Date post: | 29-Mar-2015 |
Category: |
Documents |
Upload: | duane-rezin |
View: | 214 times |
Download: | 0 times |
CURRENT METEOROLOGICAL HAPPENINGSCURRENT METEOROLOGICAL HAPPENINGS
THE SITING AND ACCIDENT CONSEQUENCES BRANCHTHE SITING AND ACCIDENT CONSEQUENCES BRANCH
DIVISION OF SITE AND ENVIRONMENTAL REVIEWS
OFFICE OF NEW REACTORS
Brad Harvey, Senior Physical ScientistJoseph Hoch, Physical Scientist
U.S. Nuclear Regulatory Commission
June 25 - 27, 2008Nuclear Utilities Meteorological Data Users Group (NUMUG)
PRESENTATION OUTLINEPRESENTATION OUTLINE
1) RECENTLY COMPLETED ACTIVITIES
2) PLANNED ACTIVITIES
3) STAFF FEEDBACK FROM REVIEWING COMBINED LICENSE APPLICATIONS
RECENTLY COMPLETED ACTIVITIESRECENTLY COMPLETED ACTIVITIES
• Revision 0 to Regulatory Guide 1.206 Issued“Combined License Applications for Nuclear Power Plants” (June 2006)
C.I.2: Site Characteristics
C.III.1: Information Needed for a Combined License Application Referencing a Certified Design
C.III.1.2 Site Characteristics
C.III.2: Information Needed for a Combined License Application Referencing a Certified Design and an Early Site Permit
C.III.2.2 Site Characteristics
• NUREG-0800 (i.e., Standard Review Plan) UpdatedReview of Safety Analysis Reports for Nuclear Power Plants (March 2007)
2.0: Site Characteristics and Site Parameters (Rev. 0)
2.3.1: Regional Climatology (Rev. 3)
2.3.2: Local Meteorology (Rev. 3)
2.3.3: Onsite Meteorological Measurements Programs (Rev. 3)
2.3.4: Short-Term Dispersion Estimates for Accident Releases (Rev. 3)
2.3.5: Long-Term Atmospheric Dispersion Estimates for Routine Releases (Rev. 3)
RECENTLY COMPLETED ACTIVITIESRECENTLY COMPLETED ACTIVITIES
• Revision 4 to Regulatory Guide 1.97 Issued“Criteria For Accident Monitoring Instrumentation For Nuclear Power Plants” (June 2006)
• Revision 1 to Regulatory Guide 1.23 Issued“Meteorological Monitoring Programs for Nuclear Power Plants” (March 2007)
• Revision 2 to Regulatory Guide 1.76 Issued“Design-Basis Tornado and Tornado Missiles for Nuclear Power Plants” (March 2007)
RECENTLY COMPLETED ACTIVITIESRECENTLY COMPLETED ACTIVITIES
Enhanced Fujita ScaleEnhanced Fujita Scale
Regulatory Guide 1.76 Tornado Intensity RegionsRegulatory Guide 1.76 Tornado Intensity Regions
UPCOMING ACTIVITIESUPCOMING ACTIVITIES
• New Regulatory GuideDesign-Basis Hurricane and Hurricane Missiles for Nuclear Power Plants
• Revision 2 to Regulatory Guide 1.145Atmospheric Dispersion Models for Potential Accident Consequence Assessments at Nuclear Power Plants
• Revision 2 to Regulatory Guide 1.111Methods for Estimating Atmospheric Transport and Dispersion of Gaseous Effluents in Routine Releases from Light-Water-Cooled Reactors
• Revision 1 to Regulatory Guide 1.194Atmospheric Relative Concentrations for Control Room Radiological Habitability Assessments at Nuclear Power Plants
• Revision 2 to Regulatory Guide 1.78Evaluating the Habitability of a Nuclear Power Plant Control Room During a Postulated Hazardous Chemical Release
• Revision 3 to Regulatory Guide 1.27Ultimate Heat Sink for Nuclear Power Plants
• Interim Staff GuidanceAssessment of Normal and Extreme Winter Precipitation Loads on the Roof of Seismic Category I Structures
UPCOMING ACTIVITIESUPCOMING ACTIVITIES
• Update to SACTI Cooling Tower Model
COL APPLICATION FEEDBACKCOL APPLICATION FEEDBACK
Thus far, the Commission has received NINE COL Applications.
The following is a summary of issues / topics that have been commonly associated with requests for additional information (RAIs) for SRP Sections 2.3.1 through 2.3.5.
2.3.1: Regional Meteorology
2.3.2: Local Meteorology
2.3.3: Onsite Meteorological Measurement Programs
2.3.4: Short-Term Dispersion Estimates for Accident Releases
2.3.5: Long-Term Dispersion Estimates for Routine Releases
COL APPLICATION FEEDBACKCOL APPLICATION FEEDBACK
SRP Section 2.3.1, Regional Meteorology
• Representativeness of Offsite Data Sources
• Identifying NCDC Climate Division
• ASCE 3-Second Gust Wind Importance Factors
• Normal and Extreme Snow Loads
• NCDC Local Storm Events Data
COL APPLICATION FEEDBACKCOL APPLICATION FEEDBACK
SRP Section 2.3.1, Regional Meteorology (Cont.)
• Correct and Adequate References
• NOAA CSC’s Hurricane Database
• Design Basis Temperatures (Adequate Return Period)
• Site Characteristics and Site Parameter Comparison Table
• Additional Information Beyond the SRP
COL APPLICATION FEEDBACKCOL APPLICATION FEEDBACK
SRP Section 2.3.1, Regional Meteorology (Cont.)
• Ultimate Heat Sink Site Characteristics
• Addressing Climate Change
• 100-Year Return Period vs. Most Severe Occurrence
COL APPLICATION FEEDBACKCOL APPLICATION FEEDBACK
SRP Section 2.3.2, Local Meteorology
• SACTI Inputs
• Additional Information Beyond the SRP
• Consequences of EPA Non-Attainment Air Quality Standards
COL APPLICATION FEEDBACKCOL APPLICATION FEEDBACK
SRP Section 2.3.3, Onsite Meteorological Measurement Programs
• Distinct COLA Sections for Preoperational and Operational Programs
• Demonstration of RG 1.23 Compliance
• Trees Surrounding the Meteorological Tower
• Submitting Hourly Meteorological Data in RG 1.23 Format
• Comparison of Hourly Data with Old Site Data and Surrounding Data
• Impacts of Nearby Structures on Measurement Accuracy and Adequacy
COL APPLICATION FEEDBACKCOL APPLICATION FEEDBACK
SRP Section 2.3.4, Short-Term Dispersion Modeling for Accident Releases
• Dispersion Model Inputs
• Adequacy of Dispersion Models
• Terrain and Water Influences
• Control Room Dispersion Modeling Input Description
• Site Map with Control Room Intakes and Release Points
• Comparison with DCD Site Parameters
COL APPLICATION FEEDBACKCOL APPLICATION FEEDBACK
SRP Section 2.3.5, Long-Term Dispersion Modeling for Routine Releases
• Dispersion Model Inputs
• Adequacy of Dispersion Models
• Terrain and Water Influences
• Comparison with DCD Site Parameters
THANK YOUTHANK YOU
QUESTIONS?