Date post: | 30-Mar-2015 |
Category: |
Documents |
Upload: | lisbeth-doidge |
View: | 216 times |
Download: | 0 times |
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 11
Date 13.02.2013
Suppliers Technical Forum - Innovation
David Pinkney
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 2
Innovation on Thameslink
• Using new products equipment and tools to reduce costs and create efficiencies
• Often teamed with headquarters, maintenance, or another programmes
• Most have a large engineering content and the development of a new product
• Often involve product acceptance and changes to ways of working
• Need to flexible, adaptable, thinking out of box
• But still supporting programme deliveryDate 00.00.00 Create your footer by changing copy in the Header and Footer section 2
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 3
Example of a successful project - New CCTV technology for London Bridge
• Use of mega pixel technology to reduce the number cameras needed for London Bridge station.
• The reduction of cameras produces reductions in brackets, power, cables
• The like for like saving for the London Bridge installation is £1m (25%) but the big saving is in maintenance – circa 60%
• Project Manager’s role was to gain acceptance by the HQ CCTV group and NR Head of Security and have the standard changed
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 4Date 00.00.00 Presentation title to go here 4
Mobile Maintenance Unit
• The MMU is a train with a workshop, stores, messing, worker transport
• Self contained train for installation and maintenance
• Moving green zone – work force protected
• Realisation is that MMUs will radically change the way we plan and manage our site work
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 5
Mobile Maintenance Unit
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 6
Mobile Maintenance Unit
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 7Date 00.00.00 Create your footer by changing copy in the Header and Footer section 7
Mobile Maintenance Unit – Status
• Nationally 7 units are needed (4 specifically in the south east)
• Aligning Thameslink with Kent
• In the tender process – 5 companies bidding
• Planning visits to users
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 8
Mobile Maintenance Unit – Status Continued
• For Thameslink two extra variants
• For tunnel working -
– To reduce costs – TOC compensation, 7 day railway
– Keeping one track open while working on the other track
– Still a mobile green zone
– Expanding slides and opening side doors
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 8
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 9
Mobile Maintenance Unit – Status Continued
• Second variant– Enables slim-line gantries to
be used
– Efficiencies in installation and maintenance
• The necessary kit is there
• Difficult bit –
– How are we going to use it?
– Define the processes
– Which variants do we need?
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 9
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 10
Cable Management Sleepers
• Replace
– Under and Over Track Crossings
– Orange Pipes and Yellow Split Ducting
• Savings of the order 95%
• Reduce risk as the track bed is not disturbed
• Two variants product accepted
• In use across the whole of Network Rail as well as Thameslink
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 11Date 00.00.00 Create your footer by changing copy in the Header and Footer section 11
Cable Management Sleepers – further work
• Modified
– Wider rebate
– Clips
– Inserts to mount third rail insulators
• Production moulds for GV54 sleeper on order
• Thameslink requirements until 2018 defined
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 12
Cable Management Sleepers
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 13Date 00.00.00 Create your footer by changing copy in the Header and Footer section 13
Negative Short Device
• The Negative Short Device will be used to improve the efficiency and safety of third rail isolations.
• Replace short circuiting straps and strap-men (can have up to 25)
• Simplifies the process considerably
• Project timescale 40 weeks
• Proposed fit NSDs to London Bridge low level
• Manual switched solution – not using SCADA
• Only 25 NSDs needed
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 14
Increase in Work Time with NSDs
• Current situation
– Available work time 2h 30m
– Complicated
– Many phone calls
• With NSDs
– Available work time 4h 00m
– Much simpler
– Far fewer phone calls
-
PICOP
Signaller
Protection Staff
ECRO
Engineering
Supervisor
Worksite Staff
COSS
-
PICOP'
Worksite Staff'
Engineering Staff'
ECRO'
COSS
00:10PICOP
requests possession
Signaller protects
possession
00:15PICOP
insructs PS to place PLB
PS#1
00:20PLB in place
x4
Confirms PLB in place
00:21Grants
possession
Requests Isolation
00:30Circuit breaker only - grants
isolation - with NSD applied
Requests to set up
worksite and test traction
circuit
Instructs to erect MB and possition SCS
#1
00:35Confirm SCS
and MB in place
Authorises the issue of
CRP
Issues CRP to COSS x 20?
