+ All Categories
Home > Documents > Critical Activity Januari

Critical Activity Januari

Date post: 14-Nov-2015
Category:
Upload: indra-pandu-prasetyo
View: 13 times
Download: 0 times
Share this document with a friend
Description:
Critical Activity January Project
Popular Tags:
12
Activity Name Remaining Duration Start Finish Total Float PPGM DONGGI 351d 12-Aug-14 A 31-Dec-15 0d MILESTONE 30d 26-Sep-15 26-Oct-15 0d SYSTEM READINESS MILESTONE 30d 26-Sep-15 26-Oct-15 0d PROCESS 4d 22-Oct-15 26-Oct-15 1d MC Individual DHU & DPCU Area 0d 22-Oct-15 5d MC Individual AGRU Area 0d 26-Oct-15 1d MC Individual BSRU Area 0d 26-Oct-15 1d UTILITY 30d 26-Sep-15 26-Oct-15 0d MC Individual Water Treatment Area 0d 26-Sep-15 1d MC Individual Chemical Area 0d 20-Oct-15 7d MC Individual Produced Water 0d 21-Oct-15 6d MC Individual Hot Oil Area 0d 22-Oct-15 5d MC Individual Fuel Gas System Area 0d 24-Oct-15 3d MC Individual Flare System Area 0d 26-Oct-15 0d ENGINEERING 14d 12-Feb-15 25-Feb-15 7d DETAIL ENGINEERING 14d 12-Feb-15 25-Feb-15 7d CIVIL 14d 12-Feb-15 25-Feb-15 7d CIVIL DRAWING 14d 12-Feb-15 25-Feb-15 7d PROCESS/UTILITY AREA 14d 12-Feb-15 25-Feb-15 7d FOUNDATION/ STRUCTURE 14d 12-Feb-15 25-Feb-15 7d EQUIPMENT FOUNDATION 14d 12-Feb-15 25-Feb-15 7d 240 - BLEED WATER TREATMENT/ SULPHUR 14d 12-Feb-15 25-Feb-15 7d Plan & Detail Foundation - Bleed Water Treatment Package (240-V-1005) 14d 12-Feb-15 25-Feb-15 7d PROCUREMENT 213d 12-Aug-14 A 15-Aug-15 2d MECHANICAL 213d 12-Aug-14 A 15-Aug-15 2d MECHANICAL PACKAGE 213d 12-Aug-14 A 15-Aug-15 2d FLARE SYSTEM 188d 05-Dec-14 A 21-Jul-15 0d VPC for Fabrication - Flare System 14d 05-Dec-14 A 28-Jan-15 0d Manufacturing - Flare System 144d 29-Jan-15 21-Jun-15 0d Delivery to Site - Flare Package 30d 22-Jun-15 21-Jul-15 0d Delivery to Site - Acid Gas Flare Package 30d 22-Jun-15 21-Jul-15 0d INCINERATOR 213d 12-Aug-14 A 15-Aug-15 2d VPC for Fabrication - Incinerator Blower, Burner & Control Instrumentation (Foreign) 7d 12-Aug-14 A 21-Jan-15 2d VPC for Fabrication - Incinerator Stack, Ducting (Local) 7d 12-Aug-14 A 21-Jan-15 3d Manufacturing - Incinerator Stack, Ducting (Local) 156d 22-Jan-15 26-Jun-15 3d Manufacturing - Incinerator Blower, Burner & Control Instrumentation (foreign) 156d 22-Jan-15 26-Jun-15 2d Delivery to Site - Incinerator Stack, Ducting 21d 27-Jun-15 17-Jul-15 3d Delivery to Site - Incinerator Blower, Burner & Control Instrumentation 50d 27-Jun-15 15-Aug-15 2d SULPHUR BAGGING SYSTEM 28d 15-Jan-15 11-Feb-15 7d VPC for Fabrication - Sulphur Bagging System 28d 15-Jan-15 11-Feb-15 7d DPCU REFRIGERANT/ CHILLER 154d 29-Aug-14 A 17-Jun-15 6d Manufacturing - DPCU 124d 29-Aug-14 A 18-May-15 6d Delivery to Site - DPCU 30d 19-May-15 17-Jun-15 6d PRE-TREATMENT DIESEL UNIT 200d 25-Nov-14 A 02-Aug-15 6d VPC & Manufacturing - Pretreatment Diesel Unit Package 170d 25-Nov-14 A 03-Jul-15 6d Delivery to Site - Pretreatment Diesel Unit Package 30d 04-Jul-15 02-Aug-15 6d MECHANICAL ROTATING 181d 06-Oct-14 A 14-Jul-15 6d HEATING MEDIUM PUMP 181d 23-Oct-14 A 14-Jul-15 6d Manufacturing - Heating Medium Pump 167d 23-Oct-14 A 30-Jun-15 6d Delivery to Site - Heating Medium Pump 14d 01-Jul-15 14-Jul-15 6d VERTICAL PUMP PACKAGE 1 181d 06-Oct-14 A 14-Jul-15 6d Manufacturing - Vertical Pump Package 1 167d 06-Oct-14 A 30-Jun-15 6d Delivery to Site - Incinerator Feed Gas KO Drain Pump (240-P-1023) 14d 01-Jul-15 14-Jul-15 6d Delivery to Site - Stripper Reflux Pump (240-P-1003 A/B) - BSRU Area 14d 01-Jul-15 14-Jul-15 6d STATIC - NON HE 194d 03-Oct-14 A 27-Jul-15 4d FIELD FABRICATION TANK 7d 03-Oct-14 A 21-Jan-15 7d ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2015 MILESTONE SYSTEM READINESS MIL PROCESS MC Individual DHU & DPCU A MC Individual AGRU Area MC Individual BSRU Area UTILITY MC Individual Water Treatment Area MC Individual Chemical Area MC Individual Produced Wate MC Individual Hot Oil Area MC Individual Fuel Gas Syst MC Individual Flare System ENGINEERING DETAIL ENGINEERING CIVIL CIVIL DRAWING PROCESS/UTILITY AREA FOUNDATION/ STRUCTURE EQUIPMENT FOUNDATION 240 - BLEED WATER TREATMENT/ SULPHUR Plan & Detail Foundation - Bleed Water Treatment Package (240-V-1005) PROCUREMENT MECHANICAL MECHANICAL PACKAGE FLARE SYSTEM VPC for Fabrication - Flare System Manufacturing - Flare System Delivery to Site - Flare Package Delivery to Site - Acid Gas Flare Package INCINERATOR VPC for Fabrication - Incinerator Blower, Burner & Control Instrumentation (Foreign) VPC for Fabrication - Incinerator Stack, Ducting (Local) Manufacturing - Incinerator Stack, Ducting (Local) Manufacturing - Incinerator Blower, Burner & Control Instrumentation (foreign) Delivery to Site - Incinerator Stack, Ducting Delivery to Site - Incinerator Blower, Burner & Control Instru SULPHUR BAGGING SYSTEM VPC for Fabrication - Sulphur Bagging System DPCU REFRIGERANT/ CHILLER Manufacturing - DPCU Delivery to Site - DPCU PRE-TREATMENT DIESEL UNIT VPC & Manufacturing - Pretreatment Diesel Unit Package Delivery to Site - Pretreatment Diesel Unit Package MECHANICAL ROTATING HEATING MEDIUM PUMP Manufacturing - Heating Medium Pump Delivery to Site - Heating Medium Pump VERTICAL PUMP PACKAGE 1 Manufacturing - Vertical Pump Package 1 Delivery to Site - Incinerator Feed Gas KO Drain Pump (240-P-1023) Delivery to Site - Stripper Reflux Pump (240-P-1003 A/B) - BSRU Area STATIC - NON HE FIELD FABRICATION TANK PPGM DONGGI CRITICAL ACTIVITY - JANUARI 2015 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Page 1 of 12 15-Jan-15
Transcript
  • Activity Name Remaining Duration

    Start Finish Total Float

    PPGM DONGGI 351d 12-Aug-14 A 31-Dec-15 0dMILESTONE 30d 26-Sep-15 26-Oct-15 0dSYSTEM READINESS MILESTONE 30d 26-Sep-15 26-Oct-15 0dPROCESS 4d 22-Oct-15 26-Oct-15 1dMC Individual DHU & DPCU Area 0d 22-Oct-15 5dMC Individual AGRU Area 0d 26-Oct-15 1dMC Individual BSRU Area 0d 26-Oct-15 1d

    UTILITY 30d 26-Sep-15 26-Oct-15 0dMC Individual Water Treatment Area 0d 26-Sep-15 1dMC Individual Chemical Area 0d 20-Oct-15 7dMC Individual Produced Water 0d 21-Oct-15 6dMC Individual Hot Oil Area 0d 22-Oct-15 5dMC Individual Fuel Gas System Area 0d 24-Oct-15 3dMC Individual Flare System Area 0d 26-Oct-15 0d

    ENGINEERING 14d 12-Feb-15 25-Feb-15 7dDETAIL ENGINEERING 14d 12-Feb-15 25-Feb-15 7dCIVIL 14d 12-Feb-15 25-Feb-15 7dCIVIL DRAWING 14d 12-Feb-15 25-Feb-15 7dPROCESS/UTILITY AREA 14d 12-Feb-15 25-Feb-15 7dFOUNDATION/ STRUCTURE 14d 12-Feb-15 25-Feb-15 7dEQUIPMENT FOUNDATION 14d 12-Feb-15 25-Feb-15 7d240 - BLEED WATER TREATMENT/ SULPHUR 14d 12-Feb-15 25-Feb-15 7dPlan & Detail Foundation - Bleed Water Treatment Package (240-V-1005) 14d 12-Feb-15 25-Feb-15 7d

    PROCUREMENT 213d 12-Aug-14 A 15-Aug-15 2dMECHANICAL 213d 12-Aug-14 A 15-Aug-15 2dMECHANICAL PACKAGE 213d 12-Aug-14 A 15-Aug-15 2dFLARE SYSTEM 188d 05-Dec-14 A 21-Jul-15 0dVPC for Fabrication - Flare System 14d 05-Dec-14 A 28-Jan-15 0dManufacturing - Flare System 144d 29-Jan-15 21-Jun-15 0dDelivery to Site - Flare Package 30d 22-Jun-15 21-Jul-15 0dDelivery to Site - Acid Gas Flare Package 30d 22-Jun-15 21-Jul-15 0d

    INCINERATOR 213d 12-Aug-14 A 15-Aug-15 2dVPC for Fabrication - Incinerator Blower, Burner & Control Instrumentation (Foreign) 7d 12-Aug-14 A 21-Jan-15 2dVPC for Fabrication - Incinerator Stack, Ducting (Local) 7d 12-Aug-14 A 21-Jan-15 3dManufacturing - Incinerator Stack, Ducting (Local) 156d 22-Jan-15 26-Jun-15 3dManufacturing - Incinerator Blower, Burner & Control Instrumentation (foreign) 156d 22-Jan-15 26-Jun-15 2dDelivery to Site - Incinerator Stack, Ducting 21d 27-Jun-15 17-Jul-15 3dDelivery to Site - Incinerator Blower, Burner & Control Instrumentation 50d 27-Jun-15 15-Aug-15 2d

    SULPHUR BAGGING SYSTEM 28d 15-Jan-15 11-Feb-15 7dVPC for Fabrication - Sulphur Bagging System 28d 15-Jan-15 11-Feb-15 7d

    DPCU REFRIGERANT/ CHILLER 154d 29-Aug-14 A 17-Jun-15 6dManufacturing - DPCU 124d 29-Aug-14 A 18-May-15 6dDelivery to Site - DPCU 30d 19-May-15 17-Jun-15 6d

    PRE-TREATMENT DIESEL UNIT 200d 25-Nov-14 A 02-Aug-15 6dVPC & Manufacturing - Pretreatment Diesel Unit Package 170d 25-Nov-14 A 03-Jul-15 6dDelivery to Site - Pretreatment Diesel Unit Package 30d 04-Jul-15 02-Aug-15 6d

    MECHANICAL ROTATING 181d 06-Oct-14 A 14-Jul-15 6dHEATING MEDIUM PUMP 181d 23-Oct-14 A 14-Jul-15 6dManufacturing - Heating Medium Pump 167d 23-Oct-14 A 30-Jun-15 6dDelivery to Site - Heating Medium Pump 14d 01-Jul-15 14-Jul-15 6d

