+ All Categories
Home > Documents > DC protection calculations – an innovative approach · DC protection calculations – an...

DC protection calculations – an innovative approach · DC protection calculations – an...

Date post: 25-Mar-2020
Category:
Upload: others
View: 12 times
Download: 0 times
Share this document with a friend
15
DC protection calculations – an innovative approach R. Leach, D. Tregay & M. Berova Parsons Brinckerhoff Ltd, UK Abstract As part of a recent major re-signalling scheme for a DC electrified railway, substantial changes were made to the track layout and electrical feeding/switching arrangements. In addition, as part of this scheme, the opportunity was taken to introduce a novel approach to the way negative bonding in the return circuit is configured, made possible by the introduction of axle counters, in place of track circuits, for train detection purposes. As a consequence, the overall impact on electrical impedance was unclear. The need arose to determine firstly whether the existing protection settings for the track feeder circuit breakers remained safe in the light of these changes and secondly whether the settings could be improved, thereby offering the potential to increase services and/or run longer trains. This paper outlines the challenges that needed to be overcome in gathering, processing and validating input data to arrive at a complete, coherent and consistent set of data necessary for determining the maximum fault impedances seen by each of the circuit breakers. The paper goes on to present the development, implementation and application of the methodology for the calculation of the protection settings, including validation of the results. The results from the calculations were surprising and contrary to original expectations. Keywords: calculations, traction, power, DC, protection, relay, settings, spreadsheet, fault, impedance, overcurrent, overhang, tee, data, hand, modelling, schematic, equivalent and circuit. 1 Introduction As the result of a major re-signalling project in the UK, the permanent way layout and the third rail DC traction power supply infrastructure underwent substantial change, both in terms of the track layout, particularly at switch Power Supply System Analysis, Design and Planning 171 www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press 10 doi:10.2495/978-1-84564- -/ 498 7 17
Transcript

DC protection calculations – an innovative approach

R. Leach, D. Tregay & M. Berova Parsons Brinckerhoff Ltd, UK

Abstract

As part of a recent major re-signalling scheme for a DC electrified railway, substantial changes were made to the track layout and electrical feeding/switching arrangements. In addition, as part of this scheme, the opportunity was taken to introduce a novel approach to the way negative bonding in the return circuit is configured, made possible by the introduction of axle counters, in place of track circuits, for train detection purposes. As a consequence, the overall impact on electrical impedance was unclear. The need arose to determine firstly whether the existing protection settings for the track feeder circuit breakers remained safe in the light of these changes and secondly whether the settings could be improved, thereby offering the potential to increase services and/or run longer trains. This paper outlines the challenges that needed to be overcome in gathering, processing and validating input data to arrive at a complete, coherent and consistent set of data necessary for determining the maximum fault impedances seen by each of the circuit breakers. The paper goes on to present the development, implementation and application of the methodology for the calculation of the protection settings, including validation of the results. The results from the calculations were surprising and contrary to original expectations. Keywords: calculations, traction, power, DC, protection, relay, settings, spreadsheet, fault, impedance, overcurrent, overhang, tee, data, hand, modelling, schematic, equivalent and circuit.

1 Introduction

As the result of a major re-signalling project in the UK, the permanent way layout and the third rail DC traction power supply infrastructure underwent substantial change, both in terms of the track layout, particularly at switch

Power Supply System Analysis, Design and Planning 171

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

doi:10.2495/978-1-84564- - /498 7 17

and crossing (S&C) locations, and in the plain line sections of the rail network. The installation of new types of running rails and the renewal of the traction return (negative bonding cables) based on a new technique [1] meant that existing circuit impedances needed to be revisited to determine whether existing DC circuit breaker protection settings remained safe, or needed to be modified in the light of the changes. This necessitated carrying out protection setting calculations for 36 electrical sections, some standard plain line and others, involving diverging routes, resulting in complex feeding arrangements.

