+ All Categories
Home > Documents > Delhi Metro Railway-Group 4

Delhi Metro Railway-Group 4

Date post: 10-Apr-2018
Category:
Upload: bhaskar-das
View: 219 times
Download: 1 times
Share this document with a friend

of 16

Transcript
  • 8/8/2019 Delhi Metro Railway-Group 4

    1/16

    DELHI METRO RAILWAY CORPORATION

    BHARANI SHANKAR (1011162)BHASKAR DAS (1011163)

    BHUPESH VERMA (1011164)BITANGSHU BARAL (1011165)DEBASMITA PANJA (1011166)

  • 8/8/2019 Delhi Metro Railway-Group 4

    2/16

    P

    age

    2

    TABLE OF CONTENTS

    EXECUTIVE SUMMARY .......................... .......................... ......................... .......................... ......................... . 3

    OVERVIEW ......................... .......................... ......................... ........................... ......................... ...................... 4

    INNOVATION & SOCIAL IMPACT ................................. ........................... ......................... .......................... 5

    INNOVATION IN OVERCOMING THE BARRIERS ........................ .......................... ......................... ......... 6

    ASSESSMENT .......................... .......................... .......................... ......................... .......................... .................. 9

    CONCLUSION ................................................................................................................................................ 11

    APPENDIX 1 ................................................................................................................................................. 13

    APPENDIX 2 ................................................................................................................................................. 14

    APPENDIX 3 ................. .......................... .......................... ........................... ......................... ....................... 15

    REFERENCES ................................................................................................................................................ 16

  • 8/8/2019 Delhi Metro Railway-Group 4

    3/16

    P

    age

    3

    EXECUTIVE SUMMARY

    The Delhi Metro Railway Corporation (DMRC) was setup in 1995, by the Government of India and state

    government of Delhi to provide the city with a reliable transportation system which could reduce the

    vehicular congestion and also cater to the rapidly growing population. The major funding for the

    project was provided by the Japanese International Cooperation Agency (JICA), with the Central and

    Delhi State Governments proving a substantial portion. The rest was financed by loans and property

    development.

    The metro network has been planned to spread across 413 kilometers by the year 2021 and was

    divided into four phases for construction. The construction of Phase I began on October 1, 1998 and

    was successfully commissioned by 11th November 2006 with an estimated cost of completion of

    `10,571 crore. Presently construction is in-progress for 121 kilometers in Phase II. Phase III and

    Phase IV are estimated to be completed by 2015 and 2021.

    Even though infrastructure projects in India have been plagued with delays, cost overruns and

    inefficiency, the Delhi Metro project has managed to avoid all these issues by excellent project

    management, focus on technology, cost control and effective management of the various

    stakeholders. The success of the project can be gauged based on the output on the following fronts -

    Improved public transit and a long-term scalable solution to the traffic solution problem The environmental benefits due to reduced growth of vehicular population, annual fuel savings

    and substantial reduction in air pollution

    A renewed focus on improving urban transport by replicating the MRTS system in other cities Adoption and indigenization of state-of-the-art civil engineering and construction technologies Transformation of the urban social landscape of Delhi

    The project has its share of detractors too; who have pointed out that the project has not taken into

    consideration the social and economic inequities that afflict the Indian society. Public transport has

    served as a leveler and the high fares may affect the mobility of the lower strata. Cheaper mass

    transport options like Bus Rapid Transit Systems (BRTS) have not been explored completely due to the

    focus on the metro rail system. In addition a large portion of Delhi Metros revenue comes from its real

    estate portfolio, which may not be a viable model for other cities to emulate.

    On an overall basis, Delhi Metro represents an iconic image for a new India that symbolizes growth,

    pride, ownership and respect for the values being instilled by the new system. As an emblem of public

    infrastructure in India, it represents the hope that such projects can transform the lives of the citizens

    and serve as a template of future implementations.

