Place photo here © 2013 IBM Corporation Richard T. Travis Data Center Readiness for HANA 1
Transcript
Page 1: Data Center Readiness for HANA Part 2 DR and BC

Place photo here

© 2013 IBM Corporation

Richard T. Travis Data Center Readiness for HANA

1

Page 2: Data Center Readiness for HANA Part 2 DR and BC

Place photo here

© 2013 IBM Corporation

Oliver Rettig Richard Travis

Architecture Options for Business Continuity of SAP HANA systems

2

Page 3: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

Topics

•  The SAP HANA Project Process –  How we get into trouble from the outset.

•  SAP HANA Use Cases: –  Why they are important

•  Data Center Critical Considerations –  Backup and Recovery

–  High Availability –  Disaster Recovery –  Business Continuity

•  Q & A

3

Page 4: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

The SAP HANA Project Process

Functional Business IT and Facilities

Engage All Parties in Parallel

FIRST EARLY

ALWAYS

Page 5: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

SAP HANA Deployment Options for Different Use Cases

5

Technology Platform

SAP  HANA  

BI  Clients  

SQ L   MD

X   BIC

S  3rd  Party  

Non  SAP  Data  Source  

In-Memory

Compu?ng  Engine  

Data  Modeling  

ETL  

Reporting

Accelerators

SAP  HANA  

BI  Clients  

SQL  

MD

X   BICS  

3rd  Party  

Replica?on  

SAP  Business  Suite  

Tradi?onal  DB  

In-Memory

Compu?ng  Engine  

Data  Modeling  

SAP  HANA  

Read  

SAP  Business  Suite  

SAP  UI  

Tradi?onal  DB  

In-Memory

Compu?ng  Engine  

Data  Modeling  

Replica?on  

e.g. Demographics & Google Maps

e.g. SAP ERP: Operational reporting

e.g. SAP ERP: CO-PA

Page 6: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

SAP HANA Deployment Options for Different Use Cases

6

Products on In-Memory DB

SAP  HANA  

BW  

Tradi?onal    Extractors  

SAP  Business  Suite  

Tradi?onal  DB  

In-Memory

Compu?ng  Engine  

e.g. SAP BW -7.3 SP8- on HANA

Products on In-Memory DB

SAP  HANA  

ERP,  SCM,  CRM  

In-Memory

Compu?ng  Engine  

e.g. SAP ERP 6.0, EHP6, CRM 7.0, EHP2, SCM 7.0 EHP2, Version for HANA

Page 7: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

Use Case Deployment

• Use Cases Have Different Requirements –  Scale Up –  Scale Out –  Master Node Consideration

• Requirements Determine Architecture/Deployment –  Standalone/Scale up –  Multinode/Scale out –  High Availability Design –  Disaster Recovery Approach –  –  – 

Page 8: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

High Availability

Page 9: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

HDD replica (Disk)

- index server - statistic server

- SAP HANA® DB worker node

Standby Node 512GB

Production Node 2 512GB

FAILED Node 2 512GB

- SAP HANA® DB standby node - SAP HANA® DB worker node

X3950 7143-HBU (512GB)

Production Node 3 512GB

Production Node 1 512GB

shared filesystem - GPFS

HDD flash

data02 log02

data03(3)

log01(1)

log03(3)

data01(1)

data03(3)

log01(1)

log03(3)

data01(1)

HDD flash

data02 log02

data01(1)

data03(3)

log01(1)

log03(3)

HDD flash

log01

DB partition 1

- index server - statistic server - SAP HANA® studio

- SAP HANA® DB worker node

HDD flash

log03(3) log03

DB partition 3

flash

- index server - statistic server

- SAP HANA® DB worker node

data03

HDD flash

- index server - statistic server

X3950 7143-HBU (512GB)

X3950 7143-HBU (512GB)

X3950 7143-HBU (512GB)

Production (scale to 56 Nodes)

data01(2) data01(3) data02(1) data02(3)

data03(1) data03(2)

Log Replica (SSD)

log01(2) log01(3) log02(1) log02(2) log02(3)

log03(1) log03(2)

data01(2) data01(3) data02(3)

data03(1) data03(2)

log01(2) log01(3) log02(1) log02(2) log02(3)

log03(1) log03(2)

data02(2) data02(2)

log02(2) log02(1) log02(3)

data02(3)

data01(1) data01 Primary Data (SSD & Disk)

