+ All Categories
Home > Documents > CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design...

CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design...

Date post: 13-Oct-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
29
CREATING CONNECTIONS IN KING CITY NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 3, 2017
Transcript
Page 1: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

CREATING CONNECTIONS IN KING CITY

NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE – METROLINX

ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS – METROLINX

APRIL 3, 2017

Page 2: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

Residents could spend 109

minutes per day in traffic

GRIDLOCK COSTS OUR ECONONY

Page 3: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

REGIONAL TRANSFORMATION

Page 4: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

METROLINX

PLAN BUILD OPERATE

Page 5: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

GO EXPANSION PROGRAM

Page 6: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

BARRIE SERVICE IMPROVEMENTS

3 Parking Structures

Upgrades to 6 Stations

(new platforms,

accessibility, active

transportation, etc.)

Corridor Electrification

and Substation

Bridge Widenings

Grade Separations

2 New Stations

Davenport Diamond

Grade Separation

Proposed Stations

Grading and signal

improvements are already

underway on a six-kilometer

stretch of the line between the

York University and Rutherford

GO Stations.

14 36

168

Trips/Day

Kirby

Mulock

Innisfil

Davenport Diamond

Kirby

Mulock

Innisfil

Davenport Diamond

Page 7: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

As the volume of work increases, the importance of establishing tables

where we can have regular dialogue in support of advancing capital

infrastructure projects with municipal partners is critical to delivering

transit to communities across the region.

These opportunities include:

RER Capital Leaders Forum (network-wide table for executive

dialogue and advice related to GO expansion projects)

RER Regional Sessions (focus on providing regular updates for

municipal staff)

Municipal Program Committees (municipal specific committees

focussed on advancing specific projects)

MUNICIPAL ENGAGEMENT

Page 8: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

UPDATE ON RAIL INFRASTRUCTURE

IN KING CITY

Page 9: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

Bringing more transit options and new levels of service

doesn’t come easy.

Metrolinx is undertaking one of the largest infrastructure

projects in North America.

There is community-level disruption required to build a

region-wide, integrated transit network.

INFRASTRUCTURE NEEDS FOR GO EXPANSION

Page 10: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

Infrastructure Build:

Double track from Union to Aurora

Signal improvements

Bridge structure modifications

Bradford layover expansion and

modifications

Barrie layover expansion

Station modifications/parking expansion

Improved rail crossings

Grade separations

Customer experience improvements

Kirby

Mulock

Innisfil

Davenport Diamond

BARRIE CORRIDOR PROGRAM OVERVIEW

Page 11: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

In order to electrify, we need to build infrastructure

including traction power substations, switching stations,

paralleling stations, overhead contact systems and various

safety modifications.

This includes switching stations and paralleling stations at

Maple and Newmarket.

Design excellence is part of designing this infrastructure.

ELECTRIFICATION

Page 12: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

NEW TRACK AND NEW STATIONS

Page 13: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

NEW TRACK AND NEW STATIONS

New Track – Barrie Corridor

From Union Station to Aurora GO Station to support 15-minute

service from Union Station.

New Stations

Gormley (opened December 2016)

Kirby (near Keele Street)

Mulock (near Bayview Avenue)

Bloomington (construction mobilized)

Downsview Park

Page 14: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

Milestone Schedule

Prelim. Design Consultant

Procurement

Aug 2016 – Jan 2017

Preliminary Design Feb 2017 to Apr 2018

DBF Procurement Apr 2018 to Apr 2019

Construction Apr 2019 to Dec 2022

Scope

Surface Parking

New Kiss & Ride

Bicycle Facilities

Pedestrian Bridges

Approx. 500 Net New Parking Spaces

KING CITY GO STATION

New platform

and 2nd track

Pedestrian

bridges

Page 15: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

WHISTLE NOISE MITIGATION

The environmental assessment for additional track

covers noise impacts as a result of construction and

increased service.

The use of train whistles is governed by Transport

Canada rules and regulations.

Metrolinx will also work with King City if there is

interest in a City-led study related to whistle noise

mitigation.

Page 16: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

LEVEL CROSSINGS &

GRADE SEPARATIONS

Page 17: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

With over 50 level crossings in York Region, they will

continue to be a significant feature of the network.

All level crossings on the GO network were assessed

based on four criteria which included a number of

components:

LEVEL CROSSINGS – ROAD/RAIL INTERSECTIONS

Usage and Existing Conditions (60%) • Exposure Index (traffic and rail volumes)

• Geometry

• Accidents/Collisions

• Adjacent roadways and queuing

Operations (20%) • GO Service improvements

• Special users (e.g. local transit,

emergency services)

• Service reliability

• Station proximity

Social & Environmental (10%) • Visual improvement

• Noise improvement

• Community connectivity

Cost (10%) • Construction

• Property

• Maintenance

Page 18: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

18

LEVEL CROSSINGS: SORTING REVIEW

Among high and medium priority locations, a tiered approach was

adopted to inform prioritization and discussions with municipalities.