  • 8/8/2019 Delhi Metro Railway-Group 4

    4/16

    P

    age

    4

    OVERVIEW

    Delhi Metro Rail Corporation Ltd was setup in equal partnership by the Government of India (GoI) and

    the Government of National Capital Territory of Delhi (GNCTD) in 1995, with E. Sreedharan as the

    managing director. This development came about due to the following concerns

    Delhi saw a rapid growth in population from 57 lakhs in 1981 to 162 lakhs in 2006. This hasbeen accompanied by vehicular congestion, due to increase in number of vehicles from 5.4

    lakhs in 1981 to 51 lakhs in 2007.i

    Traffic on roads of Delhi had become a chaotic heterogeneous mix of cycles, scooters, buses,cars and rickshaws which has resulted in an increase in road accidents. The average number of

    people killed per day has increased to 5 and of those injured to 13. The position was expected

    to deteriorate further in the years to come. i

    The private bus transport which was encouraged in 1992 to supplement the public bus servicein Delhi, failed completely due to unreliability of service, extreme overcrowding, unqualifieddrivers, speeding and reckless driving, and often ran down passengers waiting at bus stops.

    ii

    This called for a policy shift to encourage public mode of transport over private form. The Central Road

    Research Institute (CRRI) had carried out an extensive analysis on the traffic characteristics of Delhi in

    1969-1970 and recommended for Mass Rapid Transit Network in the city. The first concrete step in this

    direction was, however, taken when a feasibility study for developing such a multi-modal Mass Rapid

    Transit System (MRTS) system was commissioned by GNCTD (with support from GoI) in 1989 and

    completed by Rail India Technical and Economic Services (RITES) in 1991. The initial plan for Delhi

    metro was thus conceptualized.iii

    Also Delhi was well staged for an excellent MRTS to be brought in. Ithas wide roads (roads cover 23% of the city area) and possession for construction is not difficult

    (except in the old city area). Implementation would also not involve large scale demolition of private

    properties. In addition most of the land required was under government control and hence could be

    easily acquired. i

    The metro network was planned to spread across 413 kilometers by the year 2021. The construction

    for the 65.1 km route of Phase I began on October 1, 1998 v and Delhi Metro Railway Corporation

    (DMRC) has already successfully commissioned by 11th November 2006 with an estimated cost of

    completion of`10,571 crore. Presently DMRC is working on extension of Phase II of the project (121

    kilometers) that started on September 2006 and has a demanding target of September 2010 because it

    has to be completed before the Commonwealth Games in October 2010. This means that while Phase

    I was completed in seven years and nine months, Phase II has to be constructed in three and half

    years. Phase III and Phase IV are planned to be completed by 2015 and 2021.

  • 8/8/2019 Delhi Metro Railway-Group 4

    5/16

    P

    age

    5

    INNOVATION & SOCIAL IMPACT

    The Delhi Metro Rail Corporation created a world-class mass rapid transit system, by successfully

    managing the various stakeholders like the central and state governments, the contractors, and the

    citizens of Delhi and ensured that the project was implemented smoothly by dividing it into differentphases. The first phase of the network comprised of 65.1 km of route length with 13 km of

    underground tracks called Metro corridor and 52.1 km surface or elevated tracks called Rail Corridor. vi

    A unique feature of the project was that when Phase I was sanctioned by DMRC in 1996, the Union

    Cabinet had directed that about 7% of the initial project cost should be generated through property

    development on lands which had been given to DMRC and recurring income should be generated

    through property development for paying back subordinate debts. Most of the land was made

    available to DMRC on 99 years lease at nominal rent at interdepartmental transfer rates.vii

    However

    the project has been made possible due to soft loans extended by the Japan International Cooperation

    Agencyviii

    . The capital cost of Phases I and II had been estimated at approximately `14,430 crore in

    2004. ix

    The project brought in a lot of new technologies into the country. A number of innovative practices like

    driving of tunnels with earth pressure balanced mechanical shields, ballast less track technology,

    automatic ticketing and signaling, high end communication systems between the trains and the

    operation control centers, light weight and air conditioned metro coaches and station buildings. The

    project adopted the usage of precast concrete technology which though costly ensured high quality

    and aesthetics. High-tech coaches were designed by a consortium of Mitsubishi, Japan and Rotem,

    Korea. The lines comprise both underground and surface or elevated corridors.

    Delhi Metro also has high end security features and has taken up several measures to ensure

    passenger safety. Delhi Metro strongly follows the guidelines laid down by the National Fire Prevention

    Association. It has an automatic mechanism to detect obstructions within 15 mm between doors. The

    doors remain closed during running and if open all of a sudden during movement, brakes are applied

    automatically to bring the train to a halt. The train starts moving only when all the doors are closed.

