Deliverable_ Profitability_of_Concepts _D.10_v1.0
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
i
Intelligent MegaSwapBoxes for Advanced Intermodal Freight Transport
Deliverable no. D10
Report on Results of Profitability Calculation of Concepts
Work package no.: 4
Work package name: Evaluation Phase
Lead participant: ZLW-IMA, RWTH Aachen University
Nature of Deliverable1: R
Dissemination level2: PU
Due del. date from Annex I: 19
Actual delivery date: 24
Version: 1.0
Status: final
1 R = Report; P = Prototype; O = Other
2 PU = Public; RE = Restricted to a group specified by the consortium
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
ii
Overview
Author(s): Sebastian Jursch,
Contact Person(s)
Organisation:
Address:
Email:
Tel: +
Fax: +
Sebastian Jursch
ZLW-IMA RWTH Aachen
Dennewartstr. 27, 52068 Aachen
+49 (0) 24180911-46
+49 (0) 24180911-22
Review
Date: Version: Reviewed by:
30.03.2010 00.01 CTL
04.2010 00.02 Wincanton
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
iii
1. Summary .............................................................................................................................. 1
2. Methods of Profitability Analysis ....................................................................................... 2
2.1 Introduction...................................................................................................................... 2
2.2 Return on Investment (ROI)............................................................................................. 3
2.3 Net-Present Value (NPV)................................................................................................. 4
2.4 Life Cycle Costing (LCC) ................................................................................................. 6
2.5 Value oriented cost-effectiveness estimation (NOWS) .................................................... 6
3. Considered Solutions.......................................................................................................... 9
3.1 Introduction...................................................................................................................... 9
3.2 Air-Tech-Box.................................................................................................................... 9
3.3 Fala-EC-Box .................................................................................................................. 11
3.4 Shoe-Box....................................................................................................................... 12
4. Procedure........................................................................................................................... 14
4.1 ROI & NPV .................................................................................................................... 14
4.1.1 Introduction........................................................................................................... 14
4.1.2 ROI and NPV comparison calculation:.................................................................. 15
4.1.3 Fixed and variable costs ....................................................................................... 15
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
iv
4.1.4 Economies of Scale .............................................................................................. 16
4.1.5 Modelling the transport costs function .................................................................. 17
4.1.6 Transport costs in road traffic ............................................................................... 20
4.1.7 Transport costs in rail traffic.................................................................................. 23
4.1.8 Transportkosten in shipping traffic ........................................................................ 24
4.1.9 Costs for loading and unloading ........................................................................... 26
4.1.10 Handling costs ....................................................................................... 27
4.1.11 Transport independent costs ................................................................. 28
4.2 Life Cycle Costing (LCC) ............................................................................................... 34
4.3 Value oriented cost-effectiveness estimation (NOWS) .................................................. 35
5. Findings.............................................................................................................................. 37
5.1 Return on Investment (ROI) & Net Present Value (NPV)............................................... 37
5.2 Life Cycle Costing (LCC) ............................................................................................... 47
5.3 Value oriented cost-effectiveness estimation (NOWS) .................................................. 50
6. Conclusion ......................................................................................................................... 57
7. Bibliography....................................................................................................................... 58
8. Appendix ............................................................................................................................ 62
8.1 Cost aspects of AirTech-Box ......................................................................................... 62
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
v
8.2 Benefit aspects AirTech-Box ......................................................................................... 63
8.3 Cost aspects Fala-EC-Box ............................................................................................ 64
8.4 Benefit aspects Fala-EC-Box......................................................................................... 65
8.5 Cost aspects Shoe-Box ................................................................................................. 66
8.6 Benefit aspects Shoe-Box ............................................................................................. 67
8.7 Cost Model TelliBox....................................................................................................... 68
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
vi
List of Figures
Figure 2-1: Value oriented cost-effectiveness estimation (NOWS) ......................................8
Figure 3-1: Air-Tech-Box....................................................................................................10
Figure 3-2: Fala-EC-Box....................................................................................................11
Figure 3-3: Shoe-Box.........................................................................................................12
Figure 4-1: Function of transport costs of truck, train and ship ..........................................19
Figure 4-2: Transport Cost Function for the TelliBox test track (schematically) .................20
Figure 4-3: Market share of German and foreign trucks in Germany, 1991-2010
(Crossboarder and german traffic) (2009 D BGL)..............................................................23
Figure 4-4: Considered possibilities of intermodal transport ..............................................33
Figure 5-1: Description of the NPV calculation for the Air-Tech-Box .................................42
Figure 5-2: Description of the NPV calculation for the Fala-EC-Box..................................43
Figure 5-3: Description of the NPV calculation for the Shoe-Box.......................................44
Figure 5-4: Results of ROI .................................................................................................46
Figure 5-5: NOWS-graph of AirTech-Box..............................................................51
Figure 5-6: Air-Tech-Box results of the NOWS-Workshop.................................................52
Figure 5-7: NOWS-graph of Fala-EC-Box.............................................................53
Figure 5-8: Fala-EC-Box results of the NOWS-Workshop .................................................54
Figure 5-9: NOWS-graph of Shoe-Box..................................................................55
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
vii
Figure 5-10: Shoe-Box results of the NOWS-Workshop....................................................56
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
viii
List of Tables
Table 2-1 Dependency of the ROI of the considered period................................................4
Table 4-1: Sharing of costs of an average truck for long distances (150 km) in November
2009 (Source: BGL, Statistisches Bundesamt)..................................................................21
Table 4-2: Handling of transport x to y...............................................................................33
Table 4-3: Classification matrix for costs and benefits.......................................................35
Table 5-1: Average Transport Charges each 100 km for the TelliBox ...............................37
Table 5-2: Annual transport charges for the TelliBox.........................................................37
Table 5-3: Annual costs for transhipment for the TelliBox..................................................38
Table 5-4: Annual costs for maintenance and repair .........................................................38
Table 5-5 Overview over all annual operative costs ..........................................................39
Table 5-6 Overview of investments....................................................................................47
Table 5-7: Overview of operational costs...........................................................................48
Table 5-8: Overview of maintenance .................................................................................48
Table 5-9: Overview of costs of repair ...............................................................................49
Table 5-10: Overview of transport costs ............................................................................49
Table 5-11: Overview of other costs ..................................................................................50
Table 5-12: Acquisition costs of the TelliBox designs ........................................................52
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
ix
List of Formula
Formula 2-1 .........................................................................................................................3
Formula 2-2 .........................................................................................................................3
Formula 2-3 .........................................................................................................................5
Formula 2-4 .........................................................................................................................5
Formula 5-1 .......................................................................................................................40
Formula 5-2 .......................................................................................................................40
Formula 5-3 .......................................................................................................................40
Formula 5-4: Calculation formula for the AirTech-Box .......................................................41
Formula 5-5: Calculation formula for the Fala-EC-Box ......................................................42
Formula 5-6: Calculation formula for the Shoe-Box ...........................................................43
Formula 5-7 .......................................................................................................................44
Formula 5-8 .......................................................................................................................45
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
1
1. Summary
Within the NOWS workshop, an estimation of the value orientated cost-effectiveness was
conducted for three alternative designs of the TelliBox. Participants of the workshop were
members of the project consortia of TelliBox. The cost-effectiveness was evaluated for
each design relative to today used swap-bodies. The Life Cycle Cost Analysis (LCC) also
regarded the three TelliBox solutions and the LCC workshop was conducted with the three
leaders of each TelliBox concept. The Return of Investment (ROI) and Net Present Value
(NPV) were determined for each of the three TelliBox solutions. As baseline for the
calculation, due to not yet completely definable assets, a “modified Megatrailer” was used.
