33
Eli Lilly and Company
Lilly Corporate CenterIndianapolis. Indiana 46265
(317)276-2000
October 28, 1987
REGISTERED MAILRETURN RECEIPT REQUESTED
U.S. Environmental Protection Agency230 S. Dearborn StreetChicago, Illinois 60604
Attention: Mr. Tim Conway
Dear Mr. Conway:
Re: Pristine, Inc., Superfund Site, Reading, Ohio
Attached for your information is a report by Dames and Moore on theirobservation of EPA's contractor's operations in the Pristine Phase IIRemedial Investigation Field Program. The report identifies wherefield data collection procedures were inconsistent with the supplemen-tal Quality Assurance Project Plan (QAPP) dated April, 1987. ThePristine Group feels that these inconsistencies will have an impact ondata interpretation, particularly where the data are compromised bycontaminated drilling tools and insufficient field wash blank samples.
Please include this report in the Administrative Record for this site.
Yours truly,
Donald L. Sullivan, ChairmanThe Pristine Group
DLS:pw
cc: Mr. Joseph Duff icy, EPA (w/enclosure)Ms. Mary Tyson, EPA (w/enclosure)Ms. Lynn Peterson, EPA (w/enclosure)Ms. Gloria McKinley, General ElectricMr. Fred Erdmann, Dames & MooreMr. David Ross, Procter & Gamble EPA Region S Recorfs Ctr.Ms. Jane Hessler, Eli Lilly -------
223903
REPORT ON OBSERVATION OFPRISTINE PHASE II REMEDIALINVESTIGATION FIELD PROGRAM
OCTOBER 26, 1987JOB NO. 15784-003-17
Dames & Moore
REPORT ON OBSERVATION OFPRISTINE PHASE II REMEDIALINVESTIGATION FIELD PROGRAM
OCTOBER 26, 1987JOB NO. 15784-003-17
DAMES & MOORE I k>" I *-'i"^-\l i : \ n l l ! 1 I ' - \R isi I.VIT
L I N N STRI-.LT. Mm VI . I ' lS l ' lNNATI. O I I K ' 4=>.\M nMi M = . | . »44.'
October 26, 1987
Pristine Groupc/o Eli Lilly &. Company307 East McCarty StreetIndianapolis, IN 46285
Attention: Mr. Donald L. Sullivan, Chairman
Gentlemen:
Re: Final Report on Observation of PristinePhase n Remedial InvestigationField Program
This letter accompanies one copy of Dames & Moore's report on observation of theEPA's Pristine Phase n Remedial Investigation field program. We enjoyed conducting thisinvestigation. If there are any questions regarding the report and its findings, please do nothesitate to contact us.
Very truly yours,
DAMES & MOORE
Dennis P. ConnairGeologist
Jennifer D. JohnsonProject Geologist
W. Erdmann, P.E., C.P.G.Associate
JDJ/FWE:P/R4(m)
1.0 INTRODUCTION
Following completion of Phase I of the Remedial Investigation (RI) at the Pristine,
Inc. site, the U.S. Environmental Protection Agency (EPA) developed a plan for a Phase n
RI study, designed to provide additional information in support of a feasibility study (FS)
for the Pristine site. The scope of work for the Phase n RI study was presented as part of
the supplemental Quality Assurance Project Plan (QAPP), dated April 1987 that was
prepared by Camp Dresser and McKee Inc.
Dames & Moore has been involved with the Pristine, Inc. site as a technical
consultant to the Pristine Group, and recently completed a detailed critique of the Phase I
RI report. The Pristine Group approached Dames & Moore to monitor the field activities of
the EPA REM n contractor, Roy F Weston, Inc., (Weston) during the Phase n RI Field
Investigations.
The Phase U RI field program was conducted from July 13, 1987 to August 2,
1987. Dames & Moore was notified of the field team's arrival by Dr. Riley Kinman on
July 15,1987 and was on site on July 16,1987 to monitor Weston's activities.
