Davisville Junior Public School / Spectrum Alternative Senior School
CONSTRUCTION UPDATE
Community Meeting April 16, 2019
1
AGENDA
• WELCOME/INTRODUCTIONS This meeting will update the community
on key aspects of this complex project as we start the construction phase of the new Davisville/Spectrum building
• PROJECT RECAP Reminder of the key aspects of the
project - Evolution of the design • The Site • The Building • Key Events
• TIMELINE The overall construction schedule –
identifying key milestone dates to be anticipated
• NEXT STEPS How will we keep the community
updated?
• QUESTIONS & ANSWERS
2
CONSTRUCTION UPDATE – April, 2019
3
CONSTRUCTION UPDATE – April, 2019
4
CONSTRUCTION UPDATE – April, 2019
• A new school building & integrated Childcare fronting on Davisville Ave
• Provision for a future Aquatic Centre – to be built by the City of Toronto
• Coordination with key aspects of the Midtown in Focus initiatives – through block pedestrian access & provision for a boulevard treatment along Davisville
• Addressing community concerns – site access and vehicular circulation – one-way flow from Millwood Rd to Davisville Ave
THE SITE Utilization - Key areas and features of the proposed site development
5
CONSTRUCTION UPDATE – April, 2019
6
CONSTRUCTION UPDATE – April, 2019 THE BUILDING
Vision: 21st century school
student-centred
daylight & views
learning grounds
community
7
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan
Davisville Entrance
8
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan
9
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan
10
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan
North Entrance
11
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan
feature wall (to be rendered)
12
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan
Child Care play
Kindergarten play
Kindergarten play
Entrance
13
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan
14
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Ground Floor Plan
15
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Parking Plan
THE BUILDING: Parking Plan
16
CONSTRUCTION UPDATE – April, 2019
THE BUILDING: Ground Floor Plan
17
CONSTRUCTION UPDATE – April, 2019
THE BUILDING: Second Floor Plan
18
CONSTRUCTION UPDATE – April, 2019
THE BUILDING: Second Floor Plan
19
CONSTRUCTION UPDATE – April, 2019
20
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Second Floor Plan
THE BUILDING: Second Floor Plan
21
CONSTRUCTION UPDATE – April, 2019
THE BUILDING: Second Floor Plan
22
CONSTRUCTION UPDATE – April, 2019
23
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Third Floor Plan
Spectrum
THE BUILDING: Third Floor Plan
24
CONSTRUCTION UPDATE – April, 2019
25
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Classroom Configuration
26
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Cross-Sectional Perspective
27
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: Massing Model
28
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: South-West 3D View
29
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: South Elevation
30
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: North-East 3D View
31
CONSTRUCTION UPDATE – April, 2019 THE BUILDING: North Elevation
32
CONSTRUCTION UPDATE – April, 2019 THE BUILDING
Vision: 21st century school
student-centred
daylight & views
learning grounds
community
33
CONSTRUCTION UPDATE – April, 2019
KEY EVENTS – PROJECT TIMELINE: For the replacement JK-8 school; integrated Childcare - with provision for a future Aquatic Centre
These events affected the approval and delivery of the new replacement school: •CITY OF TORONTO – Municipal Approvals – Site Plan Approval & Building Permit
• Notice of Approval Conditions (NOAC) • Demolition Permit • Conditional Building Permit • Formal Site Plan Agreement and Full Building Permit
•CITY OF TORONTO – Future Aquatic Centre – Land Lease & Shared Use Agreements • Use Agreements • Release of Identified Funding
•PROVINCE OF ONTARIO – Ministry of Education (EDU) – Approval to Proceed to Tender • Review of Cost and Program Compliance Submission • Review of Extra Ordinary Costs • Formal Release of “Approval to Proceed” (ATP) to Construction Tender
•CONSTRUCTION TENDER – • Tender Period – 6-8 weeks • Tender Review & TDSB Board Approval to Award
•TENDER AWARD – MOBILIZATION & CONSTRUCTION START
34
CONSTRUCTION UPDATE – April, 2019 Key Events Timeline:
J F M A M J J A S O N D J F M A M J J
SPA Site Plan ApprovalNOACBuilding Permit - ConditionalBuilding Permit -Full
LAND LEASE Shared Use AgreementReleased Funding
Review of Compliance$ Extra Ordinary CostsATP Approval To Proceed to Tender ``
Tender Period (6-8 weeks)TDSB Board Approval to AwardBid Hold Tender $ held Tender Award Letter of Intent
Letter of Intent TDSBConfirmation of Sub-Trade AgreementsMobilization & Start of Work
ONGOING MUNICIPAL ELECTION
PROVINCIAL ELECTION
DAVISVILLE - Key Event Timeline
2018 2019Activity
CITY - Aquatic Centre Approvals
ELECTION BLACK-OUT
CONSTRUCTION TENDER
CONSTRUCTION START
CITY - Municipal Approvals
PROVINCE - Ministry Approvals
35
CONSTRUCTION UPDATE – April, 2019
TIMELINE:
Key Stages of Construction – Identified per the Contractor`s Preliminary Schedule:
•Anticipated duration of construction – 24 months from start of work
• 3 storey structure with below-grade garage
• Complex site in an urban context
CONSRUCTION COMPONENTS:
•Shoring, Excavation & Substructure – 100 Days
•Superstructure – 165 Days
•Building Envelope – 140 Days
•Interior Finishes – 190 Days
•Site Development-Exterior & Landscape Features – 135 Days
Note: These are the major stages of construction and anticipated duration. Overlaps in schedule & efficiencies are currently being evaluated.
TDSB Staff will be involved in regular construction meetings & will provide updates to the Trustee, Superintendent and Principal.
36
CONSTRUCTION UPDATE – April, 2019
AVONDALE PS:
Replacement School - 860 pupil place school: This replacement school was opened at the beginning of April, 2019 – School occupied; landscape development & Childcare to follow for September occupancy
GEORGE WEBSTER ES:
Replacement School - 840 pupil place school: This replacement school was opened in September, 2018 – School occupied; landscape development & Childcare to follow for September occupancy
What does completion look like?
Lessons learned from previous, recent projects –
37
CONSTRUCTION UPDATE – April, 2019
NEXT STEPS:
•Communication Plan – TDSB Facility staff will provide regular updates to the School Principal (who will also be involved in construction meetings).
•As the work proceeds we will confirm the nature and timing of construction through updates that will be posted on the school’s website https://schoolweb.tdsb.on.ca/davisville/ click on “The New Build”. There is also a link to the parent page at https://davisvilleparents.com/redevelopment/ ; we will be getting quarterly construction reports which will also be posted.
HEALTH & SAFETY:
•All work will be done per industry standards, and per the City guidelines for environmental protection, noise suppression and dust control.
IN AN EMERGENCY:
•If you notice anything you can reach our Security Operations Centre at 416-395-4620
38
CONSTRUCTION UPDATE – April, 2019 THANK YOU FOR COMING –
QUESTIONS & ANSWERS: