Date post: | 07-Apr-2018 |
Category: |
Documents |
Upload: | walt-flowers |
View: | 217 times |
Download: | 0 times |
of 52
8/3/2019 Crane Sling MSHA1
1/52
CRANES, SLINGS,& YOU
They can do a lot of work
8/3/2019 Crane Sling MSHA1
2/52
They can do a lot of damage
CRANES, SLINGS,& YOU
8/3/2019 Crane Sling MSHA1
3/52
Idle Cranes
Cranes that have been idle, must be
inspected and tested before beingplaced back in service using the criteria
that applies to periodic inspection.
Special attention should be given to thehook, lifting chain and wire rope.
Review the manufacturers s ecific ins ection re uirements!
8/3/2019 Crane Sling MSHA1
4/52
Altered Cranes
Cranes that have been altered or repaired
must be inspected and tested. If loadsustaining parts are altered or repaired, a
load test should be conducted to verify the
rated load capacity of the crane. Report
issued by a qualified person and kept on
file.
8/3/2019 Crane Sling MSHA1
5/52
Load Testing
When load testing, the test load cannot
exceed 125 percent of the rated load.Hoists & cranes should be operated anumber of times at various positions.Report issued by testing organizationgiving the conditions under which systemwas load tested.
8/3/2019 Crane Sling MSHA1
6/52
Preventive
Maintenance1. Clean & lube wire rope & chain
2. Adjusting brakes
3. Checking & filling gear cases levels4. Replacing any contaminated oils
5. Lube bearings, gears, pinions, linkages, & shafts
6. Adjusting operation of limit switches7. Clean & replace pitted/burned electrical contacts
8. Cleaning or replacing air & fluid filters
9. Inspecting all controls & warning systems
8/3/2019 Crane Sling MSHA1
7/52
General Pre-Op Test
1. Disconnects are known before any test
2. Get help if youre not familiar with the cranes
3. Follow manufacturers recommendations4. Follow Checklist
5. Inspect electrical controls
6. Check for obstructions in cranes travel path
7. Test proper operation of controls
8. Observe for smooth operation of components
9. Never unwind spool completely
10.Check upper & lower limit switches
8/3/2019 Crane Sling MSHA1
8/52
Hook Pre-op Test
1. Replace if deformed or cracked
2. Check for proper function of safety latch
3. Inspect for twists from plane of unbent hook4. Check for proper swivel
5. Hook repair is not recommended
6. Emergency hook repair must be performedonly under competent supervision
7. After any hook repairs, hook must be loadtested before being returned to normal
service
8/3/2019 Crane Sling MSHA1
9/52
Rope Pre-op Test
1. Reduction in rope diameter
2. Broken or worn outside wires
3. Corroded or broken wires at end ofconnections
4. Severe kinking, crushing, cutting or
unstranding5. Corroded, cracked, bent, worn, or
improperly applied end connections
8/3/2019 Crane Sling MSHA1
10/52
Lockout-Tagout
1. Review individual crane requirements
2. Integrate lockout & maintenance
requirements3. Lockout-tagout training
4. Written program established & reviewed
5. Ask manufacturer for lockout devicerecommendations
6. Devices not always interchangeable
between different cranes
LOCKEDOUT
This Lock/Tag mayonly be removed by
NAME: __________DEPT : __________COMPLETIONDATE: ___________TIME: ____________
DONT OPERATE
DANGER
8/3/2019 Crane Sling MSHA1
11/52
Crane Safety BasicsNever allow a co-worker
between a fixed objectand a load!
2TON
DANGER
WORKINGCRANES
8/3/2019 Crane Sling MSHA1
12/52
The feeder waslowered to theground, resting in anunsecured position.The feeder rolled on
its side, pinning thevictim against thewall of an adjacent
control booth.
Fatalgram
8/3/2019 Crane Sling MSHA1
13/52
The employee was in the process ofloading a conveyor onto the trailer of histruck using the truck's crane. The cableattached to the conveyor slipped off thehook of the crane causing the conveyor to
bounce off the trailer and crush the victimwho was standing between the crane andthe trailer. He died from crushing injuries.
Fatalgram
8/3/2019 Crane Sling MSHA1
14/52
Know the safe travel
radius of the crane.Contact withelectrical sources or
other hazards canresult in catastrophicconsequences.
Safe Working Radius
8/3/2019 Crane Sling MSHA1
15/52
Load Chart
8/3/2019 Crane Sling MSHA1
16/52
Even when properly trained, equipment
properly maintained, & employees work in a
safe manner, accidents can still occurbecause crane operations are dependant on
mechanical devices that can fail. The results
can be catastrophic. You are the onlycontrolling influence that can minimize the
hazard. Your life literally is in your own
hands!
