Date post: | 18-Dec-2014 |
Category: |
Technology |
Upload: | leonardo-energy |
View: | 3,093 times |
Download: | 0 times |
Feed-in tariffs – Design options and case studies for developing countries
Leonardo Webinar 26 January 2012
Dr. des. David Jacobs
Director Renewable Energy, IFOK GmbH
Course on Regulation and Sustainable Energy in Developing Countries – Session 4
www.leonardo-energy.org/course-regulation-and-sustainable-energy-developing-countries
Agenda
FIT design and case studies:
Feed-in tariff calculation
FIT financing
Capacity caps
Local content rules
3
FIT Countries 2010
Countries with state FIT policy
Countries with national FIT policy
Source: REN21, Renewables 2010 Global Status Report
Basic feed-in tariff design
• Purchase obligation
• “Independent” from power demand
• Fixed tariff payment based on the actual power generation costs
• Price setting will be discussed in session 4
• Long duration of tariff payment
Tariff calculation
Tariff calculation methodology
Early FITs (1970-1990s): Avoided costs
Benchmark: cost for conventionally produced electricity
Tariff level is only “right” coincidentally (under- or over-compensation)
• E.g. Nicaragua, Tanzania
Tariff calculation methodology
• Tariff calculation based on technology specific generation costs
+ “reasonable” rates of return
• Don’t use “avoided costs” as point of reference
• Cost factors:
• Investment costs (material and capital costs); Grid-related and administrative costs (including grid connection, costs for licensing procedure; Operation and maintenance costs; Fuels costs (biomass and biogas)
Rate setting process
Different jurisdictions use different methodologies for setting FIT rates.
Recent research reviewed several models for rate setting, results indicate:
• Most jurisdictions use similar approaches (even if inputs and assumptions vary):
Discounted Cash Flow (DCF), after-tax analysis– Discounts to present value the estimated annual cash
flows to equity investors
Building a feed-in tariff rate calculator
Goal is to reach an appropriate rate that is high enough to spur renewable energy development while at the same time not so high as to provide windfall profits to project owners.
Tradeoffs exist:• Ease of use vs. complexity• High-level representation vs. detailed analysis• Granularity vs. time investment
Tariff calculation methodology
• Targeted IRR (Internal rate of return)
• In the EU, feed-in tariffs target at an internal rate of return of 5-9 percent (certain jurisdictions use return on equity)
• In developing countries, the targeted IRR usually needs to be higher (10-20 percent)
• Public investment (monopolist, often without profit interest); or private IPPs (profitability important)?
• Similar profitability for renewable energy projects needed as for convention energy market
Equity IRR expectation in developing countries
Figure 4: Equity IRR expectation in developing countries:
0%
5%
10%
15%
20%
25%
Infrastructure
investment
(developed
world)
Technology
risk (missing
track record)
Political risk Reg. Risk, soft
political risk,
transparency,
legal
framework
Counterparty
risk
Currency
safety cushion
Infrastructure
investment
(developing
world)
Source. Fulton et al. 2011
Tariff calculation methodology
• Assumed capital structure
• Ratio of debt and equity (80 to 20 in Netherlands; 70 to 30 in Ontario (Canada))
• Germany; different debt-equity ratio depending on each technology (reflecting their risk profile)
• South Africa: 70:30
• Higher equity share in other developing countries?
• Interest rate for the debt? (international and national analysis needed)
• Generally, debt term (duration) equals duration of feed-in tariff payment (average of 20 years)
Tariff calculation methodology
• Tax treatment
• Pre-tax calculation (taking advantages and disadvantages from national taxation scheme into account)
Post-tax: Germany, because not significant available tax benefits, and because tax liabilities vary across ownership and investor types and are difficult to generalize – also used in Malaysia Accelerated depreciation factored in (e.g. India)
Tariff calculation methodology
• Treatment of inflation (indexation)
• Necessary because of long-term tariff payment (especially in developing countries with high inflation rates)
• Usually applied to the investment share that is related to O&M costs
Tariff calculation – South Africa (2009 vs. 2011)
Tariff calculation assumptions – Malaysia (2010)
Source: Kettha 2010
Tariff calculation in Germany: Input data for wind energy
• Medium transparency in Germany
Provision ofcapital
Equity share: 25% Return on equity (100% -location): 12%
Share of debt: 75 % Interest on debt: 5 % , or 5,5 %
Time period in question 20 years
Inflation rate 2% p.a.