2 Issues relating to data

The initial approach was to update the existing calculations, relevant to the affected electrical sections, to reflect any changes in the infrastructure. However, when compiling the data, it was found that before proceeding with any analysis there were a number of issues to resolve, namely:

Record drawings often up to 20 years out of date or incomplete Recent changes arising from an earlier Traction Power Supply Upgrade

project needed to be included Feeder cable lengths not typically included in earlier calculations where

impedance values of some such feeders were actually quite significant Variety of protection relay and circuit breaker current tripping device

types needed consideration Recent drawings based on metric units whereas original calculations

utilised imperial units (miles and feet) thereby warranting conversion Mileages shown on positive (conductor rail) drawings and negative

bonding drawings not always in agreement Details of running rail types not readily available, or unknown Different running rail types in parallel within electrical sections Multiple reference points e.g. record drawings based on miles and feet

from London, permanent way drawings at switch and crossing based on local datum point, signalling drawings based on separate datum relating to extent of re-signalling project

Changes to conductor rail cross-sections, feeder cables and return circuits arising from changes to permanent-way track layouts

3 Selection of approach

3.1 Previous practice/issues

The existing protection setting calculations supplied by the client relating to previous stages of the traction power system development were based on simple hand calculations, which typically excluded cable lengths and tended to assume connection points were adjacent to the Traction Substations (TSS’s) and Track Paralleling Huts (TPH’s). This presented several issues to overcome:

172 Power Supply, Energy Management and Catenary Problems

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

Hand calculations cannot readily cope with complex layouts, or multiple changes in conductor rail and running rail types.

With hand calculations it is easy to make mistakes and difficult to check the calculations.

Often the lengths of junctions are now typically much longer. This meant that physical connection points to conductor rails and feeder/return cables were rarely adjacent, but often a considerable distance from the TSS or TPH resulting in greater cable lengths. Therefore, it became apparent that cable impedances could not be ignored.

Significant ‘Overhangs’ or ‘Tee’ feeds arising from extended junctions were omitted from the original calculations.

Historically, conductor rails were of smaller cross section, hence impedance was very similar to the feeder cables and actual connection point was not considered particularly critical.

3.2 Typical arrangements

Figures 1 - 3 below illustrate the variety of configurations typically found on most schemes of this kind and associated fault paths. Note: A ‘Tee’ feed is particularly difficult to evaluate in terms of providing suitable protection settings. This arises as a fault in the ‘Tee’ or ‘overhang’ results in fault current from the two feeding circuit breakers flowing along the same path, thereby increasing the apparent impedance seen by the circuit breakers. It is therefore necessary to determine whether a fault at the end of the ‘Tee’, or a fault at the remote end of the section represents the higher

S/S 2S/S 1

Fault

Figure 1: Normal feeding (no ‘Tee’ feed or ‘Overhang’).

S/S 2S/S 1Fault

Figure 2: Branch in section forms a ‘Tee’ feed.

Power Supply System Analysis, Design and Planning 173

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

S/S 2S/S 1Fault

Figure 3: ‘Overhang’ with positive connections remote from the substation.

impedance, in order to determine the required settings (see Figs. 2 and 3). The risk is that neither circuit breaker may trip under a fault condition. An ‘overhang’ is the extreme form of a ‘Tee’ feed in electrical circuit terms.

3.3 Approach adopted

As a consequence of the above, it was decided that hand calculations were not appropriate for this project. Instead, the process was undertaken through use of a calculation spreadsheet (PB-ProCalc) with data inputted via a customised front end template, incorporating the relevant formulae contained within Sections 8.3 & 8.7 of the client’s process document [3]. The calculations were also modified to take account of the client’s specific requirements within the guidance document [4]. The main changes from the client’s process document are clearly defined in his guidance note [4]. The designer is instructed to exclude any allowance for rail joints and bonding resistances. A 7.5% tolerance is to be added to the settings to compensate for impedance relay tolerances. Any cables over 15m in length are to be separately identified and included in the calculations. In order to validate the accuracy of the spreadsheet, a full check of the formulae within the spreadsheet was carried out using an independent Engineer within Parsons Brinckerhoff (PB). In addition, the spreadsheet was tested against one of the worked examples in the clients process document [3] and against the example ‘Tee’ feed calculation results contained in the clients Guidance document [4]. As a further means of verifying the accuracy of the spreadsheet, a second independent set of calculations were undertaken using Network Rail ‘Tee’-feed computer program [5] for all of the electrical sections on the project. The Proposed Approach was documented [6] and submitted to the client, and formal acceptance received prior to implementation.

3.4 Modelling

An equivalent circuit was created for each electrical section based on information derived from design drawings and record drawings (see section headed ‘Detailed Process’ below and the Flow Chart in Appendix A for further details).

