Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013
Transcript
Page 1: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Culvert Inventory Plan

Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013

Page 2: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Culvert Inventory PlanCulvert Inventory Plan

• Overview

• Plan Components

• Resourcing Plan

• Organization Chart

• Project Milestones

• Budget

• Other Agency Considerations

• Next Steps

• Questions

Page 3: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Overview:Overview:Goal: • Support project scoping for 2016 – 2018 STIP• Deliver inventory and condition assessment • Identify priority culverts needing repair or replacement• HMT “Priority Corridor Routes”

Recommendations:• Basic Condition Application + Advanced Condition

Application (BCA + ACA)• Resourcing Plan

Page 4: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Non-interstate: 1000 miles

Completed: 600+ miles

Remaining: 400 miles

Interstate: 700 miles

Page 5: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Resource Plan

• Centralized project management• Full-time project commitment• Field Crews – develop recruitment pool • Supplement with contractors/consultants where

needed– IT/GIS– Project Management

Page 6: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Resource Plan: Org ChartResource Plan: Org Chart

Page 7: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Culvert Inventory Target MilestonesAnticipated Target

Activity Start Date Completion Date

Training Development and Delivery Jan-13 March/April 2013

     

Basic Condition Assessment Field Data Collection (Non-Interstate Hwys)March/April

2013 Sep-13

Basic Condition Assessment Field Data Collection (Interstate Hwys)March/April

2013 Jun-14

     

Advanced Condition Assessment Field Data Collection (Non-Interstate Hwys) Jul-13 Oct-13

Advanced Condition Assessment Field Data Collection (Interstate Hwys) Oct-13 June/July 2014

     

Culvert Condition Information to Tech Centers (Non-Interstate Hwys) Nov-13 Jan-14

Culvert Condition Information to Tech Centers (Interstate Hwys) June/July 2014 Oct 2014

     

Project Completion   Oct 2014

Note: No significant field work during winter months (Nov 2013 – March 2014)

Page 8: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

BudgetBudget

2011-2013 2013-2015 Allocated Costs Total CostCost W/O Allocated

PersonnelTraining $47,500 $2,500 $50,000Initial Team $36,980 $49,020 $86,000

Basic Condition Assessment-100% Culverts on Virgin Routes $243,072 $516,528 $759,600Advanced Condition Assessment-Poor/Critical (25%) Culverts on Virgin routes (Second Trip) $45,120 $95,880 $141,000Advanced Condition Assessment Update-Poor/Critical (25%) Culverts on aged data routes (Second Trip) $10,624 $22,576 $33,200

Field Inventory Coordinator $51,520 $109,480 $161,000Geo-Environmental Support $270,000 $270,000Nonpriority Route Inventory Support $232,000 $232,000DFMS Procedure Development and Documentation $25,000 $25,000Project Manager (Consultant) $93,000 $217,000 $310,000

Application Development(Consultant) $150,000 $150,000Per Diem/Travel Costs $49,574 $105,346 $154,920Maintenance Costs $4,268 $9,069 $13,337Vehicle Costs $21,587 $45,873 $67,460Traffic Control $16,000 $34,000 $50,000GPS Equipment $44,000 $44,000ArcPad License $12,500 $12,500General Field Equipment $680 $320 $1,000

$826,425 $1,207,592 $527,000 $2,561,017 $2,034,017

"Fix-It" Corridor Culvert InventoryPreferred Option Cost Summary

Basic Condition, Interstate Basic Condition, and Advanced Condition Rating Teams

Page 9: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Maintenance Involvement• Initial local knowledge

– 1 employee, 1 day/section

• Traffic control in Portland and like areas• Options for providing prep work (if available)• Rotational Opportunities

Other ODOT staff involvement• Rotational Opportunities

Other Agency Considerations

Page 10: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Other Agency Considerations

Non–Priority Corridor Culverts

• Current culvert inventory efforts have been stopped but should be able to resume in Spring 2013.

• Field crews must attend approved training

• May require additional resources to provide support

Page 11: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Plan: Next StepsPlan: Next Steps

• Hire Project Manager• Establish Steering Committee• Report back to Leadership Teams

– HMT: Quarterly?

Page 12: Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013.

Questions?Questions?