DEHRADUN MUSSOORIE ROPEWAY
PROJECT
DISTRICT DEHRADUN
UTTARAKHAND
An Uttarakhand Tourism Development Board Initiative
Government of Uttarakhand
Dehradun
April 2018
INDEX
1. Objective
2. Project
3. Alignment
4. Technology
5. Annual Traffic
6. Purkulgaon
7. Mussoorie
8. Project Area
9. Estimated Project Cost
10. Ropeways – Infrastructure Status
11. Proposed PPP Structure
12. Proposed Eligibility Criteria
13. EOI Application
2
3
Ropeways / Cable Cars
- An Integrated & Sustainable Transport Solution
for twin cities of Dehradun & Mussoorie
OBJECTIVE
• Would reduce vehicular traffic on
Mussoorie road, thereby reducing
pollution / congestion.
• Reduce travel time in peak season - 2 /3
hours to about 20 min.
• Resolve Parking issues
• Best suited for eco-sensitive zone such
as Doon Valley
• An added attraction for the city
Aerial Passenger Ropeway
between Dehradun
(Purkulgaon / Mussoorie
Road) and Mussoorie
(Library taxi stand)
Multi-level Parking & other
commercial developments
at Terminal Points.
4
PROJECT
ALIGNMENT
5
30°24'47.00"N 78°4'2.00“E
30°27'35.50"N 78°3'58.50"E
6
Items Description
Length of the Ropeway
(approx.)
5.58 kms
Vertical rise 1,006 m
Proposed Technology Mono-cable
Detachable Gondola
(MDG)
Design Capacity 2000 PPHPD
Line Speed (avg.) 4.5 m / sec
Travel Time (approx) 18 - 20 min.
Towers 30-35
Cabins (both directions) 75
Seating capacity 10
Terminal Stations 2
Construction Period 2 years
Standards CEN / IS
TECHNOLOGY
MUSSOORIE ANNUAL TRAFFIC (in lakhs)
7
Source: Tourism Department, Government of Uttarakhand
Decadal cumulative annual growth rate is 2.9%
PURKULGAON (PROPOSED LOWER TERMINAL POINT)
8
LAND AVAILABILITY
Khasra No. Area in Ha.
236 GHA 2.265
242 1.424
237 1.947
Total 5.636
Tourism land as per govt. records
Sn Items Details Remarks
1 Total Area 22,650 sqm Khasra 236 GHA considered
2 Ground Coverage 15,000 sqm 66.6%
3 Max. Height 12.0 mtrs. Considering 9-12 mt. wide
approach road
4 Max. no. of Floors 4 (all above ground)
5 Max. Built-up area 45,000 sqm FAR of 3.0
6 Total no. of car parking 1400 – 1500 units Considering ECS of 32 sqm
As per the Uttarakhand Building Construction and Development Bye Laws / Regulations, 2011
(Amendment 2017) – DRAFT
Multi-level Parking
10
MUSSOORIE (PROPOSED UPPER TERMINAL POINT)
11
12
NORTH Existing Site
Total Area (4.25 acres)
MDDA
Parking
Mussoorie Mall road
13
Existing
house Existing MDDA
Parking
Vegetation and Existing Structures on Site
Slope Condition
The site has high slopes.
More than 85% of the site
has slope more than 32°. As
per the construction standards
for hilly areas, the buildable
slopes should be either less
than or equal to 15°. The
buildable area of the site lies
along the existing MDDA
Parking.
14
There are two options to be proposed to
the site:
• Extension of the existing MDDA
Parking.
• Multi-level car parking at feasible
slope with commercial at the terrace
level.
15
Site Plan
T
2
1
3
T Ropeway Terminal
1. MLP Block 1
2. MLP Block 2
3. MLP Block 3
16
17
18
19
20
MLP Block 2
MLP Block 1
21
MLP Block 3
22
23
Pedestrian
connections at
topmost level
Passenger
Elevators
• Proposed as an extension of the existing MDDA parking vertically as well horizontally
along the road.
• 4th floor above the ground has been proposed as commercial development.
• Connected to the mall road through pedestrian connections at the two corners of the
edge facing the mall road.
Multi- Level
Car Parking
Block 1
Total Built Area:
8,220 sqm
Floor: 6 (3 above
ground and 3 below)
Capacity: 260 cars
(43-44 cars per
floor)
MLP 1
MLP 2
24
Pedestrian
connections at
topmost level
Passenger
Elevators
• Proposed over the existing buildings below the existing MDDA Parking.
• Block 1 and Block 2 are interconnected with same ramps and entry-exit points from the
Mussoorie Dehradun road.
