+ All Categories
Home > Documents > Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given...

Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given...

Date post: 13-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
20
Decommissioning, Decontamination and Demolition of the Macau Power Station Executive Summary (English) Environmental Impact Assessment 3 August 2016 Environmental Resources Management 16/F, Berkshire House 25 Westlands Road Quarry Bay, Hong Kong Telephone 2271 3000 Facsimile 2723 5660 www.erm.com
Transcript
Page 1: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

Decommissioning,

Decontamination and

Demolition of the Macau Power

Station

Executive Summary (English) –

Environmental Impact Assessment

3 August 2016

Environmental Resources Management 16/F, Berkshire House

25 Westlands Road

Quarry Bay, Hong Kong

Telephone 2271 3000

Facsimile 2723 5660

www.erm.com

Page 2: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

ERM consulting services worldwide www.erm.com

Decommissioning, Decontamination

and Demolition of the Macau Power

Station

Executive Summary (English) – Environmental Impact

Assessment

Document Code: 0346562 EIA Executive Summary (English) Cover and

Flysheet.docx

Environmental Resources

Management

16/F Berkshire House

25 Westlands Road

Quarry Bay

Hong Kong

Telephone: (852) 2271 3000

Facsimile: (852) 2723 5660

E-mail: [email protected]

http://www.erm.com

客戶 :

Companhia de Electricidade de Macau

GMS No:

0346562

內容摘要: 日期:

3 August 2016

Environmental Impact Assessment (EIA) Study for the proposed

Decommissioning, Decontamination and Demolition of the Macau

Power Station. The EIA Study covers impacts on air quality, noise,

land contamination, water quality, waste management, and ecology.

Recommendations on appropriate mitigation measures have been

given.

審批:

Frank Wan

Partner

Revision Description Prepared Checked Approve Date

1 Executive Summary (English) – Environmental Impact Assessment MTO MTO FWan 3 Aug 16

This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known. Any such party relies on the report at their own risk.

This report has been prepared by Environmental Resources Management the trading name of ‘ERM Hong-Kong, Limited’, with all reasonable skill, care and diligence within the terms of the Contract with the client, incorporating our General Terms and Conditions of Business and taking account of the resources devoted to it by agreement with the client.

We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above.

This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known. Any such party relies on the report at their own risk.

傳閱

內部

公開

保密

Page 3: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

CONTENTS

1 INTRODUCTION 1

1.1 BACKGROUND 1

1.2 EIA STUDY 1

2 PROJECT DESCRIPTION 2

2.1 SCOPE AND NATURE OF THE PROJECT 2

2.2 SITE LOCATION AND BRIEF SITE HISTORY 2

2.3 DEMOLITION PLAN 2

2.4 TENTATIVE IMPLEMENTATION PROGRAMME 3

3 SUMMARY OF EIA FINDINGS 5

3.1 AIR QUALITY 5

3.2 NOISE 5

3.3 LAND CONTAMINATION 6

3.4 WATER QUALITY 8

3.5 WASTE MANAGEMENT 9

3.6 ECOLOGY 9

4 ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS 10

5 CONCLUSION 11

Page 4: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

1

1 INTRODUCTION

1.1 BACKGROUND

Companhia de Electricidade de Macau (CEM) is the operator of the Macau Power

Station (CMC or the “Project Site”) since the power supply concessions in

1985. Figure 1.1 shows the location of the CMC. The CMC, with a

generation capacity of about 64MW, has been in service for over 30 years and

the generation units have already exceeded their design life. CMC is now

mainly used as a source of back-up capacity due to its low efficiency. In

addition, there are also some old diesel-fired generation units on-site which

are currently out of services.

As the Macau’s economy continues to grow rapidly, there is a high demand of

land for public housing development. In 2012, the Government of Macau

Special Administrative Region (MSAR Government) informed CEM that it

would like CEM to decommission the CMC and return the concession land to

the government for public housing development. In response to the

government’s initiatives, CEM proposes to undertake the Decommissioning,

Decontamination and Demolition (DDD) of the CMC (hereafter referred to as

the Project).

