CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director
Transcript
Page 1: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

CROSSRAIL MOVING LONDON FORWARD

Martin Buck

Commercial Director

Page 2: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters What is Crossrail?

A new railway for London and the south east

Over 100 km from east to west

24 trains per hour in each direction

More than 200 million passenger journey per annum

Spacious and bright stations

And much more…

Page 3: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Crossrail route

Page 4: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Crossrail benefits

£42bn+

24

14,000 people

24 trains per hour

200 million journeys per year

Page 5: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Project progress

0.00

20.00

40.00

60.00

80.00

100.00

120.00

% C

om

ple

te

Design

Procurement

Construction

Testing & Comm.

Page 6: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Crossrail: delivering a railway

13 14 15 16 17 18

Railway Systems

Stations

Rolling Stock & Depot

NR Surface Works

Test and

Co

mm

ission

Trial Op

eration

Crossrail TOC

2012

Civils and Tunnelling

Page 7: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Tunnelling

Page 8: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Tunnelling progress: 29km

Page 9: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Spray concrete lined tunnels

Page 10: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Excavated material

On a tonne/km basis 85% of excavated

material is transported by rail or

water

Page 11: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Wallasea Island 2016

Page 12: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Central stations

8 new underground stations

Majority of main works contracts awarded

Major construction underway at all central London stations

Page 13: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Tottenham Court Road

Page 14: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Platform mock-up

Page 15: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters

London’s greatest commercial art galleries create a line-wide exhibition

7 galleries for 7 stations

One artist per station

Spencer Finch selected for Paddington for his proposal “A Cloud Index”

Funding secured from the City of London and Canary Wharf Group

The Culture Line

Page 16: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Over site developments

Page 17: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Archaeology

Page 18: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Property impacts

c.£5.5bn additional residential and commercial property value

Support 57,000 new homes

3.25 million square metres of commercial office floor space

“Crossrail is more than a new rail link, it will be the catalyst for regeneration in key locations and a driver of London’s economic growth; in particular from a property perspective.”

Page 19: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Equipping a workforce

Page 20: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Opportunities on Crossrail

Page 21: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters The new rolling stock

16

200m long trains

1,500 seated & standing passengers per train at peak times

Regenerates energy during braking (major savings in energy and CO2 emissions)

Page 22: CROSSRAIL MOVING LONDON FORWARDcic.org.uk/admin/resources/martin-buck-crossrail.pdf · 2014-02-11 · CROSSRAIL MOVING LONDON FORWARD Martin Buck Commercial Director . Header here

Header here max 30 characters Railway integration timeline

2018 2017 2016 2012

1

2013

2

2014

3

2015

4 5 6

Q1

Stage 5

2019

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Stage 4 Stage 3 Stage 2 Stage 1

7 8 9 10

Stage 1: Liverpool St (mainline) to Shenfield (May 2017)

Stage 3: Paddington (Crossrail platforms) to Abbey Wood (Dec 2018)

Stage 2: Heathrow to Paddington (mainline platforms) (May 2018)

Stage 4: Paddington (Crossrail platforms) to Shenfield (May 2019)

Stage 5: Full through service (Dec 2019)