174 Power Supply, Energy Management and Catenary Problems

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

In order to simplify the calculation process, and to arrive at worst case, the following rules were applied:

Benefits of reinforcement cabling for running rails around S&C locations and at single rail track circuited areas were excluded from calculations as worst case, on assumption these could be disconnected during maintenance, etc. and therefore not available for traction return

Running rails were assumed to be 109lb/yd (smallest cross section) throughout as per original, unless confirmed otherwise

Conductor rail also assumed to have the smallest cross section (100lb/yd), unless confirmed otherwise

In order to simplify calculations in multi-track areas, where different types of running rail are in parallel, a particular rail size was selected and the length adjusted in the spreadsheet to provide an equivalent impedance.

Cable lengths to substations and TP Huts were typically scaled from the conductor rail and negative layout drawings as exact cable lengths were not typically available

‘Tee’ points and ‘Overhangs’ were worked out separately for positive and negative circuits, making the calculations simpler to handle. This produced exactly the same result as if the elements were combined.

3.5 Fault path

The preparation of equivalent circuits for the positive side (conductor rails) was relatively straightforward, although determination of actual connection points was in some cases difficult due to imprecise record data for some areas. The situation with regard to the negative return circuits was, however, often quite complex. In some instances it was far from clear which equivalent circuit should be used for the return circuit, in particular relating to multi-track areas with substation return connections at differing points for each track (sometimes hundreds of metres apart) and potentially involving an ‘overhang’ situation. The dilemma was how to determine the position/length of the ‘overhang’ in relation to the equivalent circuit for the remainder of the main line in terms of whether a single point for all the return connections should be assumed, or each track worked out separately. If a single point of connection is assumed, the issue arises of where it should be placed: at the electrical mid-point for instance; at the closest connection point; or at the furthest point from the substation. All of these options then impact on the length of the assumed ‘overhang’, so in the end it was decided that all of these options should be tested and the worst case taken. By way of illustration, figures 4 & 5 below show two possible options for calculating fault path, with a fault occurring just beyond the substation return connections. The diagrams illustrate a 4 track railway on the left converging to a 2 track railway on the right, with distributed return connections, and a ring of cables around the junction linking all of the tracks together. In both cases the assumption has been made that some of the running rails (and associated return

Power Supply System Analysis, Design and Planning 175

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

Next substation

Substation

Fault

Figure 4: Return connections at the left hand end.

Next substation

Substation

Fault

Figure 5: Return rail connections taken at the right hand end.

cabling) are unavailable for traction return (shown dashed), due to maintenance activities for instance. The solid lines are assumed to be part of the fault path and included in the calculations, whereas the dashed lines are excluded. The overhang is shown in red for each of the options.

4 Detailed process

4.1 Process flow

The process of carrying out the protection setting calculations are discussed below and presented in the Flow Chart contained in Appendix A.

4.2 Preparation of a single track schematic diagram

A single track schematic diagram (Fig 6) of the positive and negative circuits was first prepared and marked up with all the information necessary for the definition of the geometry, circuit elements (sections of rail(s), or cables) and their dimensions and parameters, i.e. circuit references, boundaries, mileage of important points, rail types, cable sizes, points of change of rail type and identification of the circuit elements together with their respective lengths.

176 Power Supply, Energy Management and Catenary Problems

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

Positive Circuit

- ve

busb

ar

Negative (return) Circuit

- ve

busb

ar

UP MAIN

DOWN MAIN

STATION

E356

UP MAIN

DOWN MAIN

37M

406

1

37M

363

1

37M

345

5

37M

222

1

37M

238

7

37M

169

6

37M

165

2

(a)(b)(c)

(d)

(f)

(j)

(g) 37M

241

9

37M

322

5 '

37M

230

5

37M

230

5

37M

202

3

(n)

(l)(m)(o)

(p)(q)

(k)

37M

411

4

37M

139

5

37M

401

2

37M

397

1

37M

168

9

37M

144

6

(e)

37M

179

5

37M

202

3

Substation

STATION

Figure 6: Extract from a typical track schematic diagram of a traction power supply system (the shades on the negative circuit indicating different rail types).