The types of information collected by Dames & Moore included the following:
• Dates and times of activities observed
• Deviations from the work plan and procedures specified in the QAPP
• General notes on observed procedures
• Description of subsurface conditions, general air monitoring results, siteconditions
Information and details of the items we consider to be significant arc presented in
this report. The first section describes the work plan, the stated scope of work and the
supplements that were made to it during the course of the field program. The next section
details the observations made during the performance of the Phase II activities (soil
sampling, ground water sampling, borehole drilling, well installation, and soil gas
monitoring), and quality control procedures observed by the contractor. There is a brief
P/R(4)(m) .j. Privileged and ConfidentialPrepared for Counsel
section on geologic conditions and lastly, the report gives a brief description of how the
Phase n RI data may impact the FS.
2.0 FIELD PROGRAM
Work activities scheduled for the field program, according to the supplemental
QAPP included the following:
• Ground water sampling of 18 existing wells (GW45-GW62) for volatileorganic compound analysis.
• Installation of two additional monitoring wells (GW66 and GW64) in the upperoutwash lens and two monitoring wells (GW63 and GW65) in the loweroutwash lens.
• Ground water sampling of the four new wells for CLP (Contract LaboratoryProgram) organics, inorganics and SAS (Special Analytical Services) flourideanalysis.
• Hydraulic conductivity testing of the four new wells by either bail down or slugtests.
• Five surface soil samples collected near the "magic pit" for CLP organic andinorganic compound analysis.
• Ten subsurface soil samples from two soil borings near the "magic pit"analyzed for CLP organic and inorganic compounds.
• Six subsurface soil samples collected during the installation of GW63 andGW65 for CLP organic and inorganic compound analysis.
• Eleven composited surface soil samples for dioxin/furans analysis.
• Two sediment samples for dioxin/furans analysis.
• Two incinerator residue samples for dioxin/furans analysis.
Activities supplemental to the work plan that were performed during the field
program include the following:
• Drilling, sampling, and installation of an additional monitoring well (GW67)screened in the lower aquifer.
• Drilling and sampling of an additional borehole (SB44) near the northeastcorner of the site.
P/R(4)(m) -2- Privileged and ConfidentialPrepared for Counsel
I
1
• Soil gas monitoring in the vicinity of the "magic pit".
• Hydraulic conductivity tests in the 18 existing wells.
The surface soil samples, sediment samples, and incinerator residue samples
intended for dioxin analysis were sampled well in advance (early June 1987) of the
remaining field activities. Dames & Moore did not monitor the June sampling activities.
3.0 FIELD OBSERVATIONS
Proper and consistent performance of field activities and maintenance of quality
control measures were often found lacking during the Phase II field program.
Observations to this effect are detailed here and grouped according to the type of field
activity.
3.1 SURFACE SOIL SAMPLING
Five surface soil samples were collected for source characterization in the vicinity of
the "magic pit" as shown schematically on Figure 1. Each sample was obtained in
accordance with REM JJ site investigation procedure manual from within two inches of the
surface in an area of approximately two-feet-square. One sample location was directly
beneath the ventilation exhaust fan from the interior of a Cincinnati Drum Service building.
This sample is likely to reflect a combination of source characteristics rather than solely the
characteristics of the "magic pit".
3.2 SUBSURFACE SOIL SAMPLING
Subsurface soil was sampled during the drilling of SB42 through SB44 and GW63
through GW67 (see Figure 1) for the purpose of lithologic description of the soils. The
original QAPP specified that subsurface sampling should be continuous to a depth of 15
feet, proceed at 2.5-foot intervals to a depth of 35 feet, and subsequently proceed at 5-foot
intervals to the planned final depth of the boring. The supplemental QAPP does not specify
a separate sampling scheme for the Phase II borings, but each of the originally scheduled
borings (SB42 and SB43 and GW63 through GW66) were sampled using a scheme of
sampling at 2.5-foot intervals to a depth of 35 feet, followed by 5-foot intervals to the final
P/R(4)(m) -3- Privileged and ConfidentialPrepared for Counsel
depth of the boring. This scheme was altered in the sampling of both SB44 and GW67.
No samples were obtained from SB44 and GW67 before depths of 28.5 and 38.5 feet,
respectively. Both were then sampled at 5-foot intervals to final depth. This amended
sampling procedure eliminated the opportunity of using the supplemental borings to further
define the character and extent of the upper outwash lens.