1.2 EIA STUDY

In accordance with the list of designated projects for the administrative

environmental impact assessment (EIA) framework《需進行環境影響評估的

工程項目類別清單》(試行), this Project is classified as a Designated Project

under Item 3–Public utility electricity power plant of Part II–

Decommissioning Projects and therefore an EIA should be undertaken.

ERM-Hong Kong, Limited (ERM) is commissioned by CEM to undertake an

EIA Study for the Project in accordance with Guidelines for Preparation of

Environmental Impact Assessment Report (編寫環境影響評估報告書指引)(2014年

版) published by the Environmental Protection Bureau (DSPA).

This is the Executive Summary of the EIA Report, which describes the nature of

the Project, potential environmental impacts associated with the DDD works

and the key findings and recommendations of the EIA Study.

Page 5: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

2

2 PROJECT DESCRIPTION

2.1 SCOPE AND NATURE OF THE PROJECT

The Project includes DDD of the CMC and the off-site oil pipelines between

CMC and the pier located at Avenida da Amizade. General layout plan of the

CMC is given in Figure 2.1.

2.2 SITE LOCATION AND BRIEF SITE HISTORY

The Project Site is located at the junction of Avenida de Venceslau de Morais and

Rua dos Pescadores and surrounded by mixed of industrial/commercial

buildings and residential developments in the northern part of the Macau

Peninsula (see Figure 1.1). The surrounding environment of the Project Site is

shown in Figure 2.2.

Before CEM took over the operation of the CMC, the site has been used for

power generation for over 70 years. The development of CMC can be

described in four stages as presented in Table 1.

Table 1 Historical and Existing Generators

Stage Engines Years of Installation Status

1 D1 - D8 1905 - 1933 Already demolished and removed from Project

Site

2 D9 – D14 1933 - 1962 Already demolished and removed from Project

Site

3 D15 – D21 1964 - 1971 Out of service, still remain on Project Site

T22, T23 1973 Not operating, for back-up and emergency

service only (15.12 MW each)

T24 1973 Already demolished and removed from Project

Site

4 D25 – D28 1983 Not operating, for back-up and emergency

service only (8.48 MW each)

2.3 DEMOLITION PLAN

A conceptual demolition approach and sequence have been developed by

experienced DDD specialists. The demolition works will be carried out in 12

demolition zones (A to L) as listed in Table 2 and illustrated in Figure 2.3. It

should be noted that the DDD works will be implemented by appointment of

a DDD Main Contractor who will undertake the detailed design of the DDD

works. The mitigation measures recommended in this EIA Study will be

included in the specification and the findings of the EIA Study will be

developed into environmental performance requirements for the DDD

Contract.

Page 6: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

3

Table 2 Demolition Zones

Zone Description Details of Demolition Works

Zone A Tank Farm Fuel oil tank Nos. 1 – 5, including all

piping and retention wall, but

excluding the foundation of the tanks,

underground piping and cabling

Zone B Oily Water System, Chemical Store &

Water Tank No. A1

All facilities inside the room

Zone C Fuel Oil Treatment Plant All facilities inside the building,

including oil storage and gas and

combustive material storage

Zone D Exhaust Gas Stack and Chimneys Exhaust Gas Stack (including facilities

inside the basement) and chimneys

outside from the engine room up to

the top of the stack, and also including

the supporting frame of the exhaust

Zone E Auxiliary Boiler, Fire Fighting Station,

Pumps & Compressors

All facilities inside the room,

including Auxiliary Boiler, Fire

Fighting Station, Cooling Tower,

Pumps & Compressors

Zone F Gas Turbines Packages T22 & T23 Including adjacent facilities, such as

panels and earthing cubicles

Zone G Cooling Tower & Shelter Storage Area Various cooling towers on the Project

Site

Zone H On-Site Cable & Pipe Trenches All cables and pipes buried in

trenches located on the Project Site

Zone I Fuel Oil, Lube Oil & Diesel Oil Pipe Pipes, tracing from the pier to the

Project site

Zone J D25/D28 New Engine Building All facilities inside the building

Zone K D15/D21 Old Engine Building All facilities inside the building

Zone L CMC Control Building All facilities inside the building

2.4 TENTATIVE IMPLEMENTATION PROGRAMME

The preliminary project implementation programme is described in Table 3.