Specific investment costs 60 and 80 % - location: 1.756 €/kW
100 % location: 1,463 €/kW
120% aand 150 % - location: 1, 336 €/kW
Annual costs of operation Year 1-10: 2.19 ct/kWh
Year 11-20: 2.49 ct/kWh
Source: BMU 2011
Tools for tariff calculation
RET Screen http://www.retscreen.net/
CREST model from NREL https://financere.nrel.gov/finance/content/CREST-model
Adoptation to national context is required (e.g. tax burdens andinvestment incentives)
Tools for tariff calculation – CREST from NREL (inputs)
Tools for tariff calculation – CREST from NREL (cash flow)
FIT financing
Financing mechanism - Germany
Financing mechanism in liberalized electricity markets
Financing trough “burden sharing” between all electricity consumers
Differences in emerging economies and developing countries
Subsidiesfor
conventionalpower
No interna-lization ofnegative
external costs
Artificially lowelectricity
prices = high cost difference
withrenewables
• low electricity costs
• little acceptance of electricity price increases
Combined financing – Taiwan
Source: David Jacobs
• Add additional financing to the national FIT fund (levy on producers fromconventional electricity)
• Increase the retail electricity price by a certain share (after general electionsnext year)
Conventional electricity producers
Retail price increase
Renewable Energy Fund (FIT Fund)
Payment for producers under the feed-in tariff
scheme
Money
Money
Money
FIT financing in Malaysia – limited electricity price increase
Source: Kettha 2010
FIT Fund in Malaysia
FIT financing cost in Germany (additional costs per kWh)
Source: BMU 2011
International FIT financing? – The future of international climate talks?
GET FIT financing flows
Source: DBCCA, "GET FIT", April 2010
Capacity caps
Capacity cap
• Capacity cap might be necessary to control costs (limited number of project)
• To control installed capacity (in line with central planning in monopolized electricity markets)
• E.g. tariff payment for first 400 MW wind energy, first 100 MW geothermal, and first 50 MW solar PV
• In this case: Project size should also be limited
• Application process needs to be regulated (“first-come, first-served”)
• Online application to avoid fraude? – Malaysia
Source: Mendonca et al. 2009
Capped feed-in tariff in Kenya (2009)
31
• Tariff payment for 15 years
• Rate setting based on generation costs
• Support of least cost RES technologies
Technology Mainland Price ($/kWh) Capacity cap
Wind $0.09 150 MWBiomass (firm and non-firm)
$0.045-0.07
200 MW
Hydro (firm and non firm)
$0.06-0.12
150 MW
Capped feed-in tariff in Ecuador
32
• Tariff payment for 12 years
• Rate setting based on generation costs
• Cap: 2% of installed capacity
Technology Mainland Price ($/kWh)
Wind $0.09Photovoltaic $0.52Biomass and biogas $0.10Geothermal $0.09Small-hydro up to 5 MW $0.06Small-hydro 5 MW-10 MW $0.05
Annual Quota on RE Capacity in Malaysia (MW)
Year Biomass Biogas Mini-Hydro Solar PV Solid WasteTotal per Annum
2011 110 20 60 9 20 219
2012 40 15 50 11 30 146
2013 50 15 60 13 40 178
2014 60 25 60 15 50 210
2015 70 25 60 17 60 232
2016 80 25 60 19 40 224
2017 90 30 50 21 40 231
2018 100 30 40 24 30 224
2019 100 30 30 28 30 218
2020 100 25 20 33 20 198
: : : :
2030 280 2 282
: : : :
2040 850 2 852
: : : :
2050 1,350 2 1,352
Source: MBIPV 2010
Annual Quota on RE Capacity in Malaysia (MW)
Source: MBIPV 2010
Capacity cap
• Disadvantages:
• “Stop-and-go” investment cycles – difficulty to establish a national industry (similar to tender)
• Unsustainable market development
Local content requirement
Local content requirement
• Several countries have introduced local content requirements in national support mechanisms, i.e. obligations to produce a certain share of renewable energy equipment locally/nationally (e.g. Spain, China, India, Argentina - Chubut, Ontario - Canada, Malaysia, Italy)
