Dec 7, 1999 D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning Goals and timeline Overview of Silicon Read out “Stand alone” commissioning Cosmic Ray Stand Barrel / Disk read-out Commissioning in Collision Hall Marcel Demarteau Fermilab Outline Director’s Review on Installation and Commissioning
Transcript
Page 1: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

DØ Silicon Hookup and Commissioning

Goals and timeline Overview of Silicon Read out “Stand alone” commissioning Cosmic Ray Stand Barrel / Disk read-out Commissioning in Collision Hall

Marcel DemarteauFermilab

Outline

Director’s Review on Installation and Commissioning

Page 2: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Goals

Ensure data integrity at the level of 1014 - 1015, i.e allow for loss of 1 bit in 1014 - 1015 bits transferred

Provide adequate operating margin for device Ensure adequate diagnostics tools and controls Exercise control logic Exercise Data Acquisition and filtering scheme Exercise offline software

Timeline

Commission read out electronics in phases “on the bench” without detectors attached

Integrate final components as soon as available Read out small scale setup in final configuration Enlarge scope of read out

Page 3: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Current Status

Complete read out system installed in cleanroom in LabC Final version of all read out components, except Interface

Board System run in checksum mode in Level 3 node

» SVX chips downloaded to read out set data value

» All channels read out; data constant

» Calculate checksum (sum of all bits) in VBD

» Data transferred to L3 node; checksum compared

» If checksum different: read in and analyze even

Page 4: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

A) Ran with multiple VME Read out Buffer (VRB) boards, without low mass cable and long transmission line, with direct regeneration of signals at hdi, 3-chip hdi’s only

System equivalent of ~22,000 channels

Data transfer on VME at ~ 12 Mbytes/s

Very low noise on data transfer backplane Proper handshaking between read out elements Data integrity > 1013

(~ 1 non-fatal error every ~30 minutes)

B) Ran with single chain (hdi) in close to final configuration, including low mass cable, 30’ 3M/50 conductor cable. Optimized impedance matching for data and control lines on sending and receiving ends

Successfully operated all hdi types Mapped out operating margin for all hdi types Data integrity > 1013 for all hdi types with

comfortable operating margin

C) Written raw data to disk, unpacked and analyzed “offline” within L3 framework and online monitoring program (Examine)

Page 5: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

DØ - D7 Data bus lines

Clock strobe

Read out at 53 MHz

DValid

18.8 nsStrobe channel id Strobe data

7-8 ns Operating Margin

1.00E-15

1.00E-14

1.00E-13

1.00E-12

1.00E-11

1.00E-10

1.00E-09

1.00E-08

1.00E-07

1.00E-06

1.00E-05

1.00E-04

1.00E-03

1.00E-02

1.00E-01

1.00E+00

0 2 4 6 8 10 12 14 16 18

WCLK Delay (nsec) (w.r.t. D7 rising edge)

"By

te"

Err

or

Ra

te

3-CHIP (No R||) 9-CHIP (R||=140 Ohms) 3-CHIP (R||=100 Ohms)

Upper limits

Bus lines D0/D7

WCLK and DVALID

signal risetime of 2-3 ns

Page 6: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Schedule and Resources

12/05/99: Expand to 6 chains with low mass configuration

12/15/99: Implement new interface board

» 50 80 conductor cable with SVX power provided through cable

» monitoring capabilities added

Verification of data acquisition and data integrity will be ongoing effort

Task Resource bckg FTE Time

Read-out M. Demarteau PhysF 0.2 f or duration

M. J ohnson PhysF 0.2 f or duration

A. J uste PhysF 1.0 f or duration

A. Lefl at PhysU 1.0 03/ 00 - 06/ 00

M. Utes EEF 0.5 f or duration

Y. Zverev EEU 1.0 f or duration

OPEN Phys. 1.0 f or duration

Page 7: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Cosmic Ray Setup

Install up to 12 ladders in spare Be support structure and exercise full read out system, DAQ, L3 and on/offline software, controls and monitoring

First step in trying to operate full barrel diskTitle:C:\Silicon\Cables\10%test2.eps Creator:AutoCAD PSOUTPreview:This EPS picture was not savedwith a preview included in it.Comment:This EPS picture will print to aPostScript printer, but not toother types of printers.

