+ All Categories
Home > Documents > Critical Path Method - R1

Critical Path Method - R1

Date post: 03-Jun-2018
Category:
Upload: soumitra-gupta
View: 225 times
Download: 0 times
Share this document with a friend

of 19

Transcript
  • 8/11/2019 Critical Path Method - R1

    1/19

    Critical PathMethod

    www.projectbaseline.in

  • 8/11/2019 Critical Path Method - R1

    2/19

    History

    The critical path method (CPM) is a project

    modeling technique developed in the late

    1950s by Morgan R. Walker of DuPont and

    James E. Kelle Jr. of Remin ton Rand.

    www.projectbaseline.in

  • 8/11/2019 Critical Path Method - R1

    3/19

    Application

    CPM is commonly used with all forms of

    projects, including

    Construction Aerospace and defense

    Software Development

    www.projectbaseline.in

    esearc ro ects Product Development

    Engineering, and Plant maintenance,

    among others. Any project with interdependent activities can

    apply this method of mathematical analysis.

  • 8/11/2019 Critical Path Method - R1

    4/19

    Basic Technique

    The essential technique for using CPM is to

    construct a model of the project that includes the

    following:

    A list of all activities required to complete the

    pro ect typ ca y categor ze w t n aWork Breakdown Structure),

    The time (duration) that each activity will take

    to completion, and The dependencies between the activities.

    www.projectbaseline.in

  • 8/11/2019 Critical Path Method - R1

    5/19

    Basic Technique

    Using these values, CPM calculates

    The longest path of planned activities to the

    end of the project The earliest and latest that each activity

    can start and finish without makin the

    project longer.

    This process determines which activities

    are "critical" (i.e., on the longest path) and

    which have "total float" (i.e., can be delayedwithout making the project longer).

    www.projectbaseline.in

  • 8/11/2019 Critical Path Method - R1

    6/19

    Basic Technique

    In project management, a critical path is the sequenceof project network activities which add up to the

    longest overall duration. This determines the shortest time possible to

    complete the project.

    An l n ivi n h ri i l h ir l

    impacts the planned project completion date (i.e.there is no float on the critical path).

    A project can have several, parallel, near critical

    paths. An additional parallel path through the network with

    the total durations shorter than the critical path is

    called a sub-critical or non-critical path.

    www.projectbaseline.in

  • 8/11/2019 Critical Path Method - R1

    7/19

    PERT Chart

    Activity-on-arrow diagram ("PERT Chart") is

    where each activity is shown as a box or node

    and the arrows represent the logicalrelationships going from predecessor to

    successor as shown here in the "Activity-on-

    no e agram .

    www.projectbaseline.in

    ES EF

    LS LF5

    A

    ES EF

    LS LF12

    B

  • 8/11/2019 Critical Path Method - R1

    8/19

    Activity Relationships

    Finish-to-Start (FS):

    A relationship between activities in which the start of a successoractivity depends on the finish of its predecessor activity.

    Start-to-Start (SS)

    A relationship between activities in which the start of a successoractivity depends on the start of its predecessor.

    www.projectbaseline.in

  • 8/11/2019 Critical Path Method - R1

    9/19

    Activity Relationships

    Finish-to-Finish (FF):

    A relationship between activities in which the finish of asuccessor activity depends on the finish of its predecessor.

    Start-to-Finish SF :

    A relationship between activities in which a successor activitycannot complete until its predecessor starts.

    Lags (or Leads):

    An offset or delay from an activity to its successor. A Lag can bepositive or negative

    www.projectbaseline.in

  • 8/11/2019 Critical Path Method - R1

    10/19

    Activity Box

    ES EF

    LS LF5

    A

    www.projectbaseline.in

    ES = Early StartEF = Early FinishLS = Late StartLF = Late FinishA = Activity Name

    5 = Duration Of Activity

  • 8/11/2019 Critical Path Method - R1

    11/19

    Activity Network Diagram

    ES EF

    5A

    ES EF

    LS LF

    10B

    ES EF

    LS LF

    8C

    ES EF

    7E

    www.projectbaseline.in

    LS LF ES EF

    LS LF

    12D

    LS LF

    Activity NameA. Ordering of PumpB. Pump ManufacturingC. Pump TransportationD. Pump Foundation

