1/69
DAG Traffic Primer
May 24, 2012
CASEY ARBORWAY PROJECT
7/31/2019 DAG Traffic Primer Meeting
2/69
1. Previous Traffic Analysis Summary
2. Updates Post Planning Phase
3. Signal Coordination
4. Parking Supply
5. Transit Service and Accommodations
6. DAG #3: Mobility, Monday, June 18, 2012
Todays Agenda
7/31/2019 DAG Traffic Primer Meeting
3/69
Key Assumptions in Traffic AnalysisTraffic Calming
Level of Service (LOS) & Queue Results
Right Turn TreatmentsTraffic Operations
Pedestrian Crossings
Transit Accommodations
Emergency Response Times
Alternative Routes
7/31/2019 DAG Traffic Primer Meeting
4/69
7/31/2019 DAG Traffic Primer Meeting
5/69
How to calm traffic with wide median DAG #3
Rights on Red Allowed Design allows but
requires further
discussion on DAG #3
Level of Service (LOS) Presentation today
LOS with 2-lanes in each direction DAG #3
Location of Pedestrian and bike paths DAG #3
Path Analysis for all modes Experience
of Corridor
Presentation today
7/31/2019 DAG Traffic Primer Meeting
6/69
North/south and east/west traffic flows Clarify
Alternative Regional Routes - Walk Hill? Clarify Design or
Construction Phase?
Parking loss of off-street impacts on
design
Presentation today
Emergency Response during Construction DAG #4
24 hour review of traffic volumes (peak and
non-peak)
Presentation today
7/31/2019 DAG Traffic Primer Meeting
7/69
Previous Traffic Analysis
Summary
A Look Back
7/31/2019 DAG Traffic Primer Meeting
8/69
7/31/2019 DAG Traffic Primer Meeting
9/69
Key Assumptions inTraffic Analysis
7/31/2019 DAG Traffic Primer Meeting
10/69
Top 5 Areas of Concern Today
7/31/2019 DAG Traffic Primer Meeting
11/69
7/31/2019 DAG Traffic Primer Meeting
12/69
7/31/2019 DAG Traffic Primer Meeting
13/69
:
Casey Overpass (Regional): + 5%
Surface Roads (Regional & Local): + 12%
+ 13%
+ 10%
7/31/2019 DAG Traffic Primer Meeting
14/69
Overall volumes
Travel times
Air Quality
7/31/2019 DAG Traffic Primer Meeting
15/69
Traffic Calming
7/31/2019 DAG Traffic Primer Meeting
16/69
7/31/2019 DAG Traffic Primer Meeting
17/69
Level of Service &Queue Analysis Results
7/31/2019 DAG Traffic Primer Meeting
18/69
7/31/2019 DAG Traffic Primer Meeting
19/69
7/31/2019 DAG Traffic Primer Meeting
20/69
7/31/2019 DAG Traffic Primer Meeting
21/69
Regional AnalysisCentral Transportation Planning
Staff Analysis
7/31/2019 DAG Traffic Primer Meeting
22/69
CTPS Regional Traffic Model
Model runs for At-Grade and Bridge
Alternatives
Initial results show no significant changes to:
Traffic Volumes
Vehicle Miles Traveled (VMT)
Vehicle Hours Traveled (VHT)
Air Quality/Emissions
7/31/2019 DAG Traffic Primer Meeting
23/69
7/31/2019 DAG Traffic Primer Meeting
24/69
Traffic Operations Improved for both
alternatives over existing conditions (see
Technical Memoranda)
Acceptable traffic operations provided forboth alternatives
Queues managed within available
storage area
Operations comparable for at-grade and
bridge alternatives
7/31/2019 DAG Traffic Primer Meeting
25/69
Travel Time Comparison
Travel times for existing based oncurrent volumes and presented forcomparison only
Travel times for alternatives basedon 2035 volumes and analysis
Travel times are for peak hours
7/31/2019 DAG Traffic Primer Meeting
26/69
Peak Hour Travel Time Results
Both alternatives improve overall travel times within
the project limits
Overall travel times for the alternatives are
comparable
At-grade improves travel time for many moves,
particularly north-south
At-grade increases travel time for affected left-turns
and east-west regional traffic (30-90 seconds)
Regional delays offset local travel time increases
7/31/2019 DAG Traffic Primer Meeting
27/69
Future Operations with Modified
Lane Configurations
1. Pros and Cons of different lane
configurations
2. Queues and signalization
3. Right sizing roadway 2016 versus 2035
7/31/2019 DAG Traffic Primer Meeting
28/69
Right-Turn Treatments
7/31/2019 DAG Traffic Primer Meeting
29/69
Traffic Operations
7/31/2019 DAG Traffic Primer Meeting
30/69
Future Traffic Conditions: Summary
7/31/2019 DAG Traffic Primer Meeting
31/69
East West
Regional Travel
Regional travel times relatively unchanged for
