+ All Categories
Home > Documents > Cpm Requirement

Cpm Requirement

Date post: 28-Feb-2018
Category:
Upload: clarrize-angelica-paitan
View: 224 times
Download: 0 times
Share this document with a friend

of 14

Transcript
  • 7/25/2019 Cpm Requirement

    1/14

    CTIVITY DURATION

    DAYS

    JOB DESCRIPTION

    1-2 1 Relocation of boundaries-cleaning2-3 2 Construction of eld oce

    2-4 5 Delivery of materials2-5 2 Staing and batter boards3-5 ! Digging"e#cavation4-5 1$ Cutting and assembling of steel

    reinforcements4-% $ Dummy3-! 12 &aing of forms and door 'ambs5-! ( )ositioning steel reinforcement5-% 5 *orms and sca+oldings

    5-, , lectrical. /lumbing and 0ater /i/econnections!-, $ Dummy!-( 2 )ouring of footings and columns%-, 1 Removal of forms

    %-1$ 12 C laying and baclling,-1$ % eams and slab forms. reinf nd various

    /i/ing installations,-( $ Dummy

    ,-11 , Roof framing and roong seet

    (-11 4 )ouring of beam and slabs1$-11 2 Construction of stair0ays1$-13 12 )lastering and tile 0ors11-12 2 6nstallation of doors and 0indo0s(-14 3 )lumbing 7 drainage system12-14 2 6nstallation of /lumbing #tures12-13 3 6nstall electrical 0iring 7 #tures13-15 , )ainting and varnising

  • 7/25/2019 Cpm Requirement

    2/14

    14-15 2 *inal 0or and cleaning

  • 7/25/2019 Cpm Requirement

    3/14

    2 4 ! ,1$

    12

    14

    1!

    1,

    2$

    22

    24

    2!

    2,

    3$

    32

    34 3! 3, 4$ 42

    44

    4!

    4,

    5$

    52 54

    (-14

    2-3

    3-! 5-!!-(

    3-5 (-11

    2-5 5-,

    ,-11

    12-

    1414-

    151-

    2

    %-

    , ,-1$

    2-4

    1$-

    11

    4-5

    11-

    12

    5-%12-13

    %-1$

    1$-13

    13-15

  • 7/25/2019 Cpm Requirement

    4/14

    EXCAVAITION

    60 sq. m. X 434.27 Pesos / sqm = 26,056.00

    ROOFING WORKS

    Roof = 1.2 x 500 = 60,000.00

    Steel Deck Cap = 12 x 750 = 9,000.00

    Roofing Nails= 2.4 x 250 = 600.00

    TOTAL 69,600.00

    ROOF FRAMING

    Angle Bar = 60 x 450 = 27,000.00

    Purlins = 60 x 350= 21,000.00

    Anchor Bolt = 60 x 50= 3,000.00

    (Welding Services) = 333.33333 x 20000= 20,000.00

    D8 S8

    C86968:D;R86

  • 7/25/2019 Cpm Requirement

    5/14

    TOTAL = 71,000.00

    FLOOR WORKS

    1st Floor

    Tiles = 200 x 280 = 56,000.00

    Adhesive = 12 x 220 = 2,640.00

    Cement = 12 x 230 = 2,760.00

    TOTAL = 61,400.00

    REINFORECMENT

    Footings

    Rebar 12mm Type 1 (Long Bars) = 8 x 325 = 2,600.00

    Rebar 12mm Type 2 (Long Bars) = 8 x 325 = 2,600.00

    Rebar 10mm Type 1 (Alternating Bars) = 5 x 135= 675.00

    Rebar 10mm Type 2 (Alternating Bars) = 5 x 135= 675.00

  • 7/25/2019 Cpm Requirement

    6/14

    TOTAL = 6,550.00

    Column

    Rebar 12mm Type 1 (Long Bars) = 32 x 325 = 10,400.00

    Rebar 16mm Type 2 (Long Bars) = 13 x 340= 4,200.00

    Tie Wire = 13 x 90= 1,170.00

    TOTAL = 143,910.00

    Beam

    Rebar 12mm Type 1 (Long Bars) = 24x 325 = 7,800.00

    Rebar 16mm Type 2 (Long Bars) = 10x 340= 3,400.00

    Tie Wire = 10x 90= 900.00

    TOTAL = 108,900.00

  • 7/25/2019 Cpm Requirement

    7/14

    FORMWORKS (1st Floor)

