Date post: | 03-Apr-2018 |
Category: |
Documents |
Upload: | immortalmarx |
View: | 214 times |
Download: | 0 times |
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 1/19
Delay, Disruption and
Acceleration
Michael J.R. Kremer
Contract Management in
International Construction
Beijing, April 28, 2009
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 2/19
Delay, Disruption and Acceleration · April 2009 1
1. Introduction
Time is of essence in basically every constructionproject
Yet, delays of some sort are general rule, rather
than the exception
Consequence: claims for extension of time, issue of acceleration
Therefore, closer look to:
What are the obligations as to time in general?
When and how does acceleration become relevant?
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 3/19
Delay, Disruption and Acceleration · April 2009 2
2. Contractor„s obligations as to time
Modern construction contracts typically foresee threeseparate, but inter-related express obligations:
First obligation: Contractor to complete works by
certain date or within specified period; possibly withstage or sectional completion obligation
Second obligation: Contractor to progress the works
regularly and diligently
Third obligation: Contractor to prepare and work to anaccepted program (work schedule)
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 4/19
Delay, Disruption and Acceleration · April 2009 3
2.1 First obligation: specific date/period
In case of “period for completion”, identification of “commencement date” as well as periods crucial
e.g.: x months from the “Commencement Date”
clarification of “days” and “weeks”
If no date or period foreseen: obligation to complete“by a reasonable time”
Standard form contracts regularly provide for
express obligation
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 5/19
Delay, Disruption and Acceleration · April 2009 4
2.1 First obligation: specific date/period (cont‟d)
Effect of specific date of completion typically no qualification as of the essence
clauses for extension of time or liquidated damages
prevent such interpretation
Specific date of completion of little assistance inmanagement of the project
Employer wants to take action early to avoid late
completion
stage or sectional completion obligations andliquidated damages give only limited recourse
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 6/19
Delay, Disruption and Acceleration · April 2009 5
2.2 Second obligation: “progress regularly”
If specific date for completion agreed, no “implied”second obligation
Contractor has right to plan, execute and progress
the works
severe evidential difficulties for Employer Therefore: express obligation (regularly included
in standard form contracts)
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 7/19
Delay, Disruption and Acceleration · April 2009 6
2.2 Second obligation: “progress regularly” (cont‟d)
Effect of express obligation to proceed regularlyand diligently“Proceed continuously, industriously and efficiently with
appropriate resources so as to progress steadily towards
completion substantially in accordance with the contract.”
Contractor may not slow down even if ahead intime schedule
Employer may have remedy of damages, even if
completed in time, if Employer can show “loss”
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 8/19
Delay, Disruption and Acceleration · April 2009 7
2.3 Third obligation: program
“program/work schedule” no legal term Requires basic information of activities or operation
with a list of dates for commencement and completion
of respective activities
Types of programs:Bar Chart Network Program Line of Balance
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 9/19
Delay, Disruption and Acceleration · April 2009 8
2.3 Third obligation: program (cont‟d)
Potential roles of the program: Monitor role:
- milestone program
- progress program
- prediction program
Dynamic role
- management program- compensation program
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 10/19
Delay, Disruption and Acceleration · April 2009 9
3. Employer„s obligations as to time
Completion of obligations specified in the contract e.g. supply information, provide material, execution
of certain pre-condition works, permits,
appointment of engineer etc.
- at times specified in program
- or reasonable times with regard to execution of works
Typically no obligation to comply with approved
program, rather obligation not to hinder Contractor
implied obligation not to hinder implied obligation to cooperate
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 11/19
Delay, Disruption and Acceleration · April 2009 10
4. Acceleration
What does the term mean? What is the benchmark? Basically, tow situations relating to the overall
works:
Contractor is required to finish earlier than the
contractual date- variation of the contract, i.e. constructive order/change order
- constructive acceleration
Contractor is likely to complete later than the
contractual completion date- acceleration to reduce delays
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 12/19
Delay, Disruption and Acceleration · April 2009 11
4.1 Constructive acceleration
typical example for constructive acceleration claim:
Equipment procured by Employer from a third-party is
delivered late. Contractor‟s words are delayed.