Crane Safety Basics
8/3/2019 Crane Sling MSHA1
17/52
1. No history of unsafe acts in workplace
2. Mature & safe attitude
3. Ability to react quickly in an emergency4. Drug & alcohol free
5. Good depth perception
6. Good hearing and vision7. Thoroughly trained
8. Understand lift requirements
9. No medication that will interfere with operation
OperatorRequirements
8/3/2019 Crane Sling MSHA1
18/52
Safe Practices1. Test controls & brakes at start of shift2. Dont operate unsafe cranes or hoists
3. Test brakes by a short lift to ensurecontrol
4. Move loads only after being signaled by
designated, qualified signaler
8/3/2019 Crane Sling MSHA1
19/52
1. Never carry loads over anyone
2. Never carry loads past anyone
3. Signalers in line-of-sight of operator
4. No riders on loads or hooks
5. No unauthorized person operating crane6. Lockout before maintenance or repairs
7. Frequently inspect cranes
Safe Practices
8/3/2019 Crane Sling MSHA1
20/52
1. Hook directly over load before lifting
2. Document & maintain inspection records
3. Check warning devices & signals4. Signalers must watch load
5. Operators must watch signalers
6. Know travel path in advance of lift7. Know where to set down load
8. Will new location support weight
Safe Practices
8/3/2019 Crane Sling MSHA1
21/52
FatalgramThe employee was using a truckequipped with a hydraulic boom to
position a tire on the hub of acaterpillar loader. The tire fell off thehook and struck the employee on hishead and neck.
8/3/2019 Crane Sling MSHA1
22/52
FatalgramThree steel plates weighing nearly 6,000pounds were tied together by one nylon
strap. They were lifted about 5 feet by acrane in order to slide a second straparound them. The truck driver walkedunder the suspended load, and at that
moment, the strap around the steel platesbroke. The plates fell striking the victim.He died from head injuries.
8/3/2019 Crane Sling MSHA1
23/52
FatalgramA cement take-up pulley weight for aconveyer was being lifted into position by a
crane. To lift the weight, straps wereattached to four pins that had been set intothe cement weight. The employee was ridingon the 3,000 pound weight as it was being
lifted. One of the pins pulled out of theweight causing the employee to lose hisbalance and fall 35 feet to the ground. Hedied from sustained injuries.
8/3/2019 Crane Sling MSHA1
24/52
1. Only one person is designated signaler
2. Maintain line-of-sight with operator
3. Operator acknowledges every signal
4. Stop operation if comprehension is lost
5. Operators must watch signalers6. Plan in advance where load is going
7. Will new location will support the weight
Signaler SafePractices
8/3/2019 Crane Sling MSHA1
25/52
1. Raise hooks to limit switches
2. Place controls in off position
3. Place main power switch in off position
4. Visual check for dangerous conditions
5. Report defects immediately
6. Tagout defective equipment immediately
7. Report cranes not in operation
8. Follow manufacturers recommendations.
Leaving or Parking
8/3/2019 Crane Sling MSHA1
26/52
1. Size, weight, & center of gravity of load
2. Number of sling legs
3. Angle sling makes with horizontal line4. Rated capacity of sling
5. History of care & usage of sling
Lifting Factors
8/3/2019 Crane Sling MSHA1
27/52
1. Crane hook must be directly above
center of gravity
2. If crane hook is too far to one side ofcenter of gravity, dangerous tilting and
unequal stress to sling leg will result
Size, Weight, &Center of Gravity
8/3/2019 Crane Sling MSHA1
28/52
1. Rated capacity varies depending upon
type of sling, size of sling, & type of hitch
2. Consult with manufacturer3. Older slings must be used with additional
caution
4. Sling charts based on new sling usage.
Capacity of Sling
8/3/2019 Crane Sling MSHA1
29/52
1. Mishandling & misuse of slings are
leading cause of sling-related accidents
2. Proper care essential for maximumservice & safety
3. Always protect slings with cover saddles,
burlap padding or wood blocking toprevent sharp bends & cutting edges.
Care & Usage
8/3/2019 Crane Sling MSHA1
30/52
1. Use a Dynamometer
2. Check shipping papers
3. Check nomenclature plates4. Use industry standard tables or charts
5. Consult equipment manufacturer
6. Estimate using weights of similar loads7. Never lift based on a guess
8. Stay within 50% of cranes rated capacity
when estimating loads
Estimating LoadWeight
8/3/2019 Crane Sling MSHA1
31/52
1. Chains
2. Wire Rope
3. Fiber Rope
4. Synthetic Web
5. Cargo Nets.
Rigging & Slings
Each type hasadvantages anddisadvantages!
