Cryogenic system in P4:Possible options
S. Claudet & U. Wagner
LHC Workshop, “Chamonix XlV”January 2005
(Mostly for RF & beam scrubbing)
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Content
Brief recall of present situation Concerns
– Cooling capacity– Pressure stability– Coupling with items operated at higher pressure– Periodic cavity conditioning and developments
Possible alternative cooling schemes Summary
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Getting familiar with the subject
LHC Design report, p 134 for description of ACS cryogenics and requirements
Schematic views:– Single cavity module: LHCACSGA0006– QRL sector 3-4: LHCLSQR_0041– QRL sector 4-5: LHCLSQR_0042
Minutes of meetings between RF & Cryo Minutes of LHC Hardware Commissioning
Global overview ?!?
Interface to be further studied & finalised !!!
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Layout UX45, top view
ACS
QRL
QUI
QURC
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Layout UX45, side view
ACS
QUI
QRL
WRL
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Cooling capacity (1/3)
Injection NominalMaximu
m operation
Absolute Maximu
mMV/m 2.75 5.5 8.25 11.0
Static W 150
Margin W 25
Dynamic
W 25 100 225
Total W 200 275 400 950
“LHC Design report”, recently completed by AB/RF
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Cooling capacity (2/3)
Chamonix XIII 2004 / UW0
2
4
6
8
10
12
14
16
18
Comparing loads and capacities (1)Static
4.5 - 20 K
1.8 K
50 - 75 K20 - 300 K
DynamicCalculated load for Nominal operation compared to installed capacity for sector 8-1
Equivalent capacity [kW]Load calculated1997Load calculated2001Installed capacity
71 % surplus44 % surplus
Chamonix 2004, p 252
Equiv
ale
nt
capaci
ty
[kW
]
Some margin left at
Nominal mode
Nominal mode: no need for capacity upgrade
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Cooling capacity (3/3)
Chamonix XIII 2004 / UW0
2
4
6
8
10
12
14
16
18
Comparing loads and capacities (2)Static 4.5 - 20 K
1.8 K
50 - 75 K20 - 300 K
Dynamic
Calculated load for Ultimate operation compared to installed capacity for sector 8-1
Equivalent capacity [kW]Load calculated1997Load calculated2001Installed capacity
Load seen by1.8 K ref.24% surplus
Load seen by4.5 K ref.14% missing
Chamonix 2004, p 252
Equiv
ale
nt
capaci
ty
[kW
]
Lack of capacityof the 4.5 K
Refrigerators
Ultimate mode: obvious needfor capacity
upgrade
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Capacity for beam scrubbing
Chamonix 2004, p 253
Equiv
ale
nt
capaci
ty
[kW
]
00.511.522.53
Sector 1-2Sector 2-3Sector 3-4Sector 4-5Sector 5-6Sector 6-7Sector 7-8Sector 8-1Sector 1-2Sector 2-3Sector 3-4Sector 4-5Sector 5-6Sector 6-7Sector 7-8Sector 8-1
Load [W/m/aperture]
BS cooling loop loads (other than e-ecloud)Maximum available capacity for e-ecloudLoss of capacity w/r to local limitationW/o Ex-LEP turbine upgradeWith Ex-LEP turbine upgrade
450 GeV and Nominal Beam IntensityTurbine upgrade decided in 2004, (contract F529)
Cooling capacity in line with hydraulic capacity of beam
screens
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Pressure stability (1/2)
1000
1100
1200
1300
1400
1500
1600
21-Sep-04 26-Sep-04 1-Oct-04 6-Oct-04 11-Oct-04 16-Oct-04 21-Oct-04 26-Oct-04 31-Oct-04
0
200
400
600
800
1000
1200
+/- 100 mbar
+/- 5 mbar
with an average of 10 quench per day
line D "equivalent" pressure
cavities pressure
Pre
ssur
e [
mba
r] LHe level [m
m]
SM18
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Pressure stability (2/2)Request: 1.350 bar ± 15 mbar
Nota: LHe level control at low possible value will increase GHe volume for intrinsic pressure stability
Pre
ssur
e [
mba
r]
SM18
1340
1345
1350
1355
1360
25-Sep-04 26-Sep-04
+/- 5 mbar
7 quench 15 quench
cavities pressure
Try with Line D (60m3) as buffer and return valve in QUI for Pressure control
If not OK, then use return control valve of module for Pressure control
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Coupling via return line D (1/3)
During some operating modes, QRL - Line D will be operated at pressures above Cavities Maximum Allowed Working Pressure
Cool-down:
3.5 B to 1.3 B
Sector quench:
6 to 15 B
Warm-up:
1.3 to 3.5 B
2.0 B Safety device
1.550 B Beam Dump
1.500 B High Voltage off
1.450 B RF off
1.350 B Nominal value
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Coupling via return line D (2/3)
Normal cooldown of a LHC sector
300-4.5 K
Start of ACS and DFBs cooldown
Initial ramp: dTmax* < 75 K
* max temp. difference across magnet
Chamonix 2004, p 206
LHC Project Workshop, Session 6 - Chamonix January, 21 2004 G. Riddone, AT Department
+ 2 d to 1.9K
Cool-down of ACS to be started
when QRL- line D pressure is low
enough
Compatible with overall schedule
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Coupling via return line D (3/3)
Industrial cryogenic check-valve installed in refrigerators, DFB’s
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Conditioning & tests requirements
Commissioning or conditioning:– After installation before beam:6 months– After yearly warm-up to 300 K: 1
week– After a short stop (T ≤ 50 K): 1-2 hours
Not critical, even if frequent quenches at the beginning
Could be a good idea, but not yet the baseline !!!
