PETRONET LNG LIMITED
CORPORATE PRESENTATION
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 2/22
PLLPLL – – DAHEJ TERMINALDAHEJ TERMINAL
SHAREHOLDERS
ONGC, BPCL, GAIL & IOCL – (Public Sector Undertakings)
GDFI (Strategic Partner), Asian Development Bank , Institutions & Public
DAHEJ TERMINAL
oca e n one o e us es n us r a u s n es ern n a.
10.0 MMTPA capacity
7.5 MMTPA sourced through Long Term Contract with RasGas
Additional LNG being sourced through Spot /Short Term Contracts
Entered into marketing alliance with GAIL, IOCL & BPCL under a passthrough contract
Connected to major trunk pipelines HBJ, DUPL and GSPL network
Currently supplying around 21% of total gas consumption
DAHEJTERMINAL
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 3/22
SECOND LNG BERTH AT DAHEJSECOND LNG BERTH AT DAHEJ
Developing second LNG Jetty at Dahej Terminal.
. .
Existing marine facilities adequate for 11.0 MMTPA
of LNG.
New Jetty helps mitigating risk.
Facilitating berthing of tankers up-to 260,000 CBM
Q-Max .
Commissioning – III Quarter, 2013.
– .
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 4/22
LNG STORAGE TANKSLNG STORAGE TANKS
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 5/22
DAHEJ EXPANSION FACILITIESDAHEJ EXPANSION FACILITIES
HP PUMPSHP PUMPS SHELL & TUBE VAPORIZERSSHELL & TUBE VAPORIZERS
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 6/22
DAHEJ EXPANSION FACILITIESDAHEJ EXPANSION FACILITIES
AIR HEATER GTG
GLYCOL WATER SYSTEM
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 7/22
PETRONET’S III LNG VESSELPETRONET’S III LNG VESSEL --ASEEM ASEEM
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 8/22
INDIA’S GAS INFRASTRUCTUREINDIA’S GAS INFRASTRUCTURE
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 9/22
INTEGRATED POWER PLANT AT DAHEJINTEGRATED POWER PLANT AT DAHEJ
Completed Detail Feasibility Report for a 1200 MW Power Plant.
In process - Land Acquisition & Environment Clearance.
LNG terminal facilitates harnessing Cold Energy.
Configuration of:
3 x 356 MW total 1068 MW Sin le shaft CCGT Investment of US 700 Million
10% increase in power generation capacity, arising out of harnessing cold energy.
Aggregate Project cost of about Rs 3,000 crore (Rs 2.80 crore / MW).
Primary fuel for Project to be sourced from international markets.
Aggregate gas requirement of 1.0–1.1 MMTPA.
–to Power Plant.
Implementation time-frame of 12-15 months for pre-development activities & further 27-33 monthsfor commencement of commercial operations.
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 10/22
LNG TRUCK LOADING FACILITIESLNG TRUCK LOADING FACILITIES –– DAHEJDAHEJ
Truck Loading facility at Dahej terminal wascommissioned in August 09, 2007 as a Pilot
.
Currently about 3-4 trucks are loaded on dailybasis & total of around 1700 trucks have beenoa e a e.
Facility can handle 2500 loadings per year.
At present LNG (by road tanker) is being sold tothree consumers – two in Gujarat and one inMaharashtra.
Several new customers (up to 800 KMS) arelined up for off-take of LNG for industrial andcity gas use.
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 11/22
TRUCK LOADING FACILITIESTRUCK LOADING FACILITIES –– DAHEJDAHEJ
WEIGH BRIDGE VAPORISATION FACILITIES
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 12/22
SOLID CARGO PORT PROJECTSOLID CARGO PORT PROJECT-- DAHEJDAHEJ
Petronet formed a 26% Joint Venture Company with the Adani Group to execute a Solid Cargo.
Port is being constructed North of the existing LNG jetty in Dahej
Being executed in two phases
Handling 18.0 MMTPA of cargo/year
Cost Rs.1200 crore (US$240 Million)
Scheduled to be completed by August, 2010 (Phase-I) & December, 2010 (Phase-II)
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 13/22
SOLID CARGO PORT PROJECTSOLID CARGO PORT PROJECT-- DAHEJDAHEJ
PILE DRIVING IN MAIN BERTH 1 APPROACH BUND
13
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 14/22
KOCHI LNG TERMINALKOCHI LNG TERMINAL
LNG Terminal is a part of newly created Special Economic Zone and PLL is one of the Co-developers.
Capacity - 2.5 MMTPA, expandable to 5.0 MMTPA
Whessoe - Project Management Consultant.
Site Grading and Reclamation Work – Completed.
Work for building two LNG Storage Tanks awarded to IHI, Japan.
, .
Work related to Marine Facilities awarded to Afcons Infrastructure Limited.
Work related to Administration Buildin Warehouse Worksho & Occu ational Health Centre
awarded to MARG Limited.
Scheduled Mechanical Completion– December, 2011SITE FOR KOCHI LNG TERMINAL
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 15/22
KOCHI LNG TERMINALKOCHI LNG TERMINALFACILITIES
Jetty & other Marine Facilities for handling ship
IMPLEMENTATION SCHEDULE
sizes (65000 m3 to 216000 m3)
Unloading and vapor return arms Two Full Containment Storage Tanks (155000 M3
net Capacity)n- an umps, o o ompressors
Re-condenser, Booster Pumps 2 High Pressure Shell & Tube Vaporizers.
1 High Pressure Shell & Tube Vaporizer for Heat.
1 Submerged Combustion Vaporizer. Metering Units, Gas Turbine Generators Air Heaters, Utilities Cold Heat Recover Condensate Water Stora e
Additional investment on Vaporizer Plant/Utilities for handling 5 MTPA will be US$100million(approx.) SITE FOR KOCHI LNG TERMINAL
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 16/22
KOCHI PROJECTKOCHI PROJECT
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 17/22
TANK 101 & 102TANK 101 & 102
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 18/22
MARINE FACILITIESMARINE FACILITIES
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 19/22
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 20/22
PLLPLL-- FINANCING STRUCTUREFINANCING STRUCTURE
Particulars Dahej Dahej Expansion Kochi Total
Equity CapitalInternal accruals/Premium
170-
-85*
-210*
170295
Shareholders Fund 170 85 210 465
Debt 280 235 490 1005
Total Means of Finance 450 320 700 1470
*PLL generates approx. US$ 100 Million cash from its existing operations. After servicingshareholders, the balance will be used to finance Expansion Projects.
8/12/2019 DAHEJ TERMINAL LNG
http://slidepdf.com/reader/full/dahej-terminal-lng 21/22
CAPITAL EXPENDITURE/INVESTMENTCAPITAL EXPENDITURE/INVESTMENT
--Particulars Rs. (Crore) US$ (Million)
CAPEX
2nd Jetty at Dahej (2013) Power Plant at Dahej (March, 2013) Kochi LNG Terminal First uarter 2012
10003200
220700
3600 800
INVESTMENT
o argo or – w an ecem er,
Grand Total 7900 1742
The Company has also undertaken expansion of an Institution to accommodate 500additional differently abled /challenged children (difficult to put a value to this initiative).