ORIGINAL PAPER
Deep-Seated Slope Failures Induced by InappropriateCutting in China
Hong-Yue Sun • Yu Zhao • Yue-Quan Shang •
Yang Yu • Quan-Li Zhao
Received: 5 December 2011 / Accepted: 14 July 2012 / Published online: 25 August 2012
� Springer-Verlag 2012
Abstract Given insufficient geological investigation and
inadequate interpretation of geological settings, remedial
works for localized cut slope collapses may induce large-
scale failures and cause remarkable damage, as well as
economical loss. A number of recent reports have addres-
sed individual large-scale failures due to inappropriate
cutting, but the systematic classification of failure patterns
has received less attention. In this study, a re-profiling
triggered landslide is described in detail. The deep slip
surface is located by field measurements; then, the stability
of the slope before and after cutting is assessed with the
limit equilibrium method. Three types of slopes prone to
deep-seated failures are introduced: the loose deposits type,
the ancient landslide type, and the deep adverse disconti-
nuities type. The mechanism of each failure pattern is
illustrated with a case study. The stability analyses indicate
that inappropriate slope profiling may greatly reduce the
factor of safety (FS) of a slope. Recommendations are
given for mitigating the deep-seated landslide induced by
inappropriate cutting, and a case history of successful
measures is presented.
Keywords Cut slope � Deep-seated landslides �Geological investigations � Profiling �Limit equilibrium method
1 Introduction
During expressway construction in mountainous areas,
slope cuts are frequently designed to run along the toe of a
natural slope, as shown in Fig. 1. Landslides may occur
within slope cuts (Voight 1979) due to inappropriately
designed profiles without due geological investigations
(Fuchsberger 2008; Lee and Hencher 2009) or rainfall-
induced pore water pressure (Okagbue and Ifedigbo 1995;
Sugiyama et al. 1995; Raj 1998; Yoo and Jung 2006;
Abderahman 2007; Lee and Hencher 2009). Moreover,
human activities and erosion/slaking encourage the
undercutting or degradation of slope cuts, which also affect
slope stability (Odemerho 1986; Malkawi and Taqieddin
1996).
To mitigate cut slope failures, re-profiling is one of the
most commonly used corrective measures. The use of
re-profiling may increase the factor of safety (FS) of the cut
slopes while reducing the FS of the natural slopes, since the
location of the neutral points is always dependent on that of
the slip surfaces (Hutchinson 1977). Generally, little
money is spent on ground investigation for cut slopes in
China, and the target area of investigations and stability
analysis is always limited to the zone of cut slopes. Thus,
the potential for large-scale landslides along deep slip
surfaces is frequently ignored. Although individual deep-
seated landslides induced by inappropriate cutting were
reported in China (Deng et al. 2009) and in Korea (Lee and
Hencher 2009), less attention has been paid to the geo-
logical conditions that are prone to such failures.
In this study, a re-profiling triggered landslide is first
described in detail. The deep slip surface is located by field
measurements, and then the stability of the slope before
and after cutting is assessed with the limit equilibrium
method. Three types of slopes prone to deep-seated failures
H.-Y. Sun
Department of Ocean Science and Engineering,
Zhejiang University, Yuhangtang Road,
Hangzhou 310058, China
Y. Zhao (&) � Y.-Q. Shang � Y. Yu � Q.-L. Zhao
Department of Civil Engineering, Zhejiang University,
Yuhangtang Road, Hangzhou 310058, China
e-mail: [email protected]
123
Rock Mech Rock Eng (2012) 45:1103–1111
DOI 10.1007/s00603-012-0292-4
are introduced, and the mechanism of each failure pattern
is illustrated with a case study. The description of rocks
and soils in this paper mainly follows the terminology used
by Geotechnical Engineering Office (GEO 1988).
2 A Typical Large-Scale Landside Induced
by Toe Disturbance
Although the proportion of more intensely weathered rock
is generally closer to the ground surface, the existence of
deeply embedded weak planes should not be neglected.