    VERTICAL PUMP PACKAGE 1 181d 06-Oct-14 A 14-Jul-15 6dManufacturing - Vertical Pump Package 1 167d 06-Oct-14 A 30-Jun-15 6dDelivery to Site - Incinerator Feed Gas KO Drain Pump (240-P-1023) 14d 01-Jul-15 14-Jul-15 6dDelivery to Site - Stripper Reflux Pump (240-P-1003 A/B) - BSRU Area 14d 01-Jul-15 14-Jul-15 6d

    STATIC - NON HE 194d 03-Oct-14 A 27-Jul-15 4dFIELD FABRICATION TANK 7d 03-Oct-14 A 21-Jan-15 7d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    MILESTONE

    SYSTEM READINESS MILPROCESS

    MC Individual DHU & DPCU AMC Individual AGRU AreaMC Individual BSRU AreaUTILITY

    MC Individual Water Treatment AreaMC Individual Chemical AreaMC Individual Produced WateMC Individual Hot Oil AreaMC Individual Fuel Gas SystMC Individual Flare System

    ENGINEERING

    DETAIL ENGINEERINGCIVILCIVIL DRAWINGPROCESS/UTILITY AREAFOUNDATION/ STRUCTUREEQUIPMENT FOUNDATION240 - BLEED WATER TREATMENT/ SULPHURPlan & Detail Foundation - Bleed Water Treatment Package (240-V-1005)

    PROCUREMENT

    MECHANICALMECHANICAL PACKAGE

    FLARE SYSTEMVPC for Fabrication - Flare System

    Manufacturing - Flare SystemDelivery to Site - Flare PackageDelivery to Site - Acid Gas Flare Package

    INCINERATORVPC for Fabrication - Incinerator Blower, Burner & Control Instrumentation (Foreign)VPC for Fabrication - Incinerator Stack, Ducting (Local)

    Manufacturing - Incinerator Stack, Ducting (Local)Manufacturing - Incinerator Blower, Burner & Control Instrumentation (foreign)

    Delivery to Site - Incinerator Stack, DuctingDelivery to Site - Incinerator Blower, Burner & Control Instru

    SULPHUR BAGGING SYSTEMVPC for Fabrication - Sulphur Bagging System

    DPCU REFRIGERANT/ CHILLERManufacturing - DPCU

    Delivery to Site - DPCUPRE-TREATMENT DIESEL UNIT

    VPC & Manufacturing - Pretreatment Diesel Unit PackageDelivery to Site - Pretreatment Diesel Unit Package

    MECHANICAL ROTATINGHEATING MEDIUM PUMP

    Manufacturing - Heating Medium PumpDelivery to Site - Heating Medium PumpVERTICAL PUMP PACKAGE 1

    Manufacturing - Vertical Pump Package 1Delivery to Site - Incinerator Feed Gas KO Drain Pump (240-P-1023)Delivery to Site - Stripper Reflux Pump (240-P-1003 A/B) - BSRU Area

    STATIC - NON HEFIELD FABRICATION TANK

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 1 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    Delivery to Site - Raw Material Bioreactor Tank (240-R-1001) - BSRU Area 7d 03-Oct-14 A 21-Jan-15 7dCOLUMN AGRU-BSRU 105d 10-Nov-14 A 29-Apr-15 4dManufacturing - Column AGRU-BSRU 75d 10-Nov-14 A 30-Mar-15 4dDelivery to Site - Column - AGRU Area 30d 31-Mar-15 29-Apr-15 4d

    FILTER AND COALESCER PACKAGE 1 194d 16-Dec-14 A 27-Jul-15 4dManufacturing - Filter & Coalescer Package 1 180d 16-Dec-14 A 13-Jul-15 4dDelivery to Site - Filter & Coalescer Package 1 14d 14-Jul-15 27-Jul-15 4d

    PIPING 191d 15-Jan-15 24-Jul-15 5dPIPE 191d 15-Jan-15 24-Jul-15 5d1ST MTO 191d 15-Jan-15 24-Jul-15 5d1ST MTO FRP MATERIAL 191d 15-Jan-15 24-Jul-15 5dTBE Piping 1st MTO FRP Pipe 14d 15-Jan-15 28-Jan-15 5d1st CBE & PO - FRP Pipe 7d 29-Jan-15 04-Feb-15 5d1st Manufacturing - FRP Pipe 140d 05-Feb-15 24-Jun-15 5d1st Delivery to Site - FRP Pipe 30d 25-Jun-15 24-Jul-15 5d

    ELECTRICAL 197d 15-Jan-15 30-Jul-15 4dELECTRICAL EQUIPMENT 197d 15-Jan-15 30-Jul-15 4dVARIABLE SPEED DRIVE 197d 15-Jan-15 30-Jul-15 4dManufacturing - Soft Starter 167d 15-Jan-15 30-Jun-15 4dDelivery to Site - Soft Starter 30d 01-Jul-15 30-Jul-15 4d

    CONSTRUCTION 281d 08-Sep-14 A 22-Oct-15 4dCIVIL 123d 08-Sep-14 A 17-May-15 4dCPP AREA 123d 08-Sep-14 A 17-May-15 4dPOWER & CONTROL STATION 97d 08-Sep-14 A 21-Apr-15 1dCONTROL ROOM 97d 08-Sep-14 A 21-Apr-15 1dSTRUCTURE 81d 08-Sep-14 A 05-Apr-15 1dCivil Structural Work - Control Room 60d 08-Sep-14 A 15-Mar-15 1dRaise Floor Installation - Control Room 21d 16-Mar-15 05-Apr-15 1d

    MISC. WORK 16d 06-Apr-15 21-Apr-15 1dCable Tray Instrument Installation - Control Room 16d 06-Apr-15 21-Apr-15 1d

    PROCESS 81d 26-Feb-15 17-May-15 4dAGRU AREA 15d 03-May-15 17-May-15 4dSTEEL STRUCTURE 15d 03-May-15 17-May-15 4dSTRUCTURE 15d 03-May-15 17-May-15 4dSteel Structure Installation - Structure 1 (240-T-1002, 240-D-1003) 15d 03-May-15 17-May-15 4d

    BLEED WATER TREATMENT/ SULFUR AREA 28d 26-Feb-15 25-Mar-15 7dCONCRETE STRUCTURE 28d 26-Feb-15 25-Mar-15 7dPACKAGE 28d 26-Feb-15 25-Mar-15 7dEquipment Foundation - Package - Bleed Water Treatment/ Sulphur Area 28d 26-Feb-15 25-Mar-15 7d

    MECHANICAL 232d 15-Jan-15 03-Sep-15 7dCPP AREA 232d 15-Jan-15 03-Sep-15 7dPROCESS 232d 15-Jan-15 03-Sep-15 7dAGRU AREA 78d 30-Apr-15 01-Aug-15 6dEQUIPMENT INSTALLATION 78d 30-Apr-15 01-Aug-15 6dCOLUMN 35d 30-Apr-15 04-Jun-15 7dMAIN ABSORBER (240-T-1001) 3d 30-Apr-15 02-May-15 4dInstallation - Main Absorber (240-T-1001) - AGRU Area 3d 30-Apr-15 02-May-15 4d

    FLASH GAS ABSORBER (STR 1) (240-T-1002) 17d 18-May-15 04-Jun-15 7dInstallation - Flash Gas Absorber (240-T-1002) on Structure 1 3d 18-May-15 20-May-15 7dPlatform Installation - Flash Gas Absorber (240-T-1002) 14d 21-May-15 04-Jun-15 7d

    VESSEL 20d 18-May-15 08-Jun-15 4dACID GAS FLASH DRUM (STR 1) (240-D-1003) 17d 18-May-15 04-Jun-15 7dInstallation - Acid Gas Flash Drum (240-D-1003) on Structure 1 - AGRU Area 3d 18-May-15 20-May-15 4dPlatform Installation - Acid Gas Flash Drum (240-D-1003) - AGRU Area 14d 21-May-15 04-Jun-15 7d

    FEED GAS KO DRUM (240-D-1001) 17d 21-May-15 08-Jun-15 4dInstallation - Feed Gas KO Drum (240-D-1001) - AGRU Area 3d 21-May-15 23-May-15 4dPlatform Installation - Feed Gas KO Drum (240-D-1001) - AGRU Area 14d 24-May-15 08-Jun-15 4d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    Delivery to Site - Raw Material Bioreactor Tank (240-R-1001) - BSRU AreaCOLUMN AGRU-BSRU

    Manufacturing - Column AGRU-BSRUDelivery to Site - Column - AGRU Area

    FILTER AND COALESCER PACKAGE 1Manufacturing - Filter & Coalescer Package 1

    Delivery to Site - Filter & Coalescer Package 1PIPINGPIPE1ST MTO1ST MTO FRP MATERIAL

    TBE Piping 1st MTO FRP Pipe1st CBE & PO - FRP Pipe

    1st Manufacturing - FRP Pipe1st Delivery to Site - FRP Pipe

    ELECTRICALELECTRICAL EQUIPMENTVARIABLE SPEED DRIVE

    Manufacturing - Soft StarterDelivery to Site - Soft Starter

    CONSTRUCTION

    CIVILCPP AREA

    POWER & CONTROL STATIONCONTROL ROOM

    STRUCTURECivil Structural Work - Control Room

    Raise Floor Installation - Control RoomMISC. WORKCable Tray Instrument Installation - Control Room

    PROCESSAGRU AREASTEEL STRUCTURESTRUCTURESteel Structure Installation - Structure 1 (240-T-1002, 240-D-1003)

    BLEED WATER TREATMENT/ SULFUR AREACONCRETE STRUCTUREPACKAGEEquipment Foundation - Package - Bleed Water Treatment/ Sulphur Area

    MECHANICALCPP AREAPROCESS

    AGRU AREAEQUIPMENT INSTALLATION

    COLUMNMAIN ABSORBER (240-T-1001)Installation - Main Absorber (240-T-1001) - AGRU Area

    FLASH GAS ABSORBER (STR 1) (240-T-1002)Installation - Flash Gas Absorber (240-T-1002) on Structure 1

    Platform Installation - Flash Gas Absorber (240-T-1002)VESSEL

    ACID GAS FLASH DRUM (STR 1) (240-D-1003)Installation - Acid Gas Flash Drum (240-D-1003) on Structure 1 - AGRU Area

    Platform Installation - Acid Gas Flash Drum (240-D-1003) - AGRU AreaFEED GAS KO DRUM (240-D-1001)

    Installation - Feed Gas KO Drum (240-D-1001) - AGRU AreaPlatform Installation - Feed Gas KO Drum (240-D-1001) - AGRU Area

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 2 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    PUMP 13d 15-Jul-15 01-Aug-15 6dSTRIPPER REFLUX PUMP (240-P-1003 A/B) 7d 15-Jul-15 24-Jul-15 5dInstallation - Stripper Reflux Pump (240-P-1003 A/B) - AGRU Area 3d 15-Jul-15 18-Jul-15 5dAlignment - Stripper Reflux Pump (240-P-1003 A/B) - AGRU Area 4d 19-Jul-15 24-Jul-15 5d

    AMINE SUMP PUMP (240-P-1006) 7d 23-Jul-15 01-Aug-15 6dInstallation - Amine Sump Pump (240-P-1006) - AGRU Area 3d 23-Jul-15 26-Jul-15 6dAlignment - Amine Sump Pump (240-P-1006) - AGRU Area 4d 27-Jul-15 01-Aug-15 6d

    DRAIN HYDROCARBON PUMP (240-P-1016) 7d 23-Jul-15 01-Aug-15 6dInstallation - Drain Hydrocarbon Pump (240-P-1016) - AGRU Area 3d 23-Jul-15 26-Jul-15 6dAlignment - Drain Hydrocarbon Pump (240-P-1016) - AGRU Area 4d 27-Jul-15 01-Aug-15 6d