    Emergency measures are also provided. Security on the Delhi Metro is handled by the CentralIndustrial Security Force. Closed-circuit cameras, metal detectors and X-ray baggage inspection

    systems are some of the security features that have been used in the Delhi Metro. Escalators, elevators

    and tactile tiles to help the visually impaired persons are present in all the stations.v

    The trains use centralized automatic train control (CATC) comprising of automatic train operation

    (ATO), automatic train protection (ATP) and automatic train signaling (ATS) systems. Intercoms are

  • 8/8/2019 Delhi Metro Railway-Group 4

    6/16

    P

    age

    6

    available for Emergency communication between passengers and drivers. Route maps and LCD display

    systems are present in every coach. Contactless, stored-value smartcards are used for fare collection.

    DMRC has joined hands with Google India recently to provide train schedules to mobile devices

    through Google maps.vi

    Though the first metro of India was opened by Kolkata, it could not boost the confidence of the

    Government to go forward further with similar schemes in other cities. Delhi Metro has been a trend

    setter for several projects involving mass transit system in our country. The implementation period has

    taken less time than what was expected. Many cities like Mumbai, Chennai, Bangalore, Hyderabad,

    Kochi and Chandigarh are expected to get metro systems over the next few years, being encouraged by

    the system in Delhi. xi

    Delhi Metro has also been appreciated for its environment friendly practices. It has got awards for

    environment consideration aspect from the United Nations. Extensive measures for environment

    protection like conducting rainwater harvesting have been taken. Delhi Metro has also implemented

    efficient technologies like regenerative braking systems to reduce the overall power requirement.x

    DMRC is one of the two metros all over the world to be ISO 14001 certified for environment

    friendliness.xi

    The Metro has provided employment benefits to unskilled labor especially during the construction

    phase. Delhi Metro has resulted in a hike in house property prices which has benefitted land and house

    property owners. Since there has been a diversion of a portion of the city traffic to Metro, savings in

    fuel consumption have taken place resulting in foreign exchange savings. It reduced the need for

    parking spaces, expansion of roads, flyovers, construction of new roads etc. in areas which are being

    served by it. Petrol and CNG have been substituted by electricity thereby reducing air pollution.xxv

    INNOVATION IN OVERCOMING THE BARRIERS

    Infrastructure projects in India have been plagued with rampant corruption, cost overruns, political

    inertia and interference, bureaucratic inefficiency. The MRTS project for Delhi which was first

    conceived in 1969, did not make much headway until the late 1990s due to issues with project funding,bureaucratic hassles and lack of clarity between central, state governments on who was responsible

    for urban mass rapid transit. It was in 1995 that DMRC was finally incorporated as a separate entity

    and the initial financing was obtained through a combination of international and local funding

    sources. 64% of the project cost was funded by the Japanese International Cooperation Agency (JICA);

    28% was funded equally by the Central and Delhi State Governments; both governments financed a

  • 8/8/2019 Delhi Metro Railway-Group 4

    7/16

    P

    age

    7

    further 5% through loans to cover land acquisition costs and the last 3% of the costs were to be funded

    through property development.vii The Delhi project also had to overcome many barriers, some of which

    are discussed below -

    Technology

    Technology exchange was a salient feature in the development of the Delhi Metro. A main

    requirement in the global bidding process for contracts was that there should be at least one Indian

    partner, which led to technology absorption by Indian firms, localization, re-engineering and

    indigenization of technology. Special construction technologies like trenchless digging, use of

    ballastless tracks and precast concrete were used which reduced the project duration. Some of the

    major technology challenges include -

    Tunneling in the Old Delhi area where buildings had weak foundations. The tunnels weretherefore constructed at a depth of more than 20 meters.

    Metro viaducts were built over railway bridges without disturbing the traffic A continuous pre-stressed box girder of length 553 meters was built across the river Yamuna

    using a special technique called incremental launching without traffic disruption. The bridge

    was completed in a period of just 30 months and there are no joints which enables a smoother

    journey.xii

    Delhi Metros success has ensured that Indian companies are now almost self sufficient in technology

    to take up similar projects in other cities. xiii

    Project Execution

    The DMRC project was headed by E. Sreedharan who had vast experience in the implementation of the

    Kolkata Metro and the Konkan Railway (which was the first big project to be completed under the

    Build-Operate-Transfer basis). He was given full autonomy on all matters and was the last authority on

    tenders. He implemented the following processes which enabled completion of the project within the

    stipulated deadlines -

    The DMRC had a lean organizational structure comprising of only 2 departments - projectorganization and operation & maintenance. The organization culture was based on punctuality,

    honesty and strict adherence to timelines.