The complex discontinuities of a slope require detailed
geological investigation before cutting a slope. Further-
more, due attention should be paid to the possibility of
further damage in a wider range once a localized failure
occurs. Despite the lack of sufficient geological investi-
gations and stability assessment, a slope was re-profiled
after a small-scale failure along the S26 expressway in
Zhejiang Province, China, and, consequently, deformed in
a wider range.
2.1 General Description of Hongyan Landslide
In 2005, it was decided to form a cut slope in a natural
hillside near Hongyan (longitude 120�300E, latitude
28�520N) of Xianjun County in China, to allow the con-
struction of the Zhuyong (S26) expressway. The two-lane
carriageway was designed to pass the toe of a natural slope
with an original slope angle ranging from 25� to 40�. The
right lane (close to the river) was on the bridge, while the
left lane (close to the mountain) was beside the cut slope.
The original design of the cut was less than 10 m, and no
large-scale excavation was involved. In August 2005, a
temporary cut of 6 m was formed at the toe to construct the
bridge, as shown in Fig. 2. During a 593-mm rain event
from 9 November to 14 November [China Meteorological
Administration (CMA), China Meteorological Data Sharing
Service System; http://cdc.cma.gov.cn/], the groundwater
table was uplifted, and water started to seep out from the
cut face. The groundwater level indicated by waters at the
toe and boreholes is shown in Fig. 3. At about 2 pm on 16
November 2005, a landslide mass (HP1) slid out after
continuous rain and turned over the bridge peers, as shown
in Fig. 2. The landslide was approximately 75 m long and
80 m wide, with a total volume of about 45,600 m3. The
scarp is located at the elevation of 430 m, approximately
40 m above the toe (Fig. 3).
2.2 Geological Setting
The study area is located within very thick (5–15 m)
quaternary deposits (el-dlQ) that are mainly composed of
yellowish-gray clay with gravel contents. The gravel level
of the quaternary clay-gravel is seen just above the older
Fig. 2 Photograph of the Hongyan landslide
Fig. 1 A natural high slope above the cut slope
0
Loose deposits
410
430
390
20 40 60 80 100 120
Landslide HP1
Original terrain line
Hubakeng RiverSlip surface
Tuff rock
Elevation(m)
Highly weathered
Moderately weathered
Slightly weathered
Groundwater table
Fig. 3 Cross-section of the Hongyan landslide (HP1)
1104 H.-Y. Sun et al.
123
rocks (Upper Jurassic J3x, gray-purple crystalline tuff
rocks). Three major joint sets trending 330�/76�, 118�/73�,
and 25�/8� (direction/dip) fragment the rock mass into
pieces of about 0.2–0.5 m in length. The joints are mostly
steeper than the slope angle, which generally do not form
direct sliding planes.
The soil of the quaternary formation is highly porous
and permeable, and contacts with the underlying weathered
and jointed rocks. Rainwater generally seeps quickly
downward through the quaternary deposits into bedrock
fissures and stops by the intact rock. The groundwater
outflow at the outcrops of the toe indicates that the
downslope flows are mainly through the stratum of highly
weathered bedrock.
2.3 Remedial Measures
At the beginning of 2006, another geological investigation
was conducted. In accord with the engineering conditions,
several reinforcement methods were installed to improve
the stability of the slope, as shown in Fig. 4. First, stabi-
lizing piles were designed to penetrate the loose deposits
and highly weathered rock to reach stable rock. From
August 2006 to December 2006, two rows of stabilizing
piles (rows A and B) were constructed in the upper portion
of the slope. Between July 2007 and August 2007, the
slope was excavated to seven levels to reduce the weight of
the slide body and to allow the construction of bridge
peers. However, the piles were not long enough to stabilize
the slope due to poor interpretation of the borehole data.
During the excavation works, two large tension cracks
(L1 and L2) appeared above the highest cutting face, and
both cracks were continuously deformed. Construction was
forced to stop. In 2007–2008, the owner chose another
corporation to take over the project due to the poor per-
formance of the previous company. The new company
carried out another investigation and proposed two more
rows of stabilizing piles (rows C and D) to be installed, as
shown in Fig. 4. Field measurement of the slope started at
the beginning of 2009.
2.4 Field Measurement
To observe the behaviors of the slope, both shallow and
deep deformation was monitored from January 2009.
