+ All Categories
Home > Documents > Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11,...

Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11,...

Date post: 24-Dec-2015
Category:
Upload: jasper-cobb
View: 242 times
Download: 1 times
Share this document with a friend
31
Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005
Transcript
Page 1: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Cummins ISBTest Development Task Force

Cummins Surveillance Panel

Mark Sarlo, SwRI

January 11, 2005

Page 2: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

ISB Test Development Progress

• Labs and Engines

• Procedure

• Special Parts and Cam Measurement

• Modifications to Hardware and or Procedure

• Move Forward to Matrix

Page 3: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

ISB Engine

• 5.9L ISB MY04, CPL 8123. This engine is certified at

2.0 g NOx/bhp-hr

• Fuel system Common Rail

• CPL 8123

• Low idle 800 RPM (ECM 750 RPM)

• High idle 3,000 RPM

• Rated 300 hp @ 2,600 RPM

• Torque peak 600 lbf-ft @ 1,600 RPM

Page 4: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

ISB Engines at Labs

• SwRI @ San Antonio, Completed 830-2 and 1004-3

• PE @ San Antonio, Completed two 830-2 and one 1004-3

• Lubrizol @ Wickliffe, Completed 1004-3

• ExxonMobil @ Paulsboro, Preparing to Run Reference Oil

• Valvoline, Ashland, May Run Older Engine Configuration

• Afton, Richmond, Waiting on Engine, Waiting on Cell Space

Page 5: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

ISB Procedure Highlights

• 350 Total Hours, (100-hr Stage A, 250-hr Cyclic Stage B)• First 100 Hours at 1,600 RPM & 20 kg/hr, 107 kPa abs EBP, 110 C

Oil Temp, 99 C Coolant Out, 68 C Int Man• Retard Timing 14-16° to Generate Soot (use NGET)• Soot Window of 3.25 +/- 0.25% at 100 Hours• Charge Engine with 14.5kg Oil Total (Some into Filter)• Two Flushes• External Oil Adder System, External Tube & ShellOil Cooler• Oil Sample @ 25, 50, 75, & 100 Hr, 1,000 g Forced Add• Return Timing to “Native Timing” for Final 250 hr Stage B• Run Multi-step Valvetrain Wear Cycle for next 250 hr• Oil Sample @ 150, 200, 250, 300, & 350 hr with No Additional Oil

Adds

Page 6: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

ISB Procedure Highlights

• Coolant Out Temperature 99 Degrees C

• Engine Oil Sump Temperature 110 Degrees C

• Fuel Temperature 40 Degrees C

• Intake Manifold Air Temperature 68 Degrees C, 114mm

• Estimate 8,000 L Fuel per Test

• Use Cummins Complete PG Coolant

• 107 kPa Absolute Exhaust Back Pressure Set in Stage A, Open for Stage B

Page 7: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Cummins ISB Stages A & B

Page 8: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

ISB Test Numbering

• 64-001-57216596-0000 (Example)

• First Number is Lab’s Cell Number (64)

• Second Number is Run Number for that Cell (001)

• Third Number is Cummins Engine SN (57216596)

• Fourth and Final Number is Hours on Engine After 80-

hour Break-in Procedure

Page 9: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Cummins ISB, Typical Soot

Page 10: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Cummins ISB Soot, Stage A

Page 11: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Cummins ISB Soot, Stage B

Page 12: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Cummins ISB Cyclic Stage B

Page 13: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Cummins ISB Stage B Cycle

Page 14: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Special Parts

• CPD to Maintain and Etch Critical Parts

• Parts to be Etched in Sets and Sequentially, 1 Through 12

• CPD to Maintain Inventory of Three New Engines

• New Engine Will Require 80 hr Break-in

• Engine Life Dependent on Lubricants Evaluated

• Estimate Up-to Ten Tests per Engine Block

• Points of Wear Include Camshaft & Tappet Bores in Block

Page 15: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Camshaft Wear Measurements

• Camshaft Lobes are Flat (Not Tapered)

• Most Wear Occurs on Ramps, Not Nose

• Use Adcole Gage to Measure

• Cam Supplier to Measure

• Investigating Alternate Measurement

• Investigate Cam Shipping to Assure Safety

• Matrix-Related Cams Shipped to Warren

• Candidate Cams Directly to Cam Supplier

Page 16: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Camshaft Measurements

• Batch of Cams Pre-measured by Adcole

• CPD Maintains BOT Data

Page 17: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Special Parts Measurements for Matrix?

• Crosshead Weightloss (mg)

• Tappet Weightloss (mg) AFTER EnSolve® Cleaning

• Tappet Heightloss (mm)

• Tappet Stem OD wear (mm)

• Tappet Slider Surface Profile Wear in Two Planes @ 90°

• Valve Adjusting Screw Weightloss (mg)

• Valve Rocker Lever Socket Weightloss (mg)

• Valve Rocker Shaft Weightloss (mg)

• Valve Push Rod Weighloss (mg)

Page 18: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Special Parts Measurements for Matrix?

• Camshaft Lobe Wear, Conventional (mm)

• Camshaft Lobe Wear, Adcole Method

• Camshaft Bearing Journal Wear, Conventional (mm)

• Camshaft Bearing Journal Wear, Adcole Method

• Tappet Bore Wear in Parent Block (mm)

• Cam Bore Wear in Parent Block (mm)

• Valve Lash Change (mm)

• Sludge Rating for Rocker Cover with and without Baffle

• Sludge Rating for Oil Pan

Page 19: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Tappet Face Wear, Center and Maximum

Page 20: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Tappet Face Wear, Center and Maximum

Page 21: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Tappet Face Wear, Center and Maximum

Page 22: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

New Generation Engineering Tool (NGET)®

• Latest Version not as User-Friendly While Logging

• Parameters to Measure Sent Out as ISBParameter.lay File

• NGET® is Used to Adjust Timing for First 100 hr

Page 23: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Summary

• Warren to Supply Updated Procedure in ASTM Format

• Discrimination Proven with Mini-Matrix?

• Matrix Design

• Industry Participation, Stand Installation, Timing????

Page 24: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Mini-Matrix Data

Page 25: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Mini-Matrix Data

Page 26: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Mini-Matrix Data

Page 27: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Mini-Matrix Data

Page 28: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Mini-Matrix Data

Page 29: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Mini-Matrix Data

Page 30: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Mini-Matrix Data

Page 31: Cummins ISB Test Development Task Force Cummins Surveillance Panel Mark Sarlo, SwRI January 11, 2005.

Cummins ISB Pan Fitting Locations for External Oil Adder System