Table.2 Preliminary Project Implementation Programme

Stage Time

Stage 1 – Preparation April to July 2016 - EIA study and Pre-DDD preparation, eg

building services investigation.

Stage 2 - Implementation May to September 2016 – procurement arrangements for the

DDD Contract.

July to November 2016 – removal of Asbestos Containing

Materials (ACM) by a qualified Asbestos Contractor and

removal of majority of the plant and equipment by CEM

maintenance contractor.

November 2016 to October 2017 (a) – demolition of the above

ground structures and the remaining plant and equipment.

Page 7: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

4

Stage Time

Note:

(a) This is assumed that 2 active demolition zones will be undertaken at the same time. This

duration can be shortened (by about 3 months to July 2017) by increasing the number of

active demolition zones from 2 to 3 at the same time. The key environmental impact

associated with this option will be noise impact, which has been addressed in the noise

impact assessment.

Page 8: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

5

3 SUMMARY OF EIA FINDINGS

3.1 AIR QUALITY

The potential air quality impacts (potential release of asbestos fibres and dust)

associated with the DDD works have been evaluated. The removal,

handling, storage, transportation and disposal of asbestos containing materials

(ACM) will be undertaken in accordance to relevant guidelines published by

the DSPA and Hong Kong SAR Government in order to avoid release of

asbestos fibres to the atmosphere.

Fugitive dust may be generated during the demolition of the concrete

buildings and structures within the Project Site boundary, as well as from

temporary stockpile of excavated soil and dusty materials on site. It is not

anticipated that the removal of about 760m long above-ground section of the

oil pipelines between CMC and the oil jetty east to the Macau Reservoir will

cause adverse air quality impact. With the implementation of the

recommended dust mitigation measures and good construction site practices,

potential fugitive dust emissions will be minimised and unacceptable dust

impacts to the identified air sensitive receivers (see Figure 3.2) is not

anticipated.

Regular dust monitoring and site audits will be carried out during the

demolition works to confirm that the recommended mitigation measures are

properly implemented and verify the findings of the EIA Study.

3.2 NOISE

The DDD works will be carried out during day-time (i.e. 08:00 - 20:00 hrs) on

Monday through Saturday. Powered mechanical equipment will be used for

the DDD works which have the potential to cause noise impact to the noise

sensitive receivers (NSRs) in the vicinity of the Project Site.

A detailed construction noise impact assessment has been undertaken to

predict the noise levels at the representative NSRs (see Figure 4.2) due to the

DDD works. As there are no noise criteria for general construction works

under the Law No.8/2014 - Prevention and Control of Environmental Noise.

Reference has been made to the construction noise assessment criteria

stipulated in the Technical Memorandum on Environmental Impact

Assessment Process (EIAO-TM) issued under Environmental Impact

Assessment Ordinance (EIAO) published by Environmental Protection

Department of Hong Kong SAR Government. Potential noise impacts arising

from general construction works during normal working hours (ie 08:00 to

20:00 hrs on any day not being a Sunday or public holiday under Law

No.8/2014) at the openable windows of buildings were assessed based on the

noise assessment criteria presented in Table 4.

Page 9: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

6

Table 3 Assessment Criteria for General Construction Works other than Percussive

Piling

Sensitive Use Noise Standards (dB(A))

� Domestic Premises 75 dB(A) (30min)

� Educational Institutions including nurseries 70 dB(A) (30min)

� Educational Institutions (during examination periods) 65 dB(A) (30min)

Note:

(a) Reference to Table 1B of the EIAO-TM.