Page 19: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

Four proposed grade separations:

Rutherford Road: adjacent to station, EA

completed by York Region, planning underway,

highest overall EI forecast on GO network.

Wellington Street East: adjacent to station,

heritage elements to be considered.

McNaughton Road: adjacent to station.

Steeles Avenue East: adjacent to station, EA

underway by City of Toronto

RESULTS: LEVEL CROSSINGS IN YORK REGION

Page 20: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

Metrolinx will continue

to work with municipal

counterparts to plan for

and advance grade

separations where

possible.

Metrolinx recommends

a longer term plan be

considered beyond the

current program to

move additional projects

forward through

planning and design,

subject to approvals

and funding.

This would allow for

continued progress on a

pipeline of locations not

proceeding immediately

as part of this RER

program.

RER Program

RER Grade Separations

Future Projects

Recommended additional planning and

design (subject to approvals and funding)

Beyond RER

Municipal Partners

Federal Support

LEVEL CROSSINGS: LONG TERM PLAN

RER Program

Page 21: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

NEXT STEPS: LEVEL CROSSINGS

Study to identify recommended improvements for at-

grade crossings

Municipal input will be part of this exercise

Launch region-wide Community Advisory Committee

Grade Separation Projects:

Finalize municipal agreements

Complete or initiate Environmental Assessment as required

Enhanced Safety and Education Awareness

Page 22: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

COMMUNITY ENGAGEMENT

Page 23: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

Briefings:

October 13 2017: met with local residents,

King City Staff, and Councillor Mortelliti,

regarding the overflow parking lot at King City

United Church.

After detailed traffic reports were shared, it

was agreed that the street of concern would

not require any signage, as current traffic level

is well under any numbers that would be a

cause of concern.

23

COMMUNITY ENGAGEMENT TO DATE

Page 24: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

24

Metrolinx recognizes that with new infrastructure and construction

comes impacts to the community that must be worked through with

residents and their elected officials.

A regional Municipal and Community regional tour is currently

underway that creates an annual schedule for getting to every

municipal council and for providing a comprehensive narrative for

residents of each municipality that details what this program will look

like locally.

We are working with municipal partners to schedule local

consultations on new stations.

We are developing a community charter which will commit the

organization to building the regional transportation system in a way

that is respectful of the communities it touches.

This is in addition to the standard community relations support that

we have traditionally provided on the ground on projects like

Georgetown South and the Eglinton Crosstown.

HOW WE ARE GOING TO WORK WITH YOU

Page 25: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

COMMUNITY ENGAGEMENT: PROJECT CYCLE

•Work with municipal partners/community to inform the details of the project, address design concerns and build momentum.

•Focus on minimizing impact to residents, keeping the community informed and managing/being responsive to issues as they arise.

•Formal consultation period included in the TPAP

•Introduce the project to municipal partners & community and ask for initial feedback

•Work with residents to establish why the project is needed and proposed approach

Planning & Feasibility

Environmental Assessment

(only applies to new infrastructure )

Design & Procurement

Construction

25

Page 26: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

As our region grows our transit system needs to grow too.

Page 27: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

APPENDIX

Page 28: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

REGIONAL TRANSPORTATION PLAN

25 YEAR VISION 2012

Creating new connections across our region

Page 29: CREATING CONNECTIONS IN KING CITY - Metrolinx Engage · Aug 2016 – Jan 2017 Preliminary Design Feb 2017 to Apr 2018 DBF Procurement Apr 2018 to Apr 2019 Construction Apr 2019 to

OVER $30B IN INVESTMENT IN THE

GTHA’S RAPID TRANSIT NETWORK

68 KM OF NEW

BUS RAPID TRANSIT

Partially in-service, with remainder under construction:

Viva in York Region

Mississauga Transitway

In design / planning: Hamilton A-Line

74 KM OF NEW

LIGHT RAIL TRANSIT

Under construction: Eglinton Crosstown In procurement: Finch West Hurontario Hamilton B-Line In design / planning: Sheppard East

EXPANDING GO

TRAIN SERVICE More service on all

lines Electric trains,

every 15 minutes or better in both directions, for most GO customers

23 more stations

and line extensions to serve new markets

CONNECTING IT ALL TOGETHER Expanding and

revitalizing Union Station, the heart of the regional network

Completing the implementation of PRESTO across the region


Recommended