CSE 7315 - SW Project Management / Module 13 - Function Points and Related MethodsCopyright © 1995-2001, Dennis J. Frailey, All Rights Reserved Slide 1
CSE7315M13
January 10, 2001
SMU CSE 7315 / NTU SE 584-NPlanning and Managing a
Software Project
Module 13Size Estimating Methods
Part 2 - Function Points and Related Methods
Slide # 2 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Objective of This Module• To discuss function point methods
and related size estimating methods
Slide # 3 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Detailed Planning - Processes
EstimateScheduleEvaluate
Source InformationStatement of Work
RequirementsConstraintsStandardsProcesses
Historyetc.
WBS Size
Effort &
Cost
Schedule
OKCompleteDetailedPlanning
Revise &Negotiate
Not OK
EstimateSize
EstimateEffort and
Cost
Slide # 4 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Architecture of Spreadsheet
CoCoMo BasedEstimate
Other EffortEstimates ...
Analogy basedSize Estimate
SoftwareReuse
Analysis
Final EffortEstimate
ProductivityBased Effort
Estimate
Other SizeEstimates ...
Final SizeEstimate
Expert BasedSize Estimate
Size / Reuse Effort Effort & Cost Schedules
Generic Schedule
Effort Schedule
Labor Schedule
Cost Schedule
Slide # 5 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Function Point Methods(background)
• Function points measure the size of the customer’s requirements, or the size of the functionality to be produced, rather than the physical size of the software– This is analogous to measuring the size
of a house by counting the number and types of rooms, rather than by square footage
Slide # 6 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Function Point Methods
• Function Points as a size unit
• Function Point Analysis as an estimating method
Slide # 7 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Function Points are a Unitof Size
• “Function points” may be directly correlated to effort, memory requirements, or even to lines of code– All of the estimating methods discussed
previously can be used with function points as the size unit
– For example, you can compare new software with previous software, or use the wideband Delphi techniques
Slide # 8 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Function Point Analysis (FPA) is a Method of Estimating
• The function point method was developed by Allan Albrecht and refined by others (see references) to deal with situations where much was known about the functionality of the software but little about the structure or the size in “lines of code”.
Slide # 9 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Function Point Methods• The original definition by Albrecht
was based on transaction oriented systems – This concept of a “function” may not
work as well with other types of software
• Variations exist for real time, object oriented, and other kinds of applications
Slide # 10 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
(*) This is a goal of all size estimating methods.
Goals of Function Point Analysis
• To predict size accurately, as early as possible
• To provide a mechanism to track and monitor “scope creep” (*)– The difference in the number of function
points after requirements analysis, design & delivery is an indication to how much the scope of a project has grown
Slide # 11 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Albrecht’s Model of a Computer Software
Application
InternalLogical Files
(ILFs)
End User / Other ProgramsEO EI EQ
External
Queries
External
Outputs
External
InputsDataBase
(ExternalInterface
Files)
Slide # 12 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Categories of Functions - I1. External Inputs (EI)– An elementary process where data flows
in across the system boundary2. External Outputs (EO)– An elementary process where
“derived-data” flows out across the system boundary
3. External Queries (EQ)– An elementary process which outputs
data from ILFs based on the data input
Slide # 13 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Categories of Functions - II4. Internal Logical Files (ILF)– A logically related group of data that
resides entirely within the applications boundary and is maintained through EIs
5. External Interface Files (EIF) – A logically related group of data that is
used for reference purposes only – The data resides entirely outside the
application
Note: the idea of splitting files into internal & external is credited to Capers Jones in the early 1980’s.
Slide # 14 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Function Point Methodin a Nutshell
1) Count the functions in each category2) Establish the complexity of each:– High, Medium, or Low
3) Establish weights for each complexity4) Multiply each function by its weight and
then sum up to get total function points5) Adjust for application characteristics
Slide # 15 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Function Point ExampleCategory Simple Average ComplexEO 3 4 5
Weights 4 5 7
Points 12 20 35
Total Points for External Outputs: 67
Slide # 16 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Function Point Formula“Unadjusted” Function Points (UFP)
= EO points + EI points
+ EQ points + ILF points + EIF points
Slide # 17 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Adjustment Factor“Adjusted” FP = UFP * VAF
• VAF is an “application characteristics value adjustment factor” that ranges from 0.65 to 1.35 (see appendix A)
• VAF is determined by application characteristics that cannot be counted but that affect the application as a whole– Ease of use, reliability, flexibility, etc.
Slide # 18 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Note on Adjustment Factor• Some studies have shown that the
adjustment factor degrades the function point metric, resulting in lower accuracy
• Thus some authors prefer to leave out the adjustment factor and, instead, to assess application characteristics in the process of estimating effort
Slide # 19 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
The Devil is in the Details• How do you establish the weights?• How do you identify the functions?• How do you determine the
adjustment factor?• What do you do if your application
seems to have different kinds of functions other than Albrecht’s?