Figure 5 plots the variation of the horizontal displacement
of four monitored points measured at the slope surface
(P04 and P08 are on the slope surface, not on top of the
piles). Over a period of 9 months, the displacement grew
linearly at a rate of 0.1–0.2 mm/day. The movement of the
monitored points seems to show a similar trend, which
indicates that the slope was moving as an entire body.
Three inclinometers were installed at cx01, cx03, and
cx06 to measure the deep displacement (Fig. 4). The dis-
placement is first plotted on the cross-section, and then the
maximum dislocated locations of the inclinometers are
connected with a smooth curve. Combined with ground
crack locations, two potential sliding surfaces are obtained
as shown in Fig. 4. It is obvious that the supporting piles
were too short to provide any resistance at any of the
potential sliding planes.
2.5 Slope Stability Analysis
The stability of the natural slope at different excavation
stages was assessed with the Morgenstern–Price method
580
100
560
540
520
500
480
460
440
420
400
380
360
120 140 160 180 200 220 240 260 280 300 320 340 360 380
P04
P08
P16
P19
cx06cx01
cx03
Stabilizing piles of row CStabilizing piles of row D
Crack L1
Crack L2
Stabilizing piles of row A
Stabilizing piles of row B
Expressway
Projectedslip surface
Initial profile
Original terrain
Modified profile
Groundwatertable
Fig. 4 Profile of the Hongyan
slope: reinforcement measures,
monitoring points, and potential
slip surfaces
Deep-Seated Slope Failures Induced by Inappropriate Cutting in China 1105
123
(Morgenstern and Price 1965), within the framework of
limit equilibrium methods. The mechanical parameters at
the slip surface are not accessible due to the complex
geological structures of the slope. Thus, the parameters C
and u were obtained by inversion analysis assuming that
the slope was in a critical state after re-profiling (the lowest
slip surface and the groundwater table in Fig. 4 are used).
Then, the FS of the slope along the same slip surface was
calculated at the original terrain and after the initial cut. As
illustrated in Table 1, the FS decreased by less than 0.03
after the temporary cut was formed, but it decreased by
0.41 after re-profiling. Thus, re-profiling was the main
factor that induced the movement of the slope along the
deep slip surface.
3 Deep-Seated Landslides Induced by Inappropriate
Slope Cutting
Generally, slope classifications based on geological
conditions are developed from the RMR classification
(Bieniawski 1989) and the Q classification (Barton et al.
1974). SMR (Romana 1991) is a well-known geological
conditions-based method that uses the summation of
weighted contributing factors. It is also used to qualita-
tively assess slope stability (Umrao et al. 2011). However,
it is not suitable to be implemented in this study for several
reasons. First, it is less effective when failures of slopes are
dominated by one single contributing factor. Second, the
study contains not only rock slopes but also slopes covered
with loose deposits. Third, a deep-seated landslide often
covers a large area where the geological conditions varied
spatially; thus, it is difficult to collect complete data or to
choose representative parameters. Therefore, the case his-
tories are practically classified using major geological
features instead of the more sophisticated SMR method.
Besides the high quasi-homogeneous type, deep-seated
landslides induced by toe disturbance usually take place in
three types of geological environments: slopes with thick
deposits, ancient landslides, and slopes where adverse
discontinuities were excavated and exposed. Landslides in
thick deposits comprise 80 % of all landslides in Zhejiang
Province, China (The Ministry of Land and Resources
2003). The deposits are usually formed from slope sedi-
ments, collapse deposits, landslides deposits, and a small
amount of fluvial sediments. Even cutting merely 3 m into
the toe may substantially increase the risk of landslide
(Zhou et al. 2006). In addition, underground water is usu-
ally active at the interface between loose deposits and
bedrock due to the difference between their permeability.
Under the effect of self-weight and the flows of ground-
water, a large amount of fine clay particles and organic
matters deposit near this interface that becomes a potential
slip surface. Cutting into the passive section of such a slope
may induce creeping deformation and may later cause non-
continuous sliding along certain secondary slip planes.
Numerous colluvium slopes slide along the interface
between the loose deposits and bedrock during the cleaning
process of small-scale failures.