The comparison with swap-bodies and Megatrailer shows in addition the profitability
compared to current solutions.
Generally it could be shown that the benefits for each design strongly dominate the costs
independent of the risk attitude of the decision maker. This means that even when all costs
of any type and with any probability are aggregated and compared with only direct benefits
with a high probability, the benefits still exceed the arising costs.
After evaluating the results of the NOWS-method and the ROI & NPV, it can be stated that
an investment for any TelliBox can be recommended. However, the evaluation of the
results almost gives no preference for any design variant of the TelliBox as with NOWS for
any scenario only a tendency can be given. The tendency of NOWS is also for LCC, ROI &
NPV the same:
1. Fala-EC-Box
2. Shoe-Box
3. AirTech-Box
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
2
2. Methods of Profitability Analysis
2.1 Introduction
Before making an investment, one should take into consideration under inclusion of all
available information the financial consequences of a decision. The more in the long term
the results of the investment are, the more it is difficult to revise them and the costs of a
false decision are higher. The TelliBox is used operational, for the transport of a product
from A to B, and can be pulled therefore, in principle, any time out of traffic. However, with
a prospective life span of ten years it is a strategic investment, which is why an analysis
concerning its economic efficiency is of basic meaning. A distinction is drawn between
static and dynamic calculation methods. The essential difference lies in the fact that the
dynamic methods discounts future amounts and therefore are closer to reality, because
they take into consideration capital costs and the inflation. As a static method the net
present value method (NPV, Net Present Value) is suited of the Return on investment
(ROI), as a dynamic method for the following calculation. Enterprise success assumes a
logical focusing on profitability, problem solutions and customer use which indicates a
change of a reactive solution finding to a proactive generator of customised solutions. An
economic efficiency draught to these requirements is the Life-Cycle Costing (LCC). As a
dynamic method the net present value method (NPV) is likewise the static Return of
investment (ROI) suited for the calculation. To examine also non-monetary dimensions like
flexibility, costs for employee's training or loss of working hours onto the calculation, so
that one can reach high product quality, customer contentment or share of the market, it
requires to a model like the value oriented cost-effectiveness estimation (NOWS). The
results of these single calculations and methods are merged in the chapter 5 and are
brought into connection.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
3
2.2 Return on Investment (ROI)
An identification number from the controlling to the profitability analysis of enterprises
which is formed from the relation by profit and the total capital (company capital and
outside capital) is original the ROI. This is equivalent to the product of sales profitability
and handling frequency of the total capital (Breuer 2000).
Thereby the ROI is the relation from profit and invested capital returns in percent:
ROI = capitalInvested
incomeinvestmentwithassociatedx %100
Formula 2-1
Because in this case only the cost side will be looked at and cost savings correspond to a
profit increase, the formula can be modified as following (Schulte 2007):
ROI = capitalInvested
investmenttroughsavingsCostx %100
Formula 2-2
If one liked to compare investment alternatives with each other, they must underlie the
same basic conditions (identical time span, consideration of the same costs, e.g.,
disposal). Besides, the achieved profit can be covered to any time interval. Mostly one
covers it to a year (success divided into periods) or to the whole life span (complete
success). If one accumulates the profits, the time to which they have reached the
investment costs shows the break even point. At that time the investment has amortised.
Hypothesis: One looks at the example row from Table 2-1. There are three possibilities to
calculate the ROI:
1. The given period is the first year. The resulting ROI is 33,3%
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
4
2. If the profits are the same in all periods, one can cover the net amount of a period to
the investment sum. In this example you get a ROI of 35000 / 25000 x 100% =
140%.
3. One looks at the whole life span: ROI = 200%
Table 2-1 Dependency of the ROI of the considered period
Year Value
Year 0 Year 1 Year 2 Year 3
Cost 25.000 € 5.000 € 5.000 € 5.000 €
Gain 0 € 40.000 € 40.000 € 40.000 €
Accrued costs 25.000 € 30.000 € 35.000 € 40.000 €
Cumulative Net Amount -25.000 € 10.000 € 45.000 € 80.000 €
ROI 33,33% 128,57% 200,00%
Critically is to observe that in the ROI analysis no statement about the risk of the
investment and the amount of the profit is done (Breuer in 2006).
Comparing two investment alternatives with distinct life span, the ROI is not applicable.
Nevertheless, one can cover the net present value of the costs saved by the investment to
the investment sum. Due to the consideration of the order of the payments through
discounting it is basically getting a dynamic method. However, the identified number
corresponds still to the ROI: „ With investment of an amount, one gets back x times of this
amount as a profit “ (Breuer in 2000).
2.3 Net-Present Value (NPV)
The net present value (NPV) is a dynamic procedure to the profitability calculation.
Because the time of the payments is taken into consideration, it is more expressive than
the ROI and should be preferred to this (Breuer in 2006).
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
5
The discounting of all payments linked with the investment on the investment time will be
done by the discount rate i:
TT
1t
tt0 )i1(L)i1(RINPV −
=
−++++−= ∑
Formula 2-3
Respectively at constant Cash-Flow: T
T
T
t0 )i1(Li)i1(
1)i1(RINPV −
++
⋅+
−++−=
NPV Net Present Value
I Invest
Rt Cash-Flow in period t (= Invest – Proceeds)
L Liquidation proceeds
i Discount rate
T Life span of invest
Formula 2-4
If the net present value is positive, the investment is to be carried out. Is to be decided
between several alternatives, the investment with the higher capital value is to be chosen.
If a negative cash flow is gained in a period, the investment should be liquidated if no more
obligations are connected with the investment or payments occur in a later period (when
achievement time and payment time break up).