Production Node 2 512GB

data02(1)

SAP HANA Appliance – Scale Out with High Availability

9

- index server - statistic server

- SAP HANA® DB worker node

- index server - statistic server

- SAP HANA® DB worker node

DB partition 2

SAP HANA® DB

System Memory

X3950 7143-HBU (512GB)

Page 10: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

Datacenter 2

Datacenter 1

HANA Standby node

Stretched HA (single node), up to metro distance

•  Two data centers in metro distance (dependent on network latency and bandwidth)

•  1 + 1 + quorum, no non-prod system allowed on secondary site

•  Quorum node ideally at third location, frequently installed at primary location

•  Automatic failover with GPFS functionality, one GPFS cluster

•  For BW on HANA and Suite on HANA

10

HANA Worker node

Primary replica

Secondary replica

Quorum

Page 11: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

HANA Stretched HA with GPFS – Network setup

11

SAP HANA ACTIVE NODE SAP HANA

STANDBY NODE

QUORUM NODE ISL

HANA cluster network GPFS network

Datacenter 1 Datacenter 2

Datacenter 3

Page 12: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

HA for single node configs in one DC SAP HANA system replication

•  Low RTO, because the data is already active in memory in the secondary system

•  Independent of the HW implementation

• Manual failover or additional cluster failover functionality

• Applicable for all use cases

12

Page 13: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

Disaster Recovery Business Continuity

Page 14: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

Datacenter 1

Datacenter 2

DR Single node: with GPFS (synchronous)

•  Two data centers in metro distance (dependent on network latency and bandwidth)

•  1 + 1 + quorum (one GPFS cluster) On the secondary site the HANA instance is not started, secondary site can be used for ONE different SAP HANA system (e.g. Non-prod) with storage expansion (EXP2524)

•  Quorum node ideally at third location, frequently installed at primary location

•  Manual failover

•  For BW on HANA and Suite on HANA

14

HANA Worker node

Quorum

HANA Standby node

Non-prod HANA

Primary replica

Secondary replica

Page 15: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

DR Scale out: GPFS Replication (synchronous) aka. Storage Replication

•  SAP Note 1755396 •  Synchronous replication •  Secondary site (identical setup active + standby) can be used for a

different SAP HANA system (e.g. Non-prod) with storage expansion •  Not applicable for Suite on HANA

15

Datacenter 1

Datacenter 2

Page 16: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

DR Scale out: SAP HANA Synchronous System Replication

•  Low RTO, because the data is already active in memory in the secondary system

•  Independent of the HW implementation

•  Independent of the use case

16

Page 17: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

DR Scale out: SAP HANA Synchronous System Replication (available with SPS 6)

• Similar as before, but on the secondary site a non-prod system can run (duplicate persistence required)

•  Higher RTO, because „Table pre-load“ is turned off

•  Independent of the HW implementation

•  Independent of the use case

17

Page 18: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

DR Single Node and Scale Out: SAP HANA Asynchronous System Replication (available with SPS 6)

• 

18

Long distance

Page 19: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

GPFS and Disaster Recovery

Page 20: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

GPFS introduced concurrent file system access from multiple nodes.

Evolution of the global namespace: GPFS Active File Management (AFM)

Multi-cluster expands the global namespace by connecting multiple sites

AFM takes global namespace truly global by automatically managing asynchronous replication of data

GPFS GPFS

GPFS

GPFS

GPFS

GPFS

1993 2005 2013

Page 21: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

AFM Mode: Single-Writer

• Data written to a cache • Asynchronous replication back to home

• Can have multiple read-only caches

RW

Single-Writer

RO RO RW

Page 22: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

AFM Mode: Asynchronous Replication (GPFS TL-2)

• Asynchronous Replication in HA Pair – Cache site does the writing – Home site is failover

• Cache Fails – New cache can be defined

• Home Fails – New Home can be defined

High Availability

RW

RO

Page 23: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

Q & A

Page 24: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation

Thank you for your Attention

24

•  IBM's SAP Alliance page – http://www.ibm-sap.com

•  SAP’s IBM Alliance page – http://service.sap.com/ibm

Richard T. Travis SAP Infrastructure Architect!"!IBM ATS!

4 Center Court!Bay City, MI!!

Phone (720) 395-1579!Mobile (989) [email protected] !

