent housing.

Extremely Low-Income (ELI): Housing units offered at rental rates below market value to households making up to 30 percent of the area median income (AMI).

Very Low-Income (VLI): Housing units offered at rental rates below market value to households making 31 to 50 percent of the AMI.

Low Income (LI): Housing units offered at rental rates below market value to households making 51 to 80 percent of the AMI.

As of the current reporting period, the Measure A funding commitment will assist in developing almost 17 percent of the total housing units per the program goals. Exhibit 4 below summarizes the development commitment of 27 percent of the goal for PSH units, approximately 10 percent of the goal for ELI housing units, and 25 percent of the goal for VLI housing units. None of the housing developments currently underway include RRH units. There are also 78 units of LI housing currently being built or planned for development, of which the Program Guidelines do not stipulate a development goal for this classification of housing.

Exhibit 4 Housing Development Goals vs Units Under Development

Project Name No. of

Units ** PSH RRH ELI VLI LI

Villas on the Park 83 83 0 0 0 0

The Veranda 18 6 0 6 6 0

Gateway Senior Apartments 74 37 0 0 5 32

Crossings on Monterey 38 20 0 0 11 7

Quetzal Gardens 70 24 0 23 0 23

Leigh Avenue Senior Apartments 63 63 0 0 0 0

Sango Court 101 40 0 31 14 16

North San Pedro 134 109 0 0 25 0

Corvin Apartments 145 80 0 0 65 0

Page Street Apartments 81 27 0 27 27 0

Totals 807 489 0 87 153 78

Program Goals 4,800 1,800 1,600 800 600 N/A*Percentage of Units in

Development 16.81% 27.17% 0.00% 10.88% 25.50% N/A Source: Data provided by the Office of Supportive Housing. * Program Guidelines do not stipulate a development goal for LI units. ** Note: The number of units exclude units dedicated for property managers for each development.

Page 7: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

Page 6 of 7

Although no new housing developments were allocated Program funds this last quarter, there are several adjustments related to how the number of units per development were categorized in Exhibit 4 above. Four of the housing developments contained inaccurate data when categorizing the volume of housing units by type in the last quarterly report. These were clerical errors from County staff, have since been corrected, and do not reflect any changes from developers or housing development plans. After receiving updated information from the Office of Supportive Housing, we highlight the following adjustments that occurred:

Sango Court had 71 units for ELI listed in the last report. This number has been adjusted to 31, as 40 of these units are actually PSH. This does not affect the total count of 101 total units.

North San Pedro had 58 units listed for ELI, which have been adjusted to zero. There were also 76 units for VLI, which has been adjusted to 25. These 109 units have been properly reclassified as PSH. These adjustments do not affect the total count of 134 units.

Corvin Apartments had 77 units listed for ELI, which has been adjusted to zero, and 68 units for VLI, which has been adjusted to 65. These 80 units have been properly reclassified as PSH. These adjustments do not affect the total count of 145 units.

Page Street Apartments had 54 units listed for VLI, which has been adjusted to 27, as 27 of these units were supposed to have been classified as PSH. This adjustment does not affect the total count of 81 units.

As of June 30, 2018, the Program has committed approximately 15.57 percent of all allowable bond proceeds to finance 16.81 percent of its housing goals, as observed in Exhibit 5 below. These ratios have not changed as of September 30, 2018, since no new housing developments were allocated Program funding at this time.

Exhibit 5 Program Commitments as a Percentage of Housing Goals

Housing Programs Program Funds Committed

Supportive Housing Development Program $111,030,000

HTSV Supportive Housing Fund $11,900,000

First time homebuyer loan program $25,000,000

Totals $147,930,000

Percentage of Max Bond Allowance Committed 15.57%1

Percentage of Affordable Units in Development 16.81%1Percentage of total allowable bond funds expended on housing development is calculated by dividing $950 million by the $147,930,000 committed or expended to-date.