Ancient landslides are remarkably sensitive to environ-
mental changes. The foot of an ancient landslide is often
the passive section and, thus, is the key part to sustain the
stability of the slope. Removal of the toe will probably
reactivate the ancient landslide. In the Austrian Alps, the
stability of an ancient landslide was ignored prior to
expressway construction. A minor excavation near the toe
reactivated the landslide, and the expressway was pushed
outward (Fuchsberger 2008). In the West Hubei Province
of China, digging a trench for natural gas first induced
a localized slope failure and then triggered the huge
Baiyangping landslide (Zhu 2010).
Discontinuities, such as faults, joints, schistosities, and
contact interfaces, endow slopes with a complex structure
and discontinuous mechanical properties. The physical and
mechanical properties of rock masses vary spatially. In
many situations, adverse discontinuities might not be rec-
ognized prior to the construction of a cut slope. If due
attention is not paid to the adverse discontinuities exposed
during construction, the cut slope and even the natural
0 20 40 60 80 100 120 140 160 180 200 220 240-10
0
10
20
30
40
50
60
70D
ispl
acem
ent i
n ho
rizo
ntal
dir
ectio
n /m
m
Time /d
P04 P08 P16 P19
Fig. 5 Horizontal displacement of monitoring points during the
period 10 March 2009 to 10 November 2009 (refer to Fig. 4 for point
locations)
Table 1 Parameters of the Hongyan slope obtained from the back-
ward and forward analysis
Unit
weight
(kN/m3)
Cohesion
C0 (kPa)
Friction
angle u’
(�)
FS after
re-profiling
FS before
re-profiling
FS of
original
slope
22.5 35 42 1.00 1.41 1.44
1106 H.-Y. Sun et al.
123
slope behind it may be endangered. For instance, com-
pressive discontinuities dipping downslope were exposed
during slope profiling for the Meihe Expressway KII1 in
Guangdong, China; consequently, a deep-seated landslide
was triggered (Wang 2006). In the following subsections,
one case is presented for each type of failure pattern.
3.1 Loose Colluvium Slopes
The Xiaodan landslide in Southern Zhejiang Province,
China, is a typical example of the loose deposits type. An
existing national road was to be widened for the con-
struction of a new expressway; the cut slope was designed
as 4 m maximally (Fig. 6). The natural slope is 30�–40� at
the base and 15�–25� at higher ridges. Soon after the toe
was removed, transverse cracks appeared above the cutting
surface, and then localized slope failures took place. In
addition to the low strength of clayed gravel, precipitation
in the rainy season also made the steep slope prone to
localized failures. The collapses were considered to result
from the poorly designed slope profile and the rainy season.
Thus, the collapsed soil was cleaned in the usual way
without any extra attention, causing progressive cracking at
the upper part of the slope.
A reinforced-concrete retaining wall (4 m high) was
then installed at the toe to prevent it from collapsing again.
However, the drainage system of the retaining wall was
blocked due to the poor construction conditions in the rainy
season. As a result, groundwater stopped and accumulated
behind the wall, which increased the groundwater level
near the toe. Obviously, this failed to prevent further
cracking at the slope surface behind the wall (Fig. 7). To
continue steady construction without a detailed geological
investigation, large-scale re-profiling was performed to
prevent further collapses. Then, the Xiaodan landslide
occurred along the deep slip surface, as shown in Fig. 7.
The maximum length and width of the slide mass was
approximately 140 and 135 m respectively, with a thick-
ness of 15–20 m.
Assuming that the strength and other parameters of the
deep slip surface were the same before and after profiling,
the slope stability was assessed with the methodology
discussed in Sect. 2.5. As shown in Table 2, the FS
decreased by merely 0.01 after initial profiling, but there
was a decrease of 0.13 after large-scale re-profiling. The
massive landslide was triggered by two serious mistakes in
the remedial measures. First, a timely geological investi-
gation was not conducted; thus, it was ignored that the
entire slope might slide along the deep sliding plane.
Second, inappropriate slope profiling reduced the weight of
the passive section and, thus, increased the possibility of a
large-scale landslide.