    E. Pump Erection

    Assumptions 7 day work week FS Relationships No Lag or Leads

  • 8/11/2019 Critical Path Method - R1

    12/19

    Forward Pass

    ES=6 EF=15

    10B

    ES=16 EF=23

    8C

    In Forward Pass Early Dates are calculated

    Forward Pass

    www.projectbaseline.in

    ES=1 EF=5

    LS LF

    5A

    LS LF LS LF

    ES=6 EF=17

    LS LF

    12D

    ES=24 EF=30

    LS LF

    7E

    Early Finish = Early Start + Duration - 1

  • 8/11/2019 Critical Path Method - R1

    13/19

    Backward Pass

    ES=1 EF=5

    A

    ES=6 EF=15

    LS=6 LF=1510

    B

    ES=16 EF=23

    LS=16 LF=238

    C

    ES=24 EF=30

    E

    In Backward Pass Late Dates are calculated

    www.projectbaseline.in

    LS=1 LF=5ES=6 EF=17

    LS=12 LF=23

    12D

    LS=24 LF=30

    Late Start = Late Finish - Duration + 1

    Backward Pass

    Assuming LF = 30

  • 8/11/2019 Critical Path Method - R1

    14/19

    Total Float

    ES=1 EF=5

    ES=6 EF=15

    LS=6 LF=15

    10B

    ES=16 EF=23

    LS=16 LF=23

    8C

    ES=24 EF=30

    Total Float = The amount of time the activity can be delayed before delayingthe Project Finish Date

    = =

    www.projectbaseline.in

    LS=1 LF=5

    5A

    ES=6 EF=17

    LS=12 LF=23

    12D

    LS=24 LF=30

    7E

    Total Float = Late Finish Early Finishor Late Start Early Start

    Assuming LF = 30

    TF=0

    TF=6

    TF=0

  • 8/11/2019 Critical Path Method - R1

    15/19

    Critical Path Scenario-I

    ES=1 EF=5

    ES=6 EF=15

    LS=6 LF=15

    10B

    ES=16 EF=23

    LS=16 LF=23

    8C

    ES=24 EF=30

    Activities with Total Float =< 0 are on the Critical Path

    = =

    Scenario I Late Finish of the project = 30

    www.projectbaseline.in

    LS=1 LF=5

    5A

    ES=6 EF=17

    LS=12 LF=23

    12D

    LS=24 LF=30

    7E

    Activities A, B, C and E are on the Critical Path (Longest Path)Activity D can be delayed by 6 days before delaying the finish date of the Project

    Assuming LF = 30

    TF=0

    TF=6

    TF=0

  • 8/11/2019 Critical Path Method - R1

    16/19

    Critical Path Scenario-II

    ES=1 EF=5

    ES=6 EF=15

    LS=16 LF=25

    10B

    ES=16 EF=23

    LS=26 LF=33

    8C

    ES=24 EF=30

    Activities with Total Float =< 0 are on the Critical Path

    = =

    Scenario II Late Finish of the Project is greater than 30 i.e. 40

    www.projectbaseline.in

    LS=11 LF=15

    5A

    ES=6 EF=17

    LS=22 LF=33

    12D

    LS=34 LF=40

    7E

    There is no critical activittesBut the Longest path is Activities A, B, C and EFor Activity E, C is a driving activity as Finish Date of C determines the Start Date of EAnd D is Non Driving

    Assuming LF = 40

    TF=10

    TF=16

    TF=10

  • 8/11/2019 Critical Path Method - R1

    17/19

    Critical Path Scenario-III

    ES=1 EF=5

    ES=6 EF=15

    LS=0 LF=9

    10B

    ES=16 EF=23

    LS=8 LF=17

    8C

    ES=24 EF=30

    Activities with Total Float =< 0 are on the Critical Path

    =- =-

    Scenario III Late Finish of the Project is Less than 30 i.e. 24

    www.projectbaseline.in

    LS=-5 LF=-1

    5A

    ES=6 EF=17

    LS=6 LF=17

    12D

    LS=18 LF=24

    7E

    All the activities are critical

    Assuming LF = 24

    TF=-6

    TF=0

    TF=-6

  • 8/11/2019 Critical Path Method - R1

    18/19

    Total Float

    Positive Total Float

    We can delay the activity

    Zero Total Float

    Negative Total Float

    The activity is already delayed

    www.projectbaseline.in

  • 8/11/2019 Critical Path Method - R1

    19/19

    Crashing Of Project

    It is a project Schedule Compression, which is

    performed for the purpose of decreasing total

    Period of the project.Different Methods of Crashing of the Activities: First Crash Activities on the Critical (Longest) path.

    Change the lags between activities Reduce the Duration of activities Increase the Resources

    Change the Working time : 5 day workweek to6/7 day workweek


Recommended