The discount rate takes into consideration the capital costs which are to be set for the
investment (e.g., interest for the loan) which is raised by a risk premium. Critically is to be
marked that the calculation interest rate is subjective (which is why the acceptances in
particular above the risk premium should be called explicit) and the height must be
estimated for the payments and presume a perfect capital market on which debtor interest
and deposit rates are identical. The NPV itself tells nothing about the investment volume. If
one compares different investment alternatives, it can seem that the alternative with the
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
6
higher NPV is not practicable, because also the investment is higher and exceeds,
perhaps, the budget.
2.4 Life Cycle Costing (LCC)
The Life-Cycle Costing is a proactive procedure to analyse and assess the costs of capital
goods during its life cycle. The approach contains an adaptable calculation model which is
not too complicated within defined borders scalable and keeps the look for the essentials.
This method can be easily adapted to different applications. Basis for the LCC are
measurable input dimensions which split themselves in issues and income which results
during the whole life cycle. Issues that count for the TelliBox are for example the
investment, servicing and inspection, support by the manufacturer, training and use in the
company, disposal etc. In addition, other costs can be the cost for a new chassis etc. On
the income side one receives for the TelliBox comparable fixed costs like already
widespread containers as well as the liquidation at the end of the life cycle. Cost factors
can be above also identified by the analysis of all expense factors and optimisation
potentials be indicated. The total expenses reflect the reliability of the product, because
unimportant subsequent costs do not originate from failure and shutdown. With respect to
this one recognises a paradigm change in the procurement process, because with priority
not the invest cost, but the total expenses is looked and putatively uneconomical ones and
expensive capital goods regarding the total expenses can be substantially cheaper
(Schweiger 2009). This point could be important with marketing of the TelliBox, because it
is expected to be more expensive, but amortise, however, on a continuing basis and is
more economic with rising traffic amount.
2.5 Value oriented cost-effectiveness estimation (NOWS)
The NOWS method (Strina/Uribe 2004; Strina et al. 2003, Uribe et al. 2004) is a
participation-oriented, entrepreneurial cybernetic approach for the evaluation of costs and
benefits of an investment. The method enables a decision maker on investment
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
7
opportunities to combine the classical analysis of investment in monetary terms with
relevant non-monetary variables or the so-called soft factors in the profitability analysis.
The intersection point of the cost and benefit curve provides a profitability indicator
comparing different scenarios with each other. This approach needs to be considered in
comparison to the classical economic efficiency approaches: these conventional
approaches limit themselves basically to the quantifiable objectives in terms of monetary
data, e. g. costs and revenues (so called “harder” factors). In contrast, the NOWS
approach considers non-monetary objectives such as time, quality, flexibility, employee
perspectives or organizational environment (so called “softer” factors) to be evaluated in
terms of money.
The NOWS-method consists of seven phases which form the basis for all participation-
oriented processes as well as the learning processes (Unger 1998) of all participants and
also the organization. Figure 2-1 gives an overview on the NOWS method. In step one, a
representative, interdisciplinary team is created from executives and employees who are
affected by the measures and strategies. Within the project TelliBox the interdisciplinary
team for the NOWS-workshop was already given by the project consortia.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
8
Ste
p5
5d
5c
5b
5a
Evaluation of the investment
Collection and
Classification €Evaluation and
monetization
Investment-
decision
Formation of an interdisciplinary team
Ste
p1
Pro
ble
m S
olv
ing
Pro
ce
ss
Ste
p3 Target Situation
Ste
p4
Collection of actions
Ste
p7 Reflection
Visualisation of
costs and benefits
Ste
p6
Creation and implementation of an action plan
Ste
p2
Initial Situation
Ste
p5
5d
5c
5b
5a
Evaluation of the investment
Collection and
Classification €Evaluation and
monetization
Investment-
decision
Formation of an interdisciplinary team
Ste
p1
Pro
ble
m S
olv
ing
Pro
ce
ss
Ste
p3 Target Situation
Ste
p4
Collection of actions
Ste
p7 Reflection
Visualisation of
costs and benefits
Ste
p6
Creation and implementation of an action plan
Ste
p2
Initial Situation
Figure 2-1: Value oriented cost-effectiveness estimation (NOWS)
In step two, a description of the initial situation, a definition of the target situation (step
three) and the collection of actions in step four build the basis of the research project
TelliBox.
Step five evaluates for each action the cost-effectiveness in order to realize the investment
decision in step six. Step seven builds a reflection of the decision process in form of a
second, ex-post NOWS-evaluation.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
9
3. Considered Solutions
3.1 Introduction
For the evaluation phase three concepts has been examined. The concepts are the
AirTech-Box, Fala-EC-Box and the Shoe-Box/3D-Box. These three concepts will be briefly
described within this chapter.
3.2 Air-Tech-Box
Key system of the AirTech-Box is a airbag system which is able to lift the floor and hence
allows to design a fixed sidewall of 600mm height. On the fixed bottom frame part with a
height of 130mm is a liftable bottom frame placed. The liftable part is used as the loading
platform and lifted by using airbags and external energy. The Airtech system works with
folded aluminium side doors on the left and right sides, rear portal doors and steel
corrugated front wall and a liftable roof with mechanical system (Figure 3-1).
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
10
Figure 3-1: Air-Tech-Box
The special components of the Airtech solution essentially are:
• The airbag system that can lift the liftable floor 420mm for loading from the sides.
To load or unload from the rear there is no lifting needed.
• The liftable floor is made from 30mm aluminium and is actually the loading platform
of the box.
• The fixed sidewalls with a height of 600mm starting from the bottom. The main
function is to support the whole structure due to its stiffness.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
11
3.3 Fala-EC-Box
The Fala-EC-Box is emerged from the former solutions Fala-Box and EC-Box. The main
idea is to have one fixed side wall on the right side of the 160mm bottom frame and folded
side walls on the left side (Figure 3-2). The bottom frame square elements are asymmetric
constructed. The cross members are not parallel mounted. On the left side of the bottom
frame, the height of outside frame is reduced to the middle. In case of loading, the
deflections of the outside frame are 80mm, but the design of the outside frame helps keep
the allowed maximum deflections. The roof can be lifted only between the 40 ft top corner
casting” (Deliverable D8).
Figure 3-2: Fala-EC-Box
The special components of the Fala-EC-Box essentially are:
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
12
• One fixed side wall
• Special designed bottom frame
• The roof can be lifted between the 40 ft position
3.4 Shoe-Box
Idea of the concept Shoe-Box is that the whole construction supports to carry weight. It
uses the open able side walls as part of the construction so that it can reduce the
deflections (Figure 3-3). The Shoe-Box has three open able sides, the rear door and each
side door. It has a relative low bottom frame and a more stable roof frame. In addition to
the other concepts the Shoe-Box concept has a middle post where two of the four door
packages (each package consists of two doors) are attached. The bottom frame shelters a
goose neck tunnel with a height of 80mm.