3.2 Ancient Landslides Type
The failure of slope K81 along the Jinhua–Lishui–Wenzhou
expressway in Zhejiang Province, China, is a typical
example of the ancient landslide type. The expressway was
designed to bypass the toe of a natural slope whose slope
angle is 35�–42�. The slope consists primarily of volcanic
tuffs of Upper Jurassic strata, showing a fairly clear
boundary between the fractured rock and relatively intact
rock in Figs. 8 and 9. The relatively intact rock has mainly
two different sets of joints trending 320�–340�/80�–90�(direction/dip) and 215�–225�/50�–60�, respectively. Among
the complex joints in the fractured zone, the dominated set
trends 150�–160�/50�–60�, the direction of which is almost
opposite compared with that of joints in the relatively
intact rock. The contrasting joint attitudes indicate that the
rock of the fractured zone had once undergone rotation in
historical sliding.
The cut slope was initially designed to be less than 30 m
high (Fig. 10). However, a localized collapse occurred
during the excavation; the failure was attributed to the low
Highway
Horizontal Distance (m)
180170160150140130120110100908070605040302010
Bedrock
NW334
110
Elevation (m)
100
80
90
70
60
30
40
20
10
50Loose Deposits
o
OriginalRoad
160 170 180
Subgradeexcavation
Fig. 6 Localized slope failure
induced by the toe cutting for
expressway construction
Deep-Seated Slope Failures Induced by Inappropriate Cutting in China 1107
123
strength of the fractured rock. To solve the problem, the
slope was re-profiled to a 100-m cut; then, two rows of
anchors with 6-m spacing and of length 10–15 m were
installed on each stair. The spacing and length of anchors
was designed to protect each step from localized collapse.
After cutting, field engineers found that the slope
deformed in a wider range. Thus, an in-depth geological
investigation and field survey, including borehole drilling
and geological radar detection, were conducted. The
investigation permitted us to map the geological section at
A–A0 in Fig. 10. A deep slip surface due to rock friction
was evident from the exposure of the cut face and from the
video taken using a borehole camera. The slip surface has a
plane of weakness embedded that consists of discontinu-
ously distributed clay. Based on the geological conditions,
it was confirmed that the slope was an ancient landslide
type. Eventually, further anchoring into the ancient land-
slide was performed even after slight anchoring was
complete. In the adjustment, the strength parameters of the
slip surface are calculated by backward analysis assuming
the FS of the slope taking a value of 1.0 after re-profiling
(Table 3). To ensure that the FS is no less than 1.25,
another 380 anchors were installed and pre-stressed to tie
back the slope. The anchor cables had a pre-stress force of
750 kN and lengths varying from 22 to 40 m based on the
geological conditions.
The contribution of initial profiling and re-profiling was
also assessed (Table 3). The excavation of the 30-m cut
slope reduced the FS of the ancient landslide by 0.1.
However, 553 m3 of rock mass per unit width (1 m) were
excavated in the re-profiling. The slope cutting reduced the
FS by 0.11. Hence, slope re-profiling without an in-depth
geological investigation was the immediate cause that
reactivated the ancient landslide. Although the final
anchoring plan ensured the stability of the slope, it caused
enormous economic losses.
3.3 Adverse Discontinuity Type
The landslide K103 along the Hangzhou–Jinhua–Quzhou
expressway in Southeastern China was induced by the
excavation and exposure of adverse discontinuities at the
toe. The slope of the original terrain was 20�–35�, where
the massive rock at the surface is underlain by adverse
discontinuities. Initially, an 18-m cut was formed, as shown
in Fig. 11. However, during construction, tension cracks
and superficial collapses occurred several times. The cut
was then arbitrarily adjusted to a height of 45 m without an
in-depth geological investigation. A retaining wall was also
constructed to withstand the slope behind it.
