+ All Categories
Home > Documents > Customer Charge On behalf of all DNs 25 October 2010.

Customer Charge On behalf of all DNs 25 October 2010.

Date post: 29-Jan-2016
Category:
Upload: bethany-lamb
View: 214 times
Download: 0 times
Share this document with a friend
20
Customer Charge On behalf of all DNs 25 October 2010
Transcript
Page 1: Customer Charge On behalf of all DNs 25 October 2010.

Customer ChargeOn behalf of all DNs25 October 2010

Page 2: Customer Charge On behalf of all DNs 25 October 2010.

History of the Customer Charge

______________________________________________________________________________________________________________________________

• Originally determined by Transco

• Subsequent adjustments for:• Removal of Meter reading costs, 1997 (PC17)• Removal of Metering costs, 2000 (PC58)• SSP conversion to capacity charge, 2007

(DNPC01)

• All current DN charges are based on these original National basis charging structures

Page 3: Customer Charge On behalf of all DNs 25 October 2010.

The current Customer Charge_____________________________________________________________________________________________________________________________

_

• Customer Charges generate around 30% of Collected Revenue; over 90% is collected from SSPs (circa £30/ SSP annually).

• Supply Points with an AQ above 732 MWh have a capacity based power function.

• Supply Points with an AQ between 732 MWh and 73.2MWh have a fixed unit capacity charge and an additional per supply point element.

• Supply Points with an AQ less than 73.2MWh have a fixed unit capacity charge.

Page 4: Customer Charge On behalf of all DNs 25 October 2010.

Recent activity_____________________________________________________________________________________________________________________________

_

• Final area of methodology in the 2006 Ofgem report to be reviewed

• Relevant costs were identified in DNPC05

• DNs have prepared to consult on this area prior to change of governance

• DNPC08 responses suggest that some shippers may not be happy to see further changes close to the point of governance change

Page 5: Customer Charge On behalf of all DNs 25 October 2010.

Proposed way forward_____________________________________________________________________________________________________________________________

_

• Move forward with the review of the customer charge under the new governance regime

• Start the review process now, in order to not “lose” 3 months, and provide as much time as possible between decision and implementation.

• Requires buy-in from shipper community to engage in the process in advance of January.

Page 6: Customer Charge On behalf of all DNs 25 October 2010.

Potential Timeline_____________________________________________________________________________________________________________________________

_

Date Action Governance

October 2010 Presentation of issue and some potential solutions to DCMF Existing DCMF

November 2010 Receive feedback and further ideas, to enable development of UNC Modifications

Existing DCMF

December 2010 DNs develop Modifications and circulate in draft for comment/discussion at DCMF

Existing DCMF

2 January 2011 DNs and/or shippers issue Modifications to JO for inclusion at next Modification Panel, recommending issue for consultation

UNC

20 January 2011 Modification Panel decides pathway:WorkgroupConsultation (15 WD) (if consultation…)

UNC

11 February 2011 Final date for representations UNC

17 February 2011 FMR not ready for 5 days in advance due to close out date UNC

17 March 2011 Modification Panel votes on recommendation UNC

?? Ofgem decision (KPI 25 days) UNC

ASAP after decision JO update UNC with legal text if it includes transitional arrangements UNC

1 April 2012 Implementation Date UNC

Page 7: Customer Charge On behalf of all DNs 25 October 2010.

Relevant objectives_____________________________________________________________________________________________________________________________

_

• (a) that compliance with the charging methodology results in charges which reflect the costs incurred by the licensee in its transportation business;

•(b) that, so far as is consistent with (a), the charging methodology properly takes account of developments in the transportation business;

•(c) that, so far as is consistent with (a) and (b), compliance with the charging methodology facilitates effective competition between gas shippers and between gas suppliers.

Page 8: Customer Charge On behalf of all DNs 25 October 2010.

Costs underlying the Customer Charge

______________________________________________________________________________________________________________________________

• Emergency costs

• Service Pipe replacement costs

• Service pipe operational costs e.g. leakage

• Service Pipe depreciation

• A share of indirect costs

Page 9: Customer Charge On behalf of all DNs 25 October 2010.

Emergency Costs_____________________________________________________________________________________________________________________________

_

• Emergency costs are driven by the existence of service pipes in the ground.

•No evidence of correlation between the volume of gas flowing through a service pipe or its capacity, and the likelihood that that pipe may have an emergency situation or the level of emergency cost incurred.