Array of 4 scintillator counters form external trigger

Momentum analyzing steel, pT

> 2 GeV/c

Data Rate ~ 1 cosmic/min

Ladder installation in progress

Page 8: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Setup

6 ladders read out through low mass cable in final configuration

6 ladders read out through high mass cable: Total of 9216 channels

Barrels will be cooled and interlocked First cosmic ray recorded 12/20/99

Ingredients

Detector Control and Monitoring Secondary Data Path Data Acquisition Online data monitoring (Examine)

Page 9: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Detector Controls and Monitoring

All slow controls and monitoring uses 1553 protocol1553 interface to Si detector only available with new Int.Brd.

DetectorDetector

Readout CrateReadout CrateControls CrateControls Crate

UNIX Hosts

Control Room PCs

EPICS Clients: SVX Download Low Voltage High Voltage 1553 Devices Rack Monitor

EPICS Clients: SVX Download Low Voltage High Voltage 1553 Devices Rack Monitor

Controls

Ethernet

ORACLEORACLE

HardwareDatabase

EPICS DB GeneratorEPICS DB Generator

1553

Download of Sequencer and SVX chips, not optimized SVX and bias Voltage control done, need implementation

1553 Monitoring devices, currents, temperatures Cooling monitoring and interlock Oracle database design population and interface

Available

In progress

Page 10: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Secondary Data Path

DetectorDetector

Readout CrateReadout Crate

Host Processor: Calibration

Host Processor: Calibration

ORACLEORACLE

HardwareDatabase

PwrPC

PwrPC

Motorola 68k or Power PC

Ethernet

PTP Connection

Intended for calibration processes and monitoring

For Silicon: calculation of pedestals and gains

Front-End software finished as stand alone

Available

In Progress Porting to cosmic ray setup Jan 00 Exercise system Feb 00 Database interface first pass March 00 Database retrieval April 00

L3 NodeL3 Node

Page 11: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Run Configuration

Module addressing and read out » chip id, pedestal, gain, ladder barrel, Temp address, I

address

Task Resource bckg FTE Time

Epics Dwnld D. Buchholz PhysU 0.1 f or duration

H.M. Wang PhysU 0.5 f or duration

HV / LV D. H. Zhang PhysF 0.2 f or duration

1553 F. Bartlett PhysF 0.2 f or duration

G. Savage CPF 0.2 f or duration

D.H. Zhang PhysF 0.4 f or duration

2nd DP D. Buchholz PhysU 0.1 f or duration

X.L. Fan PhysU 0.5 f or duration

L.J . Pan PhysU 1.0 until 01/ 00

OPEN Phys. 1.0 f or duration

Hardware DB X.L. Fan PhysU 0.5 f or duration

Production DB OPEN Phys. 1.0 f or duration

OracleDatabase

Readout ConfigurationReadout Configuration

Geometry parametersGeometry parameters

Calibration ConstantsCalibration Constants

Monitoring DevicesMonitoring Devices

Control ParametersControl Parameters

Page 12: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Data Acquisition

DetectorDetector

L1/2 Trig SimulL1/2 Trig Simul

L3 SupervisorL3 Supervisor

L3 VRCL3 VRC

Readout CrateReadout Crate

L3 FilterL3 Filter

Collector / RouterCollector / Router

Data Logger

Data Logger

Disk

Data Cable

Data Cable

UNIX Hosts

NT Level 3

Ethernet

Trigger and Readout

Data Distributor

Data Distributor

Control Room PCs

ExamineExamine

All pieces to exercise full data acquisition chain are in place

Read out to L3 system extensively tested

Online Examine SMT analysis code tested on raw data

First pass at full read out with 12 ladder test Dec 99/Jan 00

Will slowly ramp up to enlarge read out and complexity of tools

L3 Tools: data unpacking, hit finding, track reconstruction

Page 13: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Timeline for development Dec 99:

» 6-12 ladder setup and test controls and monitoring Dec 99 - Jan 00:

» Cosmic Ray data taking; online monitoring with Examine Feb 00:

» First pass at L3 filtering and alignment

» First pass at secondary data path Mar 00:

