Date post: | 11-Jan-2017 |
Category: |
Technology |
Upload: | glen-alleman |
View: | 189 times |
Download: | 3 times |
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
IPM2016
CPM-200: Scope and Organization Management
Lesson C: Using Technical Performance Measures to Inform Earned Value Performance
Glen B. Alleman Thomas J. CoonceNiwot Ridge, LLC Institute for Defense [email protected] [email protected]+1 303 241 9633 +1 703 362 2568
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Learning Objectives
• TLO #1: The student will recognize what a Technical Performance Measure (TPM) is in the context of the Professional Education Program Case Study as well as DOD and INCOSE Systems Engineering Guidance.
• TLO #2: The student will be able identify and select TPMs using the example Work Breakdown Structure from the Case Study.
• TLO #3: The student will learn how to prepare descriptions of TPMs needed to assess the physical “progress to plan” of the program.
• TLO #4: The student will able to judge the validity of a TPM from a list of TPM’s from the notional program.
2
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Components we’ll meet along the way to a credible PMB
ObjectiveStatusandEssentialViewstosupporttheproactivemanagementprocessesneededtokeeptheprogramGREEN
RiskManagement
SOWSOO
ConOpsWBS TechnicalandOperational
Requirements
CWBS&CWBSDictionary
IntegratedMasterPlan(IMP)
IntegratedMasterSchedule(IMS)
MeasuresofEffectiveness
MeasuresofPerformance
MeasuresofProgress
KeyPerformanceParameters
ProgramSpecificKeyPerformanceParameters
TechnicalPerformanceMeasures
EarnedValueManagementSystem
TPMsLiveHere
PerformanceMeasurementBaseline
TLO#1
3
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Can Earned Value Alone Get Us To Our Destination?
• How do we increase visibility into program performance?• How do we reduce cycle time to deliver the product?• How do we foster accountability?• How do we reduce risk?• How do we start our journey to success?
IncreasingtheProbabilityofSuccessmeans…ConnectingTheDotsBetweenEVMandTPMtoReachOurDestination
TLO#1
4
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Increasing the Probability of Program Success Means …
Risk
SOW
Cost
WBS
IMP/IMS
TPM
PMB
Building A Credible Performance Measurement Baseline
This is actually harder than it looks!
TLO#1
5
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Identifying the TPMs starts with good Systems Engineering
TLO#1
6
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Some More Guidance
Systemsengineeringusestechnicalperformancemeasurements tobalancecost,schedule,andperformancethroughoutthelifecycle.Technicalperformancemeasurementscompareactualversusplannedtechnicaldevelopmentanddesign.Theyalsoreportthedegreetowhichsystemrequirementsaremetintermsofperformance,cost,schedule,and progressinimplementingrisk handling.Performancemetricsaretraceabletouser–definedcapabilities.―DefenseAcquisitionGuide
(https://dag.dau.mil/Pages/Default.aspx)
In The End ― It’s Always About Systems Engineering
TLO#1
7
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
This Has All Been Said Before
… the basic tenets of the process are the need forseamless management tools, that support anintegrated approach … and “proactive identificationand management of risk” for critical cost, schedule,and technical performance parameters.― Secretary of Defense, Perry memo, May 1995
Why Is This Hard To Understand?§ We seem to be focused on EV reporting, not the use of
EV to manage the program.§ We think getting the IPMR out the door is the end of
Program Planning and Control’s efforts, not the beginning.
TPM Handbook 1984
TLO #1
8
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Back To Our Technical Performance Measures
Technical Performance Measures do what they say,
Measure the Technical Performanceof the product or service produced by
the program.
TLO#2
9
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
To develop TPMs we first need to define some other measures
• Measures of Effectiveness (MoE)• Measures of Performance (MoP)• Key Performance Parameters (KPP)• Then we can define the Technical
Performance Measures (TPM)
10
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Measure of Effectiveness (MoE)
Measures of Effectiveness …• Are stated in units meaningful to the buyer,• Focus on capabilities independent of any technical
implementation,• Are connected to the mission success.
