Long Beach Unified School District 1
Jordan High SchoolMajor Renovation
David Starr Jordan High SchoolMajor Renovation
Community Update December 16, 2013
Long Beach Unified School District 2
Jordan High SchoolMajor Renovation
Project Goals1. Creating 21st century learning environments for the next generation
• Create career technical education labs2. Renovation and replacement of aging infrastructure
• Extend life of building systems• Improve technology infrastructure• Improve energy efficiency
3. Elimination of portables and bungalows• Declining enrollment
4. School safety and security• Improve parking and drop‐off
5. Joint‐use• Collaboration with the City of Long Beach
PROJECT GOALS & OBJECTIVES
Long Beach Unified School District 3
Jordan High SchoolMajor Renovation
Buildings proposed to be demolished shown in RED
EXISTING CAMPUS
Long Beach Unified School District 4
Jordan High SchoolMajor Renovation
PROPOSED MASTER PLAN
• Facility Program− Master Plan capacity - 3,600
students, grades 9-12− ~ 453,000 sq ft of total building
area• New Construction
− Removal of portables− Six (6) New Academy Buildings
with technical lab spaces (Small Learning Communities)
− Cafeteria Building• Renovation Work:
− Media Center, administration and band buildings
− Gymnasium, pool, and athletic fields
− Fire alarms, communications, and technology systems
− Parking lots and drop-off area− Landscaping, fencing, and site
utilities
Long Beach Unified School District 5
Jordan High SchoolMajor Renovation
PROPOSED NEW CAFETERIAPROPOSED TYPICAL NEW SMALL
LEARNING COMMUNITY (SLC)
TYPICAL DESIGN OF NEW BUILDINGS
Long Beach Unified School District 6
Jordan High SchoolMajor Renovation
TYPICAL DESIGN OF NEW BUILDINGS
LAB LAB LAB
CR/OFFICES
Long Beach Unified School District 7
Jordan High SchoolMajor Renovation
Construction Phase StartDate
Completion Date
Phase 1A (Interim Housing & Parking)
Jan 2014 Aug 2014
Phase 1B (Cafeteria, SLCs, & Parking)
Jul 2014 Jun 2016
Phase 1C (SLCs & Parking) Jul 2016 Jun 2018
Phase 2A (Media Ctr, Band bldg, Admin, & Parking)
Jun 2016 TBD
Phase 2B (SLCs & Spec Ed) Jul 2018 Jun 2020
Phase 3 (Science Lab) TBD TBD
Phase 4 (Auditorium) Jun 2016 Aug 2017
Phase 5 (Fields) TBD TBD
Phase 6 (Gym) TBD TBD
CONSTRUCTION PHASING
Long Beach Unified School District 8
Jordan High SchoolMajor Renovation
Long Beach Unified School District
START OF CONSTRUCTION ACTIVITIES
Construction of parking lot
Interim Housing Phase• Construction contract award:
12/17/13• Contractor: McCarthy
Building Companies Inc.• Construction start: Jan 2014• Duration: 8 months
Construction of temporary portable classrooms
Construction of new electrical substation
Construction of new tennis courts
PHASE 1A
Long Beach Unified School District 9
Jordan High SchoolMajor Renovation
• Construction Safety & Logistics– Maintain full time site supervision– Install fencing and barricades to separate construction from students, staff,
and public– Use flagmen to monitor construction traffic– Keep site and surrounding areas clean of construction debris– Perform work during normal working hours– Implement continuous safety training of construction personnel– Maintain open communication with school personnel and community
CONSTRUCTION SAFETY & LOGISTICS
Long Beach Unified School District 10
Jordan High SchoolMajor Renovation
CONSTRUCTION TRAFFIC ROUTE
Truck route from site
Truck route to site
Long Beach Unified School District 11
Jordan High SchoolMajor Renovation
CONSTRUCTION FENCING
Temporary construction fence
Construction Entrance