Good construction site practice and noise management have been

recommended to reduce the potential construction noise impact on the

identified NSRs. With the use of practical noise mitigation measures, there

are exceedances (by about 1 dB to 19 dB) of the referenced construction noise

assessment criteria during the day-time period at some of the representative

NSRs due to their close proximity to the Project Site. The impacts have been

minimised with exhausting all practical direct noise mitigation measures,

including the use of temporary movable noise barriers and scheduling of

active zones. Residual impacts are considered temporarily and reversible.

Regular site audits of the DDD works and regular noise monitoring at the

identified NSRs will be carried out to ensure the recommended mitigation

measures are properly implemented and evaluate their effectiveness. In

addition, CEM will facilitate communications with concerned parties on the

residual impacts during the DDD works.

3.3 LAND CONTAMINATION

The historical land uses and operation of the CMC have the potential to cause

land contamination at the Project Site. The potential human health risk

associated with the management of potential contaminated soil and

groundwater which may be encountered during the DDD works have been

evaluated.

Currently, Macau has no locally-derived soil and groundwater contamination

or clean-up standards. In view of the similarity in the physical setting,

development history and land-use framework between Macau and Hong

Kong, and also the fact that groundwater is not abstracted for beneficial uses

in both Macau and Hong Kong, the Risk-Based Remediation Goals (RBRGs)

developed by Environmental Protection Department of the Hong Kong SAR

Government were used for the assessment. As the CMC site will be

subsequently used for public housing development, the criteria for Urban

Residential land use stipulated under the RBRGs were adopted as the

assessment criteria.

As part of the EIA Study, a desktop review, site inspections and interviews

with the operation staff of CMC have been undertaken to identify potential

sources of soil and/or groundwater contamination due to past and present

Page 10: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

7

operations at the Project Site. The review identified data gaps for the

assessment and the potential land contamination hotspots. A preliminary

Site Investigation (SI) programme was conducted at the 12 identified hotspots

which were accessible during the EIA Study. A total of 30 soil samples and

11 groundwater samples were collected. All soil and groundwater samples

were analysed by a HOKLAS accredited laboratory for the Chemicals of

Concern (CoC) as stated in the RBRGs. The results obtained from the SI

programme were used for the land contamination assessment.

Among the 30 soil samples and 11 groundwater samples collected, the

concentrations of the CoC of all samples complied with the RBRGs except for

the following samples. The soil sample collected at 2.5m below ground level

(bgl) from Borehole BH4 was found to exceed the RBRGs with respect to the

Arsenic criterion. The soil sample collected at 3.0m bgl from Borehole BH2,

was found to exceed the soil saturation limit (Csat) for petroleum carbon range

(PCR), C17 -C35. Three groundwater samples collected from Boreholes BH2,

BH4 and BH6 were found to exceed the solubility limit for PCR C17-C35. One

groundwater sample collected from Borehole BH10 was found to exceed the

RBRGs for PCR C17–C35, the solubility limit for PCR C9-C16, C17–C35 and

Chrysene. After demolition of the existing buildings and structures at the

Project Site, further SI will be carried out at those areas which are not

accessible during the EIA Study. The findings of the further SI will be

presented in a Supplementary Contamination Assessment Report for submission

to DSPA.

Based on the findings of the preliminary SI, the total volume of impacted soil

is estimated between 5,860 and 7,500 m3. The volume of contaminated soil

will be updated after the completion of the further SI. The actual

contamination extent and volume of these impacted soil areas will be

determined by a combination of field assessments (ie checking of signs of

stained soil with petroleum products and the present of odour; and scanning

of the soil using a photoionisation detector) during excavation of the Project

Site, and confirmatory sampling and testing to determine whether the soils are

compliance with the land contamination criteria after the buildings are

demolished.

In general, when the RBRGs are exceeded, it triggers the needs of remediation

so as to mitigate the health risk future land users. As groundwater is not

utilised for beneficial uses in Macau, the risk of exposure of the future users

(residents of the public housing development) to contaminated groundwater

is considered low. However, the risk to the construction workers for the

public housing development is considered high. Recommended remediation

methods for the contaminated soil and groundwater have been outlined,

which will be updated based on the findings of the further SI. After that a

Remediation Action Plan (RAP) will be submitted to DSPA for review.