Operational measures of success that are closely related to the achievements of the mission or operational objectives
evaluated in the operational environment, under a specific set of conditions.
MoE’s Belong to the End User
TLO#2
“TechnicalMeasurement,”INCOSE–TP–2003–020–01
11
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Measure of Performance (MoP)
Measures of Performance are …• Attributes that assure the system has the
capability and capacity to perform,• Assessment of the system to assure it meets
design requirements to satisfy the MoE.
Measures that characterize physical or functional attributes relating to the system operation, measured or estimated
under specific conditions.
“TechnicalMeasurement,”INCOSE–TP–2003–020–01
MoP’s belong to the Program – Developed by the Systems Engineer, Measured By CAMs, and Analyzed by PP&C
TLO#2
12
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Key Performance Parameters (KPP)
Key Performance Parameters …• Have a threshold or objective value,• Characterize the major drivers of performance,• Are considered Critical to Customer (CTC).
Measures that Represent the capabilities and characteristics so significant that failure to meet them can be cause for reevaluation, reassessing, or termination of the program
The acquirer defines the KPPs during the operational concept development – KPPs say what DONE looks like
TLO#2
“TechnicalMeasurement,”INCOSE–TP–2003–020–01
13
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Technical Performance Measures (TPM)
Technical Performance Measures …• Assess design progress,• Define compliance to performance requirements,• Identify technical risk,• Are limited to critical thresholds,• Include projected performance.
Attributes that determine how well a system or system element is satisfying or expected to satisfy a technical
requirement or goal
TLO#2
“TechnicalMeasurement,”INCOSE–TP–2003–020–01
14
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
TPMs start with the WBSTLO#2
1.0SaferCounties/Safer
Cities
1.1SC2PrimeMission
Equipment
1.1.1.CameraSystems
1.1.1.1Camera
1.1.1.2CameraInterfaceHardware
1.1.1.3CameraIntegration
1.1.2WirelessTowerSystem
1.1.2.1WirelessTower
1.1.2.2TowerInterfaceTower
1.1.2.3TowerIntegration,Test,Assembly,and
Checkout
1.1.3MonitoringStations
1.1.3.1PCStations
1.1.3.2PCInterfaceHardware
1.1.3.3MonitoringStationsIntegration,Test,Assemblyand
Checkout
1.2SystemEngineering
/ProgramManagement
1.3SystemTestand
Evaluation
1.4Data
1.5Training
Let’s focus on the wireless towers and the services they provide to public safety, as well as convenience for the citizens.We’ll need MOPs, MOEs, KPPs, before we define the TPMsThen we’ll connect these TPM’s to assessing the performance of the work in the IMS.
15
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
§ This is where TPMs are connected with the MoE’s and MoP’s
§ For each deliverable from the program, all the “measures” must be defined in units meaningful to the decision makers.
§ Here’s some “real” examples.
Connecting the MoE, MoP, KPP, and TPMs
1. Providebandwidthfor5,000simultaneousvoiceanddatausers
2. Providelocationservicefor911
3. Provide99.5%availabilitytousers
MeasuresofEffectiveness(MoE)
1. NetReady2. E911LocationQuality3. Phone
Interoperability4. Manpower5. Availability
KeyPerformanceParameters(KPP)
1. NetReady§ IPv4/6compliance§ 1GbEthernet
2. Locationquality§ Accuracythreshold@60M
§ Integritythreshold@40M
3. Phoneinteroperability§ Processingcapabilitymeetsgrowthmatrix
4. Manpower§MTBC>1000hrs§MCM<2hrs
5. Availability§ Clearthreshold>99%§ Noisethreshold>90%
MeasuresofPerformance(MoP)
1. NetReady§ Standardmessagepackets
2. LocationQuality§Multipathallocationbudget
§Multipathbiasprotection3. PhoneInteroperability
§MOSAcompliant§ Civilcompliant
4. Manpower§ Operatingelapsedtimemeters
§ Standbyelapsedtimeindicators
5. Availability§ Phasecentervariations
TechnicalPerformanceMeasures(TPM)
MissionCapabilitiesandOperationalNeed
TechnicalInsight– Riskadjustedperformancetoplan
TLO#2
16
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Identifying Technical Performance Measures
Technical Performance Measures must be technicaland must describe the performance in units of measure
meaningful to the decision makers.TPM’s are not counts of things delivered. TPMs are not assessments of completed work through effort or cost.