Page 25: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation 25

IBM Systems solution for SAP HANA sizes / building blocks / upgrade path

Size XS S S+ M L

Building Block x3690 X5 x3690 X5 x3950 X5 x3950 X5 x3950 X5

Part Number (Sys x - config)

7147-HAx 7147-HBx 7143 - HAx 7143 - HBx 7143 – HBx + 7143 – HCx

Intel CPU 2 x E7 2870 2 x E7 2870 2 x E7-8870 4 x E7-8870 8 x E7-8870

RAM 128 GB DDR3 (8 x 16GB)

256 GB DDR3 (16 x 16GB)

256 GB DDR3 (16 x 16 GB)

512 GB DDR3 (32 x 16 GB)

1 TB DDR3 (64 x 16 GB)

Log Storage 10 x 200 GB 1.8‘‘ MLC SSD

10 x 200 GB 1.8‘‘ MLC SSD

1.2 TB ioDrive2 FusionIO 1.2 TB ioDrive2 FusionIO 2 x 1.2 TB ioDrive2 FusionIO

Data Storage - - 8 x 900 GB 10k SAS HDD 8 x 900 GB 10k SAS HDD 16 x 900 GB 10k SAS HDD

Storage Ctrl 2 x M5015 2 x M5015 1 x M5015 1 x M5015 2 x M5015

Data / Log Storage Summary

1.6 TB RAID 5 data and log storage

1.6 TB RAID 5 data and log storage

5.4 TB RAID5 data storage 1 TB log storage

5.4 TB RAID5 data storage 1 TB log storage

10.8 TB RAID5 data storage 2 TB log storage

Ethernet 4 x 10 GbE, 6 x 1 GbE 4 x 10 GbE, 6 x 1 GbE 4 x 10 GbE, 6 x 1 GbE 4 x 10 GbE, 6 x 1 GbE 8x 10 GbE, 12 x 1 GbE

Upgrade Option Scale Up or Scale out

XS - > S Up to 16 node scale out with HA, SAP certified

S+ à M M à „XM“ and L (with L-option) Up to 56 node scale out with HA, SAP certified

L à XL or XXL Up to 56 node scale out with HA, SAP certified

Software Preload: SLES4SAP GPFS SAP HANA

Preload: SLES4SAP GPFS SAP HANA

Preload: SLES4SAP GPFS SAP HANA

Preload: SLES4SAP GPFS SAP HANA

Preload: Addtl. GPFS lic.

Page 26: Data Center Readiness for HANA Part 2 DR and BC

© 2013 IBM Corporation © 2013 IBM Corporation 26

IBM Systems solution for SAP HANA

Size „XM“ XL XXL

Building Block x3950 X5 x3950 X5

Part Number (Sys x - config)

7143 - HDx 7143 – HDx + 7143 – HEx

7143 – HDx + 7143 – HEx + add. storage

Intel CPU 4 x E7-8870 8 x E7-8870 8 x E7-8870

RAM 1 TB DDR3 (64 x 16 GB or 32 x 32 GB)

2 TB DDR3 (128 x 16 GB or 64 x 32 GB)

4 TB DDR3 (128 x 32 GB)

Log Storage 1 x 1.2 TB ioDrive2 FusionIO

2 x 1.2 TB ioDrive2 FusionIO 4 x 1.2 TB ioDrive2 FusionIO

Data Storage 8 x 900 GB 10k SAS HDD

16 x 900 GB 10k SAS HDD 24 x 900 GB 10k SAS HDD

Storage Ctrl 1 x M5015 2 x M5015 2 x M5015, 1 x M5025

Data / Log Storage Summary

5.4 TB RAID5 data storage 1 TB log storage

10.8 TB RAID5 data storage 2 TB log storage

16.2 TB RAID5 data storage 4 TB log storage

Ethernet 4 x 10 GbE, 6 x 1 GbE 8 x 10 GbE, 12 x 1 GbE 8x 10 GbE, 12 x 1 GbE

Upgrade Option Scale Up

„XM“ à XL XL à XXL (with additional memory, ioDrive2, M5025, EXP 2524)

Software Preload: SLES4SAP GPFS SAP HANA

Preload: SLES4SAP GPFS SAP HANA

Preload: SLES4SAP GPFS SAP HANA

Single node only for SAP Business Suite on HANA


Recommended