Samples for chemical analysis were taken from SB42, SB43, GW63, and GW65
as indicated in the supplemental QAPP.
3.3 BOREHOLE DRILLING
For use in onsite drilling of SB42, SB43, and GW63 the driller's augers and split
spoon samplers were decontaminated using a water rinse and steam cleaning. In offsite
drilling of GW64, GW65, and GW66 the augers were not decontaminated between uses
and in the sampling of GW64, GW65, GW66, GW65, and SB44 the split spoon samplers
were not decontaminated between uses, thus introducing the possibility of cross-
contamination.
According to the original QAPP, wastes generated by offsite drilling should have
been drummed for later disposal. During the Phase n RI field program, the drilling
wastes, both onsite and offsite, including hydraulic fluid discharged by the drilling rig
during the drilling of SB44 (onsite) were left in place without treatment.
3.4 GROUND WATER SAMPLING
The ground water sampling technique of some members of the field team involved
filling the sample bottles by pouring from the top of the well bailer, while for others it was
common practice to use a gloved hand to push back the bailer ball to start a flow of water
from the bottom of the bailer. The second technique could have led to contamination from
the glove and volatilization of the sample if the water flowed too forcefully from the bailer.
Conductivity, temperature, and pH readings were obtained at the time of sampling
for some of the ground water samples, including those from GW64, GW65, and GW67.
P/R(4)(m) -4- Privileged and ConfideniialPrepared for Counsel
However, for the majority of the remaining samples these readings were taken after the
sample was removed to another work site.
Sampling of GW63 was stopped on July 29,1987 and resumed after re-purging on
July 30,1987 allowing a time interval of 15 hours to pass between collection of portions of
the total sample.
Extra quantities of water (as much as 500 gallons) used in the installation of GW65
and GW67 should have warranted additional well development efforts to purge the
formation of the introduced water before sampling for chemical analysis. However, the
normal development procedures of bailing the well dry 24-hours before sampling was
followed for both wells.
A two-inch O.D. teflon bailer was used to sample all of the wells except for GW67
which was sampled with a polypropylene bailer. Dedicated, woven nylon cord was used
to lower and raise the bailers.
3.5 AIR MONITORING
Air quality onsite and offsite was monitored using an Organic Vapor Analyzer
(OVA) during activities such as soil sampling and borehole drilling. The purpose of air
monitoring was to maintain an assurance of safe working conditions and to screen samples
for gross contamination. Performance of air monitoring was in accordance with the
supplemental QAPP except on August 1,1987 when the OVA operator failed to notice the
improper functioning of the meter during the drilling of the first 10 feet of SB44.
3.6 HYDRAULIC CONDUCTIVITY TESTS
The Phase II RI workplan specified the use of the newly installed wells for aquifer
hydraulic conductivity tests. Baildown tests were conducted at three of the new wells,
GW63, GW64, and GW66. GW65 was too dry for use and the testing of GW67 was put
off until after the initial Phase II field work was completed.
P/R(4)(m) -5- Privileged and ConfidentialPrepared for Counsel
Supplemental to the Phase E workplan, conductivity tests were conducted at the 16
of 18 Phase I wells that contained measurable quantities of water. At least 5 of the 16 wells
were tested using a Hermit® probe slug test rather than a baildown test Slug tests using a
Hermit® probe involve the recording of pressure changes near the bottom of the well as a
solid slug of known volume is lowered into the water column or raised out of it. A
baildown test is considered a type of slug test, but in this case the volume removed from
the well is a quantity of water and the aquifer reaction is measured as the recovery of the
water level in the well rather than a return to equilibrated pressure within the well as
detected by an electronic pressure transducer. The potential for discrepancies between the
two types of tests should be given full consideration.
Baildown and Hermit® probe test procedures were appropriately performed at each
well with the exception of GW64. At GW64 the field personnel compromised the value of
a baildown test by introducing the Hermit® slug to the water column between the 60 and
120 minute baildown recovery readings, thus disturbing the natural recharge of the well
3.7 DECONTAMINATION
During the field activities prior to July 22, 1987 some members of the field team
were using an acetone rinse as part of decontamination procedures while others were not
In addition, the grade of acetone (reagent grade) was not up to standards required in
standard professional practice (pesticide grade), the acetone container was made of plastic,
which is known to dcsorb certain compounds when in contact with acetone, and there were
no field wash samples taken to verify the quality of the decontamination procedures. After
the Dames & Moore representative raised concerns on the subject on July 22,1987, the use
of acetone in decontamination procedures was stopped.