TPMs are measures of Technical Performance
TLO#3
17
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
How can we possibly know we’re on schedule or on budget without knowing if we’re technically compliant?
TLO#3
18
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Measures of Technical Parameters†
Attribute Description
AchievedtoDate § Measuredtechnicalprogressorestimateofprogressinunits ofperformance
CurrentEstimate § Valueofatechnicalparameterthatispredictedtobeachievednowor inthefuture
Milestone § Pointintimewhen anevaluationofthetechnicalmeasureisaccomplished
PlannedValue § PredictedvalueofthetechnicalparameterPlannedPerformance
Profile§ Profilerepresentingtheprojecttimephased
demonstrationofatechnicalparameterToleranceBand § Managementalertlimits
Threshold § Limiting acceptablevalueofatechnicalparameter
Variances § Demonstratedtechnicalvariance§ Predictedtechnicalvariance
TLO#3
†INCOSESystemsEngineeringHandbook
19
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
A Familiar Graphic for TPMs
Variance
PlannedValue
PlannedProfileCurrentEstimate
Milestones
Threshold
UpperControlLimit
LowerControlLimit
MeanToBetweenFailure
Time=ProgramMaturity
AchievedtoDate
TPM
TLO#3
20
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
What Do We Need To Know About This Program Through The TPMs?
• What WBS elements represent the TPMs?• What Work Packages produce these WBS
elements?• Where do these Work Packages live in the IMS?• What are the Earned Value baseline values for
these Work Packages?• How are we going to measure all these variables?• What does the curve look like for these
measurements?
TLO#3
21
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Let’s Connect Some More DotsTLO#3
Risk
SOW
Cost
WBS
IMP/IMS
TPM
PMB
❺DeliverablesdefinedintheSOW,tracedtotheWBS,withnarrativesandMeasuresofPerformance(MoP)
❹BudgetattheWorkPackagelevel,rolledtotheControlAccountsshowingcostspreadsforallworkintheIMS
❻MeasuresofPerformance(MOP)foreachcriticaldeliverableintheWBSandidentifiedineachWorkPackageintheIMS,usedtoassessmaturityintheIMP
❶TheProductsandProcessesina“wellstructured”decomposition,traceabletothedeliverables
❷ IMScontainsalltheWorkPackages,BCWS,Riskmitigationplans,withtracestotheIMPmeasuringincreasingmaturitythroughMeasuresofEffectiveness(MOE)andKPPs
❸TechnicalandProgrammaticRisks ConnectedthroughtheWBS,RiskRegister,IMPandIMS
ThePMBistheDocumentofRecordfortheProgramPerformanceisMeasured
throughthePMB
22
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Raison d'etre for Technical Performance Measures
The real purpose of Technical Performance Measures is to reduce Programmatic and Technical RISK
Risk
SOW
Cost
WBS
IMP/IMS
TPM
PMB
TLO#4
23
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Key Elements of A Good TPM
• Traceability – Requirements to WBS to TPMs to EV control accounts.
• Impact – How much WBS work, & therefore EV money, is covered by the TPM(s)? What is effect?
• TPM Banding/Sensitivity – What banding (R/Y/G) and sensitivity (EV impact) should be used for each TPM?
• Technical Readiness Level – What’s the state of the technology supporting the requirement(s) for which TPM is a metric?
