CREATE Program Chicago Region Environmental and Transportation Efficiency (CREATE) Program Overview August 2018
Transcript
Page 1: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

CREATE ProgramChicago Region Environmental and Transportation

Efficiency (CREATE) Program

Overview

August 2018

Page 2: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

2

What is CREATE?

A $4.4 billion Public-Private Partnership (PPP) designed to

improve transportation flow through Chicago focusing on:

• Increased capacity, speed, reliability for freight train traffic

• Separation of freight & commuter trains at 6 key junctions

• Elimination of 25 road/rail grade crossings (grade separations)

CREATE is a cooperative project involving:

• US Department of Transportation (FHWA & FRA)

• Illinois Department of Transportation (IDOT)

• Chicago Department of Transportation (CDOT)

• Cook County

• 6 major North American freight rail carriers and 2 switching railroads

• 2 passenger carriers (Amtrak and Metra)

Page 3: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

3

CREATE Partners

Page 4: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

4

Why CREATE?

• Freight rail trade (by value) within Chicago will more than

double from 2012 to 2045*

• Passenger, freight and motorist delays are experienced

daily on the current system

• The region must improve freight movement and mitigate

negative impacts

• Freight movements in Chicago are a NATIONAL and

INTERNATIONAL issue, not just a regional one

“Global trade follows the path of least resistance. It will go where there are the fewest impediments.” -UPS

*U.S. DOT Freight Analysis Framework 4.0

Page 5: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

5

The U.S. Rail Network Depends on Chicago

• 25 percent of all U.S. rail traffic touches Chicago

• 46 percent of all intermodal units in the U.S. touch Chicago

• 54 percent of intermodal units to/from the ports of Seattle/Tacoma touch Chicago

• 26 percent of intermodal units to/from Los Angeles/Long Beach touch Chicago

Source: 2006 Waybill Sample, based on traffic analysis by ALK Assoc.

Page 6: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

6

CREATE: Keeping the Nation’s Economy Moving

Page 7: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

7

Top Global Container Ports, 2014

Source: Chicago – Chicago Metropolitan Agency for

Planning Freight Snapshot; American Association of Port

Authorities, 2014

0

5

10

15

20

25

30

35

4035.20

33.87

23.8022.37

19.4518.42

16.62 16.16 15.40 15.16 14.75

Twen

ty F

oo

t Eq

uiv

ale

nt

Un

ite

s (T

EU)

Mill

ion

s

Ports

Page 8: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

8

Top U.S. Container Ports, 2014

Source: Chicago – Chicago Metropolitan Agency for

Planning Freight Snapshot; American Association of Port

Authorities, 2014

0

2

4

6

8

10

12

14

16 15.40

8.34

6.82

5.77

3.46 3.35

2.39 2.391.95 1.79Tw

en

ty-F

oo

t Eq

uiv

ale

nt

Un

its

Mill

ion

s

Page 9: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

9

CREATE Program – 70 Projects

• 25 road/rail grade separations

• 6 passenger/freight rail grade

separations

• Railroad projects to improve rail

infrastructure and upgrade

technologies

• Viaduct improvement program

• Grade crossing safety enhancements

• Rail operations and visibility improvements

Page 10: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

10

Four Corridors

• Passenger Corridors

• East-West Corridor

• Beltway Corridor

• Western Ave. Corridor

Page 11: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

11

Page 12: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

12

Project Status Summary

Page 13: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

13

INFRA Grant Award

$474 million will complete design of the entire 75th Street CIP,

build half of 75th Street CIP and build the Argo BRC Connection

CREATE partners committed $28 million above and beyond

their original intent to push forward & accomplish this phase

$132 million federal INFRA funds closes the gap and pushes

this next phase of the project toward the finish line

75% publicly funded project

Page 14: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

14

National Support

• Ford Motor Company

• UPS

• Caterpillar

• Ingredion

• Walgreens

• Wisconsin Electric Power Company ( WEC

Group)

• Illinois Corn Growers Association

• Illinois Petroleum Council

• Midwest Soybean Association

• Indiana Chamber of Commerce

• Ohio Chamber of Commerce

• Indiana Dept of Transportation

• Iowa Dept of Transportation

• Kansas Dept of Transportation

• Michigan Dept of Transportation

• Minnesota Dept of Transportation

• Wisconsin Dept of Transportation

• Northwestern Indiana Regional Planning

Commission

• Southwest Michigan Planning Commission

The Entire Bipartisan Illinois Congressional Delegation

Page 15: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

15

75th Street CIP – Existing Conditions

Four Environmentally Linked Projects:

Forest Hill Junction & 71st Street Grade Crossing

• North-south CSX tracks cross

three other east-west tracks

and one city street

Belt Junction

• Five tracks cross paths and

converge into two tracks

• Multiple freight & passenger

routes cross paths

80th Street Junction

• Six tracks cross paths and

converge into two tracks

Environmental Impact Statement (EIS) is complete

Page 16: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

16

Rail Operations Map – Existing Conflicts

Page 17: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

17

Rail Operations Map – Proposed Final Conditions

Page 18: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

18

Review of Project

• Local Mobility

(Viaducts)

• Forest Hill

Junction

• Metra

Reliability

Columbus Ave.

