+ All Categories
Home > Documents > Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013...

Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013...

Date post: 30-Mar-2015
Category:
Upload: lisbeth-doidge
View: 216 times
Download: 0 times
Share this document with a friend
Popular Tags:
25
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney
Transcript
Page 1: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 11

Date 13.02.2013

Suppliers Technical Forum - Innovation

David Pinkney

Page 2: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 2

Innovation on Thameslink

• Using new products equipment and tools to reduce costs and create efficiencies

• Often teamed with headquarters, maintenance, or another programmes

• Most have a large engineering content and the development of a new product

• Often involve product acceptance and changes to ways of working

• Need to flexible, adaptable, thinking out of box

• But still supporting programme deliveryDate 00.00.00 Create your footer by changing copy in the Header and Footer section 2

Page 3: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 3

Example of a successful project - New CCTV technology for London Bridge

• Use of mega pixel technology to reduce the number cameras needed for London Bridge station.

• The reduction of cameras produces reductions in brackets, power, cables

• The like for like saving for the London Bridge installation is £1m (25%) but the big saving is in maintenance – circa 60%

• Project Manager’s role was to gain acceptance by the HQ CCTV group and NR Head of Security and have the standard changed

Page 4: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 4Date 00.00.00 Presentation title to go here 4

Mobile Maintenance Unit

• The MMU is a train with a workshop, stores, messing, worker transport

• Self contained train for installation and maintenance

• Moving green zone – work force protected

• Realisation is that MMUs will radically change the way we plan and manage our site work

Page 5: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 5

Mobile Maintenance Unit

Page 6: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 6

Mobile Maintenance Unit

Page 7: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 7Date 00.00.00 Create your footer by changing copy in the Header and Footer section 7

Mobile Maintenance Unit – Status

• Nationally 7 units are needed (4 specifically in the south east)

• Aligning Thameslink with Kent

• In the tender process – 5 companies bidding

• Planning visits to users

Page 8: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 8

Mobile Maintenance Unit – Status Continued

• For Thameslink two extra variants

• For tunnel working -

– To reduce costs – TOC compensation, 7 day railway

– Keeping one track open while working on the other track

– Still a mobile green zone

– Expanding slides and opening side doors

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 8

Page 9: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 9

Mobile Maintenance Unit – Status Continued

• Second variant– Enables slim-line gantries to

be used

– Efficiencies in installation and maintenance

• The necessary kit is there

• Difficult bit –

– How are we going to use it?

– Define the processes

– Which variants do we need?

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 9

Page 10: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 10

Cable Management Sleepers

• Replace

– Under and Over Track Crossings

– Orange Pipes and Yellow Split Ducting

• Savings of the order 95%

• Reduce risk as the track bed is not disturbed

• Two variants product accepted

• In use across the whole of Network Rail as well as Thameslink

Page 11: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 11Date 00.00.00 Create your footer by changing copy in the Header and Footer section 11

Cable Management Sleepers – further work

• Modified

– Wider rebate

– Clips

– Inserts to mount third rail insulators

• Production moulds for GV54 sleeper on order

• Thameslink requirements until 2018 defined

Page 12: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 12

Cable Management Sleepers

Page 13: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 13Date 00.00.00 Create your footer by changing copy in the Header and Footer section 13

Negative Short Device

• The Negative Short Device will be used to improve the efficiency and safety of third rail isolations.

• Replace short circuiting straps and strap-men (can have up to 25)

• Simplifies the process considerably

• Project timescale 40 weeks

• Proposed fit NSDs to London Bridge low level

• Manual switched solution – not using SCADA

• Only 25 NSDs needed

Page 14: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 14

Increase in Work Time with NSDs

• Current situation

– Available work time 2h 30m

– Complicated

– Many phone calls

• With NSDs

– Available work time 4h 00m

– Much simpler

– Far fewer phone calls

-

PICOP

Signaller

Protection Staff

ECRO

Engineering

Supervisor

Worksite Staff

COSS

-

PICOP'

Worksite Staff'

Engineering Staff'

ECRO'

COSS

00:10PICOP

requests possession

Signaller protects

possession

00:15PICOP

insructs PS to place PLB

PS#1

00:20PLB in place

x4

Confirms PLB in place

00:21Grants

possession

Requests Isolation

00:30Circuit breaker only - grants

isolation - with NSD applied

Requests to set up

worksite and test traction

circuit

Instructs to erect MB and possition SCS

#1

00:35Confirm SCS

and MB in place

Authorises the issue of

CRP

Issues CRP to COSS x 20?