After the expressway came into operation, the retaining
wall was found to be toppled and cracked. Numerous
cracks were evident on the middle to the upper part of the
slope. The largest crack was opened to almost 1 m wide
Loose Deposits
50
10
20
40
30
60
70
90
80
100
Elevation (m)
110
NW334
Bedrock
20 40 60 80 100 120 140 160 180
Horizontal Distance (m)
Highway
Cut Zone
10 30 50 70 90 110 130 150 170
o
Fig. 7 The Xiaodan landslide triggered by large-scale slope cutting
140400 20 60 80 100 120
Elev.221m
Elev.246m
Elev.280m
340240160 180 200 220 260 280 320300 360
water interception trench
Fig.9
fractured rock mass
relatively intact rock mass fractured rock massboundary line offractured rock mass
A
A'
Fig. 8 Rock profile of the cut
face of the K81 slope
Table 2 Parameters of the Xiaodan slope obtained from the back-
ward and forward analysis
Unit
weight
(kN/m3)
Cohesion
C (kPa)
Friction
angle u(�)
FS after
re-profiling
FS before
re-profiling
FS of
original
slope
20.3 19 20 1.00 1.13 1.14
1108 H.-Y. Sun et al.
123
and sheared 0.5–0.8 m out-of-plane. The cracked and dis-
located retaining wall, tilted drainage ditch, and cracked and
uplifted road all indicate that the entire slope was losing its
stability and threatening the safety of the expressway. As
shown in Fig. 11, the landslide is 400 m long and 140 m
high, with a thickness of 15–40 m. The total volume of the
slide mass is estimated to be 160 9 104 m3.
After the deep-seated landslide occurred, a 10�–25�dipping fault was revealed by a series of borehole drillings.
The fault zone is 1–13-m thick and mainly composed of
highly weathered tuff and tuffaceous sandstone (polyhedral
structure, taupe or maroon, some joints filled with maroon
clay). The rock masses are very weak and prone to soft-
ening in water. The rock above the fault zone is highly
weathered tuff stone and conglomerate (gray or purple,
largely disturbed), whereas the rock beneath the slip sur-
face is gray-purple conglomerate with good integrity.
The stability of slope was then assessed using the
geological cross-section in Fig. 11. Compared with the
initially designed cut slope (18 m), the re-profiling plan
(45 m) reduced the FS by 0.07 (Table 4). The exposure of
the deep adverse joins and the resistance reduction due to
the re-profiling were major factors contributing to the slope
failure.
4 Recommendations for Mitigating Slope Failures
Induced by Inappropriate Cutting
4.1 General Recommendations
Sufficient geological investigation is needed in order to
assess the stability of a slope and prevent failures. The
existence of any adverse geological features should be
determined before cut slope construction or at least after
cut slope failures. It is mandatory to describe the zonation
of rock units, detect the existence of any plane of weak-
ness, and assess all possible failure patterns.
It is important to analyze the causes of localized failures
and their effect on the stability of the natural slopes.
Table 3 Parameters of the K81 slope obtained from the backward
and forward analysis
Unit
weight
(kN/m3)
Cohesion
C (kPa)
Friction
angle u(�)
FS after
re-profiling
FS before
re-profiling
FS of
original
slope
21.8 25 34 1.00 1.11 1.21
Fig. 9 Boundary between relatively intact rock mass and fractured
rock mass
Ele
vatio
n (
m)
original slope terrain
Modified profile
Highway
anchor cable
clayey soil
failure plane
Initial designed profile
fractured rock mass
relatively intact rock mass
320
300
280
260
240
220
200
Fig. 10 The geological cross-section at K81 ? 820 (A–A0 in Fig. 8)
Mod
ified
Profil
eInitially Designed Profile
Original Terrain
200
180
160
140
120
100
80
60
40
20
80
60
40
20
Projected slip surface
Adverse discontinuities
Fig. 11 Profile of the K103
slope and the deeply hidden slip
surface
Deep-Seated Slope Failures Induced by Inappropriate Cutting in China 1109
123
Cutting the toe of a slope in a critical state likely induces
localized collapses that could be the beginning of a deep-
seated landslide. This possibility of deep-seated sliding
should be thoroughly investigated prior to further excava-
tion works, especially when the slope is a loose deposits
type, ancient landslide type, or adverse discontinuities type.
The principle, ‘‘reinforcement first and cutting follows’’,
is effective to avoid deep-seated landslides. The most
effective measure is to reinforce the slope before or during
cutting in order to maintain the stability of the slope.
Re-profiling should be carried out prudently. Note that
re-profiling reduces the stability of the slope above the
excavation line.