ImplementingTechnicalPerformanceMeasurement,MikeFerraro,GeneralEngineer,PEO/SYSCOMConference
TLO#4
24
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Determination of Physical % Complete must be informed by both task completion and technical
status
4Progress of a set of tasks – Drawings Completed– Lines of Code Written– Work Products Produced– Reviews Completed
• Progress of the technical status – Critical TPM Achievement– System Capabilities Met– Quality of Work Products– System Under Review Acceptable
Measuringprogressofwhatpeopledo
MeasuringprogressoftheResultofwhatpeopledo
Progressismeasuredbyeffectiveness ofoutcomestotheenduser
Physical % Complete P%C
TLO#4
BCWPii=1
N
∑ = BCWSi × P%Cii=1
N
∑
25
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Connecting the EV VariablesIntegratingCost,Schedulele,andTechnicalPerformance
AssuresProgramManagementhastheneededperformanceinformationtodeliveron‒time,on‒budget,andon‒specification
TechnicalPerformanceMeasuresCost Schedule
ConventionalEarnedValue
+=
§ MasterScheduleisusedtoderiveBasisofEstimate(BOE)nottheotherwayaround.
§ Probabilisticcostestimatingusespastperformanceandcostriskmodeling.
§ Labor,Materiel,andotherdirectcostsaccountedforinWorkPackages.
§ Riskadjustmentsforallelementsofcost.
CostBaseline§ EarnedValueisdilutedbymissingtechnicalperformance.
§ EarnedValueisdilutedbypostponedfeatures.
§ EarnedValueisdilutedbynoncompliantquality.
§ AllthesedilutionsrequireadjustmentstotheEstimateatComplete(EAC)andtheToCompletePerformanceIndex(TCPI).
TechnicalPerformance§ Requirementsaredecomposedintophysicaldeliverables.
§ DeliverablesareproducedthroughWorkPackages.
§ WorkPackagesareassignedtoaccountablemanager.
§ WorkPackagesaresequencedtoformthehighestvaluestreamwiththelowesttechnicalandprogrammaticrisk.
ScheduleBaseline
TLO#4
26
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
TPM ChecklistMoE MoP TPM
Traceabletoneeds,goals,objectives,andrisks.
TraceabletoapplicableMOEs,KPPs,systemlevelperformancerequirements,andrisks.
TraceabletoapplicableMoPs,systemelementperformance,requirements,objectives,risks,andWBSelements.
Definedwith associatedKPPs.
Focusedontechnicalrisksandsupportstrades betweenalternativesolutions.
Furtherdecomposed,budgeted,andallocatedtolowerlevelsystemelementsintheWBSandIMS.
EachMoEindependentfromothers.
Providedinsightintosystemperformance.
Assignedanowner,theCAMandWorkPackageManager.
EachMoEindependentoftechnicalanysolution.
Decomposed, budgetedandallocatedtosystemelements.
Sourcesofmeasureidentified andprocessesforgeneratingthemeasuresdefined.
Address the requiredKPPs. Assignedan“owner,”theCAMandTechnical Manager.
Integratedintotheprogram’sIMSas partoftheexitcriteriafortheWorkPackage.
TLO#4
27
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Summary of TPM Benefits
• Measures of results based on technical achievement
• Integrated technical performance with budget and schedule – providing an integrated systems approach to performance measurement
• Establishes the linkage between engineering and cost/schedule considerations in program management decision making
• Measures the programmatic impact of technical variance in terms of risk
• Reduces subjectivity through the establishment of technical performance baseline
TLO#4
28
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Past Issues with Earned Value Management and Scheduling
• Ability to take credit for all work accomplished• How to defend what work was earned• Identifying EV milestones in the schedule focused
attention on those tasks so that maximum earned value could be taken
• IMS was too detailed to manage the program• CAM’s used other means to manage and assess
progress related to their work; i.e. detailed schedules• Detailed schedules did not reflect what was reported in
IMS
29
Solution(– Quantifiable(Backup(Data((QBD)
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Quantifiable Backup Data (QBD)
• A QBD is a supplement to the IMS to help manage discrete work at a lower level than is maintained in the IMS
• The QBD measures the work objectively– 748-C calls out on Page 1– Objectively assess accomplishments at the work
performance level• QBD’s are part of the PMB• QBD’s do not replace the EVMS Earned
Value Techniques (EVT)30
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Quantifiable Backup Data (QBD)
• A detailed listing of tasks necessary to complete all scope in a work package during the defined period of performance.
• It is an approach used to objectively measure performance– Each task on the list is weighted – total weighting equals 100% of the
work package BAC (weighting is important, should not be equal weighting on every task).