    A team of people received training at Hong Kongs Mass Rapid Transit Railway to get a firsthand understanding of the nuances of the project.

    The contract awarding and procurement processes were simple, transparent without anysubjective elements. This prevented corruption and ensured a level playing field.

  • 8/8/2019 Delhi Metro Railway-Group 4

    8/16

    P

    age

    8

    Thorough planning and effective project design were the focus areas. Adherence to theschedule was stressed and the project progress was reviewed every week. Employees had

    schedules with reverse clocks to indicate the number of days left before important deadlines.

    Primavera Project Planner, special software was used for project planning and monitoring. Theresource management module alerted managers in case of shortage or excess of resources. Thesoftware also tracked the various project activities completed at different levels vs. the actual

    schedule. Managers were also alerted of critical / upcoming activities so that they can be

    tracked / rescheduled if necessary. All these were required as a days work lost resulted in a

    loss of`50 lakhs.xii

    Cost Control

    The main reason for cost over-runs in big projects is non-adherence to the project schedule due to

    delays in land acquisition, legal hurdles, etc. Some of the cost control measures which were

    implemented in DMRC include -

    The Delhi Metro Railway (Operation & Maintenance) Act, 2002 provided special powers toDMRC to acquire land for the metro / other utilities or property development in order to

    recover costs. This law superseded Delhis local municipal laws and stay orders could not be

    issued by lower courts. It has not provided for resettlement and rehabilitation and deals with

    the cash component only. However many were displaced without any say and litigations are

    still in process.

    DMRC entered into a special agreement with Delhi Transco Ltd power supply at low rates. Italso negotiated with the central government for exemption of import duty and excise tax and

    with the state government for exemption of sales tax and work contract tax, resulting in cost

    savings of about `1800 crore.

    Pacific Consultants International (PCI) provided overall consultancy for the project. A major partof the project was supervised by consultants and construction was delegated to a consortium of

    contractors. This reduced the in-house governance cost drastically.xii

    Managing the stakeholders

    The main stakeholders of the project included the central and state governments, funding agencies,

    contractors and the public. DMRCs autonomy was ensured in recruitments, promotions, land acquisition and awarding of

    contracts. No decision was reviewed / changed unless there was a need for it from a

    professional or technical perspective.

    JICA which was the lead financier and was engaged throughout the project.

  • 8/8/2019 Delhi Metro Railway-Group 4

    9/16

    P

    age

    9

    DMRC organized community interaction programs to elicit solutions from the public on variousissues.

    IIT Delhi was involved in planning alternate traffic arrangements to that inconvenience to thegeneral public due to the construction work was minimum. In addition care was taken so that

    other utilities (like water pipes, sewers, etc) were diverted before the work commenced on aparticular section.

    xii

    By virtue of the above, the number of persons employed per kilometer of track was only 45, which is a

    third of that employed for the Kolkata Metro Rail project. The first phase of the project which was

    estimated to cost about `6000 crore (at 1996 prices), was completed at a cost of`10571 crore.xiv

    ASSESSMENT

    India has a very unenviable track record for unimplemented urban plans, and the biggest achievement

    of the Delhi Metro rail project has been efficient construction and running a technically advanced

    operation in a challenging environment.

    The effectiveness of the project can be assessed in five themes

    Improved public transit has ensured that the project hasprovided a long lasting solution for commuters in a traffic

    congested city like Delhi. Approximately 1.05 million passengers

    use the metro system of normal weekdays.xv

    The environmental benefits are assumed to be in range of 1,800fewer buses on the roads, annual fuel savings of `1712 million

    and substantial reduction in air pollution.xvi

    Political consensus on the project has resulted in itsendorsement by most of the political and social constituents,

    which has in turn has resulted in encouraging other cities to

    opt for such metro systems. DMRC which was able to

    implement the metro network ahead of schedule and on

    budget, is the consultant on many such projects.