The DDD works will mainly involve above-ground works and hence the

potential exposure of PCR to the site workers will be low. If groundwater is

needed to be pumped to facilitate the demolition works, the groundwater will

be tested to confirm that it complies with the discharge standards to the sewer.

Page 11: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

8

If pollutant concentrations exceeded the discharge standards, the

groundwater will be treated prior to discharge.

Considering the programming constraints and the fact that the impacted soil

layers are relatively thin and near the surface, source removal by excavation of

the impacted soil for off-site treatment (even though the soil PCR

concentrations are within RBRGs) is regarded as the most effective way of

groundwater clean-up at the Project Site and to avoid or minimise potential

impact to construction workers of the public housing development and future

residents of the development. After removal of the impacted soil layer

(which is likely the sources of the groundwater contamination), it is expected

that the groundwater quality will be improved. The excavated soils which

exceeded the RBRGs for Industrial land use or the Soil Saturation Limit

(whichever the lower) will be treated off-site before disposal at the

Construction Waste Landfill per DSPA’s requirement. After the remediation

works, a Remediation Report will be prepared and submitted to DSPA.

In addition, precautionary and mitigation measures have been recommended

to minimise the impact to construction workers during the DDD works,

subsequent construction of the housing development and the future land

users.

To ensure that the recommended mitigation measures are properly

implemented and the DDD works will not cause secondary land

contamination, regular site inspections and verification sampling and testing

of the remediated soils and groundwater to be discharged from the Project

Site will be carried out. The potential impacts due to management of

potential contaminated soil and groundwater that may be encountered from

the Project Site are considered acceptable with the implementation of the

recommended mitigation measures.

3.4 WATER QUALITY

The potential water quality impacts associated with the DDD works have been

evaluated. Water bodies within the Study Area and potentially polluting

activities from the Project have been identified. The potential water quality

impacts from the Project have been assessed with respect to the applicable

criteria.

Potential sources of water quality impact during the DDD works include

construction site runoff, wastewater from decontamination of plant and

equipment, contaminated groundwater from dewatering (if necessary), and

sewage from demolition workforce. Potential water quality impacts for each

potential source of impact have been evaluated and appropriate mitigation

measures have been considered to minimise the identified impacts. With the

implementation of the recommended control measures, it is anticipated that

the Project will not cause unacceptable water quality impacts on the nearby

water bodies. Regular site audits during the DDD works will be carried out

to ensure the proper implementation of the proposed mitigation measures.

Page 12: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

9

3.5 WASTE MANAGEMENT

The types (including construction and demolition materials, surplus

excavated soil, chemical waste (including asbestos waste) and general waste)

and quantities of waste to be generated during the DDD works have been

identified and estimated as far as practicable. The potential impacts

associated with handling, storage and disposal of these wastes have also been

evaluated. Analysis of waste management implications involving the

consideration of DDD methods and programme was conducted at the early

stage of the Project to try to reduce waste generation and to maximise

opportunities for reuse and recycling of waste from the DDD activities.

Waste segregation will be carried out as far as practicable so as to maximise

the quantity of materials to be recycled and disposal of the wastes at the

appropriate waste treatment or disposal facilities. With the implementation

of good site practices and recommended waste management arrangements,

the DDD activities will not cause adverse waste management or

environmental impacts. Regular site audits during the DDD works will be

carried out to ensure the proper implementation of the proposed mitigation

measures.

3.6 ECOLOGY

As the DDD works will be carried out mainly within the Project Site and along

the of the oil pipelines between the CMC and the off-site jetty, which are

located in an urban/disturbed area of low ecological value, the potential

ecological impacts are considered low. The removal of the pipelines is not

expected to affect any trees and overall the ecological impacts are negligible.

One bat species of conservation importance was recorded roosting within the

landscaped areas of the Project Site and a different insectivorous species was

observed foraging there at night during the baseline ecological survey. The

trees (particularly the Chinese Fan-palms Livistona chinensis) within the Project

Site will be transplanted or felled prior to the DDD works, which have the

potential to impact on the bats. Given that alternative roosting and foraging

sites for these species have been identified in the habitats that are in close

proximity to the Project Site, the potential impact to the bats due to lose the

landscape area will be minimal.