Confirm SCS and MB in place #1
Circuit Breaker Isolation
Sub-section CB1
Value Adding WorkFrom 00:40 to 04:45
4 hours
04:45Returns CRP
04:48Marker boards
removed
04:47Confirms
removal of Marker Boards
04:50Request
recharge of traction current
04:53Confirm traction
current on
04:54Request
handback of the
possession
04:55Instructs
removal of PLBs
04:56Confirm
removal of PLBs
05:00Hands back possession
Signaller takes back possession
04:46Remove
marker boards
Communication Chain for Isolations using Negative Short Devices
Circuit Breaker Isolation
Sub-section CB1
Value Adding WorkFrom 01:15 to 03:45
2:30 hours
Existing Communication Chain for Isolations
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 15
NSD Savings
• Reduction in resource needed over 2 years = £840k
• Reduced communication over 2 years, 208 hours = 52 extra shifts
• Not cancelling the first and last trains over 3 years = £300k
• Reduction in risk
– Reduced requirement for line blockages
– Less staff on the infrastructure
– Reduced involvement from interface stakeholders
– No strapping in the wrong area
– Reduced communications
– Reduced staff on track / less chance of injury
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 16
Snow displacer
• Very simple, inexpensive length of foam that sits in the point ends
• Stops snow (anything else) from entering and jamming the points
• Saves delay minutes
• Saves energy (30%) by insulating the point heaters
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 16
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 17
Snow displacer installation
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 18
Snow displacer – status
• Thameslink is part of the national programme
• Trial underway at Hither Green
• Further work –
– Develop a version for the very narrow end of the points
– Arrange for points to be automatically fitted to the points at the factory
– ‘Productionise’ the existing snow displacer for easier fitting
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 18
Electro-luminescent PPE
• Worked very closely with the suppler Fhoss to complete final development
• Thameslink Route Access Team is testing 10 sets of PPE
• Battery life 12 hours
• A worker can be seen 1 ½ miles down the track
• Compliant with Rail Standards
• Additional cost is not significant
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 19
Pavegen – electrical energy from foot falls
• Sustainable renewable energy
• Floor tiles form the green area in the ‘mock up’ photo
• Hopefully drive assets such as destination boards
• Trial site in the station to be set up
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 20
CCTV Scanning of Pantographs
• A damaged pantograph or shoe can cause much damage to the infrastructure and very many delay minutes
• Even more when we are at 24 trains per hour
• CCTV scanning will allow damaged trains to be sidelined before they enter the Thameslink central core
• An installation at Farringdon will check that the pantograph is down as the train travels south into the third rail area
• Probably the trial site will be at Farringdon
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 21
A camera installation showing the housing containing the radar, flash and camera
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 22
CCTV Scanning of Pantographs
A drawing of a typical installation in the Nederlands
Balise Bars
• Can be used for Balise Bars from Siemens, Alstrom and others
• Can be fitted or removed in less than 2 minutes using standard tools
• Use standard rail fittings so no drilling or digging out the ballast
AWS magnets
• Ordinary ferrite magnets –
– Lose strength due to interference in third rail areas
– Bulky heavy
– Require frequent maintenance or rebuilding
• Vortok - Rare Earth Magnets
– With an opposing coil and digital control electronics
– Smaller and Lighter
– Little or no loss of strength
– Plug coupled so quick to fit
Innovation on Thameslink
• Not just be confined to Network Rail
• Surely our partners have innovations as well
• Example – Invensys use the IBM Rational tool provides platform for integrating and synchronizing product development processes
• The need - Invensys Rail Dimetronic needed to improve its competitiveness and reduce time-to-market for its solutions. This required automating, streamlining and increasing control over development processes.
• The solution The company used integrated IBM® Rational® software to automate code generation and speed developers' response to frequent changes and new traffic signal requirements.
• The benefit The company reduces time-to-market for products by 40 percent and reduces cost and risks of development by generating all code in compliance with coding standards.
• This case study has been published by IBM
• Please tell me of your innovations on Thameslink
• Are there opportunities for partnering?
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 25