    New technologies were introduced into the country via thisproject, including advanced tunneling techniques, ballast-less

    track technology, sophisticated signaling system with

    automatic train protection, ticketing system etc. The project management expertise which was

    developed during the course of the project will serve as a trendsetter for future mega public and

    private projects. xi

    REDUCTION IN FUEL CONSUMPTIONDUE TO PHASEI & II

    CNG82.91Million

    Kg

    Petrol 87.5Million liters

    Diesel 15.75Million liters

    Phase

    I + II

    Buses1800

    2Wheelers320000

    Cars90000

    3Wheelers

    19000

    Estd REDUCTION IN VEHICLES (2011)2

  • 8/8/2019 Delhi Metro Railway-Group 4

    10/16

    P

    age

    10

    The metro has also enabled transformation of the urban social landscape of Delhi, by inculcating aculture of discipline, order, routine and cleanliness in the community. The technology and scale of

    the project has attracted attention of the global community on the city thereby allowing it to stake

    a claim as a world-class city.xvii

    However studiesxviii have suggested that the project has not been able to avoid the inequities which

    result from the economic disorientation caused by the land appropriations along the route (whose final

    alignment is guided by property development considerations).

    Most of the affected are slum dwellers and lower income category families, who have been

    marginalized further by relatively high metro fares. In a city with such visible disparity between the rich

    and the poor, low cost (and sometimes subsidized) transport mechanism had been serving as one of

    the levelers. Also the lack of dissenting opinion on the project has meant that cheaper options like Bus

    Rapid Transit Systems (BRTS) have not been explored completely. In addition Delhi Metro has used the

    large tracts of land it got from the government for develop real estate and now 33 per cent of its total

    revenue is coming from the same (in comparison to 54 per cent from traffic).xix

    Delhi Metros profit is

    boosted by what it earns from real estate, which may not be a viable model for other cities to emulate.

    The accelerated rate of construction due to the completion of phase II before the Commonwealth

    games resulted in few accidents as listed below -

    Aug 28, 2007: A crane driver died after a concrete block fell on him due to a "technical failure"at a Delhi Metro construction site in Mayur Vihar in east Delhi.

    Oct 19, 2008: An under construction flyover collapsed in east Delhi due to mechanical failureleading to the death of at least two people. Nearly 30 people were injured.

    Jan 21, 2008: A laborer was killed at a Delhi Metro construction site in east Delhi due to thecollapse of one side of the construction site.

    July 12, 2009: An under construction bridge collapsed during erection process near centralsecretariat causing five casualties and injuring the other five.

    These incidents questions the safety norms followed during the construction phase by DMRC and its

    contractors.xx

    The DMRC is also not able to manage the increasing passenger traffic. The increased frequency ofservices has sometimes led to technical snags. xxi,xxii In addition to that the feeder bus service has not

    able to achieve the desired result.xxiii

    Some of the allegations leveled by CAG (Comptroller and Auditor General of India) audit against DMRC

    include -

    Neither the central nor the state government is involved in the management of the companyand the companys board does not have any independent directors. In some cases, changes

  • 8/8/2019 Delhi Metro Railway-Group 4

    11/16

    P

    age

    11

    were made to the contracts after they were awarded and there were some discrepancies in

    evaluating the contracts. In phase II of the project with the 2010 Commonwealth Games as

    target, some tests pertaining to the construction were conducted in non-accredited

    laboratories and DMRC has not maintained proper records of the testing reports.xxiv

    The loan of nearly `6600 crores to DMRC has been subsidized by the central government andno dividend has been paid for the governments equity component. Together they constitute a

    loss of nearly `1000 crores. xxii

    DMRC acquired more land than what was legitimately required, nearly 32.5 lakh square feet ofland was acquired for phase I. No record has been maintained for the acquired land. In

    addition, DMRC is not paying property tax for the land under development.xxii

    DMRC also does not have a visible second rung leadership and Sreedharan has been blamed for not

    nurturing one who can take over from him. DMRC was setup in 1996 and there is no public face other

    for the organization other than Sreedharan. This could lead to a leadership void when he retires.xxv

    CONCLUSION

    Best Practices in the Delhi Metro Rail Corporation (DMRC)

    The Delhi Metro Rail Corporation has incorporated state-of-art technology which represents the

    commitment of the organization towards the adherence of the one of the best practices in the world.