It is recommended that prior to the removal or felling of the trees at the Project

Site, the concerned trees will be inspected to confirm that no Short-nosed Fruit

Bat is present. If any Short-nosed Fruit Bat is observed roosting on tree, tree

felling/removal works will be postponed until the bats have left. With the

implementation of recommended control measure, the unacceptable

ecological impact due to the DDD works is expected. Regular site audits

during the DDD works will be carried out to ensure the proper

implementation of the proposed mitigation measures..

Page 13: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

10

4 ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

To confirm effective and timely implementation of the mitigation measures

recommended in the EIA Report, an Environmental Monitoring and Audit

(EM&A) programme has been developed by which the implementation of the

recommended mitigation measures can be tracked and checked, and their

effectiveness can be verified.

During the DDD works, regular site inspections and audits will be conducted

to confirm that recommended mitigation measures have been properly

implemented.

Regular dust (in terms of 24-hour averaged Respiratory Suspended

Particulates) and noise monitoring will be carried out at the representative

sensitive receivers; and testing of the groundwater to be discharged to the

sewer will be carried out in order to monitor the environmental performance

of the DDD works and to confirm compliance with the regulatory

requirements or assessment criteria.

Further SI will be conducted at the identified land contaminated hotspots that

cannot be accessed during the EIA Study upon completion of the demolition

of structures and buildings in the concerned areas to confirm any soil and/or

groundwater contamination. The extent of the soil and groundwater

contamination estimated in the EIA Report will be reviewed based on the

findings of the further SI. With necessary, the RAP will be updated. Upon

completion of the remediation works, the remediation works and results will

be presented in the Remediation Report which will be submitted to DSPA for

review.

Page 14: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

11

5 CONCLUSION

The implementation of this Project is in line with the MSAR Government’s

policy objective of optimising land use on the crowded Macau peninsula.

With the implementation of recommended good construction site practices

and mitigation measures, no adverse residual impacts due to the Project are

envisaged.

This EIA Study has therefore confirmed the overall acceptability of the

environmental impacts likely to arise due to the DDD works. An

environmental monitoring and audit (EM&A) programme (including regular

environmental monitoring and site audit) will be implemented to verify the

impacts predicted of the EIA Study and to ensure the recommended mitigation

measures are properly implemented by the Project Proponent.

Page 15: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

File: T:\GIS\CONTRACT\0346562\Mxd\EIA\0346562_Project_Location.mxdDate: 28/4/2016

Legend

Surface Pipeline

Underground Pipeline

Project Boundary

0 200100Meters

´

Figure 1.1

Project Location

Page 16: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

FILE: 0346562eDATE: 28/04/2016General Layout of the Power Plant

Figure 2.1

N

Page 17: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

Zone L

Zone K

Zone J

Zone H

Zone H

Zone H

Zone H

Zone G

Zone G

Zone G

Zone G

Zone F

Zone F

Zone E

ZoneE

Zone E

ZoneD

Zone C

Zone B

Zone B

Zone A

File: T:\GIS\CONTRACT\0346562\Mxd\EIA\0346562_Demolition_Zones.mxdDate: 28/4/2016

Legend

CMC Site Boundary

0 5025Meters´

Figure 2.3

Demolition Zones

Zone I

Zone I

Overview of Zone I

Zone DescriptionZone A Tank FarmZone B Oily Water System, Chemical Store & Water Tank No.A1Zone C Fuel Oil Treatment PlantZone D Exhaust Gas Stack and Chimneys

Zone EAuxiliary Boiler, Fire Fighting Station, Pumps next to thisBuilding and Compressors behind this Building

Zone F Gas Turbines Packages T22 and T23Zone G Cooling Tower & Sheltered Storage AreaZone H Cable and Pipe TrenchesZone I Fuel Oil Pipe, Lube Oil Pipe and Diesel Oil PipeZone J D25/D28 Engine RoomZone K D15/D21 Engine RoomZone L Control Building