Figure 3-3: Shoe-Box
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
13
The special components of the Shoe-Box solution essentially are:
• The side walls carry weight and are the main supporting element of the whole
structure
• Gooseneck tunnel with a height of 80mm
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
14
4. Procedure
4.1 ROI & NPV
4.1.1 Introduction
In this chapter the single elements and assumptions of the cost model with which the ROI
as well as the NPV are calculated are explained. It concerns a "bottom up" approach. That
means that from the costs of single parameters the total expenses arise. The evaluation of
the single cost drivers affects therefore directly the final result.
In particular the haulage is subjected to strong market influence. If one takes the trips to
the seaports, one ascertains, above all, regarding container transports a big disproportion
between import and exports. Pricing of intermodal transportation from/to seaports depends
on e.g.:
- relation
- volume proportion of im-/export (efficient use of transport capacity)
- dense of services from / into hinterland regions
- competition
- energy costs.
Result: No general conclusion on transport costs can be made as they depend on the
special transport route and a.m. factors.
It is tried to fade out these outgrowths and to receive average market data in which also a
market-usual margin is included.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
15
The total expenses arise from
• Transport costs in road traffic,
• Transport costs in rail traffic,
• Transport costs in ship traffic,
• Costs for loading and unloading,
• Handling costs,
• Costs independent of transport.
4.1.2 ROI and NPV comparison calculation:
Often it is not possible to get benefit values for future products. In the case of TelliBox
there are values for costs but not for incomes. The TelliBox simplifies the forwarding
process and replaces other products. In comparison of the TelliBox to the Megatrailer and
their costs it is possible to calculate the ROI and NPV of the benefits of cost saving. The
incomes assume to be equal and can be neglected. The values for ROI and NPV would
not be absolute, but relative to the Megatrailer. It is said that the Megatrailer has a ROI of
100% and a NPV of 0 € whether it is compared with the TelliBox. The value of the TelliBox
would not say if the product is profitable, but how big the difference is to the Megatrailer. A
higher value in NPV and ROI says that the TelliBox is even more profitable than the
Megatrailer.
4.1.3 Fixed and variable costs
To estimate the efficiency of a transport medium, it is important to be aware of the up
coming costs. In general one separates fixed and variable costs.
Variable costs can be, for example, variably in relation on the covered distance
(dependent on kilometre), the loading volume, the load or the time. An easy example: With
the Carsharing one pays a fixed all-inclusive price per hour and a price per kilometre, that
covers the costs for petrol, wears etc. In the reality one cannot pull the borders so clearly.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
16
If a forwarder rents a trucking unit for one day, he pays under circumstances a steady
price. For him it concerns fixed costs. He will differently treat his own trucking unit in the
vehicle park: He carries out a part of the write-offs dependent on time (fixed costs for this
period), the other part dependent on kilometre. However, for the tenant the rent costs are
unambiguously fixed.
During in a partial expense calculation only direct costs are added in the calculation flow.
So, transport cost mostly base on the full costs principle. Hence all overhead costs to the
single tours must be added appropriate for causing. The overhead costs exist, e.g., of
administrative costs in the headquarters and a part of the costs independent of kilometre
which cannot be assigned directly to an order (e.g., amortization dependent on time).
4.1.4 Economies of Scale
fc are the fixed costs, vc in relation on the loading volume the variable costs (analogously
one could look at the load) and υ the number of pallets which can be accommodated in a
transport unit. The transport costs arise to:
Transport costs = υ⋅+ vf cc
Divided byυ , the transport costs result per pallet:
Transport costs per pallet = vf c
c+
ν
Hence the transport costs decrease per pallet, the greater the loading volume of the
container is, because the fixed costs on a bigger number of palettes can be put down.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
17
This effect is called "Economies of Scale". It matters if loading units with different
capacities are compared to each other. Today a train may be only 750 m long in Germany.
A lengthening on 1000 or even 1500 m would lower the fixed costs of the transported unit
and would thereby have huge cost advantages. Plans are discussed nowadays
(Bundesministerium für Wirtschaft und Technologie 2007).
The scale effects have a big meaning also in the intercontinental container ship industry. A
ship with a capacity of 12,000 TEU can transport a container about at half-price like one
with 1,200 TEU (Stopford 2009). In general one can also find out that on account of the
dimension effect a transport by the ship is more favourable than one by the train which is
again cheaper than road transport.
Aim of the TelliBox is it to achieve, primarily, cost advantages by the application of the
transport modes that are cheaper in comparison to truck, the train and the ship. Indeed,
there are also RoRo ships which transport complete trucks and ConRo ships which can
take up container as well as trucks, however, economic using of the transport by the ship
arises only by applying the container principle, so the optimum exploitation of the loading
area by stacking the loading units (Stopford 2009).
4.1.5 Modelling the transport costs function
The biggest interest by operating the TelliBox is transport and handling costs. Hence,
should be entered to the better understanding of the connections in the intermodal traffic at
first on carriage functions.
Figure 4-1 shows schematically the function for the transport costs for the three traffic
modes in the trimodal traffic. The transport costs dependent on kilometre are the highest
with the truck, because the energy consumption and the personnel expenditure per ton
kilometre (or per pallet and kilometre) are very high. Normally it comes one driver on one
container. But also operating expenses like tyre costs or toll which are a significant lever
within the scope of an ecological policy to raise the price of the traffic belong to these costs
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
18
dependent on kilometre. Because a barge can take more containers aboard than one truck
or train (degression of overhead costs) and also less fuel needs per container and
kilometre, the transport cost function of the ship is the lowest. For a comparison: A truck
ordinarily transports only one container and, besides, consumes 35-40 litres of diesel on
100 kilometres, while an average barge with approx. 200 TEU needs only approx. 2,000
litres for the same distance what corresponds to 10 litres for a 20-foot container or to 20
litres for a 40-foot container (Contargo in 2009). The ordinate gives the handling costs and
fixed transport costs. The unimodal used truck itself has no handling costs in traffic. Only
multimodal transport systems have additional handling costs because the loading unit has
to be put on and off the trailer for example. The costs result essentially by waiting and
loading. The handling costs in seaports are the highest by far. Inland harbour terminals are
a little more expensive as terminals in the combined traffic road and rail. The fixed costs
likewise rise by the size of the transport medium. This is up to the immobilization or
downtime. To load a 700-metre-long train with containers, can last more than two hours, a
barge half a day and a coastal ship a whole day. To the amortisation costs high fees
additionally come for the downtime in the harbours. With a cost function, as shown in
Figure 4-1 a distance to D1 would be done on road, to D2 by the train and distances about
D2 with the barge.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
19
Figure 4-1: Function of transport costs of truck, train and ship
Nevertheless, one must be aware of the fact that the traffic networks are different well
developed. In Europe the road network is linked up so well that one can apply approach-
wise an Euclidean distance measurement. The water way system is suitable for a
reasonable container transport but limited, depending on the run of the waterways and the
access of only certain regions. For many distances there are no rivers or they had to do
big detours. Even with a good ship connection, for example, from Mannheim to Rotterdam
the difference of the distances between water way and road connection amounts to 15%
(street: approx. 500 km, the Rhine: approx. 580 km). It must be taken into consideration
that the average speed with the barge is clearly slow (<10 km/h), more slowly than by train
or truck.