8/3/2019 Crane Sling MSHA1
32/52
Consult with manufacturer concerning
load capacities, usage methods,restrictions and other pertinent data forspecific types of slings
Rigging & Slings
8/3/2019 Crane Sling MSHA1
33/52
1. Never load in excess of rated capacity
2. Never use a damaged sling
3. Never pull sling from a suspended load4. Never shorten with knots
5. Suspended loads clear of everyone
6. Suspended loads clear of obstructions7. Hands & fingers clear of loads
8. Protect slings from sharp edges of load
9. Think before you affect a load.
Rules for Slings
8/3/2019 Crane Sling MSHA1
34/52
Remove from service if:
Wire RopeInspection
1. 10 distributed broken wires
2. Five broken wires on one strand3. Kinking, crushing, or bird caging
4. Evidence of heat damage
5. End attachments cracked,deformed, or worn
6. Hooks opened > 15% of the normal
throat opening or twisted > 10%
8/3/2019 Crane Sling MSHA1
35/52
Remove from service if:
1. Defective or questionable welds
2. Bending or elongation of chain links
3. Cracked or deformed links
4. Missing or removed identification tags
5. End attachments cracked, deformed, worn
6. Other suspected unsafe conditions
Chain Inspection
8/3/2019 Crane Sling MSHA1
36/52
Remove from service if:
1. Acid or caustic burns
2. Age deterioration (drying/cracking)
3. Melting or charring of sling surface
4. Snags, tears or cuts exposure of colored
thread
5. Missing or removed identification tags
6. Other suspected unsafe conditions
Web SlingInspection
8/3/2019 Crane Sling MSHA1
37/52
1. Clean sling
2. Check for damage
3. Follow proper storage rules4. Leave in good condition for next lift
5. Report damaged or defective slings
6. Follow proper disposal or replacementprocedures
After The Lift
8/3/2019 Crane Sling MSHA1
38/52
1. Dry environment, out of sunlight
2. Off floor or ground
3. Hung from hooks to prevent tangling
and easy access
4. Away from electrical sources5. By type - dont mix steel chain slings
with synthetics
6. In a controlled area
Slings Storage
8/3/2019 Crane Sling MSHA1
39/52
Consult with the sling manufacturerconcerning how sling angles affect loadcapacities for different types of slings.
Sling Angles
1000lb 1000lb 1000lb
8/3/2019 Crane Sling MSHA1
40/52
1. Angle of sling affects sling load capacity
2. Greater sling angle, greater stress
3. Multiple sling affects load capacity4. Type of sling used is a factor
5. Consult with manufacturer for proper
usage.
1000lb 1000lb 1000lb
Sling Angles
8/3/2019 Crane Sling MSHA1
41/52
Two SlingsThe use of twoslings, each
supporting thesame amount ofweight and having
the same supportangle results inequal distributionof the load weight.
500lbs 500lbs
1000lb0 Angle
8/3/2019 Crane Sling MSHA1
42/52
Sling AngleWith Vertical
Stresses Per Sling Leg1000 lbs Total Load
0 500
5 50210 50815 51820 53225 55230 57735 610
40 65345 70750 77855 87260 100080 2880
1000lb
30
577lbs 577lbs
30 Angle
Sling Angles
8/3/2019 Crane Sling MSHA1
43/52
1000lb
707lbs 707lbs
45 Angle
1000lbs 1000lbs
1000lb60 Angle
Sling Angles
8/3/2019 Crane Sling MSHA1
44/52
BA
1. Measure the distance on one sling for the same number
of units as the capacity of the sling in tons (Distance A).2. Measure the vertical distance from the point located in to
the load in tons. (Distance B).3. The number of units in this vertical distance (B) is the
working load for the sling.
Sling AnglesThe carrying capacity decreases as the spread between theslings increases. To determine the capacity of each sling ina bridle hitch:
8/3/2019 Crane Sling MSHA1
45/52
B
A
A = 2 ft. (or any unit) (2 Ton Sling Capacity)B = 1.5 ft.
Working Capacity of Each Sling = 1.5 Tons
Note: The individual sling capacity must bemore than half of the total load weight
Sling Angles
8/3/2019 Crane Sling MSHA1
46/52
Protecting Slings
Protect slingsagainst sharp
edges
8/3/2019 Crane Sling MSHA1
47/52
HAND SIGNALSHoist load:
1. Forearm vertical
2. Forefinger pointing up
3. Move hand in small
horizontal circular
motion
8/3/2019 Crane Sling MSHA1
48/52
Lower load:
1. Arm downward
2. Forefinger pointing
down
3. Move hand in small
horizontal circular
motion
HAND SIGNALS
8/3/2019 Crane Sling MSHA1
49/52
Boom Travel:
1. Arm extended forward
2. Hand open and slightly
raised
3. Make pushing motion
in the direction of travel
HAND SIGNALS
8/3/2019 Crane Sling MSHA1
50/52
Stop:
1. Arm extended2. Palm down
3. Move arm sideways,
rapidly back & forth
HAND SIGNALS
8/3/2019 Crane Sling MSHA1
51/52
Emergency stop:
1. Both arms
extended
2. Palms down
3. Move both arms
sideways rapidly
back & forth
HAND SIGNALS
8/3/2019 Crane Sling MSHA1
52/52
ProtectiveEquipment
1. Appropriate for the particular hazards
2. Maintained in good condition
3. Properly stored when not in use
4. Kept clean, fully functional, and sanitary