4.2 A Case of Successful Measures
Shangsan slope failure #2 along the Shangsan expressway
occurred after the slope toe was excavated. When an 8-m
cut was formed, a series of arcuate tension cracks appeared
on the head of the cut face. Then, the part below the cracks
collapsed, and the failure propagated progressively upward,
resulting in a step-like terrain (Fig. 12). If excavation
continued, a deep-seated landslide would likely have been
triggered.
The original slope angle is 15�–25� at the base and
10�–20� at the upper portion. The construction site is
within 10–15 m of clay–gravel stratum with crystallino-
clastic tuff rock lying beneath. The range of loose deposits
and the weathering profile of rock units were investigated
and interpreted in a rational manner (Fig. 13). Field engi-
neers determined that it is a slope of the loose deposits
type. To avoid prematurely re-profiling, its stability was
assessed along with the scale of potential sliding before any
remedial plan was made. Since the contents of gravels
varied spatially, the strength parameters are difficult to
obtain by laboratory tests. During the design, the strength
parameters of the slip surface were first calculated by
backward analysis, assuming that the slope was in a critical
state after the initial cut. Then, the strength parameters
were used to search for the most adverse slip surface within
the loose deposits and to assess the stability of the slope
along the boundary between the loose deposits and the
highly weathered tuff.
According to the analysis, reinforcement is required
before further excavation to protect the cut face and the
slope from deep-seated failure along the slip surface
(Fig. 13). A row of stabilizing piles was installed at the toe,
and then the slope was re-profiled to be step-like. The
expressway was constructed smoothly, and the slope has
not experienced any failures since.
5 Conclusions
The failure of cut slopes often results from insufficient
geological investigation prior to design and the rainy sea-
son after construction. If collapsed rock/soil masses are
directly removed without a comprehensive understanding
of the geological environment, this can increase the pos-
sibility of deep-seated sliding. Once a slope is deformed in
a wide range after toe cutting, the risk of a large landslide
should be thoroughly investigated.
Re-profiling a failed cut slope may induce deep-seated
landslides for the following types of slopes: loose deposits
type, ancient landslide type, adverse discontinuities type, or
high and steep type. Once a cut slope failure occurs, the
existence of adverse geological features should be ade-
quately investigated and mapped. The type of geological
condition should be determined, and then remedial
211.52
202.72198.82
188.82
37.00
7.40
dlQ 3-4
delQ 32
dlQ 32
delQ 31
m
m
m
196.03193.43
Designed pavement level
187.83
Elevation(m)
Elevation(m)
8 m cut
Fig. 12 Cross-section of the #2 landslide along the Shangsan
expressway
1:1.5
600
778
500
250180
190
200
210
220
230
240
Expressway
Elevation (m)
201.76
209.76
Intercepting ditch
Intercepting ditch
Reinforced concrete piles180×250
Loose depositsHighly decomposed tuff
Moderately decomposed tuff
Fig. 13 Scheme of remedial measures for the #2 landslide along the
Shangsan expressway
Table 4 Parameters of the K103 slope obtained from the backward
and forward analysis
Unit
weight
(kN/m3)
Cohesion
C (kPa)
Friction
angle u(�)
FS after
re-profiling
FS before
re-profiling
FS of
original
slope
22.2 9 14 1.00 1.07 1.13
1110 H.-Y. Sun et al.
123
measures should be made accordingly. In addition, the
feasibility of re-profiling should be sufficiently discussed in
advance. If necessary, slope reinforcement should be made
before re-profiling is carried out.
Acknowledgments This research was financially supported by the
National Natural Science Foundation of China (40972187) and the
Key Innovation Team Support project of Zhejiang Province (2009
R50050).