• The literature on function points is largely devoted to issues like these
Slide # 20 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Step by Step Details• Longstreet, Garmus, and the
International Function Point Users Group (IFPUG) have good descriptions of how to count function points
• For more information, see the reference list at the end of these notes
Slide # 21 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Calibration is Helpful - But Hard!
• Albrecht warns against attempting to calibrate for a given industry, application domain, or company
• He and others believe the specific software development organization must calibrate the FPA method to their own characteristics.
• But few organizations have enough data to do an effective calibration
Slide # 22 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Notes on Function Points
Slide # 23 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
1. Determine the Application Boundaries
The “functions” counted are those that cross the application boundary (except for internal files)
Application
External Environment
Slide # 24 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
2. Plan to Review and Update the Function Point Count
• Plan updates at key points where new information will be available, such as at major milestones
• Gather documentation, such as key requirements, constraints, and assumptions, for reference during future updates
• Record all of the functions that were counted, as well as their complexities
Slide # 25 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
3. How to Compute the Value Adjustment Factor
• VAF is based on the 14 General System Characteristics (GSCs)– The degree of influence of each GSC is
ranked from 0 - 5 as “No-Influence” to “Strong-Influence“ ; 2.5 is “typical”.
– Appendix A enumerates the GSCs
VAF = 0.65 + GSCi/100
Slide # 26 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
4. Using Function Points as Input to an Effort Estimate
• For many methods, you must convert to LOC after calculating Function Points
LOC = POINTS *CONVERSION FACTOR– Conversion factor is established
based on historical experience representing average number of lines per simple function
Slide # 27 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
What About Applications Where Function Points Don’t Seem to
Fit?• Example: Real Time Systems– Tend to have few internal files– But have very complex algorithms
• Extensions to Function Points are often used to handle non-transaction oriented systems, such as real time systems, object oriented designs etc
• Among the extensions are Feature Points and Object Points
Slide # 28 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Feature Points• An extension of the function point
method designed to deal with real time systems.
• A new category of function that represents complex algorithms
• The complexity of the algorithm is defined in terms of the number of “rules” required to express that algorithm
Slide # 29 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Algorithm Rules PointsNormalize 4 1Predictor 14 3Sort 50 7etc.TOTAL 11
Feature Point Example
Add this total to the total number of function points, after adjusting weights for internal files
Slide # 30 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Other Changes for Feature Points Method
• Lower weights for internal files• Other adjustments based on local
experience• Numerous variations in literature• The bottom line is that whatever
works for you should be used
Slide # 31 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Object Points• This approach is at a more macro
level than function points• Developed to address object
oriented designs• Assign one object point to each
unique class or object, such as a screen, output report, etc.
• The rest of the process is similar, but the weights are different
CSE 7315 - SW Project Management / Module 13 - Function Points and Related MethodsCopyright © 1995-2001, Dennis J. Frailey, All Rights Reserved Slide 32
CSE7315M13
January 10, 2001
Parametric Models
These are top-down methods based on some understanding of what factors or parameters affect the size of the software
Slide # 33 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
How Do You Determine What Factors Affect the Size?
Data AnalysisFactsabout
Which Factorshave What
Impact
ParametricModel
Slide # 34 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Several Types of Adjustment Factors
Non-sensitive Factors
0
5
10
0 1 2 3 4 5 6 7 8 9Size
Impact
Sensitive Factors
05
10
0 1 2 3 4 5 6
Size
Impact
Sum of All Factors??
05
10
1 2 3 4 5 6 7 8
Size
Impact
Linear Factors
05
10
1 2 3 4 5 6 7 8
Size
Impact
Slide # 35 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Using a Parametric Model
ParametricModel
SpecificValues
forSpecific
Situation
Expected orEstimatedBehavior
Slide # 36 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Adjustment Method Derived from Price-S®
• Define attributes for the software, as follows:
-- Software development environment
-- Software complexity -- Program data -- Project planning
Price-S® is a cost and size estimating tool originally developed by RCA and then owned by General
Electric, sold to Lockheed-Martin (Price Systems division).
Slide # 37 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Adjustment Method Derived from Price-S®
(continued) • Apply all of these attributes
by means of a complex function to adjust the size estimate
Slide # 38 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Adjustment Process
Complex andProprietary
Model
FunctionPoints
Attributes
EstimatedEquivalent
Lines of Code
Slide # 39 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Software Development Environment Attributes
• Number of design reviews planned• Number of code walkthroughs planned• Sophistication of design method– OO, SA/SD. Etc.
• Number of hardware and other software elements to integrate with
• Sophistication of test methods– Structured, modular, etc.
