+ All Categories
Home > Documents > December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a...

December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a...

Date post: 04-Jan-2016
Category:
Upload: dominic-cunningham
View: 218 times
Download: 2 times
Share this document with a friend
28
December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt and Milorad Popovic Fermilab December 5, 2007
Transcript
Page 1: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 1Chuck Ankenbrandt Fermilab

Muon Collider Design Workshop @BNL

Project X as a Hi-Rep-Rate Driver for a Muon Collider

Chuck Ankenbrandt and Milorad Popovic

Fermilab

December 5, 2007

Page 2: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 2Chuck Ankenbrandt Fermilab

Outline Introduction

What’s Project X? There are various ways to use Project X to drive a muon collider

– High repetition rate or low repetition rate

– 8 GeV protons or 50 GeV protons

– Use/don’t use Main Injector

– To drive a low/high emittance muon collider

– My talk / Dave Neuffer’s

A high rep. rate, 8 GeV front end based on Project X Summary

Page 3: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 3Chuck Ankenbrandt FermilabMuon Collider & Ionization Cooling Issues - Y. Alexahin, FNAL December 5, 2006

Muon Collider parameters

Low Emitt. High Emitt.Energy (TeV) 0.75+0.75 (=7098.4)Average Luminosity (1e34/cm^2/s) 2.7 1Average bending field (T) 10 8.33Mean radius (m) 361.4 363.8Number of IPs 4 (350m/2 each) 2 (200m each)P-driver rep.rate (Hz) 65 60Beam-beam parameter/IP, 0.052 0.1 (cm) 0.5 3Bunch length (cm), z 0.5 2

Number of bunches/beam, nb 10 1

Number of muons/bunch (1e11), N 1 12

Norm.transverse emittance (m), N 2.1 13

Energy spread (%) 1 0.1Norm.longitudinal emittance (m), ||N 0.35 0.14

Total RF voltage (GV) at 800MHz 406.6 103c 0.26103c

RF bucket height (%) 23.9 0.6Synchrotron tune 0.723 103c 0.02103c

+ - in collision / proton 0.15 /2 0.158GeV proton beam power (MW) 1.1 0.6

Low emittance option (advanced): owing to ideas by Yaroslav Derbenev (HCC, PIC) much lower 6D emittances seem to be feasible than previously thought of.

High emittance option (baseline): conceptually follows 1999 PRSTAB Muon Collider Collaboration report

Page 4: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 4Chuck Ankenbrandt Fermilab

Introduction to Project X The heart of Project X is an 8-GeV H- linac based on ILC

technology. Project X will stack beam into the Recycler to allow Main

Injector to accelerate 2.2 MW of beam to 120 GeV. Excess beam cycles will be available at 8 GeV.

http://www.fnal.gov/directorate/Fermilab_AAC/AAC_July_07/

http://www.fnal.gov/directorate/Fermilab_AAC/AAC_July_07/Agenda_Aug_07_Rev4.htm

Page 5: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 5Chuck Ankenbrandt Fermilab

Overview of Project X

120 GeV fast extraction spill1.5 x 1014 protons/1.4 sec2 MW

8 GeV H- Linac9mA x 1 msec x 5 Hz

8 GeV extraction1 second x 2.25 x 1014 protons/1.4 sec200 kW

Stripping Foil

Recycler3 linac pulses/fill

Main Injector1.4 sec cycle

Single turn transfer @ 8 GeV0.6-8 GeV ILC

Style Linac 0.6 GeV Front End Linac

From Dave McGinnis’ talk

Page 6: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 6Chuck Ankenbrandt Fermilab

Possible site layout of Project X

Page 7: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 7Chuck Ankenbrandt Fermilab

H- Injection – Transverse painting (Dave Johnson)H- Injection – Transverse painting (Dave Johnson)

End 1st injection

End 2nd injection

End 3rd injection

Foil (injected beam)

Closed orbit movement

Move off foil

Start injection Stripping foil

Closed orbit

Painting Waveforms

0

0.2

0.4

0.6

0.8

1

1.2

0 50 100 150 200 250 300 350

Injection Turns

Rela

tive A

mp

litu

de

Horizontal PaintingVertical PaintingHorizontal Removal

pulse 1 (1ms) pulse 2 (1ms) pulse 3 (1ms)

remove from foil (200 ms)