    Column

    Plywood

    Cocolumber

    Ordinary Nails

    Tie wire #16

    TOTAL = 6,557.24

    Beam

    Plywood

    Cocolumber

    Ordinary Nails

    Tie wire #16

    TOTAL = 19,906.15

    Slab

    Plywood

  • 7/25/2019 Cpm Requirement

    8/14

    Cocolumber

    Ordinary Nails

    Tie wire #16

    TOTAL = 24,857.12

    FORMWORKS (2nd Floor)

    Column

    Plywood

    Cocolumber

    Ordinary Nails

    Tie wire #16

    TOTAL = 6,557.24

    Beam

    Plywood

    Cocolumber

    Ordinary Nails

    Tie wire #16

  • 7/25/2019 Cpm Requirement

    9/14

    TOTAL = 19,906.15

    Slab

    Plywood

    Cocolumber

    Ordinary Nails

    Tie wire #16

    TOTAL = 24,857.12

    CONCRETING

    1st Floor

    Ready Mix Concrete (7days curing, 3500 psi)

    Pumpcrete Consumables

    TOTAL 80,235.00

    MASONRY WORKS

    1st Floor External Wall

  • 7/25/2019 Cpm Requirement

    10/14

    6" CHB

    Sand

    Gravel

    10 mm rebar

    Cement

    TOTAL 49,059.58

    1st Floor Internal Wall

    4" CHB

    Sand

    Cement

    Gypsum Board

    Metal Studs & Tracks

    Gypsum Screw

    Gypsum Patty

    Gypsum Tape

    TOTAL 24,047.83

    Total Cost for BOM & BOQ : 1,000,000.00 Php

    CONTRACTORS MARK UP 2!: 20,000.00 Php

  • 7/25/2019 Cpm Requirement

    11/14

    "al#$ A%%$% Ta '"AT 12!( : 120,000.00 Php

    GRAND TOTAL = 1,370,000.00 Pesos

  • 7/25/2019 Cpm Requirement

    12/14

    ACTIVITY TIME IN DAYS COST COST TO

    EXPEDITENORMAL CRASH NORMAL CRASH

    1-2 1 1 20,000 25,000 300

    2-3 1 1 5000 10,000 300

    2-4 1 1 10,000 15,000 300

    2-5 6 4 5000 12,000 300

    3-5 1 1 3000 6,000 300

    4-5 7 5 11,500 20,000 300

    4-7 4 2 50,000 65,000 300

    3-6 0 0 0 0 300

    5-6 5 4 30,000 50,000 300

    5-7 10 7 30,000 45,000 300

    5-8 5 4 70,000 100,000 300

    6-8 10 7 58,000 90,000 300

    6-9 0 0 0 0 300

    7-8 3 2 26,000 27,000 300

    7-10 1 1 10,000 15,000 300

    8-10 14 10 60,000 80,000 300

    8-9 7 5 50,000 95,000 300

    8-11 0 0 0 0 300

    9-11 7 7 150,000 200,000 300

  • 7/25/2019 Cpm Requirement

    13/14

    10-11 4 3 40,000 55,000 300

    10-13 14 14 50,000 70,000 300

    11-12 3 2 120,000 130,000 300

    9-14 3 2 30,000 50,000 300

    12-14 2 1 15,000 30,000 300

    12-13 3 2 15,000 30,000 300

    13-15 8 5 90,000 130,000 300

    14-15 2 1 6,000 7000 300

    TOTAL 994,500 1,370,000 8,400

  • 7/25/2019 Cpm Requirement

    14/14


Recommended