Slide # 40 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Software Complexity Attributes(select the one that fits)
• Commercial - no constraints• Commercial - moderate constraints– eg., must fit on a Pentium with
16Megabytes• Commercial - significant
constraints– eg. must fit on a microprocessor with
only 256K bytes and must meet significant timing constraints
Slide # 41 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Software Complexity Attributes(select the one that fits)
(continued)• Military - no constraints– eg., military data processing
application• Military - moderate constraints– eg., ground-based combat support
system• Military - significant constraints– eg., flight controls on an aircraft
Slide # 42 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Program Data Attributes• Number of unique output page formats• Number of unique display formats
(alphanumeric)• Number of unique graphic displays • Number of unique input streams• Number of unique output streams• Number of control states (decision
points)
Slide # 43 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Program Data Attributes (continued)
• Number of input message fields (unique fields)
• Number of unique operator actions• Number of unique analog signals on
input• Number of data elements in tables• Functional bulkiness (tool efficiency,
staff experience)
Slide # 44 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Project Planning Attributes• Expected requirements growth (%
of original system requirements)• Organizational know-how and
experience• Organizational business approach• Source language
Slide # 45 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Advantages of Function Pointsand Related Methods
• Estimates can be made relatively early in the project– before we know the
architecture of the software• Easier for customers to relate
the impact of change in functional requirements etc.
Slide # 46 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Advantages of Function Points
and Related Methods(continued)• Independent of programming
language, technology, and techniques
• More reliable relationship to effort– IF you can determine the right
functions to measure and the correct weights and adjustments
Slide # 47 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Disadvantages of Function Points and Related Methods• It is hard to count and track
function points– Much judgment involved– Difficult to automate
• Details, such as weights and definitions of complexity level, vary significantly from one application to the next and from one organization to the next
Slide # 48 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Disadvantages of Function Points and Related Methods
(continued)• Internal complexity of the application is
not considered– For example, housekeeping, memory
management, and other support functions• Calibration takes time, effort, and data– Although using results from similar
applications may be a good starting point
January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Many People Really Like Function Points … but ...
• Many effort/cost estimation tools use lines of code as input, so figures in function points may have to be converted – FPA may be a useful way to estimate lines of
code, regardless of whether function points are a good size unit
• More data may be available on lines of code than on function points– This depends on your company and business
Slide # 50 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
Module Summary• Function point methods do not
require information in size in lines of code, only the functions to be performed
• Other parametric methods rely on general characteristics of the software rather than specific details
Slide # 51 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
References• Albrecht, Allan J., "Measuring Application
Development Productivity," reprinted in Tutorial, Programming Issues for the Eighties (Capers Jones, editor), IEEE Computer Society Press, 1986, pp 35-44.
• Garmus, David and David Herron, Measuring the Software Process - A Practical Guide to Functional Measurements, Prentice-hall, 1996.
• International Function Point Users Group, Function Point Counting Practices Manual
Slide # 52 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
References (continued)• Longstreet, David “Function Points: Step
by Step”. Available on line at www.SoftwareMetrics.com/fpsteps.htm
• Symons, Charles, Software Sizing and Estimation, Mk II Function Point Analysis, West Sussex, England, John Wiley and Sons, 1991.
Slide # 53 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
END OFMODULE 13
CSE 7315 - SW Project Management / Module 13 - Function Points and Related MethodsCopyright © 1995-2001, Dennis J. Frailey, All Rights Reserved Slide 54
CSE7315M13
January 10, 2001
Appendix A
General System Characteristics Used to Calculate Function Point
Adjustment Factor
Slide # 55 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
The General System Characteristics
1. Data communications– How many communication facilities are
there to aid in the transfer or exchange of information with the application or system?
2. Distributed data processing– How are distributed data and processing
functions handled?3. Performance– Was response time or throughput
required by the user?
Slide # 56 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
The General System Characteristics (continued)
4. Heavily used configuration– How heavily used is the current
hardware platform where the application will be executed?
5. Transaction rate– How frequently are transactions
executed daily, weekly, monthly, etc.?6. On-Line data entry– What percentage of the information is
entered On-Line?
Slide # 57 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
The General System Characteristics (continued)
7. End-user efficiency– Was the application designed for end-
user efficiency?8. On-Line update– How many ILF’s are updated by On-Line
transaction?9. Complex processing– Does the application have extensive
logical or mathematical processing?
Slide # 58 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
The General System Characteristics (continued)
10. Reusability– Was the application developed to meet
one or many user’s needs?11. Installation ease– How difficult is conversion and
installation12. Operational ease– How effective and/or automated are
start-up, back-up, and recovery procedures?
Slide # 59 January 10, 2001
CSE 7315 - SW Project Management / Module 13 - Function Points and Related
MethodsCopyright © 1995-2001, Dennis J. Frailey,
All Rights ReservedCSE7315M13
The General System Characteristics (continued)
13. Multiple sites– Was the application specifically
designed, developed, and supported to be installed at multiple sites for multiple organizations?
14. Facilitate change– Was the application specifically
designed, developed, and supported to facilitate change?