    BSRU AREA 232d 15-Jan-15 03-Sep-15 7dEQUIPMENT INSTALLATION 232d 15-Jan-15 03-Sep-15 7dREACTOR 169d 15-Jan-15 02-Jul-15 9dBIOREACTOR TANK (240-R-1010) 169d 15-Jan-15 02-Jul-15 9dBottom Plate Installation - Bioreactor Tank (240-R-1001) - BSRU Area 10d 15-Jan-15 24-Jan-15 7dShell Plate 1 - 10 Installation - Bioreactor Tank (240-R-1001) - BSRU Area 84d 25-Jan-15 18-Apr-15 7dInternal Installation - Bio Reactor (240-R-1001) - BSRU Area 20d 09-Apr-15 28-Apr-15 7dShell Plate 11 - 12 Installation - Bioreactor Tank (240-R-1001) - BSRU Area 20d 29-Apr-15 18-May-15 7dCone Roof Installation - Bioreactor Tank (240-R-1001) - BSRU Area 7d 19-May-15 25-May-15 7dHydrotest - Bioreactor Tank (240-R-1001) - BSRU Area 30d 26-May-15 02-Jul-15 7d

    PUMP 13d 15-Jul-15 01-Aug-15 6dBIO REACTOR MEASURING PUMP (240-P-1012 A/B) 7d 23-Jul-15 01-Aug-15 6dInstallation - Bio Reactor Measuring Pump (240-P-1012 A/B) - BSRU Area 3d 23-Jul-15 26-Jul-15 6dAlignment - Bio Reactor Measuring Pump (240-P-1012 A/B) - BSRU Area 4d 27-Jul-15 01-Aug-15 6d

    AIR BLOWER KO DRUM DRAIN PUMP (240-P-1022 A/B) 7d 23-Jul-15 01-Aug-15 6dInstallation - Air Blower KO Drain Pump (240-P-1022 A/B) - BSRU Area 3d 23-Jul-15 26-Jul-15 6dAlignment - Air Blower KO Drain Pump (240-P-1022 A/B) - BSRU Area 4d 27-Jul-15 01-Aug-15 6d

    INCINERATOR FEED GAS KO DRAIN PUMP (240-P-1023) 7d 15-Jul-15 24-Jul-15 5dInstallation - Incinerator Feed Gas KO Drain Pump (240-P-1023) - BSRU Area 3d 15-Jul-15 18-Jul-15 5dAlignment - Incinerator Feed Gas KO Drain Pump (240-P-1023) - BSRU Area 4d 19-Jul-15 24-Jul-15 5d

    COMPRESSOR 14d 26-Jul-15 14-Aug-15 3dAIR COMPRESSOR BSRU (240-C-1001 A/B) 14d 26-Jul-15 14-Aug-15 3dInstallation - MCC & Control Panel Air Compressor BSRU 14d 26-Jul-15 14-Aug-15 3d

    INCINERATOR 36d 18-Jul-15 03-Sep-15 6dINCINERATOR (240-F-1001) 29d 18-Jul-15 25-Aug-15 2dInstallation - Incinerator (240-F-1001) - BSRU Area 7d 18-Jul-15 27-Jul-15 2dPanel Installation - Incinerator (240-F-1001) - BSRU Area 7d 16-Aug-15 25-Aug-15 2d

    INCINERATOR AIR BLOWER (240-C-1004A/B) 14d 16-Aug-15 03-Sep-15 6dInstallation - Incinerator Air Blower (240-C-1004 A/B) 7d 16-Aug-15 25-Aug-15 6dAlignment - Incinerator Air Blower (240-C-1004 A/B) 7d 25-Aug-15 03-Sep-15 6d

    DEW POINT AREA 28d 18-Jun-15 25-Jul-15 5dEQUIPMENT INSTALLATION 28d 18-Jun-15 25-Jul-15 5dPACKAGE 28d 18-Jun-15 25-Jul-15 5dDEW POINT CONTROL PACKAGE (260-V-1001) 28d 18-Jun-15 25-Jul-15 5dInstallation - DPCU Package (260-V-1001) @ 6 Unit - DHU & DPCU Area 21d 18-Jun-15 15-Jul-15 5dAlignment - DPCU Package (260-V-1001) @ 6 Unit - DHU & DPCU Area 7d 16-Jul-15 25-Jul-15 5d

    BLEED WATER TREATMENT 103d 26-Mar-15 18-Jul-15 7dEQUIPMENT INSTALLATION 103d 26-Mar-15 18-Jul-15 7dPACKAGE 103d 26-Mar-15 18-Jul-15 7dBLEED WATER TREATMENT PACKAGE (240-V-1005) 103d 26-Mar-15 18-Jul-15 7dInstallation - Bleed Water Treatment Bio Reactor Tank (240-V-1005) - Bleed Water Trea 28d 26-Mar-15 22-Apr-15 7dInstallation - Bleed Water Treatment Piping & Instrument - Bleed Water Treatment Area 75d 23-Apr-15 18-Jul-15 7d

    UTILITY 49d 15-Jul-15 01-Sep-15 6dDIESEL FUEL STORAGE AREA 30d 03-Aug-15 01-Sep-15 6dEQUIPMENT INSTALLATION 30d 03-Aug-15 01-Sep-15 6dPACKAGE 30d 03-Aug-15 01-Sep-15 6dPRE-TREATMENT DIESEL UNIT PACKAGE (276-V-1001) 30d 03-Aug-15 01-Sep-15 6dInstallation - Pretreatment Diesel Unit Package (276-V-1001) 30d 03-Aug-15 01-Sep-15 6d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    PUMPSTRIPPER REFLUX PUMP (240-P-1003 A/B)

    Installation - Stripper Reflux Pump (240-P-1003 A/B) - AGRU AreaAlignment - Stripper Reflux Pump (240-P-1003 A/B) - AGRU Area

    AMINE SUMP PUMP (240-P-1006)Installation - Amine Sump Pump (240-P-1006) - AGRU Area

    Alignment - Amine Sump Pump (240-P-1006) - AGRU AreaDRAIN HYDROCARBON PUMP (240-P-1016)

    Installation - Drain Hydrocarbon Pump (240-P-1016) - AGRU AreaAlignment - Drain Hydrocarbon Pump (240-P-1016) - AGRU Area

    BSRU AREAEQUIPMENT INSTALLATION

    REACTORBIOREACTOR TANK (240-R-1010)

    Bottom Plate Installation - Bioreactor Tank (240-R-1001) - BSRU AreaShell Plate 1 - 10 Installation - Bioreactor Tank (240-R-1001) - BSRU Area

    Internal Installation - Bio Reactor (240-R-1001) - BSRU AreaShell Plate 11 - 12 Installation - Bioreactor Tank (240-R-1001) - BSRU Area

    Cone Roof Installation - Bioreactor Tank (240-R-1001) - BSRU AreaHydrotest - Bioreactor Tank (240-R-1001) - BSRU Area

    PUMPBIO REACTOR MEASURING PUMP (240-P-1012 A/B)

    Installation - Bio Reactor Measuring Pump (240-P-1012 A/B) - BSRUAlignment - Bio Reactor Measuring Pump (240-P-1012 A/B) - BSRAIR BLOWER KO DRUM DRAIN PUMP (240-P-1022 A/B)

    Installation - Air Blower KO Drain Pump (240-P-1022 A/B) - BSRU AAlignment - Air Blower KO Drain Pump (240-P-1022 A/B) - BSRU

    INCINERATOR FEED GAS KO DRAIN PUMP (240-P-1023)Installation - Incinerator Feed Gas KO Drain Pump (240-P-1023) - BSR

    Alignment - Incinerator Feed Gas KO Drain Pump (240-P-1023) - BSCOMPRESSORAIR COMPRESSOR BSRU (240-C-1001 A/B)Installation - MCC & Control Panel Air Compressor BSRU

    INCINERATORINCINERATOR (240-F-1001)

    Installation - Incinerator (240-F-1001) - BSRU AreaPanel Installation - Incinerator (240-F-1001) - BSRU Ar

    INCINERATOR AIR BLOWER (240-C-1004A/B)Installation - Incinerator Air Blower (240-C-1004 A/B)

    Alignment - Incinerator Air Blower (240-C-1004 A/BDEW POINT AREAEQUIPMENT INSTALLATIONPACKAGEDEW POINT CONTROL PACKAGE (260-V-1001)

    Installation - DPCU Package (260-V-1001) @ 6 Unit - DHU & DPCU AreaAlignment - DPCU Package (260-V-1001) @ 6 Unit - DHU & DPCU A

    BLEED WATER TREATMENTEQUIPMENT INSTALLATIONPACKAGEBLEED WATER TREATMENT PACKAGE (240-V-1005)

    Installation - Bleed Water Treatment Bio Reactor Tank (240-V-1005) - Bleed Water Treatment AreaInstallation - Bleed Water Treatment Piping & Instrument - Bleed Water

    UTILITYDIESEL FUEL STORAGE AREAEQUIPMENT INSTALLATIONPACKAGEPRE-TREATMENT DIESEL UNIT PACKAGE (276-Installation - Pretreatment Diesel Unit Package (276

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 3 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    HOT OIL AREA 7d 15-Jul-15 24-Jul-15 5dEQUIPMENT INSTALLATION 7d 15-Jul-15 24-Jul-15 5dPUMP 7d 15-Jul-15 24-Jul-15 5dHOT OIL DRAIN PUMP (271-P-1003) 7d 15-Jul-15 24-Jul-15 5dInstallation - Hot Oil Drain Pump (271-P-1003) - Hot Oil Area 3d 15-Jul-15 18-Jul-15 5dAlignment - Hot Oil Drain Pump (271-P-1003) - Hot Oil Area 4d 19-Jul-15 24-Jul-15 5d

    HOT OIL TRANSFER PUMP (271-P-1001) 7d 15-Jul-15 24-Jul-15 5dInstallation - Hot Oil Transfer Pump (271-P-1001) - Hot Oil Area 3d 15-Jul-15 18-Jul-15 5dAlignment - Hot Oil Transfer Pump (271-P-1001) - Hot Oil Area 4d 19-Jul-15 24-Jul-15 5d

    FUEL GAS SYSTEM AREA 7d 28-Jul-15 06-Aug-15 3dEQUIPMENT INSTALLATION 7d 28-Jul-15 06-Aug-15 3dFILTER 7d 28-Jul-15 06-Aug-15 3dHP FUEL GAS FILTER (270-Y-1001A/B) 7d 28-Jul-15 06-Aug-15 3dInstallation - HP Fuel Gas Filter (270-Y-1001A/B) - Fuel Gas System Area 7d 28-Jul-15 06-Aug-15 3d

    LP FUEL GAS FILTER (270-Y-1002) 7d 28-Jul-15 06-Aug-15 3dInstallation - LP Fuel Gas Filter (270-Y-1002 A/B) - Fuel Gas System Area 7d 28-Jul-15 06-Aug-15 3d

    CHEMICAL STORAGE AREA 7d 23-Jul-15 01-Aug-15 7dEQUIPMENT INSTALLATION 7d 23-Jul-15 01-Aug-15 7dPUMP 7d 23-Jul-15 01-Aug-15 7dCAUSTIC TRANSFER PUMP (240-P-1020) 7d 23-Jul-15 01-Aug-15 7dInstallation - Caustic Transfer Pump (240-P-1020) - BSRU Area 3d 23-Jul-15 26-Jul-15 7dAlignment - Caustic Transfer Pump (240-P-1020) - BSRU Area 4d 27-Jul-15 01-Aug-15 7d

    FLARE SYSTEM AREA 21d 22-Jul-15 18-Aug-15 0dEQUIPMENT INSTALLATION 21d 22-Jul-15 18-Aug-15 0dFLARE 21d 22-Jul-15 18-Aug-15 0dFLARE PACKAGE (281-V-1001/ 281-FL-1001) 21d 22-Jul-15 18-Aug-15 0dInstallation - Flare Package (281-V-1001/ 281-FL-1001) - Flare System Area 21d 22-Jul-15 18-Aug-15 0d

    LP VENT GAS PACKAGE (281-V-1002/ 281-FL-1002) 21d 22-Jul-15 18-Aug-15 0dInstallation - LP Vent Gas Package (281-V-1002/ 281-FL-1002) - Flare System Area 21d 22-Jul-15 18-Aug-15 0d

    ACID GAS FLARE PACKAGE (2281-V-1003/ 81-FL-1003) 21d 22-Jul-15 18-Aug-15 0dInstallation - Acid Gas Flare Package (281-V-1003/ 281-FL-1003) - Flare System Area 21d 22-Jul-15 18-Aug-15 0d

