+ All Categories
Home > Documents > Delarosa Cost Estimation Final

Delarosa Cost Estimation Final

Date post: 19-Feb-2017
Category:
Upload: josh-de-la-rosa
View: 111 times
Download: 4 times
Share this document with a friend
24
Improving Survey Cost Estimates: Lessons Learned Applying GAO Best Practices at the US Census Bureau Josue De La Rosa U.S. Census Bureau International Field Directors and Technologies Conference May 17th-20th, 2015 Fort Lauderdale, Florida 1 Disclaimer: This presentation is released to inform interested parties of research and to encourage discussion. The views expressed are those of the authors and not necessarily those of the Census Bureau.
Transcript
Page 1: Delarosa Cost Estimation Final

1

Improving Survey Cost Estimates: Lessons Learned Applying GAO Best Practices at the US

Census BureauJosue De La Rosa

U.S. Census Bureau

International Field Directors and Technologies Conference

May 17th-20th, 2015Fort Lauderdale, Florida

Disclaimer: This presentation is released to inform interested parties of research and to encourage discussion. The views expressed are those of the authors and not necessarily those of the Census Bureau.

Page 2: Delarosa Cost Estimation Final

2

Objectives Introduce the GAO Best Practice Cost

Estimation Guide Twelve Steps of a High-Quality Cost Estimating

Process Lessons Learned Applied the Best Practices

Page 3: Delarosa Cost Estimation Final

3

Cost Estimation Is“Summation of individual cost elements, using

established methods and valid data, to estimate the future costs of a program, based on what is

known today.”

Page 4: Delarosa Cost Estimation Final

4

Why Is Cost Estimation Important

Formulating and explaining budgets Set priorities

Cost/ Benefit Analysis Evaluations

Mitigate the risk of: Budget variances Schedule slippage Scope and quality underperformances

Page 5: Delarosa Cost Estimation Final

5

“Suggested” Best Practices Guide is a suggestion, but used by GAO in

auditing/ evaluating programs

“quality estimating process resulted in unreliable cost estimates throughout each program’s life cycle.”

“Instead of using a cost model, it used an unsophisticated spreadsheet to extrapolate”

Page 6: Delarosa Cost Estimation Final

6

The Guide Authored by the

Government Accountability Office’s Applied Research and Methods

420 Pages, Published March 2009

Page 7: Delarosa Cost Estimation Final

7

Structure of Guide 12 Steps of a High-

Quality Cost Estimating Process Initiation & Research Assessment Analysis Presentation

20 Chapters 17 Best Practice Checklist 48 Case Studies

Page 8: Delarosa Cost Estimation Final

8

Define estimate’s purpose (1) Who needs the estimate and how will the

estimate be used? What level of detail is needed? When is the estimate due?

Page 9: Delarosa Cost Estimation Final

9

Develop estimating plan (2) Experience and trained

members Subject Matter Experts

IT Survey Methods FLD

Timeline and schedule

Page 10: Delarosa Cost Estimation Final

10

Define program characteristics (3)

Establish scope of work Technical Requirements Predecessors and successors Quantities and frequency Development, test, training and production

Personnel Risk

Page 11: Delarosa Cost Estimation Final

11

Determine estimating structure (4)

Thorough Work Break Down Structure = Good Best Practice

Results or product based WBS, not activity WBS matches scope of program WBS feeds schedule, Earned Value

Management metrics and cost estimate

Page 12: Delarosa Cost Estimation Final

12

Identify ground rules and assumptions (5)

In-scope/ out of scope Start and end date Identify any schedule or budget constraints,

inflation assumptions, and travel/ travel costs Determine technology refresh cycles Effects of new rules and regulations Risk associated with assumptiosn

Page 13: Delarosa Cost Estimation Final

13

Obtain data (6) Data collection plan

technical, schedule, cost, and risk data;

Adjust data for trends, inflation, learning, and quantity adjustments cost drivers;

Determine data reliability and accuracy;

Store data for future estimates

Page 14: Delarosa Cost Estimation Final

14

Develop point estimate (7) Estimate the cost of each WBS section

Analogy (A is like B) Engineering Build-Up Parametric (Cost = Quantity x Effort) Extrapolating Expert Opinion (Not recommend)

Organizational learning curve Statistical testing of estimate Independent Cost Estimate (ICE)

Page 15: Delarosa Cost Estimation Final

15

Conduct sensitivity analysis (8)

Sensitivity analysis = tested effect of changes to cost Key assumptions and factors on cost Schedule and quantities changes

Page 16: Delarosa Cost Estimation Final

16

Conduct risk and uncertainty analysis (9)

Determine for each risk: Level of cost, schedule & technical impacts Likelihood and impact of risk Min, max & likely range Monte Carlo simulation Risk adjusted cost (reserves for risk response) Risk management plan

Page 17: Delarosa Cost Estimation Final

17

Document the estimate (10) Purpose of estimate Review of previous steps Detail methodology

Team, date, approvals Schedule, technical baseline Data sources Estimating methods and justification Risk, uncertainty, sensitivity Compare to previous estimates

Page 18: Delarosa Cost Estimation Final

18

Present estimate to management for approval (11)

Develop a briefing that presents the documented life-cycle cost estimate;

Include an explanation of the baseline and any uncertainties;

Compare estimate to the budget; Focus on largest cost elements and cost drivers; Make the content clear and complete Act on and document feedback from management; Request acceptance of the estimate

Page 19: Delarosa Cost Estimation Final

19

Update the estimate to reflect actual costs and changes (12)

Update the estimate to reflect Replace estimates with EVM Report progress on meeting cost and schedule

estimates; Perform a post mortem and document lessons

learned for variance; Document all changes to the program and

how they affect the cost estimate

Page 20: Delarosa Cost Estimation Final

20

Lessons Learned Cost Estimation Professionals

Project management experience Business Analysis Survey methodology experience Organizational Maturity

Establishing a cost estimation plan Iterations (Agile)

Page 21: Delarosa Cost Estimation Final

21

Lessons Learned (continued) Importance of reliable data

Eg Census Planning Database http://www.census.gov/research/data/planning_database/

Treat IT systems as IT systems Relationship between Total Survey Error and cost drivers

Contact attempts Sample size drivers Non-response Frame Improvements (listing)

Page 22: Delarosa Cost Estimation Final

22

Identify and Address Challenges

Page 23: Delarosa Cost Estimation Final

23

Summary Effort put into cost estimation = importance of

accuracy Good cost estimates allow for better cost

management Understand how current process compares to best

practices Minimize risk (e.g. hidden cost) Good management of cost allow for better cost

estimates

Page 24: Delarosa Cost Estimation Final

24

Contact InformationJosue De La Rosa

[email protected]


Recommended