    It has continually and proactively introduced innovative ideas like the automatic ticketing and signaling,

    air-conditioned coaches and station buildings, integrated smart card with Citibank credit card etc. in

    the process.xxvi

    The safety features implemented in the project is also one of the best among the worldwide metro

    services. DMRC has now found a place in Nova (an elite and exclusive club for medium-sized urban

    railway systems), which is an exclusive international forum for world's urban railways, that helps others

    with technology transfer and also sets the best practices standards for the industry as a whole.xxvii

    Implementation in other cities

    DMRC is also transferring the technology to metro systems of other cities. For overcoming the trafficproblems in our major cities Metros are the ideal solution. The implementation can be done in a phase

    wise manner and so the initial planning has to be done for major cities having population more than 3

    million and then in second phase the concentration should be on cities with population more than 1

    million.xxviii

  • 8/8/2019 Delhi Metro Railway-Group 4

    12/16

    P

    age

    12

    Govt

    46%

    Public

    21%

    Unskilled

    labour

    0%

    Passenger

    33%

    The major challenge in the implementation is viability and connectivity with the existing system. This is

    quite evident from the example of Kolkata Metro system which is not able to attract the estimated

    traffic. So before implementation of the system in other cities the Government or the Metro system

    has to meet the need of the commuters which basically revolves around parameters like accessibility,

    travel time, frequency and safety.xxix

    PPP (Public Private Partnership)

    In Mumbai, Metro Phase-I will be implemented on a Build-Own-Operate-Transfer basis for the period

    of 35 years. High fund requirement is also a factor to promote the PPP in this sector. An estimate

    suggests that over half a dozen cities in India will require $12.5 billion to get metro systems. Various

    models like viability gap funding (VGF) has been proposed. The central government has agreed to fund

    some of the projects by a mechanism called viability gap funding (VGF). Non-operational revenues

    constitute 30% of the total and it also signals the high possibility of PPP in the non-operational

    revenue. Economic internal return ratio of the project works out to 21.4% and the financial return ratio

    of 3% also make PPP justified in this sector.xxx

    Social Benefits

    Delhi Metro is the first railway project to be registered under Clean Development Mechanism of United

    Nations to earn carbon credits. It is slated to earn

    400,000 carbon credits for the period of 10 years

    starting from December 2007. This will generate a

    revenue of`1.2 crore in the future.xxxi Metro also

    creates an incomparable experience of short trips

    that represents the efficiency, modernity and sense

    of progress the new system. A substitution for the

    existing road transportation system is also needed

    because of the increase in the frequency of road accidents which added to the sense of insecurity for

    this mode of transportation. The Metro has also transformed the social culture giving us a sense of

    discipline, cleanliness and enhanced multifold development of the place.

    At the same time it also presents an iconic image that could generate a sense of public pride,

    ownership and respect for the values being instilled by the new system.

    xxxii

    Net Benefit of Metro viii

  • 8/8/2019 Delhi Metro Railway-Group 4

    13/16

    P

    age

    13

    APPENDIX 1

    Phase I of Delhi Metro Rail project consisted of the following three lines xxxiii

    Line Length (Kms) No. of Stations

    Shahdara-Tri Nagar-Rithala 22.06 18 Vishwa Vidyalaya-Central Secretariat 10.84 10

    Indraprastha-Barakhamba Road-Dwarka Sub City 32.10 31

    Phase II of the Delhi Metro Project consist of the following lines xxiv

    Line Length (Kms) No. of StationsShahdara Dilshad Garden 3.09 3

    Indraprastha Noida Sector 32 City Centre 15.07 11

    Yamuna Bank Anand Vihar ISBT 6.17 5

    Vishwavidyalaya

    Jahangir Puri 6.36 5Inderlok Kirti Nagar Mundka 18.46 15

    Central Secretariat Sushant Lok 27.45 19

    Dwarka Sector 9 to Dwarka Sector 21 2.76 2

    New Delhi Airport 19.20 4

    Anand Vihar KB Vaishali 2.57 2

    Central Secretariat Badarpur 20.04 15

    Phase III (planned) with a total length of 112 kilometres, has a 2015 deadline, and tentatively includesextensions to Badli, Mukundpur, Bahadurgarh, Shiv Vihar, Barwala, Ghaziabad, Gurgaon and Faridabad.xxxiv