Housing Development Timeline – Exhibit 6

Between the fourth quarter of Fiscal Year 2017-18 and first quarter of 2018-19, there were several milestones reached for housing developments. Development milestones are outlined in Exhibit 6 below, and we highlight the following activity from the last quarter:

Gateway Senior Apartments began construction on July 1, 2018, three months later than planned. Leigh Avenue Senior Apartments started construction on August 1, 2018, as planned. Sango Court obtained land use approval by July 1, 2018, as planned. North San Pedro met its goal date to secure all financing by September 19, 2018. Page Street Apartments missed its goal to obtain land use approval by September 3, 2018, but did obtain

approval by December 3, 2018.

Page 8: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

Page 7 of 7

Exhibit 6 Development Timeline: Projected vs Actual Milestones

Project Name Land Use Approval Secure All Financing Construction Starts

Construction Completed

Projected Actual Projected Actual Projected Actual Projected

Villas on the Park 11/29/2016 11/29/2016 11/14/2017 11/14/2017 3/1/2018 3/15/2018 4/1/2019

The Veranda 6/20/2017 6/20/2017 11/14/2017 12/5/2017 3/1/2018 5/15/2018 4/1/2019

Gateway Senior Apartments 4/18/2016 4/18/2016 11/14/2017 11/14/2017 4/1/2018 7/1/2018 6/1/2019

Crossings on Monterey 1/12/2016 2/21/2018 6/14/2018 5/16/2018 10/16/2018 10/16/2019

Quetzal Gardens 6/14/2017 6/14/2017 12/12/2018 1/1/2019 2/1/2020

Leigh Avenue Senior Apartments 7/10/2009 7/10/2009 5/16/2018 5/16/2018 8/1/2018 8/1/2018 2/1/2020

Sango Court 7/1/2018 7/1/2018 12/1/2018 3/1/2019 9/1/2020

North San Pedro 12/14/2011 12/14/2011 9/19/2018 9/19/18 11/1/2018 7/1/2020

Corvin Apartments 11/1/2018 5/1/2019 9/1/2019 10/1/2020

Page Street Apartments 9/1/2018 12/3/18 5/1/2019 8/1/2019 3/1/2021

Source: Data provided by the Office of Supportive Housing. Blue indicates that an action occurred ahead of schedule. Green indicates that an action occurred on schedule. Yellow indicates an action occurred later than projected, but within three months. Orange indicates an action has occurred more than three months later than projected.

Performance Dashboard

MGO has been working with the Office of Supporting Housing to design a page on their website for the Measure A performance metrics dashboard. Attached to this report is a snapshot from the website, and MGO will provide a live demonstration at the January 2019 Oversight Committee meeting. Financial Audit Attached to this report is MGO’s financial audit of the Measure A Program for Fiscal Year 2017-18. Although accounting standards require financial audits to report financial information in a specified manner, MGO reconciled expenditures reported in our annual advisory report for Fiscal Year 2017-18 to the financial audit. In summary, the audit confirms as of June 30, 2018 the following statistics:

Measure A had actually expended $19.9 million. Of the $19.9 million total expenditure, four of the 10 housing developments had accrued $7,957,771 in

actual expenditures through project reimbursements. In addition to the housing development reimbusements, $11.9 million had been awarded to Housing Trust

Silicon Valley for the Supportive Housing Fund. Finally, the audit confirms approximately $28,000 in actual expenditures for services rendered by MGO

in its capacity as the Oversight Committee’s Independent Advisor.

Page 9: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 1/9

County of Santa Clara

O�ice of SupportiveO�ice of SupportiveHousingHousing

HomeHome Housing and Community DevelopmentHousing and Community Development 2016 Measure A - A�ordable Housing Bond2016 Measure A - A�ordable Housing Bond 20162016

Measure A Housing Bond ProgressMeasure A Housing Bond Progress

2016 Measure A Housing Bond Progress2016 Measure A Housing Bond Progress

Program Overview

On November 8, 2016, the people of the County of Santa Clara approved Measure A,a proposition authorizing the County to issue up to $950 million in generalobligation bonds to acquire or improve real property for the purpose of providinga�ordable housing for vulnerable populations throughout the County. We providethe following highlights about the Measure A Program (Program):

Program funds are targeted to help construct 4,800 units of a�ordablehousing, in addition to assisting about 235 families to secure loans to financetheir first homes. In October 2017, a�er adopting a range of program guidelines over the use ofProgram funds, the County issued its first bond tranche of $250 million. As of September 30, 2018, the Program has committed almost $148 million, ofwhich $25 million is committed to the first-time homebuyer loan program,$11.9 million has been committed to a Supportive Housing Fund forpredevelopment loans, and about $111 million has been committed to 10housing developments that are in the process of developing 817 units ofa�ordable housing. As detailed in the program overview dashboard below, this means that almost16 percent of all bond proceeds are financing the development of 17 percentof the Program’s housing goals.