• Metra Rock

Island

Connection

• 80th Street

Junction

• Belt Junction

Page 19: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

19

Benefits, Impacts and Mitigation

Benefits of Meeting Purpose and Need for the 75th St. CIP

Reduces rail-rail crossing

conflicts

1. Decreased train idling

2. Decreased air emissions from

locomotives

3. Improved safety and security

Reduces road-rail crossing

conflicts

1. Elimination of the at-grade crossing at

71st Street and CSX tracks

2. Eliminates 3 ½ hours of daily road

closure3. Improved safety

Improves Rail Passenger Service

Reliability

Faster and more reliable Metra and Amtrak

service

Reduces Local Mobility Problems 1. Major improvements at 36 viaducts in

the project area

2. Improved mobility, safety, and security

for drivers, pedestrians, and cyclists3. Improved appearance of viaducts

Page 20: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

20

Project Delivery

Page 21: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

21

Partners Keep CREATE Moving

• Columbus Ave Grade

Separation – CDOT,

on behalf of CREATE

partners, awarded

Competitive State

Freight Grant ($49 M),

June 2018

Page 22: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

22

WA4 – BNSF/CN/NS/CSX

Chicago

• Crossovers

• Connection

• Bridge upgrades

• In progress

• Scheduled to be completed

2018

Reduce rail/rail conflicts

Page 23: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

23

Union Pacific Third Mainline (B2)

• Location: Melrose Park, IL

• 60 freight trains & 59 Union Pacific

Metra trains affected

• Actions

▪ Constructed 3.5-mile third main track on UP

▪ Constructed railroad bridge over Addison Creek

▪ Constructed flyover connection from the

Indiana Harbor Belt to the UP

▪ Control points reconfigured

▪ Track between the UP and IHB upgraded

▪ Metra’s Berkeley and Bellwood passenger

stations improved; pedestrian underpasses

constructed

Before

After

Page 24: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

24

Englewood Flyover (P1)

METRA/NS/Amtrak – Chicago

• Removes conflict point

between commuter,

passenger, and freight trains,

alleviating delay for

commuters and Amtrak’s

most severe delay point in the

Midwest.

• Completed 2014

Reduce rail/rail conflicts

Page 25: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

25

Englewood Flyover (P1)

South Looking North

Before 2011 After 2014

Page 26: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

26

71st St Grade Separation, (GS14)

CSX-IHB , Bridgeview

• Grade separation of

71st Street and the

IHB/CSX tracks just

west of Harlem Avenue

• Road underpass

• Completed November

2013

Eliminated road/rail conflict

Page 27: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

27

GS14 -- 71st Street/CSX Grade Separation

Before 2011 After 2013

Page 28: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

28

130th & Torrence NS –

Chicago (GS15a)

• Eliminates the at-grade crossings

of the two Norfolk Southern main

tracks with 130th Street and

Torrence Ave.

• Eliminates conflict between

railroad and access to Ford Plant

• Road Underpass

• Completed June 2015

Will eliminate road-rail conflicts

Page 29: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

29

GS15a– 130th Street & Torrence Ave. /NS Grade Separation

Before 2011 After 2015

Page 30: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

30

Viaduct Program

• Locations in the City of Chicago

• Improved roadways, sidewalks

and drainage under railroad

viaducts

• Enhanced safety and security for

motorists, pedestrians, and

bicyclists

• 37 locations completed in 2006

• 14 locations completed in 2012

(USDOT TIGER funding, $5 million)

• 11 completed in 2015/2016

(State of Illinois funding)

Page 31: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

31

Viaduct Improvement Program

Before

After

Example: 1530 S Loomis Street

After

Example: 1530 S Racine Avenue

Before

Page 32: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

32

CREATE Next Steps

•Continue to leverage all funding opportunities

•Execute 75th St. CIP grant & other grant funded projects

•Complete:

▪ Remaining Rail Corridor Projects

▪ Remaining Passenger-Freight Rail Flyover Projects

▪ Remaining Grade Separation Projects

Page 33: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th

33