    CLOSED DRAIN AREA 7d 15-Jul-15 24-Jul-15 6dEQUIPMENT INSTALLATION 7d 15-Jul-15 24-Jul-15 6dPUMP 7d 15-Jul-15 24-Jul-15 6dCLOSE DRAIN PUMP (277-P-1001 A/B) 7d 15-Jul-15 24-Jul-15 6dInstallation - Close Drain Pump (277-P-1001 A/B) - Closed Drain Area 3d 15-Jul-15 18-Jul-15 6dAlignment - Close Drain Pump (277-P-1001 A/B) - Closed Drain Area 4d 19-Jul-15 24-Jul-15 6d

    PIPING 281d 18-Dec-14 A 22-Oct-15 4dCPP AREA 281d 18-Dec-14 A 22-Oct-15 4dGENERAL 55d 18-Dec-14 A 10-Mar-15 1dSITE PIPE SHOP 55d 18-Dec-14 A 10-Mar-15 1dPRE-FABRICATION CS PIPING 52d 18-Dec-14 A 07-Mar-15 1d1st Shop Fabrication Above Ground - CS Piping 52d 18-Dec-14 A 07-Mar-15 1d

    PRE-FABRICATION SS PIPING 55d 19-Dec-14 A 10-Mar-15 1d1st Shop Fabrication Above Ground - SS Piping 55d 19-Dec-14 A 10-Mar-15 1d

    PROCESS 174d 11-Mar-15 26-Sep-15 7dAGRU AREA 56d 09-Jun-15 22-Aug-15 4dPIPING INSTALLATION 48d 09-Jun-15 11-Aug-15 5dPIPING NON PIPE RACK 48d 09-Jun-15 11-Aug-15 5dPiping Installation - AGRU connect to Vessel/ Column AGRU 35d 09-Jun-15 25-Jul-15 4dPiping Installation - AGRU connect to Stripper/Absorption Pump AGRU 14d 24-Jul-15 11-Aug-15 5dPiping Installation - AGRU connect to Drain/Sump Pump AGRU 7d 01-Aug-15 10-Aug-15 6d

    PIPING HYDROTEST 21d 25-Jul-15 22-Aug-15 4dPIPING NON PIPE RACK 21d 25-Jul-15 22-Aug-15 4dPiping Hydrotest - AGRU connect to Vessel/Column Absorption/Stripper Section 21d 25-Jul-15 22-Aug-15 4dPiping Hydrotest - AGRU connect to Pump Make Up/ Drain 7d 10-Aug-15 19-Aug-15 6dPiping Hydrotest - AGRU connect to Pump Stripper/Absorption Section 7d 12-Aug-15 21-Aug-15 5d

    BSRU AREA 147d 11-Mar-15 26-Aug-15 1d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    HOT OIL AREAEQUIPMENT INSTALLATIONPUMPHOT OIL DRAIN PUMP (271-P-1003)

    Installation - Hot Oil Drain Pump (271-P-1003) - Hot Oil AreaAlignment - Hot Oil Drain Pump (271-P-1003) - Hot Oil AreaHOT OIL TRANSFER PUMP (271-P-1001)

    Installation - Hot Oil Transfer Pump (271-P-1001) - Hot Oil AreaAlignment - Hot Oil Transfer Pump (271-P-1001) - Hot Oil Area

    FUEL GAS SYSTEM AREAEQUIPMENT INSTALLATIONFILTERHP FUEL GAS FILTER (270-Y-1001A/B)Installation - HP Fuel Gas Filter (270-Y-1001A/B) - Fuel Gas SyLP FUEL GAS FILTER (270-Y-1002)Installation - LP Fuel Gas Filter (270-Y-1002 A/B) - Fuel Gas Sy

    CHEMICAL STORAGE AREAEQUIPMENT INSTALLATIONPUMPCAUSTIC TRANSFER PUMP (240-P-1020)

    Installation - Caustic Transfer Pump (240-P-1020) - BSRU AreaAlignment - Caustic Transfer Pump (240-P-1020) - BSRU Area

    FLARE SYSTEM AREAEQUIPMENT INSTALLATIONFLAREFLARE PACKAGE (281-V-1001/ 281-FL-1001)Installation - Flare Package (281-V-1001/ 281-FL-1001) - LP VENT GAS PACKAGE (281-V-1002/ 281-FL-1002)Installation - LP Vent Gas Package (281-V-1002/ 281-FL-ACID GAS FLARE PACKAGE (2281-V-1003/ 81-FL-1003Installation - Acid Gas Flare Package (281-V-1003/ 281-FL

    CLOSED DRAIN AREAEQUIPMENT INSTALLATIONPUMPCLOSE DRAIN PUMP (277-P-1001 A/B)

    Installation - Close Drain Pump (277-P-1001 A/B) - Closed Drain AreaAlignment - Close Drain Pump (277-P-1001 A/B) - Closed Drain Area

    PIPINGCPP AREA

    GENERALSITE PIPE SHOP

    PRE-FABRICATION CS PIPING1st Shop Fabrication Above Ground - CS Piping

    PRE-FABRICATION SS PIPING1st Shop Fabrication Above Ground - SS Piping

    PROCESSAGRU AREA

    PIPING INSTALLATIONPIPING NON PIPE RACK

    Piping Installation - AGRU connect to Vessel/ Column AGRUPiping Installation - AGRU connect to Stripper/Absorption PumPiping Installation - AGRU connect to Drain/Sump Pump AGR

    PIPING HYDROTESTPIPING NON PIPE RACKPiping Hydrotest - AGRU connect to Vessel/Column Abso

    Piping Hydrotest - AGRU connect to Pump Make Up/ DraPiping Hydrotest - AGRU connect to Pump Stripper/Abso

    BSRU AREA

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 4 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    PIPING INSTALLATION 140d 11-Mar-15 17-Aug-15 1dPIPING ON PIPE RACK 126d 11-Mar-15 29-Jul-15 1dPiping Installation - BSRU on Pipe Rack 3 60d 11-Mar-15 09-May-15 1dPiping Installation - BSRU on Pipe Rack 1 45d 10-May-15 01-Jul-15 1dPiping Installation - BSRU on Pipe Rack 12 to Incinerator 21d 01-Jul-15 29-Jul-15 1d

    PIPING NON PIPE RACK 34d 03-Jul-15 17-Aug-15 1dPiping Installation - BSRU connect to Vessel/Column Reactor Section 21d 03-Jul-15 30-Jul-15 7dPiping Installation - BSRU connect to Pump Absorber Section 7d 25-Jul-15 03-Aug-15 4dPiping Installation - BSRU connect to Incinerator Section 14d 29-Jul-15 17-Aug-15 1dPiping Installation - BSRU connect to Compressor & Fan Reactor Section 7d 31-Jul-15 09-Aug-15 7dPiping Installation - BSRU connect to Pump Reactor Section 7d 01-Aug-15 10-Aug-15 6d

    PIPING HYDROTEST 20d 31-Jul-15 26-Aug-15 1dPIPING NON PIPE RACK 20d 31-Jul-15 26-Aug-15 1dPiping Hydrotest - BSRU connect to Vessel/Column Reactor Section 14d 31-Jul-15 18-Aug-15 7dPiping Hydrotest - BSRU connect to Pump Absorber Section 14d 03-Aug-15 21-Aug-15 4dPiping Hydrotest - BSRU connect to Pump Reactor Section 7d 10-Aug-15 19-Aug-15 6dPiping Hydrotest - BSRU connect to Incinerator Section 7d 17-Aug-15 26-Aug-15 1d

    DEW POINT CONTROL UNIT 21d 25-Jul-15 22-Aug-15 5dPIPING INSTALLATION 14d 25-Jul-15 12-Aug-15 5dPIPING NON PIPE RACK 14d 25-Jul-15 12-Aug-15 5dPiping Installation - Dew Point Contol Unit Package 14d 25-Jul-15 12-Aug-15 5d

    PIPING HYDROTEST 7d 13-Aug-15 22-Aug-15 5dPIPING NON PIPE RACK 7d 13-Aug-15 22-Aug-15 5dPiping Hydrotest - Dew Point Control Unit Package 7d 13-Aug-15 22-Aug-15 5d

    BLEED WATER TREATMENT 56d 19-Jul-15 26-Sep-15 7dPIPING INSTALLATION 42d 19-Jul-15 12-Sep-15 7dPIPING NON PIPE RACK 42d 19-Jul-15 12-Sep-15 7dPiping Installation - Bleed Water Treatment Unit 14d 19-Jul-15 06-Aug-15 7dPiping Installation - Bleed Water Treatment connect to Tank 14d 06-Aug-15 25-Aug-15 7dPiping Installation - Bleed Water Treatment connect to Pump 14d 25-Aug-15 12-Sep-15 7d

    PIPING HYDROTEST 14d 12-Sep-15 26-Sep-15 7dPIPING NON PIPE RACK 14d 12-Sep-15 26-Sep-15 7dPiping Hydrotest - Bleed Water Treatment connect to Pump 14d 12-Sep-15 26-Sep-15 7d

    UTILITY 229d 08-Mar-15 22-Oct-15 4dDIESEL FUEL STORAGE AREA 14d 02-Sep-15 15-Sep-15 6dPIPING INSTALLATION 7d 02-Sep-15 08-Sep-15 6dPIPING NON PIPE RACK 7d 02-Sep-15 08-Sep-15 6dPiping Installation - Connect to Pretreatment Diesel Unit Package 7d 02-Sep-15 08-Sep-15 6d

    PIPING HYDROTEST 7d 09-Sep-15 15-Sep-15 6dPIPING NON PIPE RACK 7d 09-Sep-15 15-Sep-15 6dPiping Hydrotest - Connect to Pretreatment Diesel unit Package 7d 09-Sep-15 15-Sep-15 6d

    HOT OIL AREA 35d 24-Jul-15 08-Sep-15 5dPIPING INSTALLATION 21d 24-Jul-15 21-Aug-15 5dPIPING NON PIPE RACK 21d 24-Jul-15 21-Aug-15 5dPiping Installation - Hot Oil connect to Hot Oil Tank/Pump 21d 24-Jul-15 21-Aug-15 5d

    PIPING HYDROTEST 14d 21-Aug-15 08-Sep-15 5dPIPING NON PIPE RACK 14d 21-Aug-15 08-Sep-15 5dPiping Hydrotest - Hot Oil connect to Hot Oil Fired Heater 14d 21-Aug-15 08-Sep-15 5d

    FUEL GAS SYSTEM AREA 14d 06-Aug-15 24-Aug-15 3dPIPING INSTALLATION 7d 06-Aug-15 15-Aug-15 3dPIPING NON PIPE RACK 7d 06-Aug-15 15-Aug-15 3dPiping Installation - Fuel Gas connect to Fuel Gas Filter 7d 06-Aug-15 15-Aug-15 3d

    PIPING HYDROTEST 7d 15-Aug-15 24-Aug-15 3dPIPING NON PIPE RACK 7d 15-Aug-15 24-Aug-15 3dPiping Hydrotest - Fuel Gas connect to Fuel Gas Filter 7d 15-Aug-15 24-Aug-15 3d

    WATER TREATMENT AREA 134d 08-Mar-15 05-Aug-15 1dPIPING INSTALLATION 120d 08-Mar-15 17-Jul-15 1dPIPING ON PIPE RACK 120d 08-Mar-15 17-Jul-15 1d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    PIPING INSTALLATIONPIPING ON PIPE RACK

    Piping Installation - BSRU on Pipe Rack 3Piping Installation - BSRU on Pipe Rack 1

    Piping Installation - BSRU on Pipe Rack 12 to IncineratorPIPING NON PIPE RACK

    Piping Installation - BSRU connect to Vessel/Column Reactor SectiPiping Installation - BSRU connect to Pump Absorber Section

    Piping Installation - BSRU connect to Incinerator SectionPiping Installation - BSRU connect to Compressor & Fan ReacPiping Installation - BSRU connect to Pump Reactor Section

    PIPING HYDROTESTPIPING NON PIPE RACK

    Piping Hydrotest - BSRU connect to Vessel/Column ReactPiping Hydrotest - BSRU connect to Pump Absorber Sec