I am searching for...

Housing and Community DevelopmentHousing and Community Development Continuum of CareContinuum of Care

Solutions to HomelessnessSolutions to Homelessness Need AssistanceNeed Assistance Housing toolkitHousing toolkit

Draft Performance Dashboard/Website Snapshot(third party embedding of dashboard graphics impacts a clean PDF copy)

Page 10: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 2/9

In addition, for every dollar invested by the Program, the Program incentivizesan average of $2.91 from outside investments (Public/Private LeveragingRatio).

 

Measure A 2016 Affordable Housing Bond ProgramA high level summary of Measure A key �nancial and program

performance metrics as of September 30, 2018

$900M

$800M

$700M

$600M

$500M

$400M

$300M

$700,000,000 (73.68%)

Measure A Affordable Housing Bonds

4,80

0 U

nit G

oal

0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 5,000

817* (17.02%) 3,983 (82.98%)

In Development Remaining Units to be Developed

Affordable Housing Development Goal

$260M

$240M

$220M

$200M

$180M

$160M

$140M

$120M

$100M

$80M

$60M

$40M$11,900,000 (4.76%)

$91,743,309 (36.70%)

$102,070,000 (40.83%)

The graph below on the left indicates Measure A's approval of $950 million in affordable housing bonds, of which $250 million have been issued to date. The graph below on the right indicates the status of the $250 million issued to date.

The affordable housing development goal of Measure A is to build 4,800 units of affordable housing within Santa Clara County over 10 years. As of September 30, 2018 (13 months into the program) 817* affordable housing units are committed for development.

* Note: The number of units includes units dedicated for a property manager for each development.

Page 11: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 3/9

$200M

$100M

0

$950,000,000 Authorized

$250,000,000 (26.32%)

Bonds Issued (October 2017)

Unissued Authorized Bonds

$20M

0

$250,000,000 Bonds Issued (October 2017)

$19,286,691 (7.71%)

$25,000,000 (10.00%)

Expended

First-Time Homebuyer Program Commitment

Supportive Housing Fund Commitment

Committed, Unspent Uncommitted

Key Performance Results: Bond Proceeds Committed vs Housing Units in Development

Villas on the Park

The Veranda

Gateway Senior Apartments

Crossings on Monterey

Quetzal Gardens

Leigh Avenue Senior Apartments

Sango Court

North San Pedro

Corvin Apartments

Page Street Apartments

Overall Average

0 $1 $2 $3 $4 $5 $6 $7 $8 $9 $10 $11

$4.41

$10.39

$3.06

$2.94

$4.11

$2.70

$3.53

$7.37

$0.96

$1.91

$2.91

Public/Private Leveraging Ratio

Bond Proceeds Committed and ExpendedCompared to Total Measure A Bonds

Authorized

Housing Units in Development Comparedto Program Goals

0 5% 10% 15%

15.57% ($147,930,000 / $950,000,000)

17.02% (817 units / 4,800 units)

The chart above indicates that, as of September 30, 2018, the rate in meeting the affordable housing development program goals exceeds the pro rata share of Measure A bond funds committed.

The chart below shows the leveraging ratio from outside sources for every $1 of Measure A funding committed to date per affordable housing development project.

Page 12: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 4/9

Use of Bond Proceeds

The dashboards below provide details on the estimated cost share per unit andhousing development, sources of funding by housing development, and actualexpenditures to-date. As of September 30, 2018, we provide the followinghighlights:

The Program has committed $111,030,000 to 10 housing developments,with individual commitments ranging from $1 million (The Veranda) to $29million (Corvin Apartments). When looking at the estimated cost per unit of housing, the Program hascommitted anywhere from $52,623 per unit (The Veranda) to $210,938 perunit (Leigh Avenue Senior Apartments), with an average cost share of$135,900 per unit of housing. Although $111 million has been committed by the Program for housingdevelopments, about $19.3 million has been actually expended to-date.  