Repeated request:– “Need to have the possibility of doing RF
work if machine is down for some time (magnet replacement, …)”
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Simplified cooling scheme
C (4.5 K; 3.0 bar)
D (20 K; 1.3 bar)
Warm recovery line (≤300 K; ≤1.1 bar)
4.5 KRefrigerator
QUI
QRL
SC CavitiesSafety SystemFall-back for
“low intensity”
HP
MP
LP
WarmCompressor
Station
ColdBox
Safety System
Back flow limitation
Open points:• Interface valves located in QRL Service Module• Safety system (control valve, safety valve, bursting disc)
• Back flow limitation
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Alternative cooling schemes, why?
To provide the possibility to discharge helium gas at a lower pressure than nominal 1.350 bar, increasing availability of sc cavities operation
To keep availability at least as it is now
While reviewing possible options, why not giving the possibility to operate the sc cavities independently from the sectors
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
4.5 KRefrigerator
QUI
QRL
SC Cavities
Coupler cooling
HP
MP
LP
WarmCompressor
Station
ColdBox
?
C (4.5 K; 3.0 bar)
D (20 K; 1.3 bar)
Warm recovery line (≤300 K; ≤1.1 bar)
Safety System
Safety System
Option 1: Warm returnAdvantage:• (Cool-down) / Warm-up even if line D > 1.4 bar• Recovery of ACS static losses after sector quench• Allows short period of operation if line D > 1.4 bar
Rather easily implemented
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Layout UX45, side view
ACSQRL
WRL
Detailed integration study needed to confirm the concept
Warm Recovery Line (WRL) always along
QRL
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Option 2: Cold returnAdvantage:• Cool-down / Warm-up even if line D > 1.4 bar• Recovery of ACS static losses after sector quench• Allows quick re-connection after quench• Allows short period of operation if line D > 1.4 bar• Allows operation independently from QRL / Magnets
4.5 KRefrigerator
QUI
QRL
SC Cavities
Coupler cooling
HP
MP
LP
WarmCompressor
Station
ColdBox
?
C (4.5 K; 3.0 bar)
D (20 K; 1.3 bar)
Warm recovery line (≤300 K; ≤1.1 bar)
Safety System
Safety System
Kept as back-up ?
Disadvantage:• New valve box & lines• Intervention on 2 lines• Not easily implemented
supply &
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Layout UX45, top view
ACS
QRL
QUI
QPLB - QULA: Lines between refrigerators & QUI
Additional lines as by-pass of QUI, via a valve boxFeasibility to be confirmedDetailed integration study needed to confirm the concept
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Option 3: “Process wish”Advantage:• Cool-down / Warm-up : no limitation• No limitation due to quench•Allows operation independent from QRL / Magnets
4.5 KRefrigerator
QUI
QRL
SC Cavities
Coupler cooling
HP
MP
LP
WarmCompressor
Station
ColdBox
To be defined
C (4.5 K; 3.0 bar)
D (20 K; 1.3 bar)
Warm recovery line (≤300 K; ≤1.1 bar)
Safety System
Safety System
Kept as back-up ?
Disadvantage:• Not likely to be possible
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Option 4: Dedicated compressor
Advantage:• Cool-down / Warm-up : no limitation• No limitation due to quench• Operation independent from sector
4.5 KRefrigerator
QUI
QRL
SC Cavities
Coupler cooling
HP
MP
LP
WarmCompressor
Station
ColdBox
DedicatedcompressorCapacity boost
to be defined
C (4.5 K; 3.0 bar)
D (20 K; 1.3 bar)
Safety System
Safety System
Kept as back-up ?
Disadvantage:• Coupling with 4.5K Ref. not certain if possible
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Option 5: Dedicated Ref. (at last!)
Advantage:• Cool-down / Warm-up : no limitation• No limitation due to quench• Operation independent from sector
DedicatedCompressor
DedicatedCold Box
4.5 KRefrigerator
QUI
QRL
SC Cavities
Coupler cooling
HP
MP
LP
WarmCompressor
Station
ColdBox
Kept as back-up ?
C (4.5 K; 3.0 bar)
D (20 K; 1.3 bar)
Safety System
Safety System
Disadvantage:• Where and how to install this now ?
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Layout UX45, top view (5)
ACS
QRL
Cooling capacity critical for ultimate beams, something will have to be done !
Integration study needed surface-shaft-cavern
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Summary options
Warm Return
Cold sup/ret
“process wish”
Dedicated Compressor
Dedicated Refrigerator
Now 1 2 3 4 5
Pro/consPressure in QRL-D
Minimum decouplin
g
RF more indenp.t Feasibility ?!?
Capacity RF indep.t
Budget (approx.)
100 - 150
kCHF
1 - 2 MCHF
3 - 5 MCHF
Time to install
6 - 10 months
1 - 2 years
2 - 3 years
Data provided as indications, to be further studied if necessary
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Summary The reference solution needs to be implemented, with
simple adaptations (control & check valves) to prevent perturbation due to back pressure from line D
A back-up return via the warm recovery line would prevent from major pressure excursions above 1.5 barOption
1
Option
2,3,4, 5
Option5
Any alternative cooling scheme will need a modification of the corresponding cryogenic distribution line (after concerned service module)
Additional capacity will be triggered by needs for ultimate beams or (bad!) operational experience
LHC Workshop CERN, January 2005
Session 3Cryo/RF Options
Acknowledgements
The authors would like to thank all colleagues who contributed to this work:
E. Ciapala, R. Losito, P. Maesen, O. Brunner
Y. MuttoniL. Serio, G. Riddone, L. Tavian