Page 18: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

Jardim DaMontanha Russa

螺螺螺螺螺

MacaoDaily News澳澳澳澳

EdificioAir Way飛飛飛飛

Edificio IndustrialNam Fong

南南南南飛飛

EdificioIndustrial Fu Tai富飛南南飛飛

Edificio Hantec亨亨飛飛

Escola Seono Fan DaAssociacao Comercial

De Macau商商商商商

EnvironmentalProtection Bureau

環環環環環Edificio

Golden Sea金金金螺

EdificioDragon Tower

龍龍龍

EdificioChan Chu珍珍龍

Edificio OK Garden好好金螺

Museu dasComunicacoes飛通通通通

Edificio DosCorreios

郵郵郵郵郵郵郵商郵

Reception area of theTransport Bureau交飛交交環飛交

Edificio Hoi Van海海飛飛

Edificio Ocean Garden海海金螺

Edificio PatTat Sun Chuen

八亨八八

EscolaSao Paulo聖環聖商聖

Edificio IndustrialNam Fong

南南南南飛飛

EdificioIndustrial Fu Hang

富富南南飛飛

EdificioAir Way飛飛飛飛

EdificioIndustrial Chun Foc

景景南南飛飛

Edificio IndustrialNam Leng

南南南南飛飛

Posto Operacionalda Areia Preta

黑黑環黑黑環黑黑黑黑

Nam Wa SanChun

南南八八

Tong WaSan Chun東南八八

JardimNam Ou南澳金螺

EdificioFok Hoi景海金螺

Colegio DomBosco (Yuet Wah)鮑鮑鮑鮑南鮑商

Edificio Obradas Maes母母母飛飛

EdificioKin Chit建建金螺

Edificio IndustrialCheong Long昌龍南南飛飛

EscolaHou Kong濠濠商商

File: T:\GIS\CONTRACT\0346562\Mxd\EIA\0346562_Surrounding_Environment.mxdDate: 11/7/2016

Legend

CMC Site Boundary

0 10050Meters´

Figure 2.2

Surrounding Environment of the Power Plant Site

Page 19: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

ASR10

ASR11

ASR12

ASR13

ASR14

EdificioIndustrial

Nam Fong南南南南南南

Escola Seono FanDa AssociacaoComercial De

Macau商商商商商

Jardim DaMontanha Russa

螺螺螺螺螺

MacaoDaily News澳澳澳澳

EdificioAir Way飛飛南南

EdificioIndustrial Fu Tai富南南南南南

Edificio Hantec亨亨南南

EnvironmentalProtection Bureau

環環環環環EdificioGolden Sea金金金螺

EdificioDragon Tower

龍龍龍

Edificio ChanChu

珍珍龍

EdificioO K Garden好好金螺

Museu dasComunicacoes飛通通通通

Edificio DosCorreios

郵郵郵郵郵郵郵商郵

Reception area ofthe Transport Bureau

交飛交交環南交

Edificio Hoi Van海海南南

EdificioOcean Garden

海海金螺

Edificio PatTat Sun Chuen

八亨八八

EscolaSao Paulo聖環聖商聖

Edificio IndustrialNam Fong

南南南南南南

EdificioIndustrial Fu Hang

富富南南南南

EdificioAir Way飛飛南南

Edificio IndustrialChun Foc

景景南南南南

Edificio IndustrialNam Leng

南南南南南南

Posto Operacionalda Areia Preta

黑黑環黑黑環黑黑黑黑

Nam WaSan Chun南南八八

Tong WaSan Chun東南八八

JardimNam Ou南澳金螺

EdificioFok Hoi景海金螺

Colegio DomBosco (Yuet Wah)鮑鮑鮑鮑南鮑商

Edificio Obradas Maes母母母南南

EdificioKin Chit建建金螺

Edificio IndustrialCheong Long昌龍南南南南

Escola HouKong

濠濠商商

Edificio IndustrialChong Fong商中南南南南

NovelCentre

Ocean IndustrialCentre (I & II)