Multi- Level
Car Parking
Block 2
Total Built Area:
9,160 sqm
Floor: 7 (all below
ground)
Capacity: 240 cars
(35 cars per floor)
MLP 1
MLP 2
25
Pedestrian
connections at
topmost level
Passenger
Elevators
• This block is a new construction on the site.
• The 3 floors of the building down the basement have been designated for the
rehabilitation and relocation purposes from the existing structures where the other two
parking blocks have been proposed.
Multi- Level
Car Parking
Block 3
Total Built Area:
12,080 sqm
Floor: 8 (5 above
and 3 below ground)
Capacity: 360 cars
(45 cars per floor)
26
Terminal Station
Pedestrian
connections at
topmost level
Passenger
Elevators
• Lower 3 floors are proposed for ropeway equipment and associated facilities.
• Upper 2 floors have been proposed with commercial shops like banks, offices, retail.
• The station is connected to the parking blocks at the topmost level through pedestrian
walkway and hence the mall road through the MLP block 1.
Terminal
Station
Total Built Area:
1,800 sqm
Floor: 5 (2 above
ground and 3 below)
27
Area Chart
Components No of
Units
Site Area
Acres
(sqm)
Actual Built
up area (sqm)
Actual
Ground
Coverage
(sqm)
No. of
Floors
4.25 Acres (Buildable/ Developable Area = 1.5 Acres [35.7%])
Multi Level Car Parking Block 1 260
1.51 6125
8220 1370 6
Multi Level Car Parking Block 2 240 9160 1145 7
Multi Level Car Parking Block 3 360 12080 1564 8
Commercial Area 1370 at terrace level of MLP
Block 1
Rehabilitation 2700 at lower 3 basements of
MLP Block 3
Pedestrian Connections 3 Total area = 158 sqm
Terminal Station 1800 360 5
Total area 6125 4439
Project Area
28
Description Area Ownership Components
Lower Terminal
Station
(Purkulgaon)
2.5 hectares Tourism Dept. • Boarding & De-boarding point,
DG Room, Administrative
Block, Gondola Parking space,
Clock room, Toilets & Drinking
water facilities , etc.
• Multi-level Parking
• Commercial Components
Upper Terminal
Station
(Mussoorie)
1.7 hectares Nagar Pallika
Mussoorie
(Notified Private
Forest)
Ropeway Corridor
(10m wide)
ROW for 5.5
hectares
Private land,
Reserved
Forest
Tower structures & rope
Estimated Project Cost
29
Project Cost (Rs./crores)
Survey & Investigations 5.0
Ropeway Equipment (Imported) + Civil works 200.0
Multi-level Parking at Purkulgaon (phase -1) 45.0
Multi-level Parking at Mussoorie (phase -1) 40.0
Preliminary & pre-operative expenses 60.0
Interest during construction 50.0
Total 400.0
The project has been proposed to Ministry of Tourism, Government of
India for 20% grant under its new Viability Gap Funding (VGF) Scheme.
Ropeways - Infrastructure
Ropeways got included in the Harmonised Master List of Infrastructure sub-sectors
for infrastructure lending notified by Ministry of Finance, Government of India.
30
Proposed PPP Structure
UTDB is a statutory board constituted by the
Government of Uttarakhand to develop
tourism projects and formulate tourism
policies in the state. It is chaired by the
Tourism Minister and Chief Secretary of
Uttarakhand as it's vice chairman. The
Principal Secretary/ Secretary tourism acts as
Chief Executive Officer.
UTDB
Selected
Bidder SPV
Format : Design, Build, Finance, Operate & Transfer (DBFOT)
Concession Period : 60 years including Construction Period
Construction period : 3 years
Ropeway Tariff: No ceiling
On expiry, project shall be transferred back to the Authority at Re 1/-.
31
Proposed Eligibility Criteria
Sn Parameters Details
1 Evaluation Criteria
Technical Experience 2 times project
Financial Experience (Net-worth) 25% of the project cost
O&M Experience 50% of the project cost
2 Bid Parameter Highest Concession Fee / Revenue
Share / Combination
3 Bid Security 1% of the est. project cost
4 Construction Period Performance
Security
5% of the est. project cost
The Bidding Documents shall generally be based on the Model Concession
Agreement (draft) proposed by NITI Aayog for development of Ropeway
Projects on PPP
EOI Application
1. Company Profile, management, financials, etc.
2. Experience in Infrastructure Sector esp. ropeways
3. Experience in implementing projects in hilly regions esp.
Uttarakhand
4. Availability of required technical know-how / personnel
5. Financial Resources such as net-worth, turnover, profits, etc. in
last 5 years
6. Suggestions on ropeway alignment, project profile, associated
costs, etc.
7. Assistance required from Government of Uttarakhand.
33
THANK YOU
Request you to kindly send the EOI Application with all required
details by 9th May 2018.
34