    Piping Hydrotest - BSRU connect to Pump Reactor SectioPiping Hydrotest - BSRU connect to Incinerator Section

    DEW POINT CONTROL UNITPIPING INSTALLATIONPIPING NON PIPE RACKPiping Installation - Dew Point Contol Unit Package

    PIPING HYDROTESTPIPING NON PIPE RACKPiping Hydrotest - Dew Point Control Unit Package

    BLEED WATER TREATMENTPIPING INSTALLATIONPIPING NON PIPE RACK

    Piping Installation - Bleed Water Treatment UnitPiping Installation - Bleed Water Treatment connect to T

    Piping Installation - Bleed Water Treatment conPIPING HYDROTESTPIPING NON PIPE RACKPiping Hydrotest - Bleed Water Treatmen

    UTILITYDIESEL FUEL STORAGE AREA

    PIPING INSTALLATIONPIPING NON PIPE RACKPiping Installation - Connect to Pretreatment Dies

    PIPING HYDROTESTPIPING NON PIPE RACKPiping Hydrotest - Connect to Pretreatment D

    HOT OIL AREAPIPING INSTALLATIONPIPING NON PIPE RACKPiping Installation - Hot Oil connect to Hot Oil Tank/Pump

    PIPING HYDROTESTPIPING NON PIPE RACKPiping Hydrotest - Hot Oil connect to Hot Oil Fire

    FUEL GAS SYSTEM AREAPIPING INSTALLATIONPIPING NON PIPE RACKPiping Installation - Fuel Gas connect to Fuel Gas Filter

    PIPING HYDROTESTPIPING NON PIPE RACKPiping Hydrotest - Fuel Gas connect to Fuel Gas Filter

    WATER TREATMENT AREAPIPING INSTALLATIONPIPING ON PIPE RACK

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 5 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    Piping Installation - Water Treatment on Pipe Rack 5 45d 08-Mar-15 21-Apr-15 1dPiping Installation - Water Treatment on Pipe Rack 1 45d 22-Apr-15 07-Jun-15 1dPiping Installation - Water Treatment on Pipe Rack 3 30d 07-Jun-15 17-Jul-15 1d

    PIPING HYDROTEST 14d 17-Jul-15 05-Aug-15 1dPIPING ON PIPE RACK 14d 17-Jul-15 05-Aug-15 1dPiping Hydrotest - Water Treatment on Pipe Rack 3 14d 17-Jul-15 05-Aug-15 1d

    CHEMICAL STORAGE AREA 14d 01-Aug-15 19-Aug-15 7dPIPING INSTALLATION 7d 01-Aug-15 10-Aug-15 7dPIPING NON PIPE RACK 7d 01-Aug-15 10-Aug-15 7dPiping Installation - Chemical Injection connect to Caustic Pump 7d 01-Aug-15 10-Aug-15 7d

    PIPING HYDROTEST 7d 10-Aug-15 19-Aug-15 7dPIPING NON PIPE RACK 7d 10-Aug-15 19-Aug-15 7dPiping Hydrotest - Chemical Injection connect to Caustic Pump 7d 10-Aug-15 19-Aug-15 7d

    FLARE SYSTEM AREA 59d 19-Aug-15 22-Oct-15 4dPIPING INSTALLATION 7d 19-Aug-15 28-Aug-15 0dPIPING NON PIPE RACK 7d 19-Aug-15 28-Aug-15 0dPiping Installation - Flare connect to Acid Gas Flare 7d 19-Aug-15 28-Aug-15 0dPiping Installation - Flare connect to LP Vent Stack 7d 19-Aug-15 28-Aug-15 0dPiping Installation - Flare connect to Flare 7d 19-Aug-15 28-Aug-15 0d

    PIPING HYDROTEST 7d 28-Aug-15 06-Sep-15 0dPIPING NON PIPE RACK 7d 28-Aug-15 06-Sep-15 0dPiping Hydrotest - Flare connect to Acid Gas Flare 7d 28-Aug-15 06-Sep-15 0dPiping Hydrotest - Flare connect to LP Vent Stack 7d 28-Aug-15 06-Sep-15 0dPiping Hydrotest - Flare connect to Flare 7d 28-Aug-15 06-Sep-15 0d

    PIPING PAINTING & INSULATION 45d 06-Sep-15 22-Oct-15 4dPiping Painting & Insulation - Flare System Area 45d 06-Sep-15 22-Oct-15 4d

    CLOSED DRAIN AREA 28d 24-Jul-15 30-Aug-15 6dPIPING INSTALLATION 14d 24-Jul-15 11-Aug-15 6dPIPING ON PIPE RACK 14d 24-Jul-15 11-Aug-15 6dPiping Installation - Close Drain connect to Flare Pipe on Pipe Rack 1 14d 24-Jul-15 11-Aug-15 6d

    PIPING HYDROTEST 14d 12-Aug-15 30-Aug-15 6dPIPING ON PIPE RACK 14d 12-Aug-15 30-Aug-15 6dPiping Hydrotest - Closed Drain 14d 12-Aug-15 30-Aug-15 6d

    ELECTRICAL 44d 31-Jul-15 12-Sep-15 6dCPP AREA 44d 31-Jul-15 12-Sep-15 6dPOWER & CONTROL STATION 14d 31-Jul-15 13-Aug-15 4dSUBSTATION 14d 31-Jul-15 13-Aug-15 4dEQUIPMENT INSTALLATION 14d 31-Jul-15 13-Aug-15 4dSoft Starter Install - Substation 14d 31-Jul-15 13-Aug-15 4d

    PROCESS 23d 14-Aug-15 12-Sep-15 6dBSRU AREA 23d 14-Aug-15 12-Sep-15 6dTERMINATION,MEGGER, & CONTINUITY 23d 14-Aug-15 12-Sep-15 6dTermination - Air Compressor (240-C-1001 A/B) - BSRU Area 14d 14-Aug-15 01-Sep-15 3dTermination - Incinerator Control Panel - BSRU Area 14d 25-Aug-15 12-Sep-15 2dTermination - Incinerator Air Blower (240-C-1004 A/B) - BSRU Area 7d 03-Sep-15 12-Sep-15 6d

    INSTRUMENT 174d 22-Apr-15 12-Oct-15 0dCPP AREA 174d 22-Apr-15 12-Oct-15 0dGENERAL 35d 22-Apr-15 26-May-15 1dPIPE RACK 35d 22-Apr-15 26-May-15 1dTERMINATION,MEGGER, & CONTINUITY 21d 22-Apr-15 12-May-15 1dInstrument Pulling Cable - Field Bus - Pipe Prack Area 21d 22-Apr-15 12-May-15 1d

    PANEL & JUNCTION BOX 14d 13-May-15 26-May-15 1dJB Install & Termination - Instrument - Pipe Prack Area 14d 13-May-15 26-May-15 1d

    PROCESS 105d 27-May-15 04-Oct-15 1dAGRU AREA 105d 27-May-15 04-Oct-15 1dCABLE TRAY AND PULLING CABLE 45d 27-May-15 24-Jul-15 1dInstrument Pulling Cable - AGRU Area 45d 27-May-15 24-Jul-15 1d

    TERMINATION,MEGGER, & CONTINUITY 60d 24-Jul-15 04-Oct-15 1d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    Piping Installation - Water Treatment on Pipe Rack 5Piping Installation - Water Treatment on Pipe Rack 1

    Piping Installation - Water Treatment on Pipe Rack 3PIPING HYDROTESTPIPING ON PIPE RACKPiping Hydrotest - Water Treatment on Pipe Rack 3

    CHEMICAL STORAGE AREAPIPING INSTALLATIONPIPING NON PIPE RACKPiping Installation - Chemical Injection connect to Caustic Pum

    PIPING HYDROTESTPIPING NON PIPE RACKPiping Hydrotest - Chemical Injection connect to Caustic P

    FLARE SYSTEM AREAPIPING INSTALLATIONPIPING NON PIPE RACKPiping Installation - Flare connect to Acid Gas FlarePiping Installation - Flare connect to LP Vent StackPiping Installation - Flare connect to Flare

    PIPING HYDROTESTPIPING NON PIPE RACKPiping Hydrotest - Flare connect to Acid Gas FlarePiping Hydrotest - Flare connect to LP Vent StackPiping Hydrotest - Flare connect to Flare

    PIPING PAINTING & INSULAPiping Painting & Insulation -

    CLOSED DRAIN AREAPIPING INSTALLATIONPIPING ON PIPE RACKPiping Installation - Close Drain connect to Flare Pipe on Pipe

    PIPING HYDROTESTPIPING ON PIPE RACKPiping Hydrotest - Closed Drain

    ELECTRICALCPP AREA

    POWER & CONTROL STATIONSUBSTATIONEQUIPMENT INSTALLATIONSoft Starter Install - Substation

    PROCESSBSRU AREATERMINATION,MEGGER, & CONTINUITY

    Termination - Air Compressor (240-C-1001 A/B) - BTermination - Incinerator Control Panel - BSRUTermination - Incinerator Air Blower (240-C-100

    INSTRUMENTCPP AREA

    GENERALPIPE RACK

    TERMINATION,MEGGER, & CONTINUITYInstrument Pulling Cable - Field Bus - Pipe Prack Area

    PANEL & JUNCTION BOXJB Install & Termination - Instrument - Pipe Prack Area

    PROCESSAGRU AREA

    CABLE TRAY AND PULLING CABLEInstrument Pulling Cable - AGRU Area

    TERMINATION,MEGGER, & CONT

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 6 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    Megger & Continuity Test - AGRU Area 30d 24-Jul-15 02-Sep-15 1dTermination - AGRU Area 30d 02-Sep-15 04-Oct-15 1d

    FIELD INSTRUMENT & HOOK UP 37d 10-Aug-15 24-Sep-15 4dField Instrument Installation - AGRU Area 30d 10-Aug-15 17-Sep-15 4dHook Up - AGRU Area 30d 20-Aug-15 24-Sep-15 4d

    BSRU AREA 21d 13-Sep-15 04-Oct-15 1dTERMINATION,MEGGER, & CONTINUITY 7d 27-Sep-15 04-Oct-15 1dTermination - BSRU Area 7d 27-Sep-15 04-Oct-15 1d

    FIELD INSTRUMENT & HOOK UP 14d 13-Sep-15 27-Sep-15 1dField Instrument Installation - BSRU Area 7d 13-Sep-15 20-Sep-15 1dHook Up - BSRU Area 7d 20-Sep-15 27-Sep-15 1d

    UTILITY 52d 14-Aug-15 12-Oct-15 0dDIESEL FUEL STORAGE AREA 21d 15-Sep-15 05-Oct-15 6dTERMINATION,MEGGER, & CONTINUITY 7d 29-Sep-15 05-Oct-15 6dTermination - Diesel Fuel Storage Area 7d 29-Sep-15 05-Oct-15 6d

    FIELD INSTRUMENT & HOOK UP 14d 15-Sep-15 28-Sep-15 6dField Instrument Installation - Diesel Fuel Storage Area 7d 15-Sep-15 21-Sep-15 6dHook Up - Diesel Fuel Storage Area 7d 22-Sep-15 28-Sep-15 6d

    HOT OIL AREA 21d 16-Sep-15 07-Oct-15 6dTERMINATION,MEGGER, & CONTINUITY 7d 30-Sep-15 07-Oct-15 6dTermination - Hot Oil Area 7d 30-Sep-15 07-Oct-15 6d

    FIELD INSTRUMENT & HOOK UP 14d 16-Sep-15 30-Sep-15 6dField Instrument Installation - Hot Oil Area 7d 16-Sep-15 23-Sep-15 6dHook Up - Hot Oil Area 7d 23-Sep-15 30-Sep-15 6d

    FUEL GAS SYSTEM AREA 42d 25-Aug-15 10-Oct-15 3dTERMINATION,MEGGER, & CONTINUITY 14d 26-Sep-15 10-Oct-15 3dTermination - Fuel Gas System Area 14d 26-Sep-15 10-Oct-15 3d

    FIELD INSTRUMENT & HOOK UP 28d 25-Aug-15 26-Sep-15 3dField Instrument Installation - Fuel Gas System Area 14d 25-Aug-15 12-Sep-15 3dHook Up - Fuel Gas System Area 14d 12-Sep-15 26-Sep-15 3d