overall trip Any in-bound delays at grade on New Washington
are offset by existing delays at Murray Circle
In fact, the new design of New Washington maymeter the travel times, providing more
systematic processing of traffic
7/31/2019 DAG Traffic Primer Meeting
32/69
Bar chart of traffic by time of day
Discussion
7/31/2019 DAG Traffic Primer Meeting
33/69
Pedestrian Crossings
7/31/2019 DAG Traffic Primer Meeting
34/69
Pedestrian Crossings
7/31/2019 DAG Traffic Primer Meeting
35/69
Transit Accommodations
7/31/2019 DAG Traffic Primer Meeting
36/69
Transit Signalization
7/31/2019 DAG Traffic Primer Meeting
37/69
School Bus Coordination
7/31/2019 DAG Traffic Primer Meeting
38/69
Compiling data on busvolumes by peak hour,
including deadhead buses
Coordination on bus priorities
7/31/2019 DAG Traffic Primer Meeting
39/69
Emergency ResponseTime
7/31/2019 DAG Traffic Primer Meeting
40/69
7/31/2019 DAG Traffic Primer Meeting
41/69
Alternative Routes
7/31/2019 DAG Traffic Primer Meeting
42/69
7/31/2019 DAG Traffic Primer Meeting
43/69
Local Diversions (cut-through)
7/31/2019 DAG Traffic Primer Meeting
44/69
7/31/2019 DAG Traffic Primer Meeting
45/69
Casey Project Web Site Documentshttp://www.massdot.state.ma.us/caseyoverpass/
7/31/2019 DAG Traffic Primer Meeting
46/69
Traffic
Documents
7/31/2019 DAG Traffic Primer Meeting
47/69
Meetings
Notices
Presentations Graphics
Minutes
7/31/2019 DAG Traffic Primer Meeting
48/69
7/31/2019 DAG Traffic Primer Meeting
49/69
Updates Post Planning Phase
7/31/2019 DAG Traffic Primer Meeting
50/69
Conducted by CDM Smith
Dec. 11Jan 12
7/31/2019 DAG Traffic Primer Meeting
51/69
Summary:
, the traffic analysis provided for the Casey overpass
Project has been performed in a professional manner
consistent with standard traffic engineering practices and
the guidelines of the MassDOT 2006 Project Development
and Design Guidebook.
traffic operations will be more efficient in the future year
with either alternative than the existing conditions or no
build conditions.
7/31/2019 DAG Traffic Primer Meeting
52/69
Report on Evaluation of Two DesignOptions for Casey Overpass
7/31/2019 DAG Traffic Primer Meeting
53/69
Traffic count data for Cemetery Road
Bus left-turn volumes
Minor graphic clarifications
Adjusted volumes at Orchardhill Road
7/31/2019 DAG Traffic Primer Meeting
54/69
Ongoing/Future Traffic
Analysis Summary
A Look Ahead
7/31/2019 DAG Traffic Primer Meeting
55/69
Signal Coordination
7/31/2019 DAG Traffic Primer Meeting
56/69
:
Casey Arborway (E-W)
Washington Street (N-S)
Hyde Park Avenue (N-S)
7/31/2019 DAG Traffic Primer Meeting
57/69
Parking Supply
On and Off-Street
7/31/2019 DAG Traffic Primer Meeting
58/69
Existing Parking Supply
7/31/2019 DAG Traffic Primer Meeting
59/69
Proposed Parking Supply
7/31/2019 DAG Traffic Primer Meeting
60/69
Parking changes
were reflected in
the future traffic
volumes
(i.e. -LAZparking lot)
7/31/2019 DAG Traffic Primer Meeting
61/69
Next Steps:
DAG #3: Mobility Topics
7/31/2019 DAG Traffic Primer Meeting
62/69
:
Off-Peak Design Options
Build Year LOS, queues, delays
Turn Treatments
Signal Details
Bus Operations
Cut-Thru Traffic
7/31/2019 DAG Traffic Primer Meeting
63/69
7/31/2019 DAG Traffic Primer Meeting
64/69
End of Presentation
Extra Slides
7/31/2019 DAG Traffic Primer Meeting
65/69
Conceptual AlternativesTRAFFIC
7/31/2019 DAG Traffic Primer Meeting
66/69
Traffic Simulations
Bridge Alternative
At-Grade Alternative
7/31/2019 DAG Traffic Primer Meeting
67/69
How can traffic operations be similar?
North-south traffic volumes unchanged betweenalternatives
At-grade offers additional improvements to critical north-
south link on South Street Removal of Bridge only adds east-west through traffic to
surface streets (additional thru lanes provided at-grade)
All turning movements happen at grade regardless
7/31/2019 DAG Traffic Primer Meeting
68/69
At-Grade Conceptual Alternative
DESIGNER GENERALS WARNING: THE DESIGN SHOWNHERE IS PRELIMINARY AND CONCEPTUAL, DESPITE THE
HARD LINE FINISHED STYLE RESULTING FROM THESOFTWARE PROGRAMS USED
7/31/2019 DAG Traffic Primer Meeting
69/69
Bridge Conceptual Alternative
DESIGNER GENERALS WARNING: THE DESIGN SHOWN