L4

L3 NEG

(-)-ve

L5

(+)-ve

L1

L3 POS

L2

(+)-ve

VA VB

R3NEGR3POS

R1

R4

R2

R5

Figure 7: Equivalent circuit.

The schematic diagram was then used to derive the equivalent electrical circuit (Fig 7). The left hand diagram indicated the absence or presence of a ‘Tee’-feed in the positive and/or negative circuits, left-hand or right-hand ‘Tee’ feed, whilst the right hand diagram identified the equivalent circuit components, used as input data to the calculation spreadsheet summarised in Table 1. For the purpose of traceability and clarity the schematic diagram contained a list of all the source drawings and documents from which the data has been extracted, together with any assumptions made.

4.3 Calculation of fault impedances

The data from Table 1 is then input into the Calculation Spreadsheet (PB-ProCalc), the sheet automatically determining if a ‘Tee’ feed exists or otherwise

Power Supply System Analysis, Design and Planning 177

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

Table 1: Input data summary table.

Equiv.Circuit Comp.

Ref.Type of circuit element(cable/rail)

Length (feet)

Total length(feet)

(i) Cable type ‘z’ 75 75

(h) Conductor rail type 100lb/yd 6163 6163

(g) Conductor rail type 150lb/yd 889 889

(f) Conductor rail type 100lb/yd 806 806

(e) Conductor rail type 150lb/yd 396 396

(d) Conductor rail type 150lb/yd 228 228

(c) Cable type ‘z’ 100 100

(b) Conductor rail type 150lb/yd 79 79

(a) Cable type ‘z’ 500 500

(m) 2 x Running rail type CEN60E1 327 327

2 x Running rail type CEN60E1 7 7

2 x Running rail type BS113A 294 294

(m) 2 x Running rail type CEN60E1 327 327

2 x Running rail type BS113A 250 250

2 x Running rail type 109lb/yd 51 51

L5 (cab) (k) 4 x Cable type ‘a’ 150 150

282 282L3 NEG

(l)

(l)

L3 POS

L5(Up)

L5(Down)

(n)

L1

L2

Conductor rail type 150lb/yd 282 282(j)

2 x Running rail type CEN60E1

Equiv.CircuitComp.

Ref.Type of circuit element(cable/rail)

Length (feet)

Total length(feet)

L4 (cab) (s) N/A

(r) 2 x Running rail type 109lb/yd 6216 6216

2 x Running rail type 109lb/yd 49 49

2 x Running rail type CEN60E1 340 340

2 x Running rail type BS113A 41

2 x Running rail type BS113A 176

(p) 2 x Running rail type BS113A 1068 1068

2 x Running rail type CEN60E1 82

2 x Running rail type CEN60E1 84

2 x Running rail type CEN60E1 41

2 x Running rail type CEN60E1 340

2 x Running rail type CEN60E1 176

(p) 2 x Running rail type BS113A 1068 1068

2 x Running rail type BS113A 82

2 x Running rail type BS113A 84

2 x Running rail type CEN60E1 198 198

2 x Running rail type 109lb/yd 6216 6216

2 x Running rail type CEN60E1 49

606

(r)

(q)

L4(Down)

2 x Running rail type CEN60E1 198

(o)

(o)

L4(Up)

166

217

364

(q)

and proceeds to compute the fault impedance seen by each circuit breaker feeding each electrical section (A and B) of the two track railway (in the example given). The result can be seen from Fig 8.

4.4 Derivation of protection settings

Impedance relays and Falling Voltage Overcurrent protection were the two types of DC traction feeder protection that existed on the portion of infrastructure involving this project.

178 Power Supply, Energy Management and Catenary Problems

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

SECTION LAYOUT (L1, L2, L3POS, L3NEG, L4, L5)

TEE-FEED CALCULATION

SUBSTATION LIGHT LOAD VOLTAGE VLL (V)

69.714680772.423407145

RADIAL FEED CALCULATION (remote cb tripped)

MAXIMUM FAULT IMPEDANCE

ROUTE SETTINGMAX TRACTION LOAD CURRENT IROUTE (A)

SUBSTN SOURCE IMPEDANCE MIN (RS Ohms)

SUBSTN LIGHT LOAD VOLTAGE MIN [VLL-10%] (V)

'MAXIMUM SAFE' (half-kA from falling voltage curve table)