» Database integrationTask Resource bckg FTE Time

L3 R. I llingworth PhysU 1.0 f or duration

P. v. Gemmeren PhysF 0.2 f or duration

V. Sorin PhysU 0.3 f or duration

Examine A. Kubarovsky PhysU 0.5 07/ 99 - 07/ 01

L. Shabalina PhysU 1.0 01/ 00 - 07/ 00

L. Shabalina PhysU 0.5 07/ 00 - 03/ 01

OPEN Phys. 1.0 f or duration

Alignment S. Duensing PhysU 0.3 f or duration

J . Hobbs PhysU 0.2 f or duration

H. Melanson PhysF 0.3 f or duration

T. Trippe PhysU 0.3 f or duration

Offl ine sof tw. E. Barberis PhysU 1.0 f or duration

M. Narain PhysU 0.5 f or duration

Page 14: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

March 15/00:

» Hook up of full H-disk, 48 detectors, 36864 channels; exercise all components

April 1/00:

» Hook up barrel, 72 detectors April 15/00:

» Hook up barrel and F disk, 96 detectors (~10%) May 1/00:

» 15 more detector assemblies to go (5 barrel/disk, 6 F disks, 1+3 H disks)

» one week for read out and debugging per assembly

» Done Aug 15/00

» Note, doubling the time per assembly (23 assemblies) would give completion date of Oct 7/00. Still adequate (7 H disk assemblies can go last)

Timeline

So far discussed development on small scale system (12 ladders) and commissioning of read out system. Move to full subsystem in March 00.

No assembly (barrel or disk) leaves the silicon facility without having been read out.

Page 15: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Meanwhile in the Pit

platformplatform

SEQ

SEQ

SEQ

SEQ

SEQ

SEQ

VRB Controller

Optical Link

1Gb/s

3/6/8/9 Chips

Sensor

V

B

D

V

R

B

V

R

B

V

R

B

V

R

B

68k

Secondary Datapath

VME

Low Mass

3M

1553

NRZ / CLK

SVX EMULATOR

IB

Monitoring Control

L3 HOST

ExamineExamine

Concurrent with work at the silicon facility, a complete shake down of the read out system will take place at the assembly hall of final read out configuration downstream from the interface board, including online data checking (Examine). See M. Johnsons presentation

Page 16: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Barrel and disk hookup at DAB

Hookup of cooling system immediately Run coolant above dewpoint, so no damage to detectors.

Procedure verified at silicon facility Starting 9/26/00, 5 weeks allocated for check out of silicon

detector 1.5 weeks allocated for cabling each detector end.

Note, read out has HDI-enable line, therefore, system can be fully powered at hookup time, thus instant hdi checkout. Procedure should be developed at silicon facility during full barrel/disk tests

Complete Barrel and F disk hookup in 3 weeks.

» Assuming 7days/week, 12hrs/day, this gives ~20 mins of debugging time per hdi

Two additional weeks for debugging complete barrel and F disk assembly. Hookup of H disks in parallel.

Page 17: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Resources

Task Resource bckg FTE Time

Hookup DAB A. Bean PhysU 1.0 f or duration

M. Demarteau PhysF 0.5 f or duration

C. Gerber PhysF 1.0 f or duration

M. J ohnson PhysF 0.2 f or duration

A. J uste PhysF 1.0 f or duration

E. Kajf asz PhysF 1.0 f or duration

F. Lehner PhysF 1.0 f or duration

R. Lipton PhysF 0.5 f or duration

P. Rapidis PhysF 0.5 f or duration

M. Utes EEF 0.5 f or duration

P. Van Gemmeren PhysF 1.0 f or duration

Page 18: Dec 7, 1999D0 Dir Review Inst/Com DØ Silicon Hookup and Commissioning p Goals and timeline p Overview of Silicon Read out p “Stand alone” commissioning.

Dec 7, 1999 D0 Dir Review Inst/Com

Summary

Read out system will be verified continuously. Current level of data integrity for single hdi would be adequate.

Partial barrel with cosmic ray data taking first step to final system configuration

All system components will be exercised at the silicon facility and procedures developed for DAB hookup and commissioning

Many DAQ components exist already in stand alone form,

but are not integrated. All full assemblies will have been read out at the silicon

facility before installation. Development of procedures at facility crucial.

Schedule is tight but feasible


Recommended