海金南南商郵(1期郵2期

AdvancePlaza

先先先先

EdificioIndustrial Veng Hou

永好南南南南

Edificio IndustrialKin Va

建南南南南南

Edificio IndustrialSun Cheong信昌南南南南

Bai YunGarden白白金螺

Escola ChongTak De Macau澳澳商澳商聖

EdificioMarbela海景海螺

ASR1

ASR2

ASR3

ASR4

ASR5

ASR6ASR7

ASR8

ASR9

ASR15

File: T:\GIS\CONTRACT\0346562\Mxd\EIA\0346562_RASR.mxdDate: 11/7/2016

Legend

!( Representative Air Sensitive Receivers (ASRs)

Surface Pipeline

Underground Pipeline

CMC Site Boundary

0 10050Meters

´

Figure 3.2

Locations of Representative Air Sensitive Receivers (ASRs)

Page 20: Decommissioning, Demolition of the Macau Power Station · General layout plan of the CMC is given in Figure 2.1. ... panels and earthing cubicles Zone G Cooling Tower & Shelter Storage

Ç

ÇÇ

Ç

Ç

ÇÇ

Ç

Ç

Ç

NSR8

NSR9

NSR10

Creche 1 Da AssociacaoDas Mulheres De Macau

婦婦婦婦婦婦婦

EdificioIndustrial

Nam Fong南南南南南南

Escola Seono FanDa AssociacaoComercial De

Macau商商商商商

Jardim DaMontanha Russa

螺螺螺螺螺

MacaoDaily News澳澳澳澳

EdificioAir Way飛飛南南

EdificioIndustrial Fu Tai富南南南南南

Edificio Hantec亨亨南南

EnvironmentalProtection Bureau

環環環環環Edificio

Golden Sea金金金螺

EdificioDragon Tower

龍龍龍

Edificio ChanChu

珍珍龍

EdificioO K Garden好好金螺

Museu dasComunicacoes飛通通通通

Edificio DosCorreios

郵郵郵郵郵郵郵商郵

Reception area ofthe Transport Bureau

交飛交交環南交

Edificio Hoi Van海海南南

EdificioOcean Garden

海海金螺

Edificio PatTat Sun Chuen

八亨八八

EscolaSao Paulo聖環聖商聖

Edificio IndustrialNam Fong

南南南南南南

EdificioIndustrial Fu Hang

富富南南南南

EdificioAir Way飛飛南南

Edificio IndustrialChun Foc

景景南南南南

Edificio IndustrialNam Leng

南南南南南南

Posto Operacionalda Areia Preta

黑黑環黑黑環黑黑黑黑

Nam WaSan Chun南南八八

Tong WaSan Chun東南八八

JardimNam Ou南澳金螺

EdificioFok Hoi景海金螺

Colegio DomBosco (Yuet Wah)鮑鮑鮑鮑南鮑商

Edificio Obradas Maes母母母南南

EdificioKin Chit建建金螺

Edificio IndustrialCheong Long昌龍南南南南

Escola HouKong

濠濠商商

Edificio IndustrialChong Fong商中南南南南

NovelCentre

Ocean IndustrialCentre (I & II)

海金南南商郵(1期郵2期

AdvancePlaza

先先先先

EdificioIndustrial Veng Hou

永好南南南南

Edificio IndustrialKin Va

建南南南南南

Edificio IndustrialSun Cheong信昌南南南南

Bai YunGarden白白金螺

Escola ChongTak De Macau澳澳商澳商聖

EdificioMarbela海景海螺

NSR1NSR2

NSR3

NSR4NSR11

NSR5

NSR6

NSR7

File: T:\GIS\CONTRACT\0346562\Mxd\EIA\0346562_RNSR.mxdDate: 13/7/2016

Legend

Ç Representative Noise Senstive Receivers (NSRs)

Surface Pipeline

Underground Pipeline

CMC Site Boundary

0 10050Meters´

Figure 4.2

Locations of Representative Noise Sensitive Receivers (NSRs)


Recommended