    Phase IV (planned) has a 2020 deadline, and tentatively includes further extensions to Sarai Kale KhanISBT, Sonia Vihar, Reola Khanpur, Mukundpur, Palam, Najafgarh, Ghazipur, Noida Sector 62, Gurgaon andFaridabad, having a total length of 108.5 km.xxv

  • 8/8/2019 Delhi Metro Railway-Group 4

    14/16

    P

    age

    14

    APPENDIX 2

    Delhi Metro Rail Networkxxxv

  • 8/8/2019 Delhi Metro Railway-Group 4

    15/16

    P

    age

    15

    APPENDIX 3 xxxvi

  • 8/8/2019 Delhi Metro Railway-Group 4

    16/16

    ge

    16

    REFERENCES

    i http://www.delhimetrorail.com/corporates/needfor_mrts.html

    ii The Crisis of Public Transport in India, Journal of Public Transportation

    iii http://delhigovt.nic.in/dmrc.asp

    v http://www.railway-technology.com/projects/delhi/

    vi http://www.delhimetrorail.com/corporates/history.html

    vii http://www.delhimetrorail.com/corporates/propertydvp/background.html

    viii http://web.iitd.ac.in/~tripp/delhibrts/metro/Metro/message%20in%20a%20metro%20-%20Matti.pdf

    ix http://mpra.ub.uni-muenchen.de/1658/1/MPRA_paper_1658.pdf

    x http://www.delhimetrorail.com/commuters/whats_new.html

    xi http://www.delhimetrorail.com/corporates/ecofriendly/iso14001.html

    xii http://www.indiaenvironmentportal.org.in/files/Delhi%20Metro.pdf

    xiii http://www.icjonline.com/interviews/Interview_Sreedharan_Nov_2002.pdf - Interview with E. Sreedharan

    xiv http://www.pkfindia.in/Value%20Adds/5%20IAVA%20-%20Lessons%20from%20the%20incredible%20%20Delhi%20

    Metro%20Project.pdf

    xv http://economictimes.indiatimes.com/articleshow/5973562.cms

    xvi http://www.delhimetrorail.com/corporates/ecofriendly/Chapter%205.pdf

    xvii Message in a Metro: Building Urban Rail Infrastructure and Image in Delhi, India International Journal of Urban andRegional Research

    xviii Socio-Economic Impact Assessment (SEIA) Methodology for Urban Transport Projects Provide more details

    xix DMRC Annual report 2008-2009

    xx http://www.hindustantimes.com/A-chronology-of-Delhi-Metro-accidents/H1-Article1-431402.aspx

    xxi http://www.indianexpress.com/news/widening-reach-metro-looks-at-ways-to-ease-rush/542010/0

    xxii http://www.hindustantimes.com/News-Feed/newdelhi/Crowded-stations-slow-trains/Article1-477845.aspx

    xxiii http://www.hindustantimes.com/News-Feed/newdelhi/Feeder-service-or-the-lack-of-it/Article1-484059.aspx

    xxiv http://www.cag.gov.in/html/reports/commercial/2008_PA17com/contents.htm

    xxv http://news.in.msn.com/business/article.aspx?cp-documentid=3077976

    xxvi The Indian Concrete Journal, November 2002, Delhi Metro : a trend setter project

    xxvii http://www.delhilive.com/page/delhi-metro-enters-exclusive-club-20070201756 and The Indian Concrete Journal,

    November 2002

    xxviii International Journal of Urban and Regional Research, June 2006, 277-92

    xxix Social cost benefit analysis of Delhi metro (October 2006) by Institute of Economic Growth

    xxx www.ibef.org/download/TRANSPORT.pdf

    xxxi http://economictimes.indiatimes.com/news/news-by-industry/transportation/railways/Delhi-Metro-is-first-rail-

    project-to-earn-carbon- credits/articleshow/2676012.cms

    xxxii Evaluation of public transport system systems : case study of Delhi metro by Mukti Advani & Geetam Tiwari

    xxxiii http://www.delhimetrorail.com/corporates/projectupdate/phase1_network.html

    xxxiv "Delhi Metro Master Plan 2021" - http://www.delhimetrorail.com/commuters/images/metro_map_big.jpg

    xxxv http://mapsof.net/delhi/static-maps/png/delhi-metro-rail-map

    xxxvi Mythologies, Metro Rail Systems and Future Urban Transport Dinesh Mohan (Economic & Political Weekly)


Recommended