If the transport by train or ship is planned as the main run, a pre-carriage and onward
carriage with the truck must be ordinarily carried out.
In Figure 4-2 the cost function is confronted for the TelliBox test track regarding intermodal
usage with a truck in unimodal traffic (sketched line). The leaps in the graph result from
transport costs and fixed carriage. Are the costs after the whole transport distance of the
Distance
Costs Truck
Train
Ship
D1 D2
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
20
TelliBox under those for the existing way of transport it is the basic condition for the
application of this transport unit.
At last the delivery time desired by the customers is also to be taken into consideration.
Figure 4-2: Transport Cost Function for the TelliBox test track (schematically)
4.1.6 Transport costs in road traffic
The price for the forwarding of a sending results from:
• Distance,
• weight,
• volumes or loading metres and
• perhaps surcharges for express services.
Not relevant factors like danger good impacts (no danger goods will transported with the
loading unit) are neglected. The final price contains a margin, as well as costs for empty
haulage (nationwide all together: 19.7%, long-distance traffic / trips more than 150 km:
10%) which bring no proceed (BGL 2009 A). Because there is no statistical data for
Costs
Road
Rail
Inland shipping
D1 D2 D3
Short sea shipping
Road
Distance
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
21
average prices of road transport, an approach above the internal costs of a forwarder
agent is more helpful. These values are determined monthly by the Bundesverband
Güterkraftverkehr, Logistik und Entsorgung (BGL 2009 A) by questioning forwarders. The
results are shown in Table 4-1.
The costs are differentiated in direct costs (E) which are appropriate for adding to a
transport order directly, and overhead costs (G) which must be split – on the kilometre
achievement – to come to a kilometre rate to the full costs principle. Often the
differentiation of direct costs and overhead costs is not unequivocal, e.g., the wage can be
looked as overhead costs if the driver is salaried. The wages would also result if he gets
fewer orders in a recession. However, generally one assumes that the time involved is
calculable for a distance and the wages resulting in this period can be assigned to the
order. Therefore they will be handled as direct costs.
If one looks at November, 2009, arise with one of the BGL accepted fuel consumption of
34 litres in the national long-distance traffic with an average diesel price of 0,972 €/l
(average from price in filling stations and price of large consumer, BGL 2009 B, BGL 2009
C) cost at the rate of approx. 127.8 € 100 km. The margin of the forwarders is not
considered here.
Table 4-1: Sharing of costs of an average truck for long distances (150 km) in November 2009
(Source: BGL, Statistisches Bundesamt)
percental absolute (€)
Personnel costs driver 28.56
(E) Wage 20.14 25.7
(E) Statutory social security costs 4.91 6.3
(E) Charges 2.26 2.9
Other 1.25 1.6
Vehicle operations costs (variable cost: km-dependent) 48.15
(E) km-dependent depreciation 4.26 5.4
(E) Fuel costs 25.86 33.0
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
22
(G) Additional costs (equipment urea) 0.4 0.5
(G) Lubricant cost 0.91 1.2
(G) Maintenance and repair costs 6.3 8.1
(G) Vehicle cleaning (exterior) 0.66 0.8
(G) Tire cost 2.29 2.9
(E) km-targeted road pricing 6.8 8.7
Other input costs 0.67 0.9
Fixed Costs 12.72
(G) time-dependent depreciation 4.26 5.4
(G) Debt financing costs 1.43 1.8
(G) Testing charges 0.2 0.3
(G) time-based road pricing 0 0.0
(G) Motor vehicle tax 0.52 0.7
(G) Insurance 4.2 5.4
(G) Other fixed costs 2.11 2.7
Administrative costs 10.57
(G) Personnel costs 6.09 7.8
(G) Material costs 4.48 5.7
Total costs (€/100km) 127.8
Foreign forwarders can operate clearly cheaper as from the BGL in the branch costs
development to questioned inland forwarders, because for them most cost parameters in
particular the wages are lower. The pricing pressure also appears in the fact that the
interest of foreign truck has doubled in Germany since 1991 on 36% roughly (Figure 4-3).
A reason for this is the partial abolition of the cabotage prohibition, which enables foreign,
in particular East European drivers, to transport within Germany.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
23
Figure 4-3: Market share of German and foreign trucks in Germany, 1991-2010 (Crossboarder and
german traffic) (2009 D BGL)
The assumed kilometre price of the cost model is about 127.8 € attached for 100 km for an
average hauling in the long-distance traffic. Of course higher transport prices count to the
short distances traffic which concerns in particular the pre- and onward carriage. After
consultation with forwarders the following values were collected:
Close-up range to about 50 km: All-inclusive price 150 €
Regional area less than 150 km: All-inclusive price 250 €
4.1.7 Transport costs in rail traffic
Goods trains may be only 750 m long nowadays in Germany. A capacity of 105 TEU
arises from it. One train exists of 35 wagons with three 20-foot containers in each case.
The “Bundesministerium für Wirtschaft und Technologie” checks an expansion for 1000 m
or 1500 m length with which trains could reach the capacity from barges, but itself on
account of the length could have problems while loading and unloading
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
German Truck Foreign Truck
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
24
(Bundesministerium für Wirtschaft und Technologie in 2007). The price of freight transport
via train depends on the following factors:
• Distance
• Length of the load unit
• Weight of the load unit
• perhaps danger good surcharge
• Whole train or single carriage traffic
According to the analysis of several market data is to be calculated for an average
distance of 100 kilometres on 88 € for 45 feet long container.