Final distribution after painting to 25 at H of 70 and V of 30 (STRUCT)

H-Foil H+ inj

abs

painting

Chicane (DC)

Cartoon of phase space painting with 3 linac pulsesHorizontal orbit motion during painting

Painting waveform for Recycler Injection

Aug 8, 2007 AAC meeting D. Johnson

Page 8: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 8Chuck Ankenbrandt Fermilab

Outline, revisited Introduction

What’s Project X? Ways to use Project X to drive a muon collider

Page 9: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 9Chuck Ankenbrandt Fermilab

Project X: Possible 8 GeV Upgrades

8 GeV Upgrade paths Baseline Extreme Enough?Pulse duration (msec) 1 3 1Beam current (mA) 9 25 25Repetition rate 5 10 10Beam power (MW) 0.36 6.00 2.00

The last column has about the same Recycler intensity as when the baseline Project X accumulates 3 cycles for the Main Injector.

Page 10: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 10Chuck Ankenbrandt Fermilab

Using Project X to make muons for a collider

Proton beam power of 2 MW may be enough to drive a high-luminosity, low-emittance muon collider.

The challenge is to “repackage” the protons into a useful form for a muon collider. It’s not clear what will work best for a muon collider or a neutrino

factory, so flexibility would be nice at the conceptual design stage.

– The rms bunch length should be 3 nsec or less. (Really?)

– A repetition rate of 60 Hz would match the muon lifetime at 750 GeV. (However, we may end up at a different energy.)

– Will we use one or two proton bunches to make each pair of muon bunches? Or to make multiple pairs?

– How many pairs of muon bunches will we make at a time? “Buffer rings” (two 8 GeV storage rings with large acceptances

and small circumferences) could provide the needed flexibility.

Page 11: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 11Chuck Ankenbrandt Fermilab

A specific hi rep. rate, 8 GeV example Use Accumulator(-like) and Debuncher(-like) rings.

Acc and Deb are leftovers from Fermilab’s Antiproton Source They are not very deep underground; maybe move to new tunnel?

Paint to large (~200 pi) transverse emittances in rings with small circumference to control space charge. Could strip directly into “Accumulator” or do multi-turn

transverse stacking from Recycler to “Accumulator”. Small circumference means more favorable bunching factor. Scale from space charge tune shift (~0.04) in Recycler ring.

Use h=12 and h=24 rf to make 12 ~rectangular bunches. (Note possible constraints on h1, h2: Circumference ratio) Transfer two bunches at a time to the “Debuncher”. Do a bunch rotation in the “Debuncher”. Deliver two bunches at a time to the target at 60 Hz.

Page 12: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 12Chuck Ankenbrandt Fermilab

Picture of the concept

Page 13: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 13Chuck Ankenbrandt Fermilab

ESME-One bunch

Page 14: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 14Chuck Ankenbrandt Fermilab

Twelve bunches in Accumulator

Page 15: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 15Chuck Ankenbrandt Fermilab

Shorter bunches in Accumulator

Page 16: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 16Chuck Ankenbrandt Fermilab

Longitudinal emittance scaling In the Recycler, beam will be painted to a longitudinal

emittance of about 0.25 eV sec per bunch After transfer via transverse stacking to the Accumulator,

the total longitudinal emittance will be ~ 84 times 0.25 If we form 12 bunches, each will have 84(0.25)/12 = 1.75

eV sec. If we reduce the bunch length to a total t of about 10

nsec, then E will be about 0.175 GeV = +/- 0.09 GeV So E/E = +/- 1% , well within the momentum aperture.

Page 17: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 17Chuck Ankenbrandt Fermilab

Space-charge tune shift scaling Scale from incoherent tune shift of 0.04 in Recycler

The energy (8 GeV) and the total number of protons are the same in the Recycler and the Debuncher.

The transverse stacking into the Debuncher raises the transverse emittances by a factor of eight.

The bunching factor goes down by a factor of nine.