    WATER TREATMENT AREA 21d 14-Aug-15 11-Sep-15 1dTERMINATION,MEGGER, & CONTINUITY 7d 02-Sep-15 11-Sep-15 1dTermination - Water Treatment Area 7d 02-Sep-15 11-Sep-15 1d

    FIELD INSTRUMENT & HOOK UP 14d 14-Aug-15 02-Sep-15 1dField Instrument Installation - Water Treatment Area 7d 14-Aug-15 23-Aug-15 1dHook Up - Water Treatment Area 7d 24-Aug-15 02-Sep-15 1d

    CHEMICAL STORAGE AREA 21d 15-Sep-15 06-Oct-15 7dTERMINATION,MEGGER, & CONTINUITY 7d 29-Sep-15 06-Oct-15 7dTermination - Chemical Area 7d 29-Sep-15 06-Oct-15 7d

    FIELD INSTRUMENT & HOOK UP 14d 15-Sep-15 29-Sep-15 7dField Instrument Installation - Chemical Area 7d 15-Sep-15 22-Sep-15 7dHook Up - Chemical Area 7d 22-Sep-15 29-Sep-15 7d

    FLARE SYSTEM AREA 28d 14-Sep-15 12-Oct-15 0dTERMINATION,MEGGER, & CONTINUITY 14d 28-Sep-15 12-Oct-15 0dTermination - Flare System Area 14d 28-Sep-15 12-Oct-15 0d

    FIELD INSTRUMENT & HOOK UP 14d 14-Sep-15 28-Sep-15 0dField Instrument Installation - Flare System Area 7d 14-Sep-15 21-Sep-15 0dHook Up - Flare System Area 7d 21-Sep-15 28-Sep-15 0d

    CLOSED DRAIN AREA 21d 16-Sep-15 07-Oct-15 6dTERMINATION,MEGGER, & CONTINUITY 7d 30-Sep-15 07-Oct-15 6dTermination - Closed Drain Area 7d 30-Sep-15 07-Oct-15 6d

    FIELD INSTRUMENT & HOOK UP 14d 16-Sep-15 30-Sep-15 6dField Instrument Installation - Closed Drain Area 7d 16-Sep-15 23-Sep-15 6dHook Up - Closed Drain Area 7d 23-Sep-15 30-Sep-15 6d

    PRE-COMMISSIONING 82d 05-Aug-15 26-Oct-15 0d240 - AGRU 60d 22-Aug-15 26-Oct-15 1dMC Individual - AGRU Area 1d 25-Oct-15 26-Oct-15 1d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    Megger & Continuity Test - AGRU AreaTermination - AGRU Area

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - AGRU Area

    Hook Up - AGRU AreaBSRU AREATERMINATION,MEGGER, & CONTTermination - BSRU Area

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - BSRU Area

    Hook Up - BSRU AreaUTILITY

    DIESEL FUEL STORAGE AREATERMINATION,MEGGER, & CONTTermination - Diesel Fuel Storage Ar

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - Diesel Fuel S

    Hook Up - Diesel Fuel Storage AreaHOT OIL AREATERMINATION,MEGGER, & CONTTermination - Hot Oil Area

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - Hot Oil Area

    Hook Up - Hot Oil AreaFUEL GAS SYSTEM AREATERMINATION,MEGGER, & CONTermination - Fuel Gas System Are

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - Fuel Gas System

    Hook Up - Fuel Gas System AreaWATER TREATMENT AREATERMINATION,MEGGER, & CONTINUITYTermination - Water Treatment Area

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - Water Treatment Area

    Hook Up - Water Treatment AreaCHEMICAL STORAGE AREATERMINATION,MEGGER, & CONTTermination - Chemical Area

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - Chemical Are

    Hook Up - Chemical AreaFLARE SYSTEM AREATERMINATION,MEGGER, & COTermination - Flare System Area

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - Flare System

    Hook Up - Flare System AreaCLOSED DRAIN AREATERMINATION,MEGGER, & CONTTermination - Closed Drain Area

    FIELD INSTRUMENT & HOOK UPField Instrument Installation - Closed Drain

    Hook Up - Closed Drain AreaPRE-COMMISSIONING

    240 - AGRUMC Individual - AGRU Area

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 7 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    240-1 GAS ABSORPTION SECTION 60d 22-Aug-15 26-Oct-15 1dPIPING 59d 22-Aug-15 25-Oct-15 1dCHEMICAL CLEANING 7d 04-Oct-15 11-Oct-15 1dChemical Cleaning - Gas Absorption Section AGRU 7d 04-Oct-15 11-Oct-15 1d

    FLUSHING/ BLOWING 7d 22-Aug-15 31-Aug-15 4dFlushing / Blowing - Gas Absorption Section AGRU 7d 22-Aug-15 31-Aug-15 4d

    REINSTATEMENT/ FLANGE MANAGEMENT 7d 01-Sep-15 10-Sep-15 4dReinstatement - Gas Absorption Section AGRU 7d 01-Sep-15 10-Sep-15 4d

    LEAK TEST 7d 11-Oct-15 18-Oct-15 1dLeak Test - Gas Absorption Section AGRU 7d 11-Oct-15 18-Oct-15 1d

    N2 PURGING 7d 18-Oct-15 25-Oct-15 1dN2 Purging - Gas Absorption Section AGRU 7d 18-Oct-15 25-Oct-15 1d

    INSTRUMENT 21d 04-Oct-15 25-Oct-15 1dLOOP TEST 7d 04-Oct-15 11-Oct-15 1dLoop Test - Gas Absorption Section AGRU 7d 04-Oct-15 11-Oct-15 1d

    STROKE TEST 7d 11-Oct-15 18-Oct-15 1dStroke Test - Gas Absorption Section AGRU 7d 11-Oct-15 18-Oct-15 1d

    POPING TEST 7d 11-Oct-15 18-Oct-15 1dPoping Test - Gas Absorption Section AGRU 7d 11-Oct-15 18-Oct-15 1d

    INTERLOCK TEST 7d 18-Oct-15 25-Oct-15 1dInterlock Test - Gas Absorption Section AGRU 7d 18-Oct-15 25-Oct-15 1d

    MC GAS ABSORPTION AGRU - 240-1 1d 25-Oct-15 26-Oct-15 1dMC Individual - Gas Absorption AGRU 1d 25-Oct-15 26-Oct-15 1d

    240-2 AMINE CIRCULATION 60d 22-Aug-15 26-Oct-15 1dPIPING 59d 22-Aug-15 25-Oct-15 1dFLUSHING/ BLOWING 7d 22-Aug-15 31-Aug-15 4dFlushing / Blowing - Amine Circulation AGRU 7d 22-Aug-15 31-Aug-15 4d

    REINSTATEMENT/ FLANGE MANAGEMENT 7d 01-Sep-15 10-Sep-15 4dReinstatement - Amine Circulation AGRU 7d 01-Sep-15 10-Sep-15 4d

    LEAK TEST 7d 11-Oct-15 18-Oct-15 1dLeak Test - Amine Circulation AGRU 7d 11-Oct-15 18-Oct-15 1d

    N2 PURGING 7d 18-Oct-15 25-Oct-15 1dN2 Purging - Amine Circulation AGRU 7d 18-Oct-15 25-Oct-15 1d

    INSTRUMENT 21d 04-Oct-15 25-Oct-15 1dLOOP TEST 7d 04-Oct-15 11-Oct-15 1dLoop Test - Amine Circulation AGRU 7d 04-Oct-15 11-Oct-15 1d

    STROKE TEST 7d 11-Oct-15 18-Oct-15 1dStroke Test - Amine Circulation AGRU 7d 11-Oct-15 18-Oct-15 1d

    POPING TEST 7d 11-Oct-15 18-Oct-15 1dPoping Test - Amine Circulation AGRU 7d 11-Oct-15 18-Oct-15 1d

    INTERLOCK TEST 7d 18-Oct-15 25-Oct-15 1dInterlock Test - Amine Circulation AGRU 7d 18-Oct-15 25-Oct-15 1d

    MC AMINE CIRCULATION AGRU - 240-2 1d 25-Oct-15 26-Oct-15 1dMC Individual - Amine Circulation AGRU 1d 25-Oct-15 26-Oct-15 1d

    240-3 AMINE STORAGE 22d 04-Oct-15 26-Oct-15 1dINSTRUMENT 21d 04-Oct-15 25-Oct-15 1dLOOP TEST 7d 04-Oct-15 11-Oct-15 1dLoop Test - Amine Storage AGRU 7d 04-Oct-15 11-Oct-15 1d

    STROKE TEST 7d 11-Oct-15 18-Oct-15 1dStroke Test - Amine Storage AGRU 7d 11-Oct-15 18-Oct-15 1d

    POPING TEST 7d 11-Oct-15 18-Oct-15 1dPoping Test - Amine Storage AGRU 7d 11-Oct-15 18-Oct-15 1d

    INTERLOCK TEST 7d 18-Oct-15 25-Oct-15 1dInterlock Test - Amine Storage AGRU 7d 18-Oct-15 25-Oct-15 1d

    MC AMINE STORAGE - 240-3 1d 25-Oct-15 26-Oct-15 1dMC Individual - Amine Storage AGRU - 240-3 1d 25-Oct-15 26-Oct-15 1d

    240-4 AMINE DRAIN 60d 22-Aug-15 26-Oct-15 1dPIPING 21d 22-Aug-15 17-Sep-15 4d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    240-1 GAS ABSORPTION PIPING

    CHEMICAL CLEANINGChemical Cleaning - Gas Absorptio

    FLUSHING/ BLOWINGFlushing / Blowing - Gas Absorption Section AGRU

    REINSTATEMENT/ FLANGE MANAGEMENTReinstatement - Gas Absorption Section AGRU

    LEAK TESTLeak Test - Gas Absorption Sec

    N2 PURGINGN2 Purging - Gas AbsorptioINSTRUMENT

    LOOP TESTLoop Test - Gas Absorption Sectio

    STROKE TESTStroke Test - Gas Absorption SPOPING TESTPoping Test - Gas Absorption S

    INTERLOCK TESTInterlock Test - Gas AbsorptMC GAS ABSORPTION AGMC Individual - Gas Absorp240-2 AMINE CIRCULATIOPIPING

    FLUSHING/ BLOWINGFlushing / Blowing - Amine Circulation AGRU

    REINSTATEMENT/ FLANGE MANAGEMENTReinstatement - Amine Circulation AGRU

    LEAK TESTLeak Test - Amine Circulation A

    N2 PURGINGN2 Purging - Amine CirculatINSTRUMENT

    LOOP TESTLoop Test - Amine Circulation AGR

    STROKE TESTStroke Test - Amine Circulation POPING TESTPoping Test - Amine Circulation

    INTERLOCK TESTInterlock Test - Amine CirculMC AMINE CIRCULATIONMC Individual - Amine Circu240-3 AMINE STORAGEINSTRUMENT

    LOOP TESTLoop Test - Amine Storage AGRU

    STROKE TESTStroke Test - Amine Storage AGPOPING TESTPoping Test - Amine Storage AG

    INTERLOCK TESTInterlock Test - Amine StoraMC AMINE STORAGE - 24MC Individual - Amine Stora240-4 AMINE DRAIN

    PIPING

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 8 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    FLUSHING/ BLOWING 7d 22-Aug-15 31-Aug-15 4dFlushing / Blowing - Amine Drain AGRU 7d 22-Aug-15 31-Aug-15 4d

    REINSTATEMENT/ FLANGE MANAGEMENT 14d 01-Sep-15 17-Sep-15 4dReinstatement - Amine Drain AGRU 7d 01-Sep-15 10-Sep-15 4dTightening Bolt - Amine Drain AGRU 7d 10-Sep-15 17-Sep-15 4d

    INSTRUMENT 21d 04-Oct-15 25-Oct-15 1dLOOP TEST 7d 04-Oct-15 11-Oct-15 1dLoop Test - Amine Drain AGRU 7d 04-Oct-15 11-Oct-15 1d

    STROKE TEST 7d 11-Oct-15 18-Oct-15 1dStroke Test - Amine Drain AGRU 7d 11-Oct-15 18-Oct-15 1d

    POPING TEST 7d 11-Oct-15 18-Oct-15 1dPoping Test - Amine Drain AGRU 7d 11-Oct-15 18-Oct-15 1d