– Upon completion of QBD development the QBD is placed under configuration control.
– The CAM assesses physical percent complete of each QBD task.– The percent complete is calculated from the cumulative assessments.
• The purpose of the QBD is to:– Ensure and demonstrate that all contract work is accounted for;– Ensure the schedule and budget are realistic and achievable;– Mitigate schedule and budget risks; and,– Provide a basis for objectively assessing progress for discretely
measured work packages.
31
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
32
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
What We’ll Do In Our Hands On Work Shop
Based on a notional case study for a county surveillance system, we will strategize about the system MOEs
and MOPs and decide upon appropriate TPMs to inform our
program performance and BCWP
33
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Case Study Set Up
• The county is concerned about controlling disturbances, mitigating crime, and having forensic video and sound evidence for legal purposes
• The county desires to procure a surveillance system with cameras and sound devices at strategic locations, send the data feeds via wireless technology, monitor, store and retrieve selected incidents
34
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Case Study Set Up (Continued)
• The county wants near “real time” response and desires video quality such that they can distinguish facial features and read a license plates within 20 feet from the camera
• It also wants the system to alert operators when there is evidence of a disturbance
• It wants equipment that will allow them to store five years worth of data feeds collected 24/7
35
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Case Study Set Up (Concluded)
• The county has submitted a Request for Proposal (RFP) to procure, install, test and train personnel. The county has set aside of budget of $40M and wants the system operational within 18 months. Because of the nature of the procurement, the county has required monthly IPMRs (See Handout 1 for details)
• You are the proposal manager for the contract. Your immediate job is to – Determine the system’s “Measure of Effectiveness”– Select appropriate Technical Performance Measures to
use to inform or drive reported cost and schedule progress– Propose how you will ensure the county that cost and
schedule progress is consistent with measured technical progress
36
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Handout # 1
Safer County/Safer City Surveillance Background and
Technical Requirements
37
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Exercise # 1
• What are possible Measures of Effectiveness (MOEs) of the System?
• What are possible Measure of Performance (MOPs) of the System?
• What are possible Technical Performance Measures (TPM) that could be used to drive or inform the cost and schedule progress?
38
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
AllthesemeasuresusedtoinformBCWP
Reminder: MOEs, MOPs, and TPMs are Connected to the IMP/IMS
SOWConOps
WBSCWBS
TechnicalPerformanceMeasures
MessagesofPerformance
MeasuresofEffectivenessKPPs
IntegratedMasterPlan
IntegratedMasterSchedule
PerformanceMeasurement
Baseline
TechnicalandOperationalRequirements
39
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Handout # 2
Safer County/Safer City Surveillance System
School Solution
40
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Exercise # 2
• Discuss school solution
41
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Exercise # 3
• Which WBS elements & IMS Work Packages need to be informed by TPM progress?
42
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Handout # 3
Safer County/Safer City Surveillance System
Work Breakdown Structure and Integrated Master Schedule
43
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Presentation of Workshop Results
With our MOE’s, MOP’s, KPP’s, and TPM’s let’s assess out needed
capabilities against the technical solution
44
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
Questions???
45
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
OFFICIAL VERSION
COLLEGE OF PERFORMANCE MANAGEMENTPROGRAM OF INSTRUCTION
500C VERSION 1.225 Mar 2015
Approvals:
William Mathis, V.P of Education and Certification 25 Mar 2015 [Add appropriate approval individual name and title] Date
[Add appropriate approval individual name and title] Date
[Add appropriate approval individual name and title] Date
46
CPMIPM2016RightsReservedbytheOrganizationontheCoverPage
RECORD OF CHANGES
VERSION NUMBER
DATE NUMBER OF FIGURE, TABLE OR PARAGRAPH
A*M D
TITLE OR BRIEF DESCRIPTION CHANGEREQUESTNUMBER
1 22 Feb 2014 A,M Format change for IPM 20141.1 18 Sep 2014 A,M Format change for IPMW 20141.2 25 Mar 2015 A,M Format changes
Record of Changes
47