References
Abderahman N (2007) Evaluating the influence of rate of undercut-
ting on the stability of slopes. Bull Eng Geol Environ 66(3):303–
309. doi:10.1007/s10064-006-0078-6
Barton N, Lien R, Lunde J (1974) Engineering classification of rock
masses for the design of tunnel support. Rock Mech Rock Eng
6:189–236. doi:10.1007/BF01239496
Bieniawski ZT (1989) Engineering rock mass classifications: a
complete manual for engineers and geologists in mining, civil,
and petroleum engineering. Wiley, New York
Deng L, Deng R, Lu Y, Liu Z (2009) Failure characters and origin of
Zhangjiaping Bridge in Wanzhou—Liangping expressway. In:
Proceedings of the 2nd International Conference on Transpor-
tation Engineering, Chengdu, China, July 2009, pp 1057–1061.
doi:10.1061/41039(345)175
Fuchsberger M (2008) Slope failure at a major cut for a motorway in
Austria—its cause and its stabilisation. In: Proceedings of
GeoCongress 2008: From Research to Practice in Geotechnical
Engineering, New Orleans, LA, March 2008, pp 616–625. doi:
10.1061/40962(325)25
Geotechnical Engineering Office (GEO) (1988) Guide to rock and soil
descriptions. Geoguide 3. GEO, Hong Kong
Hutchinson NN (1977) Assessment of the effectiveness of corrective
measures in relation to geological conditions and types of slope
movement. Bull Eng Geol Environ 16(1):131–155. doi:10.1007/
BF02591469
Lee S-G, Hencher SR (2009) The repeated failure of a cut-slope
despite continuous reassessment and remedial works. Eng Geol
107(1–2):16–41. doi:10.1016/j.enggeo.2009.03.011
Malkawi AIH, Taqieddin SA (1996) Geotechnical study of landslides
resulting from a highway construction in Jordan. Nat Hazards
13(1):1–15. doi:10.1007/BF00156503
Morgenstern NR, Price VE (1965) The analysis of the stability of
general slip surfaces. Geotechnique 15(1):79–93. doi:10.1680/
geot.1965.15.1.79
Odemerho FO (1986) Variation in erosion–slope relationship on cut-
slopes along a tropical highway. Singapore J Trop Geogr
7(2):98–107. doi:10.1111/j.1467-9493.1986.tb00175.x
Okagbue CO, Ifedigbo OT (1995) Engineering properties and slope
stability of road cuttings along the enugu-onitsha express road,
Southeastern Nigeria. Bull Eng Geol Environ 52(1):85–93. doi:
10.1007/BF02602685
Raj JK (1998) The failure of a slope cut into the weathering profile
developed over a porphyritic biotite granite. J Asian Earth Sci
16(4):419–427. doi:10.1016/S0743-9547(98)00015-4
Romana M (1991) SMR classification. In: Wittke W (ed) Proceedings
of the 7th ISRM International Congress on Rock Mechanics,
Aachen, Germany, September 1991, pp 955–960
Sugiyama T, Okada K, Muraishi H, Noguchi T, Samizo M (1995)
Statistical rainfall risk estimating method for a deep collapse of a
cut slope. Soils Found 35(4):37–48
The Ministry of Land and Resources (2003) Geological hazard and
mitigation in China. Geological Publishing House, Beijing (in
Chinese)
Umrao R, Singh R, Ahmad M, Singh T (2011) Stability analysis of cut
slopes using continuous slope mass rating and kinematic analysis
in Rudraprayag District, Uttarakhand. Geomaterials 1:79–87
Voight B (1979) Rockslides and avalanches, vol 2. Elsevier, Amster-
dam, pp 80– 87
Wang C-S (2006) Analysis of failure mode for shallow slide in fault
influence zone. Subgrade Eng 1:113–115 (in Chinese)
Yoo C, Jung HY (2006) Case history of geosynthetic reinforced
segmental retaining wall failure. J Geotech Geoenviron Eng
132(12):1538–1548. doi:10.1061/(ASCE)1090-0241(2006)132:
12(1538)
Zhou Z, Fu H-L, Liu B-C, Tan H-H, Long W-X, Luo Q (2006) Study
on in-situ monitoring of cut tests on a well-instrumented colluvial
slope. Chin J Rock Mech Eng 25:2065–2070 (in Chinese)
Zhu Z-J (2010) Landslides treatment of Baiyangping Area in pipeline
engineering from Sichuan to East. Oil Gasfield Surf Eng 29(7):
4–5 (in Chinese)
Deep-Seated Slope Failures Induced by Inappropriate Cutting in China 1111
123