    INTERLOCK TEST 7d 18-Oct-15 25-Oct-15 1dInterlock Test - Amine Drain AGRU 7d 18-Oct-15 25-Oct-15 1d

    MC AMINE DRAIN - 240-4 1d 25-Oct-15 26-Oct-15 1dMC Individual - Amine Drain AGRU - 240-4 1d 25-Oct-15 26-Oct-15 1d

    240 - BSRU 57d 26-Aug-15 26-Oct-15 1dMC Individual - BSRU Area 1d 25-Oct-15 26-Oct-15 1d240 - BLEED WATER TREATMENT 24d 26-Sep-15 20-Oct-15 7dMC Individual - Bleed Water Treatment 1d 19-Oct-15 20-Oct-15 7dPIPING PRE-COMISSIONING 23d 26-Sep-15 19-Oct-15 7dFlushing / Blowing - Bleed Water Treatment 7d 26-Sep-15 03-Oct-15 7dReinstatement - Bleed Water Treatment 7d 03-Oct-15 10-Oct-15 7dTightening Bolt - Bleed Water Treatment 7d 10-Oct-15 17-Oct-15 7dLeak Test - Bleed Water Treatment 2d 17-Oct-15 19-Oct-15 7d

    MECHANICAL PACKAGE PRE-COMISSIONING 51d 01-Sep-15 24-Oct-15 2dINCINERATOR 42d 12-Sep-15 24-Oct-15 2dMotor Solo Run - Incinerator - BSRU Area 3d 12-Sep-15 15-Sep-15 6dPanel Pre-Test - Incinerator - BSRU Area 14d 12-Sep-15 26-Sep-15 2dBlower Final Alignment - Incinerator - BSRU Area 7d 15-Sep-15 22-Sep-15 6dBlower Test Run - Incinerator - BSRU Area 7d 26-Sep-15 03-Oct-15 2dPilot Test - Incinerator 7d 26-Sep-15 03-Oct-15 2dDrying Out - Incinerator - BSRU Area 7d 03-Oct-15 10-Oct-15 2dCooling Down - Incinerator - BSRU Area 7d 10-Oct-15 17-Oct-15 2dRefractory Inspection - Incinerator - BSRU Area 7d 17-Oct-15 24-Oct-15 2d

    AIR COMPRESSOR BSRU 35d 01-Sep-15 08-Oct-15 3dMotor Solo Run - Air Compressor - BSRU Area 14d 01-Sep-15 17-Sep-15 3dFinal Alignment - Air Compressor - BSRU Area 21d 18-Sep-15 08-Oct-15 3d

    PIPING PRE-COMISSIONING 54d 26-Aug-15 22-Oct-15 3dFlushing / Blowing - BSRU Area 7d 26-Aug-15 04-Sep-15 1dReinstatement - BSRU Area 7d 05-Sep-15 13-Sep-15 1dTightening Bolt - BSRU Area 14d 25-Sep-15 08-Oct-15 3dLeak Test - BSRU Area 14d 09-Oct-15 22-Oct-15 3d

    INSTRUMENT PRE-COMISSIONING 21d 04-Oct-15 25-Oct-15 1dLoop Test - BSRU Area 7d 04-Oct-15 11-Oct-15 1dStroke Test - BSRU Area 7d 11-Oct-15 18-Oct-15 1dInterlock Test - BSRU Area 7d 18-Oct-15 25-Oct-15 1d

    260 - DPCU 56d 22-Aug-15 22-Oct-15 5dMC Individual - DPCU Area 1d 21-Oct-15 22-Oct-15 5dPIPING PRE-COMISSIONING 55d 22-Aug-15 21-Oct-15 5dFlushing / Blowing - DPCU Area 7d 22-Aug-15 31-Aug-15 5dReinstatement - DPCU Area 7d 31-Aug-15 09-Sep-15 5dTightening Bolt - DPCU Area 14d 10-Sep-15 24-Sep-15 5dLeak Test - DPCU Area 14d 24-Sep-15 08-Oct-15 5dRefrigerant Loading - DPCU 3d 08-Oct-15 11-Oct-15 5dSAT - DPCU 10d 11-Oct-15 21-Oct-15 5d

    278 - PRODUCED WATER 14d 07-Oct-15 21-Oct-15 6dMC Individual - Produced Water 1d 20-Oct-15 21-Oct-15 6d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    FLUSHING/ BLOWINGFlushing / Blowing - Amine Drain AGRU

    REINSTATEMENT/ FLANGE MANAGEMENReinstatement - Amine Drain AGRU

    Tightening Bolt - Amine Drain AGRUINSTRUMENT

    LOOP TESTLoop Test - Amine Drain AGRU

    STROKE TESTStroke Test - Amine Drain AGRPOPING TESTPoping Test - Amine Drain AGR

    INTERLOCK TESTInterlock Test - Amine Drain MC AMINE DRAIN - 240-4MC Individual - Amine Drain240 - BSRUMC Individual - BSRU Area

    240 - BLEED WATER TREATMC Individual - Bleed Water TPIPING PRE-COMISSIONING

    Flushing / Blowing - Bleed Water TreaReinstatement - Bleed Water Trea

    Tightening Bolt - Bleed Water TLeak Test - Bleed Water Treat

    MECHANICAL PACKAGE PINCINERATOR

    Motor Solo Run - Incinerator - BSRU AreaPanel Pre-Test - Incinerator - BSRU Area

    Blower Final Alignment - Incinerator - BSRBlower Test Run - Incinerator - BSRUPilot Test - Incinerator

    Drying Out - Incinerator - BSRU ArCooling Down - Incinerator - BS

    Refractory Inspection - IncinAIR COMPRESSOR BSRU

    Motor Solo Run - Air Compressor - BSRU ArFinal Alignment - Air Compressor -

    PIPING PRE-COMISSIONINFlushing / Blowing - BSRU Area

    Reinstatement - BSRU AreaTightening Bolt - BSRU Area

    Leak Test - BSRU AreaINSTRUMENT PRE-COMIS

    Loop Test - BSRU AreaStroke Test - BSRU Area

    Interlock Test - BSRU Area260 - DPCUMC Individual - DPCU AreaPIPING PRE-COMISSIONIN

    Flushing / Blowing - DPCU AreaReinstatement - DPCU Area

    Tightening Bolt - DPCU AreaLeak Test - DPCU AreaRefrigerant Loading - DPCU

    SAT - DPCU278 - PRODUCED WATERMC Individual - Produced Wa

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 9 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    INSTRUMENT PRE-COMISSIONING 13d 07-Oct-15 20-Oct-15 6dLoop Test - Produced Water 7d 07-Oct-15 14-Oct-15 6dStroke Test - Produced Water 3d 14-Oct-15 17-Oct-15 6dInterlock Test - Produced Water 3d 17-Oct-15 20-Oct-15 6d

    810 - INSTRUMENT CONTROL SYSTEM 1d 25-Oct-15 26-Oct-15 1d810-1 - CONTROL SYSTEM 1d 25-Oct-15 26-Oct-15 1dINSTRUMENT 1d 25-Oct-15 26-Oct-15 1dICSS 1d 25-Oct-15 26-Oct-15 1dMC Individual - DCS/ SIS 1d 25-Oct-15 26-Oct-15 1d

    UTILITY 82d 05-Aug-15 26-Oct-15 0dDIESEL STORAGE 35d 16-Sep-15 20-Oct-15 6dMC Individual - Diesel Storage 1d 20-Oct-15 20-Oct-15 6dMECHANICAL PACKAGE PRE-COMISSIONING 7d 13-Oct-15 19-Oct-15 6dPRE-TREATMENT DIESEL UNIT PACKAGE 7d 13-Oct-15 19-Oct-15 6dMechanical Run Test - Pretreatment Diesel unit (276-V-1001) 7d 13-Oct-15 19-Oct-15 6d

    PIPING PRE-COMISSIONING 6d 16-Sep-15 21-Sep-15 6dFlushing / Blowing - Diesel Storage 3d 16-Sep-15 18-Sep-15 6dReinstatement - Diesel Storage 3d 19-Sep-15 21-Sep-15 6d

    INSTRUMENT PRE-COMMISSIONING 7d 06-Oct-15 12-Oct-15 6dLoop Test - Diesel Storage 7d 06-Oct-15 12-Oct-15 6d

    HOT OIL AREA 43d 09-Sep-15 22-Oct-15 5dMC Individual - Hot Oil Area 1d 21-Oct-15 22-Oct-15 5dMECHANICAL STATIC PRE-COMISSIONING 7d 07-Oct-15 14-Oct-15 5dTANK 7d 07-Oct-15 14-Oct-15 5dFill Oil Heating Medium Storage Tank - Hot Oil 7d 07-Oct-15 14-Oct-15 5d

    MECHANICAL ROTATING PRE-COMISSIONING 14d 23-Sep-15 07-Oct-15 5dPUMP 14d 23-Sep-15 07-Oct-15 5dFinal Alignment - API Pump - Hot Oil Area 14d 23-Sep-15 07-Oct-15 5d

    MECHANICAL PACKAGE PRE-COMMISSIONING 7d 14-Oct-15 21-Oct-15 5dHOT OIL 7d 14-Oct-15 21-Oct-15 5dHot Oil Circulating Test - Hot Oil Fired Heater 7d 14-Oct-15 21-Oct-15 5d

    PIPING PRE-COMISSIONING 28d 09-Sep-15 07-Oct-15 5dFlushing / Blowing - Hot Oil Area 7d 09-Sep-15 16-Sep-15 5dReinstatement - Hot Oil Area 7d 16-Sep-15 23-Sep-15 5dTightening Bolt - Hot Oil Area 14d 23-Sep-15 07-Oct-15 5d

    INSTRUMENT PRE-COMISSIONING 13d 07-Oct-15 20-Oct-15 6dLoop Test - Hot Oil Area 7d 07-Oct-15 14-Oct-15 6dStroke Test - Hot Oil Area 3d 14-Oct-15 17-Oct-15 6dInterlock Test - Hot Oil Area 3d 17-Oct-15 20-Oct-15 6d

    FUEL GAS SYSTEM AREA 56d 25-Aug-15 24-Oct-15 3dMC Individual - Fuel Gas System Area 1d 23-Oct-15 24-Oct-15 3dPIPING PRE-COMISSIONING 14d 25-Aug-15 12-Sep-15 3dFlushing / Blowing - Fuel Gas System Area 7d 25-Aug-15 03-Sep-15 3dReinstatement - Fuel Gas System Area 7d 03-Sep-15 12-Sep-15 3d

    INSTRUMENT PRE-COMISSIONING 13d 10-Oct-15 23-Oct-15 3dLoop Test - Fuel Gas System Area 7d 10-Oct-15 17-Oct-15 3dStroke Test - Fuel Gas System Area 3d 17-Oct-15 20-Oct-15 3dInterlock Test - Fuel Gas System Area 3d 20-Oct-15 23-Oct-15 3d

    WATER TREATMENT AREA 43d 05-Aug-15 26-Sep-15 1dMC Individual - Water Treatment Area 1d 25-Sep-15 26-Sep-15 1dPIPING PRE-COMISSIONING 14d 05-Aug-15 23-Aug-15 1dFlushing / Blowing - Water Treatment Area 7d 05-Aug-15 14-Aug-15 1dReinstatement - Water Treatment Area 7d 14-Aug-15 23-Aug-15 1d

    INSTRUMENT PRE-COMISSIONING 14d 11-Sep-15 25-Sep-15 1dLoop Test - Water Treatment Area 7d 11-Sep-15 18-Sep-15 1dInterlock Test - Water Treatment Area 7d 18-Sep-15 25-Sep-15 1d

    CHEMICAL AREA 56d 20-Aug-15 20-Oct-15 7dMC Individual - Chemical Area 1d 19-Oct-15 20-Oct-15 7d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    INSTRUMENT PRE-COMISSLoop Test - Produced WaterStroke Test - Produced WaterInterlock Test - Produced Wate

    810 - INSTRUMENT CONT810-1 - CONTROL SYSTEINSTRUMENTICSSMC Individual - DCS/ SISUTILITY

    DIESEL STORAGEMC Individual - Diesel StorageMECHANICAL PACKAGE PRPRE-TREATMENT DIESEL UMechanical Run Test - Pretrea