4.1.8 Transportkosten in shipping traffic
The logistics service provider for container logistics Contargo indicates that their container
barges use 150-400 litres of diesel per operating hour. The fact that no exact value can be
given, is due to the fact that the energy consumption grows with normal driving speed
about with the 5th degree to the speed (Contargo in 2009). As an example the
consumption of the container ship San Lorenzo (1500 TEU) would be given. Indeed, this
goes on sea, however, the consumption is for barges similarly depending on the speed:
approx. 20 kn / approx. 51 t of diesel sea day
approx. 19 kn / approx. 40 t of diesel sea day
approx. 18 kn / approx. 33 t of diesel sea day
approx. 17 kn / approx. 29 t of diesel sea day
The consumption is clearly higher in journey to mountain than to valley, because the
stream velocity of the river (the Rhine: approx. 7-8 km/h) must be included and downhill is
not driven with the full power.
Transit time of a container barge from Mannheim to Rotterdam (ca. 500 km) is 36 hours
and in reverse direction 50 hours (Wincanton 2009). This corresponds to a speed of 14 or
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
25
10 km/h. Influence on the consumption also have water level, draught and driving
channels width. A loaded ship consummates with the same current relations (sufficient
place for the keel) 15-25% more fuel than one unloaded one.
Beside the price of the diesel which is transmitted in form of a bunker surcharge to the
customers the size of the container plays a role whether it is full or empty.
The approximated price is formed from three factors (not relevant costs as for example
danger good surcharges are neglected):
• Fuel price
• Distance
• Size and weight of the container (fully blank)
Like already mentioned, the ship transport is only worthwhile at a certain distance length.
With short distances the transhipment and amortisation costs would out of proportion for
the high idle period. The operational expenditures (Opex, without fuel costs) are relatively
low, because only few staff is required. A big part of the costs are capital costs (Capital
expenditures/Capex). Of course offer and inquiry determine the price. E.g. in a bottleneck
like between Calais and Dover (40 km) 682 € plus value added tax must be paid for round
trip of a mega trailer. The journey lasts approx. 90 minutes. If one chooses the piggyback
traffic by the euro tunnel with a journey time of 35 minutes, one pays 716 €. Both carriers
of traffic do no not compete.
Most barges on the Rhine have a capacity of 208 TEU, some come on 300 TEU, the
border with ships of the Jowi class lies with 500 TEU. The carriage strongly depends on
the capacity of the ship. On rivers and canals which are able to be driven because of
bridges only double stacked they are clearly higher and even uneconomical partly.
There are no studies to the carriage in the barge and coastal ship journey traffic. On the
basis of telephone conversations with experts 72 € per 100 street kilometres are to be
considered about a loaded TelliBox in the barge traffic and 100 € in the Short Sea
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
26
Shipping for an average distance as realistic. The prices of the coastal ship journey vary
very strongly. On the 350-km-long distance of Rotterdam to Hull is with pure carriage of
approx. 700 € (200 € / 100 km correspond) to count, on the approx. 600 km long distance
(over the street these would be 720 km) from Travemünde to Gdynia (Poland) with 250 €
what corresponds to 42 € on 100 km.
4.1.9 Costs for loading and unloading
The use of a transport unit depends not only on the pay load and on the load capacity, but
also on the duration which is necessary for loading. This also encloses the time which is
necessary to prepare the transport unit for the loading process. The process of loading
and unloading should take so little time as possible, because high idle times are cost-
intensive: Vehicle and load carrier amortise only if they are on the move possibly a lot,
waiting periods of the driving staff are connected with costs and the capital connection
costs of the product rise by long idle times in the depot or while handling.
An analysis of a cross-docking terminal has shown a time advantage regarding the
operating costs for handling of the Fala-Ec-Box compared with the other considered
solutions. The loading and unloading process is quite similar regarding the three different
solutions. Two persons are mostly responsible for this process. A controller co-ordinates
the expiries in the stock and provides for the fact that the load carrier is supplied with the
right goods, a stacker's driver accomplishes the loading process. If the loading height of 3
metres is not required, is to be assumed from the fact that the loading is carried out often
about the rear only, because a side loading requires more space which often does not
exist. One must think that loading is mostly possible only under a roof and cannot be
carried out therefore somewhere on the area. The time of a loading and unloading process
depends rather on the degree of the organisation of the processes. Efficient terminals
need only approx. 15 minutes for a complete loading, while other for this more than 50
minutes need.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
27
4.1.10 Handling costs
In general, size and weight of the load unit does not play a decisive role according
handling costs. There are three terminal types:
• Terminals for the combined traffic street / rail,
• Inland harbour terminals and
• Seaport terminals.
The terminals have different cost structures: The investment costs in infrastructure and the
costs of the process expiries rise from first-called to the last-called terminal type. The
German transhipment society Schiene-Straße mbH (DUSS), a subsidiary of German
railways, orders Germany-far more than 25 terminals for loading between road and rail.
Their prices can count as representative to most road rail terminals (remuneration list from
the 1st April, 2009). For a handling from road on rail are 18.50 € calculated. For a handling
of rail on rails the price amounts including the craning 37 €. The prices are not depending
on the transport unit (container, semi-trailer, swap body). By carriage on the same day the
costs decrease to 15 € or 30 €. The handling begins with letting down the handling
equipment on the loading unit, often encloses a temporary transport-conditioned storage
and ends, as soon as the handling equipment are solved by the loading unit. It mostly
come other costs and remunerations for complementary services: For the check in (Take
up of the data which are important for other partners in the transport chain and exterior
inspection of the loading unit) 1.10 €, for the allocation of the loading unit fall to the wagon
1.50 €, for holding to be ready to load of road vehicle or the carriage what proper coupling
and the bandaging of the loading unit by the vehicle / carriage contain 1.50 € in. All
together the costs add up handling to about 25 € or 45 € (rail-rail).
In inland ports the costs are subtracted as Handling. A Handling insists as a rule of two
handlings (except in the Duisburger Intermodal terminal where the water-sided and the
land-sided depot surface lie apart and be bridged therefore by an additional Handling).
That is the fact that the container is interstored by the truck or train at first on a depot
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
28
surface, before it is loaded on the ship. With a price of 21.50 € per Handling (terminal
Neuss: 20 €, terminal Mannheim Wincanton: 23 €) a total of approx. 50 € arises including
the additional costs for a transhipment. In seaports are handling costs (THC to calculate
Totally Handling Costs) from 80-150 €. In the following a realistic average of 100 € is
accepted.
4.1.11 Transport independent costs
Investment
The initial investment of the TelliBox solutions cannot be given in this project stage yet;
however, it is estimated in the first approach by the concept developers. Besides, the
purchase price of the AirTech variation would lie with 32,200 €, with the Shoe-Box
variation with 27,600 € and with the Fala-EC-Box with 23,000 €.