•Therefore it seems reasonable to allocate emergency costs by supply point or meter point.

Page 10: Customer Charge On behalf of all DNs 25 October 2010.

Service pipe Repex_____________________________________________________________________________________________________________________________

_

• Service pipe Repex costs are reported on the basis of whether they are Domestic or Non Domestic pipes.

Page 11: Customer Charge On behalf of all DNs 25 October 2010.

Service pipe Operational Costs

• Leakage• Less than 2% of customer costs• Overall leakage is considered to be primarily a cost

related to size of network rather than throughput or capacity

• No evidence of relationship with supply point size

Page 12: Customer Charge On behalf of all DNs 25 October 2010.

Service pipe depreciation 1_____________________________________________________________________________________________________________________________

_

• Most services costs in the DN asset base are those built as part of the domestic “10 metre allowance” policy.

•These depreciation costs could be apportioned to domestic supply points only or to all supply points.

•The remaining depreciation costs are made up from replaced service pipes.

Page 13: Customer Charge On behalf of all DNs 25 October 2010.

Service pipe depreciation 2_____________________________________________________________________________________________________________________________

_

10 metre allowance 10 metre allowance domestic service domestic service

pipespipes

replaced pipesreplaced pipes

Could be allocated across DOMESTIC Could be allocated across DOMESTIC supply pointssupply points

Could be allocated across ALL supply Could be allocated across ALL supply pointspoints

Could be allocated across DOM and Could be allocated across DOM and NON DOM supply points, in proportion NON DOM supply points, in proportion

to their relative asset valueto their relative asset value

Page 14: Customer Charge On behalf of all DNs 25 October 2010.

Indirect Costs_____________________________________________________________________________________________________________________________

_

• In line with other existing areas of methodology it is suggested that these costs be allocated in proportion to all the direct costs

Page 15: Customer Charge On behalf of all DNs 25 October 2010.

Costs Overview_____________________________________________________________________________________________________________________________

_

Customer Charge related costs for Northern Gas Networks

Cost Category %

Emergency 7.5%

Service Repex Expensed 15.4%

Regulated Service Depreciation 17.5%

Operational Costs 2.8%

Work Management 6.8%

Other Indirect Costs 5.8%

Shrinkage Service Leakage 1.7%

Network Rates 11.1%

License, NTS pension etc 2.8%

Scaling to Adjusted Allowed Revenue 28.6%

Total 100.0%

Page 16: Customer Charge On behalf of all DNs 25 October 2010.

Potential issues with cost Allocation

______________________________________________________________________________________________________________________________

• Service pipe costs are reported as Domestic/Non Domestic (ie Market Sector Flag), not by load size or any other basis that could be a proxy for load size.

•It is not possible at present to invoice by Market Sector flag

• The split of depreciation between original connections and replacements is not known

Page 17: Customer Charge On behalf of all DNs 25 October 2010.

Market Sector Flags_____________________________________________________________________________________________________________________________

_

Market sector flags have been a compulsory field within UK Link for around 4 years now, and over 70% of supply points have a flag.

The table shows how they correspond to SSP and LSP load categories.

Market Sector Flag

AQ Range I&C Domestic Blank% of I&C sites % of Dom sites in loadband in loadband

0 - 73.2 (SSP) 370,579 14,683,913 6,213,618 59.7% 99.8%

73.2 - 732.7 (LSP) 219,930 36,368 16,745 35.4% 0.2%

732.7 + (LSP) 30,573 321 609 4.9% 0.00%

Page 18: Customer Charge On behalf of all DNs 25 October 2010.

10m allowance v replacement pipes

______________________________________________________________________________________________________________________________

• Difficult to determine proportion of new connection vs replacement assets.

• further investigation ongoing

• At network sale, no distinction was made between different types of service pipe assets, and so again some kind of proxy may need to be identified.

Page 19: Customer Charge On behalf of all DNs 25 October 2010.

DN ideas to date_____________________________________________________________________________________________________________________________

_

• A single charge per supply point for each network

• SSP and LSP charges per supply point for each network

• A derived capacity charge

• Shipper views sought

Page 20: Customer Charge On behalf of all DNs 25 October 2010.

Next steps_____________________________________________________________________________________________________________________________

_

• Arrange November DCMF workshop for this subject

• Collect feedback today for an initial view on what DNs should look into further for discussion in November

• Shippers invited to also individually discuss any ideas with DNs for further areas to investigate ready for November


Recommended