DEL-71 Project at theUS 36/SR37 Interchange
Round Table Meeting
Ferzan M. Ahmed, P.E.- District 6 Deputy DirectorSteve Fellenger, P.E. – Project Manager
Wednesday, March 23, 2011
2
Project History
• ms consultants begin initial Safety Study and Design - Fall 2001• Existing Interchange Studies by Gresham Smith & Partners – 2004• Safety Studies by LJB Inc. - 2004 – 2006• Traffic Impact Study submitted by Northstar - 2005 • Wilson Road Constructed – 2006• Permit to Connect Wilson Road to US 36/SR 37 – Sept. 2006• Public Meeting held for Safety Project – Sept. 2007
3
• Short Term Solution - No Build Condition for the Long Term Interchange Project
• Construction Cost Estimate (Stage 2) - $4.33M
Project History
4
Project History• Early Meetings with Developers on Interchange – August 2008• Connective Roadway Network Established – October 2008• Traffic Modeling & Certified Traffic Developed – Dec. 2008 – Aug. 2009• Feasibility Studies Provided by Each Developer – 2009/2010• 2009 TRAC Application Submission – November 2009• Combined Feasibility Study – June 2010• Updated Certified Traffic – August 2010• 2010 TRAC Application Request – August 2010• Additional Modeling Completed – October 2010 & March 2011
• Safety Project Construction (No Build Condition) – Summer 2012
Interchange Project Area
6
Transportation Review Advisory Council (TRAC)
• DEL-71 project part of the 2011-2015 Draft list– Tier II Status– $5M toward Preliminary Engineering– Final List to be provided by April 2011
Schedule/Funding– Current Construction Schedule: Unknown until a preferred alternative is determined – Order of Magnitude estimate by EMH&T and ms consultants
*Includes right of way to be donated.
– Interchange – Possible Future TRAC Request - % To Be Determined– Local Road Network – Funded by Local/Developer Partnership
TRAC Request (PE)
Detailed Design
Right of Way* Construction
Interchange $5 M $4 M $1 M $40-50 MLocal Road
Network $4 M $22 M $40-60 M
Total $8 M $23 M $80-110 M
7
Task Order/NEPA
• Office of Environmental Services (OES) created task order with LJB Inc.
– Develop a Purpose and Need Statement– Determine Logical Termini– Create the Existing and Future Conditions Report
– Portions of the above Information submitted; Task Order not finalized
NEPA process determines the Preferred Alternative as the project fits the Purpose and Need Statement
8
Project DevelopmentProcess (PDP)
• New PDP designed to help projects like this move faster into Construction.
• PDP will focus on established criteria for narrowing alternatives quicker.
• PDP works to ensure design is completed concurrent with detailed NEPA work.
9
ODOT’s PDP
10
ODOT’s PDP- Next Steps
• Develop Concepts/Alternatives• Evaluate options to criteria (impacts, P&N,
ROW, Utilities, cost, etc.)• Public/Stakeholder involvement.• Conduct Detailed NEPA studies/design.• IMS/IJS study part of above work.
11
Interchange Modification Study (IMS) Process
• Interchange Feasibility Studies have examined access points on Interstate 71 both north and south of US 36/ SR 37.
• The studies also examined with and with out Big Walnut interchange as not to prevent it being part of the corridor in the future.
• IMS submitted by ms consultants on behalf of NorthGate Development for a Southern Concept Interchange – September 2010
• Much of the work for the traffic analyses has been performed and can be used in future analyses.
• ODOT agrees the Southern Concept has merit but will not provide further review until the environmental process can identify a preferred alternative. The southern concept provides more traffic relief to the US 36/SR 37 corridor.
• The NEPA (PDP) process might find another viable solution or determine different termini for the project which will need to be evaluated.