RECOMMENDED SETTING

CIRCUIT BREAKER B (kA) 6.5

0.0862535

IMPEDANCE CB B (Ohms) 0.0862535

ZROUTE (Ohms) 0.1065

CIRCUIT BREAKER A (kA) 6.5

-VE 'TEE-FEED' LENGTH - L3NEG (miles) 0.053

IB/IA at ZTmax

K' MAX

IB/IA at K' MAX

ZTmax (Ohms) -----

MAX FAULT IMPEDANCE (B) VIA MAIN (Ohms)

CIRCUIT BREAKER A (kA) 7CIRCUIT BREAKER B (kA) 7

0.012711

IMPEDANCE CB A (Ohms) 0.0862535

6000

CROSS-BONDING ALLOWANCE (Ohms) 0

MAX FAULT IMPEDANCE (A) VIA MAIN (Ohms) 0.0862535MAX FAULT IMPEDANCE (B) VIA TEE (Ohms) 0.0111041

MAX FAULT IMPEDANCE (A) VIA TEE (Ohms) 0.0804262

ZA (Ohms) -----

ZB (Ohms) -----

IB/IA at K' MIN 69.7146812.4234071

K' MIN 0.34033912.9382456

VB MINIMUM VALUE (V) 285VA & VB MAXIMUM VALUE [VLL+6%] (V) 837.4

0.0380052790

VA MINIMUM VALUE (V) 285

"EQUATION 23" VALUE 0.0076348Tee-Feed Calcs Required (Yes/No)? NO

TEE-FEED CIRCUIT R3 [=R3POS+R3NEG] (Ohms) 0.0026384

-VE SECTION LENGTH (B to 'T') - L5 (miles) 0.119+VE 'TEE-FEED' LENGTH - L3POS (miles) 0.053

+VE SECTION LENGTH (B to 'T') - L2 (miles) 0.058-VE SECTION LENGTH (A to 'T') - L4 (miles) 1.571

+VE SECTION LENGTH (A to 'T') - L1 (miles) 1.563

Figure 8: Extract from the protection setting calculations spreadsheet (PB-ProCalc) illustrating the calculation of fault impedances and protection settings.

Power Supply System Analysis, Design and Planning 179

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

4.4.1 Impedance relays For impedance type relays, 7.5% was added to the value derived in the

box headed ‘Maximum Fault Impedance’ to determine the actual figure (‘Maximum Safe’) to be used for the settings.

Recommended Settings were then derived manually by rounding up to the next 2.5mΏ, but in any event to be no more than 20% higher than those given for ‘Maximum Safe’ setting to ensure proper discrimination with the circuit breakers feeding the next electrical section.

In order to avoid unnecessarily changing existing settings, where the existing setting is between ‘Maximum Safe’ and 20% above ‘Maximum Safe’, then the recommendation has been to leave the setting unchanged

Additionally a Direct Acting Overcurrent Electromagnetic Trip is set at a higher ’common’ setting to cater for close up faults.

4.4.2 Falling voltage overcurrent protection In the case of Falling Voltage Overcurrent protection which is

principally an electromagnetic device mounted within and forming part of the mechanism of a DC circuit breaker, the settings were derived by converting the manufacturer’s standard protection curves to an impedance table (Fig 9) showing settings (kA) against impedance. The actual ‘Maximum Safe’ setting is determined by taking the impedance value from the calculation spreadsheet i.e. ‘Maximum Fault Impedance’ and then reading off the required setting in kA (rounded down to next kA value on the chart if the impedance is mid way between settings)

4.5 Route setting

This is the setting required on a particular electrical section which will allow train services to operate without resulting in ‘nuisance tripping’ and is normally advised by the client. Any settings should normally be above this value.

4.6 Summarising of results

The settings required for all of the electrical sections between adjacent substations (or substation and TP Hut) were then summarised on A4 sheets, in order that all the information relevant to those sections was available from one sheet. In all cases ‘Category 1’ safe settings were achieved (based on worst case data and feeding arrangements, hence not requiring any operational restrictions).