Villas on the Park (84/85)

The Veranda (19/20)

Gateway Senior Apartments (75/86)

$85,714 $377,948

$52,632 $546,883

$100 000 $305 514

Existing Development Projects

Estimated Cost Share Per UnitDevelopment (Number of Units/Bedrooms)

Page 13: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 5/9

Villas on the Park (84/85)

The Veranda (19/20)

Gateway Senior Apartments (75/86)

Crossings on Monterey (39/87)

Quetzal Gardens (71/141)

Leigh Avenue Senior Apartments (64/65)

Sango Court (102/129)

North San Pedro (135/136)

Corvin Apartments (146/147)

Page Street Apartments (82/83)

Average per Development (817/979)

0 $10M $20M $30M $40M $50M $60M $70M

$31,747,606

$10,390,778

$22,913,539

$17,041,968

$40,364,787

$13,500,000 (27.03%) $36,447,164

$16,000,000 (22.07%) $56,488,258

$53,029,610

$29,000,000 (50.92%) $27,946,894

$14,000,000 (34.38%) $26,716,824

$11,103,000 (25.58%) $32,308,743

Committed Measure A Funding Non-Measure A Estimated Funding

Gateway Senior Apartments (75/86)

Crossings on Monterey (39/87)

Quetzal Gardens (71/141)

Leigh Avenue Senior Apartments (64/65)

Sango Court (102/129)

North San Pedro (135/136)

Corvin Apartments (146/147)

Page Street Apartments (82/83)

Average Cost per Unit (817/979)

0 $100K $200K $300K $400K $500K $600K $700K

$100,000 $305,514

$148,718 $436,973

$138,451 $568,518

$210,938 $569,486

$156,863 $553,806

$53,333 $392,812

$198,630 $191,417

$170,732 $325,815

$135,900 $395,456

Measure A Estimated Cost Share per Unit Non-Measure A Estimated Cost Share per Unit

Sources of Funding for DevelopmentsDevelopment (Number of Units/Bedrooms)

$30M

$25M

$20M

$15M

$10M

$5M

0

Villas on the Park The Veranda Gateway SeniorApartments

Crossings onMonterey

Quetzal Gardens Leigh AvenueSenior

Apartments

Sango Court North San Pedro CorvinApartments

Page StreetApartments

$13,

500,

000

$16,

000,

000

$29,

000,

000

$14,

000,

000

Actual Expenditures (unaudited) Balance of Committed Funds

Measure A Funds Committed vs Expended by Affordable Housing Development Project

Measure A Expenditures for Affordable Housing Projects by Development Cost Category

$8M

$7M

$6M

$5M

$4M

$3M

$2M

$1M

0

Villas on the Park The Veranda Gateway SeniorApartments

Crossings onMonterey

Quetzal Gardens Leigh AvenueSenior

Apartments

Sango Court North San Pedro CorvinApartments

Page StreetApartments

$1,644,502 $607,481

$1,271,598

$2,031,928

Pre-Development Acquisition Construction

Page 14: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 6/9

Housing Program GoalsHousing Program Goals

Program housing goals aim to create 4,800 units of a�ordable housing. As ofSeptember 30, 2018, Program funds helped finance almost 17 percent of thetotal housing goal. The status of housing development goals by type of housingare as follows:

Program funds helped finance over 27 percent of the PermanentSupportive Housing (PSH) goal. Program funds helped finance almost 11 percent of the Extremely Low-Income (ELI) housing goal. Program funds helped finance over 25 percent of the Very Low-Income(VLI) housing goal. None of the current housing developments contain Rapid Rehousing (RRH)units. There are 78 units of Low-Income (LI) housing incorporated into thehousing developments; however, the Program has no housing goal for this

Page 15: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 7/9

category of housing.

The dashboards below provide detail on the number of units in development byhousing type, as well as how each housing development contributes to eachhousing goal.

