Denton Plant
Curtis KaiserManufacturing
Engineering
Denton Plant
Curtis KaiserManufacturing Engineering
• Senior at Texas A&M– Mechanical & Manufacturing
Engineering Technology– Graduation in December 2015
• Skills: – Machine shop tools, automotive
terminology and operations, social interaction, mechanical aptitude
• Career Interests– Research & development, rapid
prototyping, systems integration
Denton Plant
Side Projects• Internal ISO tool audit performed every
Thursday• Data collection for security upgrade capital
budget project• B48T bin dividers for rear window trim
Before After
Denton Plant
Time StudiesPlant Areas Filmed & Analyzed
• 579 Cab Assembly (00:33:32, 60 Tasks)• Chassis Oven (1:08:56, 49 Tasks)• Exhaust Pre-Assembly (1:48:32, 39 Tasks) • Fuel Line Prep (1:10:46, 31 Tasks)• Wiring (5:57:52, 148 Tasks)• Radiator Set (2:25:56, 116 Tasks)
Total = 13:05:34 & 443 Tasks
Denton Plant
Timer Pro
Denton Plant
Time Study Spreadsheet
Denton Plant
Curtis KaiserManufacturing Engineering
• Knowledge & Skills Gained:– Truck model differentiation– Takt time, lead time, build rate significance and
the relationship with truck sales– Assembly line A1 & A2 processes – Peterbilt’s role in the PACCAR scope– Copics and OPS truck lookup databases– Excel competency