Maintenance costs
To determine the maintenance costs of the loading unit is difficult, because there are few
statistics and they are raised in enterprise apparently not apart after the different transport
units. In conversations values of a swap body of 1,000 € arose in the year. Containers are
produced meanwhile to 95% in China and cost nowadays approx. 2000 $ a TEU. A 40
foot-HC container matches 1.68 cost equivalent units (CEU) and costs approx. 3400 $
(Containerportal 2009). Considering that this price largely cost of materials is and therefore
the utilization of a defective container brings along a return, becomes clear that it makes
sense to pull him from the traffic, as soon as it shows bigger damages. The TelliBox
should not be more servicing-intensive than a usual container. Due to the higher
investment amount also bigger repairs shall be worthwhile. The precise values of the
respective solution can be taken from the cost model in the appendix. For the chassis
higher costs should be calculated as with current loading units. The individual costs are
also listed in the appendix. Because the TelliBox is only a part of the annual run on the
chassis, these maintenance costs come only with a percentage into the calculation which
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
29
the TelliBox is on road. The calculated values with the NOWS workshop are 1040 € for the
AirTech-Box and 800 € for the Fala-EC- and Shoe-Box.
Expenses for capital commitment
The expenses for capital commitment are a size not to be neglected. They arise from
about the year seen average value of goods carried within the loading unit plus the
imputed interest rate. If the goods value amounts, for example, to 25,000 €, arise with an
interest rate of 6% of capital connection costs of 1,500 € what could corresponds to the
scale of the maintenance costs.
Liquidation proceeds
The liquidation proceed of the TelliBox depends on the current metal price. The proceed
for the AirTech-Box is approx. 280 €, for the Fala-EC-Box 480 € and for the Shoe-Box
likewise 480 €. The values in the cost model are about 200 € higher because the scrap
value of the chassis is added to the liquidation proceeds. A Chassis has a scrap value of
600 € and three boxes use one chassis. The final proceeds are approx. 480 € for the
AirTech-Box and 680 € for the Fala-EC- and Shoe-Box.
Average annual mileage
After interviews it is to be assumed that the TelliBox makes 20 round trips a year. With the
duration of 12 days per roundtrip and an average single distance of 1,300 km it comes on
yearly 52,000 kilometres.
The average annual mileage depends with the mega trailer on whether it is used
exclusively unimodal or in the combined traffic as a traffic mode for the pre carriage and
main run. Unimodal it comes with big forwarding agencies in the year on 150-250.000 km
and the biggest part might put back approx. 175,000 km. With the smaller forwarding
agencies which carry out a big interest in One Way trips it is to be calculated on a lower
annual mileage of 140-150.000 km. If it is used in the combined traffic, it puts back in the
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
30
year on account of the lower average speed and higher idle times only one third of this
distance. This relatively low mileage is one of the causes for the high kilometre prices of
the pre-carriage and post-carriage in combined traffic, in particular with short distances.
Allocation of the usage of traffic modes
The transport costs, which summarizes over the year, are the most important cost factors
and therefore have a big influence on profitability. Because there is to the TelliBox no
comparable intermodal loading unit and hence it cannot be fallen back consequently on
statistics, one must meet assumptions about the subdivision of the transport shares of the
different transport modes. If one assumes from the fact that a transport should run only on
road, it would not make sense to use the TelliBox, because the transport by the mega
trailer would be more favorable and it could take up, in addition, still a higher load weight.
An exception would be natural if thereby a deadhead would be avoided.
After independently conversations with several experts and literature research is not to be
assumed from the fact that the ship traffic will have a big interest as a traffic mode. For this
there are only a few suitable inland waterways. Only the Rhine as the most significant river
of Europe for inland shipping has to register active container traffic. In the Rotterdam
container terminals the inland ship put out in 2007 30%, the train 11% and the truck 59%
in the Modal-Split. Only 0.5% of the containers to be transported in the hinterland with the
inland ship were transported in 2008 by the Hamburg harbour. However, this segment has
growth rates from up to 40%, so that one can assume an interest of 5% in 2015. The
interest of road transport exists in the essentials of preliminary heat and casters. Main
traffic mode will be the train:
• Road: 30%
• Rail: 65%
• Inland Shipping: 2.5%
• Short Sea Shipping: 2.5%
Detour factors
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
31
The traffic networks are well developed differently. If one liked to shift unbroken truck-load
traffic to the rail, the transport distance increases. On the one hand, the terminals mostly
do not lie on the transport route, so that a detour must be accepted, on the other hand is
the road system to the railway system predominant, so that also here a longer distance
arises. The difference in inland ship traffic is even bigger. The distance from Mannheim to
Rotterdam on highway is exactly 500 km (Part of the test run in TelliBox). In spite of not
too big detours of the Rhine, the inland ship needs approx. 580 km. For the Short Sea-
Ship traffic there are no statistics to detour factors. However, one can assume from the
fact that the distance corresponds roughly to the air line, that it is ideal (above all, within
the Baltic Sea area and from the ARA harbours to the east coast of England). the
determination of metrics is a field of the Operations Research. Economists try to model
transport networks in such a way that for a distance from A to B the statistically most likely
distance can be determined by using this metrics. The metrics differs for different regions
and traffic networks. If one takes the road net as benchmark, the following circular detour
factors (ifo in 1996) arise:
• Road: 1
• Rail: 1.1
• River: 1.2
These factors help to convert the transport costs for 100 km on road, because distances
are ordinarily calculated in road kilometres. Nevertheless, the kilometre dependent costs
were calculated for the really covered distance of the transport medium.
Life-time
The life-time of the TelliBox should have a similar life span like a container. It comes into
the cost model therefore with the value of 10 years. After this term it is used either for the
scrap metal price or is resold. The compared Megatrailer has only duration of 5 years and
therefore after this duration a new has to be purchased.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
32
Transhipments a trip
To be able to calculate the handling costs which result within one year with the TelliBox,
assumptions about the distances must be done. This model assumes from the fact that the
TelliBox is handled maximum three times a trip. It can be of course that more often turned
handlings are needed; however, the transport variations described in Figure 4-4 are these
ones that mostly occur. If the transport exists of two handlings, the main run takes place
only by the train, inland or short-sea ship. Often the main run is spitted into two. At first it is
driven by the train, then with inland or short-sea ship or once more by the train. An inland
ship can also go in a seaport, from where the transport about short sea journey is
continued. The variations indicated in Figure 4-4 can be driven of course also in reverse
direction. Table 4-2 shows with which traffic mode the loading unit reaches the terminal (x)
and with which it is further transported from there (y). Considering the last column, this
states that 50% of the transports that are driven by the short-sea ship came from road,
40% of the rail and 10% of the inland ship. The values performed in the table are
estimations on the basis of information from conversations with project partners and in
intermodal traffic operating actors.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
33
Figure 4-4: Considered possibilities of intermodal transport
Table 4-2: Handling of transport x to y
Y X
Street Rail River Short Sea
Road 0 0.9 0.9 0.5
Rail 0 0.1 0.1 0.4
River 0 0 0 0.1
Short Sea 0 0 0 0
Factor of Equalization
This factor serves to take into consideration loading units with different pay load and
different load volume (see chapter 6).