• These requirements can be implemented in national feed-in tariff mechanisms
• Establish a national renewable energy industry
• Take advantage of positive macro-economic effects
Source: Mendonca et al. 2009
Local content requirement Chubut
• Province in Argentina:
• Wind energy law 2005, Article 4, states:
• „... to enjoy this benefit, the wind mills installed have to comply with a timeline detailed further below of including components made or assembled in the Province of Chubut:a) As from 1 January 1999: 10%b) As from 1 January 2001: 30%c) As from 1 January 2003: 60%d) As from 1 January 2005: 80%e) As from 1 January 2007: 100%“
• Outcome: low incentive and rigid timeline impended wind power development in Argentina
Local content requirement Ontario
• Local content wind: 25%; 50% in 2012
• Local content solar: 40-50%; 60% in 2011
Local content requirement Ontario
• Complex definitions needed (Ontario): Solar PV
Designated Activity Qualifying
Percentage
Silicon that has been used as input to solar photovoltaic cells manufactured in an Ontario refinery.
10%
Silicon ingots and wafer, where silicon ingots have been cast in Ontario and wafers have been cut from the casting by a saw in Ontario.
12%
The crystalline silicon solar photovoltaic cells, where there active photovoltaic layer(s) have been formed in Ontario.
10%
Local content requirement Ontario
Solar photovoltaic modules (i.e. Panels), where the electrical connections between the solar cells have been made in Ontario and the solar photovoltaic module materials have been encapsulated in Ontario.
13%
Inverter, where the assembly, final wiring and testing has been done in Ontario.
9%
Mounting systems, where the structural components of the fixed or moving mounting systems have been entirely machined or formed or cast in Ontario. ….
9%
Wiring and electrical hardware that is not part of other Designated Activities (i.e. items 1, 2, 3 and 5 of this table) sourced from an Ontario Supplier.
10%
All on-site and off-site labour and services. For greater certainty, this Designated Activity shall apply in respect of all Contract Facilities.
27%
Total 100%
Local content requirement
• Problem: potential confliction with international trade rules (WTO)
• Malaysia: Adder for nationally produced equipment:
Malaysian tariff structure for solar PV
Source: Kettha 2010
International “worst” practice
International “worst” practise
• Low tariff = no tariff (e.g. Argentina: Premium tariff payment of 0.37 €cent/kWh for wind energy)
• Assessment report can help to correct tariff level
• Unnecessary high tariffs
• PV in Spain; PV in Czech Republic
• High rates of return; attracts speculation; unsustainable market
growth
• Short payment durations (annual changes)
• Germany until 1999; Spain until 2004, some Indian provinces
•Size specific tariffs (huge differences in tariff levels)
• Spain
Books on FIT design
The Evolution of FITs in Germany, Spain and France http://www.ashgate.com/default.aspx?page=637&title_id=11456&edition_id=1496
0&calcTitle=1
The feed-in tariff handbook
http://www.earthscan.co.uk/?tabid=92822
Online policy advice: How to design good feed-in tariffs?
Online policy advice:
Make your own FIT law
www.futurepolicy.org
Thank you for your attention!!!
Dr. des. David Jacobs I Director Renewable Energy IFOK GmbH
Reinhardtstraße 58
10117 Berlin
Tel.: +49 30 536077-27
E-Mail: [email protected]
www.ifok.de
© 2010, IFOK GmbHIFOK behält sich alle Urheber-, Marken-, Leistungsschutz- sowie sonstigen Rechte an den Inhalten der Präsentation vor. Ohne schriftliche Einwilligung durch IFOK dürfen diese Inhalte oder Teile davon weder bearbeitet oder verwertet noch Dritten zugänglich gemacht werden.Titel
Seite 48