5 Further development

Since undertaking the original calculations, further work has taken place to determine whether network modelling would help in determining worst case fault scenarios in complex areas and possibly offer an alternative means of

180 Power Supply, Energy Management and Catenary Problems

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

Set

tin

g

(A

)

10000 9500 9000 8500 8000 7500 7000 6500 6000 5500 5000

46 52 58 65.5 73 81 89 98 107 118 129 Impedance (milliΩ)

Figure 9: Chart of overcurrent settings versus impedance including half (kA) settings (for circuit breaker type RJR530L).

independently checking the spreadsheet results. Proprietary nodal analysis modelling software (B2Spice) was used for this purpose, as it requires little training and allows circuits to be built up easily from standard components. It also allows components to incorporate formulae, such that the operator only has to enter data in terms of along track length (feet, metres, miles, etc), rather than having to work out each component separately. Figure 10 above illustrates a typical circuit built using B2Spice, and has been arranged so that it reflects the schematic diagram in fig 6, with the positive circuit shown at the top and the return circuit (running rails) at the bottom.. Each track has been represented separately (in this case a 2-track railway), as it is quite often the case that each track will have different rail types, hence all changes in rail types, both positive and negative, can be fully incorporated into the model. If required, cross-bonding of running rails at regular intervals can be introduced, although generally omitted in the case illustrated, other than at the tee point. Once built, faults can be introduced where required and voltages at substations ‘A’ and ‘B’ adjusted to determine worst case fault conditions under radial or tee feed conditions.

Power Supply System Analysis, Design and Planning 181

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

STATIONCable (c)

228 ft (d)

R3 (pos + neg)B

VA

R5

Substation

Cable (k)

Cable (a)Cable (i)

V

R4

R2

889 ft (g)6163 ft (h) 806 ft (f) 396 ft (e) 79 ft (b)

6216 ft (r) 606 ft (q) 1068 ft (p) 364 ft (o) 327 ft (m) 301 ft (l)

R1

BA

282 ft (j+n)

Running Rails

Conductor RailConductor Rail

Running Rails

Tee pos

Tee neg

750

0*Cableneg

750

933.07

51*Runrail109

75*Cablepos

79*Conrail150

250*Runrail113198*RunrailRT60

84*Runrail113 327*RunrailRT60

228*Conrail150396*Conrail150

82*Runrail113176*RunrailRT60

340*RunrailRT60

38*Cableneg

-24.30u

6216*Runrail109

49*Runrail109

41*Runrail113

6216*Runrail109

49*RunrailRT60

41*RunrailRT60

6163*Conrail100 889*Conrail150

327*RunrailRT60

7*RunrailRT60

294*Runrail113

500*Cablepos

282*Conrail150

282*RunrailRT60

84*RunrailRT60

198*RunrailRT6082*RunrailRT60176*Runrail113

340*RunrailRT60 1068*Runrail113

1068*Runrail113

806*Conrail100

100*Cablepos

Figure 10: Detailed equivalent circuit (using B2Spice) showing elements extracted from the schematic and summary tables.

The models were found to produce identical results to the spreadsheets, hence proving to be a very effective way of checking the PB-ProCalc results. This calibration then, in effect enhances confidence in the PB-ProCalc for use as a reliable tool for this type of application.

6 Discussions and conclusions

It was originally thought that the enhancements and reinforcement to the negative bonding arrangements as described in [1], together with changes to conductor rail size, would logically lower the associated electrical impedances in comparison to the existing infrastructure. Benefits may have been realised in the form of allowing increases in (current based) protection settings, thus permitting higher train currents in section. However, the overall impact was seen to be minimal. This was due to a range of factors which included modifications to the S&C layout and associated detailed electrical feeding arrangements, together with the application of the methodology contained in the client’s process document. This was further supplemented by the corresponding guidance note [4], namely working within the parameters of 7.5% when undertaking the calculations, thus allowing retention of many existing settings. If one was to stay within parameters of 2.5%, as suggested by [3] then definite changes would have been warranted. Consequently, the resultant sensitivity of the calculations to the actual negative bonding reinforcement was seen to be relatively low. Moreover, the majority of settings calculated were noted as being close to existing and therefore not necessitating any changes. Only in a few instances were recommendations made to change settings (actually requiring settings to be reduced). Although no major changes were perceived, this exercise was still seen to be of great benefit in that it provides a solid basis for future applications

182 Power Supply, Energy Management and Catenary Problems

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

when ascertaining these types of protection settings. This approach was considered pragmatic and gave a scientific means of calibration between the spreadsheet mathematics and software. Moreover, the method allows for further refinement and development as changes take place in the future. The further development work undertaken has provided additional confidence in the spreadsheet and methods developed, offering an alternative approach for consideration when undertaking calculations in the future.