B

N

n

tot2

~

CB lar

2C

B rfbr

2

1

rf

l

br

ar

B

B

8

Page 18: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 18Chuck Ankenbrandt Fermilab

Flexibility Above example was for 60 Hz; however…

Could form fewer bunches in rings Could combine bunches externally (cf. next slide) Rep rate as low as 10 Hz (once per linac cycle) may be feasible

Analogy: Tevatron Collider Started with one pair of bunches at design luminosity of 1030

Went to 3x3, mainly to reduce events per crossing Implemented electrostatic separators and went to 6x6 Now at 36x36

Page 19: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

Very High Rep Rate via CW Linac For a muon collider rep rate of 65 Hz with ten bunch pairs,

the front end might run at 650 or 1300 Hz. A 50-GeV neutrino factory might also run at ~ 1 kHz. Those rates might best be delivered via a CW linac. Rol Johnson, CA and MP wrote a letter to the Fermilab

Steering Group suggesting that possibility. Arguments for a CW linac:

It’s easier to operate a superconducting linac CW (no transients) Low peak rf power => lots of inexpensive klystrons Jlab is existence proof Could be a multipurpose facility

December 5, 2007 19Chuck Ankenbrandt Fermilab

Page 20: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 20Chuck Ankenbrandt Fermilab

An external combiner to reduce rep rate at target

Several bunches enter

Bunches converging upon exit

Page 21: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 21Chuck Ankenbrandt Fermilab

Summary: Project X for Muon Collider A flexible way to deliver short intense 8-GeV proton

bunches from Project X to a muon collider target station at various rep rates has been found.

The scheme uses the full 8-GeV capability of Project X upgraded to 2 MW of beam power.

The scheme uses Accumulator-like and Debuncher-like storage rings.

A CW linac could provide even higher rep rates. Dave Neuffer will talk about using the Main Injector as

part of the strategy.

Page 22: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 22Chuck Ankenbrandt Fermilab

Backup Slides

Page 23: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 23Chuck Ankenbrandt Fermilab

Pros and Cons

Page 24: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 24Chuck Ankenbrandt FermilabMuon Collider & Ionization Cooling Issues - Y. Alexahin, FNAL December 5, 2006

Muon Collider parameters

Low Emitt. High Emitt.Energy (TeV) 0.75+0.75 (=7098.4)Average Luminosity (1e34/cm^2/s) 2.7 1Average bending field (T) 10 8.33Mean radius (m) 361.4 363.8Number of IPs 4 (350m/2 each) 2 (200m each)P-driver rep.rate (Hz) 65 60Beam-beam parameter/IP, 0.052 0.1 (cm) 0.5 3Bunch length (cm), z 0.5 2

Number of bunches/beam, nb 10 1

Number of muons/bunch (1e11), N 1 12

Norm.transverse emittance (m), N 2.1 13

Energy spread (%) 1 0.1Norm.longitudinal emittance (m), ||N 0.35 0.14

Total RF voltage (GV) at 800MHz 406.6 103c 0.26103c

RF bucket height (%) 23.9 0.6Synchrotron tune 0.723 103c 0.02103c

+ - in collision / proton 0.15 /2 0.158GeV proton beam power (MW) 1.1 0.6

Low emittance option (advanced): owing to ideas by Yaroslav Derbenev (HCC, PIC) much lower 6D emittances seem to be feasible than previously thought of.

High emittance option (baseline): conceptually follows 1999 PRSTAB Muon Collider Collaboration report

Page 25: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 25Chuck Ankenbrandt Fermilab

The Primary Matrix

Left wing Center Right wing

Hillary   Rudy

Barack   Mitt

John   John

Ankle-biters   Ankle-biters

Page 26: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 26Chuck Ankenbrandt Fermilab

Choices Hi rep rate or low rep rate? 8 GeV or 50 GeV? Ankenbrandt or Neuffer?

Page 27: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 27Chuck Ankenbrandt Fermilab

Rep. Rate High   Low

Low   High

Ep 8 GeV   50 GeV

The Front End Matrix

Page 28: December 5, 2007 1 Chuck Ankenbrandt Fermilab Muon Collider Design Workshop @BNL Project X as a Hi-Rep-Rate Driver for a Muon Collider Chuck Ankenbrandt.

December 5, 2007 28Chuck Ankenbrandt Fermilab

Introduction

Young-Kee’s Steering Group likes Project X. Pier asked: Can Project X be used for a muon collider? We can and should provide an affirmative, simple, flexible

response to Pier and the Steering Group.


Recommended