Confirm SCS and MB in place #1

Circuit Breaker Isolation

Sub-section CB1

Value Adding WorkFrom 00:40 to 04:45

4 hours

04:45Returns CRP

04:48Marker boards

removed

04:47Confirms

removal of Marker Boards

04:50Request

recharge of traction current

04:53Confirm traction

current on

04:54Request

handback of the

possession

04:55Instructs

removal of PLBs

04:56Confirm

removal of PLBs

05:00Hands back possession

Signaller takes back possession

04:46Remove

marker boards

Communication Chain for Isolations using Negative Short Devices

Circuit Breaker Isolation

Sub-section CB1

Value Adding WorkFrom 01:15 to 03:45

2:30 hours

Existing Communication Chain for Isolations

Page 15: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 15

NSD Savings

• Reduction in resource needed over 2 years = £840k

• Reduced communication over 2 years, 208 hours = 52 extra shifts

• Not cancelling the first and last trains over 3 years = £300k

• Reduction in risk

– Reduced requirement for line blockages

– Less staff on the infrastructure

– Reduced involvement from interface stakeholders

– No strapping in the wrong area

– Reduced communications

– Reduced staff on track / less chance of injury

Page 16: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 16

Snow displacer

• Very simple, inexpensive length of foam that sits in the point ends

• Stops snow (anything else) from entering and jamming the points

• Saves delay minutes

• Saves energy (30%) by insulating the point heaters

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 16

Page 17: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 17

Snow displacer installation

Page 18: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 18

Snow displacer – status

• Thameslink is part of the national programme

• Trial underway at Hither Green

• Further work –

– Develop a version for the very narrow end of the points

– Arrange for points to be automatically fitted to the points at the factory

– ‘Productionise’ the existing snow displacer for easier fitting

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 18

Page 19: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Electro-luminescent PPE

• Worked very closely with the suppler Fhoss to complete final development

• Thameslink Route Access Team is testing 10 sets of PPE

• Battery life 12 hours

• A worker can be seen 1 ½ miles down the track

• Compliant with Rail Standards

• Additional cost is not significant

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 19

Page 20: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Pavegen – electrical energy from foot falls

• Sustainable renewable energy

• Floor tiles form the green area in the ‘mock up’ photo

• Hopefully drive assets such as destination boards

• Trial site in the station to be set up

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 20

Page 21: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

CCTV Scanning of Pantographs

• A damaged pantograph or shoe can cause much damage to the infrastructure and very many delay minutes

• Even more when we are at 24 trains per hour

• CCTV scanning will allow damaged trains to be sidelined before they enter the Thameslink central core

• An installation at Farringdon will check that the pantograph is down as the train travels south into the third rail area

• Probably the trial site will be at Farringdon

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 21

A camera installation showing the housing containing the radar, flash and camera

Page 22: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 22

CCTV Scanning of Pantographs

A drawing of a typical installation in the Nederlands

Page 23: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Balise Bars

• Can be used for Balise Bars from Siemens, Alstrom and others

• Can be fitted or removed in less than 2 minutes using standard tools

• Use standard rail fittings so no drilling or digging out the ballast

Page 24: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

AWS magnets

• Ordinary ferrite magnets –

– Lose strength due to interference in third rail areas

– Bulky heavy

–  Require frequent maintenance or rebuilding

• Vortok - Rare Earth Magnets

– With an opposing coil and digital control electronics

– Smaller and Lighter

– Little or no loss of strength

– Plug coupled so quick to fit

Page 25: Date 00.00.00Create your footer by changing copy in the Header and Footer section1 1 Date 13.02.2013 Suppliers Technical Forum - Innovation David Pinkney.

Innovation on Thameslink

• Not just be confined to Network Rail

• Surely our partners have innovations as well

• Example – Invensys use the IBM Rational tool provides platform for integrating and synchronizing product development processes

• The need - Invensys Rail Dimetronic needed to improve its competitiveness and reduce time-to-market for its solutions. This required automating, streamlining and increasing control over development processes.

• The solution The company used integrated IBM® Rational® software to automate code generation and speed developers' response to frequent changes and new traffic signal requirements.

• The benefit The company reduces time-to-market for products by 40 percent and reduces cost and risks of development by generating all code in compliance with coding standards.

• This case study has been published by IBM

• Please tell me of your innovations on Thameslink

• Are there opportunities for partnering?

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 25


Recommended