Procedural inconsistencies such as those observed in the decontamination
procedures for sampling equipment were, in part, caused by the lack of a complete QAPP
document for the second phase RI and the resultant need to consult rwo or more documents
to reference proper procedures. Another factor was a lack of communication between
members of the field team. This problem was compounded by a change of personnel rwo
days before the end of the field program.
P/R (4 )i m) .5. Privileged and ConfidentialPrepared for Counsel
4.0 GEOLOGIC CONDITIONS
The addition of GW67 and SB44 (Rgure 1) to the list of field activities was advised
by the Weston office after the drilling of GW65 to a depth of 77 feet failed to reveal the
lower boundary of the lower outwash lens and the glacial till unit that was expected to
underlie it Drilling of SB44 revealed the till at a depth of approximately 40 feet but no
trace of till was found in GW67. The effort to find the location of the glacial till was made
in order to determine the feasibility of placing a slurry wall along the eastern boundary of
the site to contain contaminants. The feasibility of a slurry wall depends on the ability to tie
into an underlying impermeable layer such as the till.
At GW67, materials that are believed to be part of the lower outwash lens of the
upper aquifer system are much thicker than similarly designated deposits to the west and
north. In addition, they are in direct contact with deposits that are believed to represent the
middle outwash lens above and, because of the absence of the till layer, the lower aquifer
(public water supply aquifer) below. A rapidly drawn conclusion about this condition is
that at the southeast comer of the site (in the vicinity of GW65 and GW67) water draining
through the middle and lower outwash lenses of the upper aquifer will reach the lower
aquifer many times faster than at other locations onsite.
5.0 CONCLUSIONS
The problems described in Section 3.0 above should be addressed in the final
analysis of data generated by the Phase IIRI. Procedural inconsistencies in sampling and
decontamination constitute the most serious problems with the Phase H field investigation.
Without back-up information such as field wash blank samples and complete
documentation of procedures, the value of analytical data generated from the samples is
compromised.
The impact of the geologic conditions revealed at GW65 and GW67 should involve
significant changes to the original modeling of the site geology and consequently
modifications to the calculations of contaminant movement and the assessment public health
risk. In addition, the construction of a slurry wall containment system around the Pristine
site no longer appears to be a feasible atemative.
P/R(4)(m) -7- Privileged and ConfidentialPrepared for Counsel
III APPENDIX A
SAMPLING ACTIVITIES
II
Sample Location
SS01 through SS05SB43GW63GW65GW67
Sample Medium
Surf ace soilSubsurface soilSubsurface soilSubsurface soilSubsurface soil
Time
17:0010:0015:008:308:30
Date
07/16/8707/22/8707/22/8707/29/8707/31/87
GW52GW48 and GW57GW61GW59GW60GW58GW54GW56GW62GW50,GW51andGW53GW66GW63
GW 65 and GW67
GroundGroundGroundGroundGroundGroundGroundGroundGround
waterwaterwaterwaterwaterwaterwaterwaterwater
Ground waterGround waterGround water
Ground water
16:309:3015:3016:3017:3011:2015:3013:3015:15
11:0016:0020:0011:0010:00
07/16/8707/17/8707/20/8707/20/8707/20/8707/21/8707/21/8707/21/8707/21/87
07/23/8707/29/8707/29/8707/30/8708/02/87
P/R(4)(m)
-z.-
\j A ̂ =
ffl % g-= -n E(g
3 fljw w
Si o
c. m
UJ
(O
ir;r-60i
~^~*-:
.̂ MP;r4:
•i j;
>miWfl . :
'{'>!'• tf 'I * ~ " '•'- .'W'// •'* " S :£ 2 </>'•»///'.// / • c;s «?a o«^//;/
^ «-:& OH
',rt̂
U)0),/wr
^rtfi-
(0CO
i ,-—-
' ^LJ >
/,' '-
Af Oo .'.̂. o
, - u
s§
Ni*? -V-