Permanent Support Housing (PSH) - 1,800 Unit Goal

Rapid Rehousing (RRH) - 1,600 Unit Goal

Extremely Low Income (ELI) - 800 Unit Goal

Very Low Income (VLI) - 600 Unit Goal

Low Income (LI)

0 200 400 600 800 1,000 1,200 1,400 1,600 1,800

489 1,311

1,600

87 713

153 447

78

Units in Development Remaining Units to Meet Goal

Housing Goals by Affordable Housing Category

PSH

RRH

ELI

VLI

LI

0 50 100 150 200 250 300 350 400 450

83 6 37 20 24 63 40 109 80 27

6 23 31 27

6 5 11 14 25 65 27

32 7 23 16

Villas on the Park The Veranda Gateway Senior Apartments Crossings on Monterey Quetzal Gardens Leigh Avenue Senior Apartments Sango Court North San Pedro

Corvin Apartments Page Street Apartments

Housing Projects by Affordable Housing Category(Number of Units)

(Number of Units)

Page 16: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 8/9

List of housing developments funded by Measure A HousingBond:Select any development below to view a detailed summary of the project.

HousingHousing

DevelopmentDevelopment

Total #Total #

of Unitsof UnitsStatusStatus

PROJECTEDPROJECTED

COMPLETION DATE COMPLETION DATE

1. T he Ve randa 19under

constructionMay 2019

2. Villas on the Park 84under

constructionDec 2019

3. Gateway Senior

Apartments75

under

constructionDec 2019

4. Crossings on Monterey 39under

constructionDec 2019

5. Leigh Ave Senior

Apartments64 pre-construction Feb 2020

6. Page Street

Apartments82 pre-construction May 2021

7. North San Pedro

Apartments135 pre-construction July 2020

8. Quetzal Gardens 71 pre-construction Apr 2020

9. Corvin Apartments 146 pre-construction Jan 2021

10. Sango Court 102 pre-construction Sep 2020

11. Agrihood Senior

Apartments 165 pre-construction Jan 2022

12. Evans Lane Community

Village 61 pre-construction Feb 2021

13. West San Carlos

Housing 80 pre-construction Jan 2022

14. Blossom Hill Housing 147 pre-construction Sept 2021

15. Alum Rock Family

Housing 87 pre-construction Aug 2021

16. Roosevelt Park 80 pre-construction Apr 2022

17. Markham Plaza I 153 Renovation Sept 2020

18. Markham Plaza II 152 Renovation Sept 2020

19. Curner Studios 179 Revovation Dec 2020

Total New Units 1,437

Total Revovated

Units 484

Page 17: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

1/15/2019 2016 Measure A Housing Bond Progress - Supportive Housing - County of Santa Clara

https://www.sccgov.org/sites/osh/HousingandCommunityDevelopment/AffordableHousingBond/Pages/2016Measure_a_progress.aspx 9/9

Total Units 1,921

 

Last updated: 1/15/2019 4:10 PM

Report a problem with this pageReport a problem with this page

ABOUT SCCGOVABOUT SCCGOV

Agencies &

Departments

Contact Us

County Holidays

Newsroom

Parking and

Transit

Information

TERMS OFTERMS OF

USEUSE

Accessibility

Links Policy

Privacy

Policy

Terms of Use

MOBILEMOBILE

GALLERYGALLERY

SCCDineOut

SCCVector

SCCVOTE

Weed Hazard

SCC SOCIALSCC SOCIAL

MEDIAMEDIA

Facebook

Twitter

All Content Copyright © All Content Copyright © 2019 2019 , County of Santa Clara, CA, County of Santa Clara, CA

Page 18: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

COUNTY OF SANTA CLARA HOUSING BOND PROJECTS FUNDS

Independent Auditor’s Reports,

Financial Statements, and Independent Accountant’s Report

For the Year Ended June 30, 2018

Page 19: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 20: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 21: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 22: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 23: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 24: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 25: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 26: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 27: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 28: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 29: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 30: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in
Page 31: County of Santa Clara - Amazon S3...County of Santa Clara 2016 Measure A Citizens’ Oversight Committee Independent Advisor’s Quarterly Report, First Quarter FY 2018-19 Period in

Recommended