    PIPING PRE-COMISSIONINGFlushing / Blowing - Diesel Storage

    Reinstatement - Diesel StorageINSTRUMENT PRE-COMMISSIOLoop Test - Diesel Storage

    HOT OIL AREAMC Individual - Hot Oil Area

    MECHANICAL STATIC PRE-COTANKFill Oil Heating Medium Storage

    MECHANICAL ROTATING PRE-COPUMPFinal Alignment - API Pump - Hot O

    MECHANICAL PACKAGE PRHOT OILHot Oil Circulating Test - Hot O

    PIPING PRE-COMISSIONINGFlushing / Blowing - Hot Oil Area

    Reinstatement - Hot Oil AreaTightening Bolt - Hot Oil Area

    INSTRUMENT PRE-COMISSLoop Test - Hot Oil AreaStroke Test - Hot Oil AreaInterlock Test - Hot Oil Area

    FUEL GAS SYSTEM AREAMC Individual - Fuel Gas Sy

    PIPING PRE-COMISSIONINGFlushing / Blowing - Fuel Gas System Area

    Reinstatement - Fuel Gas System AreaINSTRUMENT PRE-COMIS

    Loop Test - Fuel Gas System AStroke Test - Fuel Gas SystemInterlock Test - Fuel Gas Sys

    WATER TREATMENT AREAMC Individual - Water Treatment Area

    PIPING PRE-COMISSIONINGFlushing / Blowing - Water Treatment Area

    Reinstatement - Water Treatment AreaINSTRUMENT PRE-COMISSIONING

    Loop Test - Water Treatment AreaInterlock Test - Water Treatment Area

    CHEMICAL AREAMC Individual - Chemical Area

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 10 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    PIPING PRE-COMISSIONING 21d 20-Aug-15 15-Sep-15 7dFlushing / Blowing - Chemical Area 7d 20-Aug-15 29-Aug-15 7dReinstatement - Chemical Area 14d 29-Aug-15 15-Sep-15 7d

    INSTRUMENT PRE-COMISSIONING 13d 06-Oct-15 19-Oct-15 7dLoop Test - Chemical Area 7d 06-Oct-15 13-Oct-15 7dStroke Test - Chemical Area 3d 13-Oct-15 16-Oct-15 7dInterlock Test - Chemical Area 3d 16-Oct-15 19-Oct-15 7d

    FLARE SYSTEM AREA 49d 06-Sep-15 26-Oct-15 0dMC Individual - Flare System Area 1d 25-Oct-15 26-Oct-15 0dPIPING PRE-COMISSIONING 14d 06-Sep-15 21-Sep-15 0dFlushing / Blowing - Flare System Area 7d 06-Sep-15 14-Sep-15 0dReinstatement - Flare System Area 7d 14-Sep-15 21-Sep-15 0d

    INSTRUMENT PRE-COMISSIONING 13d 12-Oct-15 25-Oct-15 0dLoop Test - Flare System Area 7d 12-Oct-15 19-Oct-15 0dStroke Test - Flare System Area 3d 19-Oct-15 22-Oct-15 0dInterlock Test - Flare System Area 3d 22-Oct-15 25-Oct-15 0d

    CLOSE DRAIN AREA 14d 30-Aug-15 16-Sep-15 6dPIPING PRE-COMISSIONING 14d 30-Aug-15 16-Sep-15 6dFlushing / Blowing - Close Drain Area 7d 30-Aug-15 08-Sep-15 6dReinstatement - Close Drain Area 7d 09-Sep-15 16-Sep-15 6d

    MECHANICAL COMPLETION 0d 26-Oct-15 26-Oct-15 0dMC Overall 0d 26-Oct-15 0d

    COMMISSIONING 97d 26-Sep-15 31-Dec-15 0dBEFORE GAS IN 8d 26-Sep-15 04-Oct-15 1dUTILITY 8d 26-Sep-15 04-Oct-15 1dWATER TREATMENT AREA 8d 26-Sep-15 04-Oct-15 1dStart Up & Commissioning - Water Treatment Area 7d 26-Sep-15 03-Oct-15 1dEnergize - Water Treatment Area 1d 03-Oct-15 04-Oct-15 1d

    AFTER GAS IN 59d 26-Oct-15 24-Dec-15 0dWELLPAD 1d 26-Oct-15 27-Oct-15 0dGas In - Well Pad 1d 26-Oct-15 27-Oct-15 0dStart Up & Commissioning - Well Pad 1d 26-Oct-15 27-Oct-15 0d

    FLOW LINE 2d 27-Oct-15 29-Oct-15 0dGas In - Flow Line 1d 27-Oct-15 28-Oct-15 0dStart Up & Commissioning - Flow Line 1d 28-Oct-15 29-Oct-15 0d

    INLET MANIFOLD 2d 29-Oct-15 31-Oct-15 0dGas In - Inlet Manifold 1d 29-Oct-15 30-Oct-15 0dStart Up & Commissioning - Inlet Manifold 1d 30-Oct-15 31-Oct-15 0d

    INLET SEPARATION 2d 31-Oct-15 02-Nov-15 0dGas In - Inlet Separation 1d 31-Oct-15 01-Nov-15 0dStart Up & Commissioning - Inlet Separation 1d 01-Nov-15 02-Nov-15 0d

    START UP GAS TREATER 3d 02-Nov-15 05-Nov-15 0dGas In - Start Up Fuel Gas Treater 1d 02-Nov-15 03-Nov-15 0dStart Up & Commissioning - Fuel Gas System Area 1d 03-Nov-15 04-Nov-15 0dProduce LP Fuel Gas for Heating System, Flare, Glycol Reboiler 1d 04-Nov-15 05-Nov-15 0d

    FLARE SYSTEM 11d 26-Oct-15 06-Nov-15 0dStart Up & Commissioning - Flare System (by LPG) 7d 26-Oct-15 02-Nov-15 2dIn Service - Flare System 1d 02-Nov-15 03-Nov-15 2dFuel Gas In from Start Up Treater - Flare System 1d 05-Nov-15 06-Nov-15 0d

    HOT OIL SYSTEM 11d 26-Oct-15 06-Nov-15 0dStart Up & Commissioning - Hot Oil System (by LPG) 7d 26-Oct-15 02-Nov-15 3dFuel Gas In from Start Up Treater - Hot Oil System 1d 05-Nov-15 06-Nov-15 0d

    AGRU SYSTEM (LOW PRESSURE) 6d 02-Nov-15 08-Nov-15 0dGas In - AGRU Bypass Booster Compressor 1d 02-Nov-15 03-Nov-15 2dStart Up & Commissioning - AGRU on Low Pressure 3d 05-Nov-15 08-Nov-15 0d

    DHU & DPCU SYSTEM 4d 05-Nov-15 09-Nov-15 0dGas In LP Gas from AGRU - DHU & DPCU 1d 05-Nov-15 06-Nov-15 0d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    PIPING PRE-COMISSIONINGFlushing / Blowing - Chemical Area

    Reinstatement - Chemical AreaINSTRUMENT PRE-COMISS

    Loop Test - Chemical AreaStroke Test - Chemical AreaInterlock Test - Chemical Area

    FLARE SYSTEM AREAMC Individual - Flare Syste

    PIPING PRE-COMISSIONINGFlushing / Blowing - Flare System Area

    Reinstatement - Flare System AreaINSTRUMENT PRE-COMIS

    Loop Test - Flare System AreaStroke Test - Flare System ArInterlock Test - Flare System

    CLOSE DRAIN AREAPIPING PRE-COMISSIONING

    Flushing / Blowing - Close Drain AreaReinstatement - Close Drain Area

    MECHANICAL COMPLETIMC Overall

    BEFORE GAS INUTILITYWATER TREATMENT AREAStart Up & Commissioning - Water TrEnergize - Water Treatment Area

    AWELLPADGas In - Well PadStart Up & Commissioning FLOW LINEGas In - Flow LineStart Up & CommissioningINLET MANIFOLDGas In - Inlet ManifoldStart Up & CommissioninINLET SEPARATIONGas In - Inlet SeparationStart Up & CommissioninSTART UP GAS TREA

    Gas In - Start Up Fuel GStart Up & CommissionProduce LP Fuel Gas fFLARE SYSTEM

    Start Up & CommissioninIn Service - Flare SysteFuel Gas In from StartHOT OIL SYSTEM

    Start Up & CommissioninFuel Gas In from StartAGRU SYSTEM (LO

    Gas In - AGRU Bypass Start Up & CommissioDHU & DPCU SYST

    Gas In LP Gas from AG

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 11 of 12 15-Jan-15

  • Activity Name Remaining Duration

    Start Finish Total Float

    Start Up & Commissioning - DHU & DPCU 3d 06-Nov-15 09-Nov-15 0dFUEL GAS SYSTEM 1d 09-Nov-15 10-Nov-15 0dProduce LP Fuel Gas for Process System 1d 09-Nov-15 10-Nov-15 0d

    GAS FUEL GTG 15d 10-Nov-15 25-Nov-15 0dGenerator Test - Gas/Diesel Fuel GTG A/B/C - Power Generation 14d 10-Nov-15 24-Nov-15 0dSynchronizing Test - Gas/Diesel Fuel GTG B/C - Power Generation 14d 10-Nov-15 24-Nov-15 0dIn Service - Gas/Diesel Fuel GTG A/B/C - Power Generation 1d 24-Nov-15 25-Nov-15 0d

    BOOSTER COMPRESSOR 9d 25-Nov-15 04-Dec-15 0dTest Run - Booster Compressor - Booster Compressor Area 2d 25-Nov-15 27-Nov-15 0dOver Speed Trip Test - Booster Compressor - Booster Compressor Area 2d 27-Nov-15 29-Nov-15 0dGas In - Booster Compressor Area 1d 29-Nov-15 30-Nov-15 0dStart Up & Commissioning - Booster Compressor Area 4d 30-Nov-15 04-Dec-15 0d

    BSRU 29d 10-Nov-15 09-Dec-15 0dChemical Loading - BSRU Area 6d 10-Nov-15 16-Nov-15 1dChemical Circulation for Bacterie Growth - BSRU Area 7d 16-Nov-15 23-Nov-15 1dGas In - BSRU Area 1d 23-Nov-15 24-Nov-15 1dStart Up & Commissioning - BSRU Area 14d 25-Nov-15 09-Dec-15 0d

    AGRU, DHU, DPCU (HIGH PRESSURE) 5d 04-Dec-15 09-Dec-15 0dGas In - AGRU,DCU, DHU High Pressure from Booster Compressor 1d 04-Dec-15 05-Dec-15 0dStart Up & Commissioning - AGRU, DCU, DHU High Pressure 4d 05-Dec-15 09-Dec-15 0d

    TRUNK LINE 3d 09-Dec-15 12-Dec-15 0dGas In - Trunk Line 1d 09-Dec-15 10-Dec-15 0dStart Up & Commissioning - Trunk Line 2d 10-Dec-15 12-Dec-15 0d

    SALES GAS SENORO 12d 12-Dec-15 24-Dec-15 0dGas In From Trunkline - Senoro 1d 12-Dec-15 13-Dec-15 0dStart Up & Commissioning - Senoro 7d 13-Dec-15 20-Dec-15 0dSAT Gas Metering - Senoro 4d 20-Dec-15 24-Dec-15 0d

    PERFORMANCE TEST & OPERATIONAL ACCEPTANCES 7d 25-Dec-15 31-Dec-15 0dPerformance Test 7d 25-Dec-15 31-Dec-15* 0dOperational Acceptance 0d 31-Dec-15 0d

    ec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2015

    Start Up & CommissiFUEL GAS SYSTEMProduce LP Fuel Ga

    GAS FUEL GGenerator TesSynchronizing In Service - G

    BOOSTERTest Run - BoOver SpeedGas In - Bo

    Start Up &BSRU

    Chemical Loading Chemical CircuGas In - BSRU

    Start UpAGRU,

    Gas In - AStart UpTRUN

    Gas In Start U

    SGas In

    StaS

    PPGM DONGGI

    CRITICAL ACTIVITY - JANUARI 2015

    Remaining Level of EffortActual Level of Effort

    Actual WorkRemaining Work

    Critical Remaining WorkMilestone

    Page 12 of 12 15-Jan-15


Recommended