Acknowledgements

The authors would like to thank Network Rail for their permission to publish this paper. The support of Thomas Palfreyman, Head of Electrification, PB Ltd in developing this calculation process and spreadsheet, and in reviewing this paper, is also recognised. Much of this paper has been reproduced from the paper entitled ‘DC protection calculations – an acceptable approach’, authors R. Leach, D. Tregay & M. Berova, first presented at the Eleventh International Conference on ‘Computer System Design and Operations in the Railway and other Transit Systems’ (COMPUTERS IN RAILWAYS XI) and can be found in section 6, page 425, of the book of conference papers (WIT Transactions on the Built Environment, Volume 103), © 2008 and is reproduced with permission of WIT Press, Southampton, UK.

References

[1] Development of an Improved Traction Return System, Eur Ing Raymond Leach and Dennis Tregay, paper Railway Engineering – 2007, 9th International Conference, London, UK, 20/21 June 2007.

[2] NR/SP/ELP/21051 ‘Calculation of Protection Settings for DC Circuit Breakers’, Issue 2 dated Dec.2005

[3] NR/GN/ELP/27006 ‘Calculation of Protection Settings for DC Track Feeders, Issue 2 dated April 2006

[4] Network Rail Southern Region Power Supply Upgrade Project - Guidance Note A437-00-DC-32031 ‘DC Protection Setting Calculation’, Issue C1.0 dated 11 May 2004

[5] Network Rail Computer Programme “RUN FILE DC3.EXE” [6] Parsons Brinckerhoff (PB) Methodology for Undertaking Protection Setting

Calculations associated with re-modelling and negative bonding changes (Issue 1 dated 07/09/06)

Power Supply System Analysis, Design and Planning 183

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

Appendix A: Flow-chart of the protection setting calculation process for the Tee feed case

Yes

No Analyse the electrical section layout to determine worst case scenario

Establish the type of electrical section equivalent diagram

Using the existing and As Built drawings populate the schematic diagrams with the coordinates (in Miles and Feet) of important points, including mile posts, points of cable connections, points of change of conductor / running rail type, point tips, etc.

Is the electrical section over switches

or crossings?

Provide existing records drawings, including: •Comprehensive Track Diagrams •Arrangement of conductor rail, hook switches and jumper cables •Arrangement of track circuits & negative bonding •Others, e.g. Signalling plans

Provide survey drawings showing the existing arrangement of the permanent way, conductor rail and negative bonding

Obtain all necessary input data

Provide relevant standards, guidance notes and other instructions

Produce a schematic diagram for each electrical section based on the Comprehensive Track Diagram (CTD), including the conductor rail and the negative bonding layout showing points, substations, TPHuts, cable connections, types of conductor and running rails, etc.

Provide drawings showing the As Built arrangement of the Permanent Way, Conductor rail and Negative Bonding

Provide existing records for protection settings calculations, including type of protective devices and current settings

B A

184 Power Supply, Energy Management and Catenary Problems

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10

Note: In plain line feeding case latter comparison stage is omitted.

Yes No

B

Carry out a check & correct error(s)

Is the discrepancy due to alignment remodelling, different contact rail or

negative bonding design or repositioning of the equipment?

No Yes

No Yes

No

A

Using the information in the schematic diagram populate the Summary table with the types and lengths of the equivalent circuit components.

Compare the data describing the equivalent components in the schematic diagram with those in the existing protection settings calculation records

Do the data agree?

Establish the reason for discrepancy

Independent check of the schematic diagram and input data

Error(s) found?

Protection settings – Results (A)

Run NR Protection Setting calculation software (Tee-feed)

Protection settings – Results (B)

Running PB DC Protection Setting calculation spreadsheet

Do Results (A) agree with Results (B)?

Comparison of protection settings results (A) and (B)

Overall independent check

Yes

Power Supply System Analysis, Design and Planning 185

www.witpress.com, ISSN 1755-8336 (on-line) WIT Transactions on State of the Art in Science and Engineering, Vol 39, © 20 WIT Press10


Recommended