Contractor applies for Extension of Time (EOT). Interimassessment of the Engineer denies EOT; final review
still pending. Employer presses Contractor to increase
resources to make up for the delay.
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 13/19
Delay, Disruption and Acceleration · April 2009 12
4.1 Constructive acceleration (cont‟d)
Contractor„s stark choice: Continue in hope to prove EOT or “accept” to be in
default temporarily and take steps to mitigate
Nature of problem: contract‟s EOT procedures
and contractor‟s “temporary default” Conclusion: Constructive acceleration claim
presents significant legal difficulties; claim for
disruption may be possible with fewer legal
difficulties
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 14/19
Delay, Disruption and Acceleration · April 2009 13
4.2 Acceleration to reduce delays
The issue of right or obligation to reduce the effect of qualifying delays may arise in three ways:
- Contractor‟s may have right to choose how to deal with a
qualifying delay and whether to accelerate or not and to
recovery on the basis of this right;
- Contractor may be entitled to EOT and any associated loss
only to the extent that he has mitigated the effect of the delays;
- Contractor may be under an obligation to progress the works
including an express obligation to mitigate delays and the
failure to do so prevents remedies of EOT/associated losses.
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 15/19
Delay, Disruption and Acceleration · April 2009 14
4.2 Acceleration to reduce delays (cont‟d)
Mitigation of delay by acceleration? Contractor reacts to the qualifying delay
- most contracts provide for EOT provisions and express termsfor agreement for acceleration
- generally no right of contractor to accelerate and recover costs
(except if “constructive order”) - “reasonabless”-argument
Contractor does not react to the qualifying delay- Generally no obligation where EOT provisions apply
Mitigation by managing delay?
obligation to re-plan recourses and activities
obligation to progress “regularly & diligently” includesmanaging of effects of delay
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 16/19
Delay, Disruption and Acceleration · April 2009 15
4.3 Obligation to accelerate?
Differentiation by reason for delay:
Delay not caused by Contractor, i.e. entitled to EOT- no obligation; only by means of separate agreement
Delay caused by Contractor:- in principle no obligation (discretion of contractor in regard of
his own culpable delay)- contract may provide power to order Contractor to adopt
acceleration measures
“Indirect” obligation
Contractor must weigh costs of acceleration, chance of recovery against liquidated damages potentially leviedagainst him
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 17/19
Delay, Disruption and Acceleration · April 2009 16
4.4 Entitlement to acceleration
Contractor may perceive commercial advantageto accelerate; generally only bound by completion
date
Generally no obligation of the Employer to co-
operateException: entitlement of acceleration provided in
the contract and bound to program
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 18/19
Delay, Disruption and Acceleration · April 2009 17
5. Conclusion
Time is of the essence in construction projects
The effort of planning, negotiating and draftingdoes not end at providing sophisticated terms for the event of delays by
finding a realistic completion date,
incorporating EOT provisions and delay relatedliquidated damages
Instead, the same though and sophisticationshould be put in addressing delays in terms of
acceleration, rather than only dealing with them interms of EOT and liquidated damages.
7/28/2019 Delay, Disruption and Acceleration
http://slidepdf.com/reader/full/delay-disruption-and-acceleration 19/19
Clifford Chance, Königsallee 59, 40215 Düsseldorf, Germany
© Clifford Chance 2009
Clifford Chance Partnerschaftsgesellschaft von Rechtsanwälten, Wirtschaftsprüfern,
Steuerberatern und Solicitors · Sitz: Frankfurt am Main · AG Frankfurt am Main PR 1000
www.cliffordchance.com
Delay, Disruption and
Acceleration
#960898
Contract Management inInternational Construction
Beijing, April 28, 2009