Pre-carriage Onward carriage
Barge
Rail
Short Sea Shipping
Rail Onward
carriage
Barge
Rail
Short Sea Shipping
Pre-carriage
Short Sea Shipping Onward
carriage
Barge Pre-carriage
2 Transhipments
3 Transhipments
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
34
4.2 Life Cycle Costing (LCC)
For the life cycle costing there are several indicators needed to give an overview what cost
may occur. These indicators should only describe the costs that result from operation. The
costs that are generated in production are not part of this analysis. Therefore it is partially
called customer oriented life cycle costing. To describe the life cycle costs for the customer
the following categories of costs must be identified: Investment costs, operational costs,
maintenance costs, cost of repair, costs due to transport and maybe other costs. These
cost categories were identified by literature research and expert interviews. To identify the
cost indicators within each category several interviews were performed. Because of the
current stage of the development and design of each solution it is not possible to quantify
each indicator. Hence the indicator shows the relations of costs between the solutions in
percent. Nevertheless the cost indicators that came out of the literature research and the
interviews are:
• Investment costs: Initial Invest, training, waste and disposal costs.
• Operational costs: Operating time, insurance and energy costs.
• Maintenance costs: Door, hinge, lifting mechanism, roof, floor, corrosion protection,
attaching parts and sealing.
• Cost of repair: Personal and probability of loss.
• Cost of transport: Cleaning costs, handling costs and storage costs.
• Other costs: Costs of chassis, cancellation costs and duration of tie-down.
The relation and the estimation of each indicator were done by a workshop. Participants of
the workshop were the leaders of each concept. Every indicator was explained and
discusses and afterwards evaluated within the group. The results and the allocation of the
indicators are shown in chapter 6.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
35
4.3 Value oriented cost-effectiveness estimation (NOWS)
The opening of boarders in the East of the European Union result in an increase of freight
transport volume. Nowadays, this entails in a disproportional raise of transportation of
goods by means of road traffic. The European Union’s objectives of achieving intermodal
integration and operational optimization can therefore be regarded as the definition of the
target situation (step three). Intelligent MegaSwapBoxes for Advanced Intermodal Freight
Transport can be seen as one possible action to achieve this target situation by shifting the
intermodal traffic in favor of rail and short sea traffic (step four).
The focus of the NOWS-workshop was to evaluate the cost-effectiveness of three different
TelliBox designs. It was agreed by the consortia that for each design, all annually costs
and benefits for a freight forwarder operating with one kind of the TelliBox design had to be
evaluated in 2015. At this time it was assumed that the ramp-up phase would have been
completed. To achieve an independency the collection of costs and benefits of each
design in step 5a are described relatively to standardized swap-bodies which are used
today. All benefits respectively costs were classified in their type of occurrence as well as
their probability of occurrence. The layout of the matrix is shown in Table 4-3.
Table 4-3: Classification matrix for costs and benefits
Probability Costs
Benefits high Medium low
direct 1 3 6
indirect 2 5 8
Ty
pe
difficult to ascertain 4 7 9
Easy to rate aspects with a direct monetary effect are defined as direct aspects. Hence,
direct benefits are defined as cutback of capital- or maintenance-costs whereas acquisition
costs and training costs are rated as direct costs. Prospective aspects such as external
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
36
consulting costs or productivity gain for benefits are defined as indirect as they are harder
to rate. Even so-called “difficult to ascertain“ aspects can be considered with the NOWS-
method. The positive effect of the image of a project or on a company can be regarded as
a beneficial aspect of this type. On the contrary costs that occur due to stress that
employee experience can be rated as difficult to ascertain.
The beneficial aspects then are accumulated from one to nine according to the numbers
shown in Table 4-3. In contrast, cost aspects are accumulated from nine to one (Weydant
2000). This process enables the evaluation of costs and benefits at different risk levels.
Consequently, in the beginning, only secure benefits and full costs are compared. This
would resemble the behavior of a pessimistic decision maker. The accumulated costs and
benefits each form a curve. The effectiveness of an investment is determined by the
intersection of the two curves. At this point the accumulated costs and benefits are equal.
In the NOWS-workshop for the TelliBox-project each design was assessed independently
by a group of the participants of the workshop. Each group consisted of designated
experts. In order to guarantee a comparability of the results, the groups could discuss their
results within a set-up marketplace-phase with the other groups. On the basis of the three
matrices all aspects were quantified by all participants together.
:
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
37
5. Findings
5.1 Return on Investment (ROI) & Net Present Value (NPV)
At this point the results of the return on investment (ROI) and net present value (NPV) of
the TelliBox are shown. Some of THE transport costs are the same for each of the three
solutions. Therefore it is in this case further called just TelliBox.
At first the transport costs are calculated like in Table 5-1 shown for the TelliBox.
Table 5-1: Average Transport Charges each 100 km for the TelliBox
Transport Charges
(€/100km)
Factor of Detour
Transport Charges real
(€/100km)
TelliBox: Divison of Transport Carriers
TelliBox: Transport Charges
(€/100km)
Street 127.8 1 127.8 30% 38.38
Rail 80 1.1 88 65% 57.2
Barge 60 1.2 72 2.5% 1.8
Short Sea 100 1 100 2.5% 2.5
99.84
Now taking into account an interest in short distances and distant area (less than 150 km)
from 25% in the pre- and onward carriage, which are calculated inclusively with 200 €, the
whole carriage resulting within one year can be calculated. They arise from the sum of the
costs for the short distances and the product from annual run achievement less the short
distances which are attached with 100 km in each case, and kilometre-related transport
costs. According to Table 5-2 these amount to 55,917 €.
Table 5-2: Annual transport charges for the TelliBox
Annual Mileage (km)
Transport Charges (€/100km)
Costs for short trips (€)
Annual Transport Charges (€)
52000 99.84 4,000 55,917
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
38
In the calculation of the annual transhipment costs one goes out once more from 20 round
trips and the acceptance grieved on top about the subdivision of the transhipments. As in
Table 5-3 shown these add up to 2,478 €.
Table 5-3: Annual costs for transhipment for the TelliBox
Number of Transshipments/year
Costs/Transshipment (€)
No Shipping 0 0
1 Shipping: Road-Rail 33.4 50
1 Shipping: Road-Barge 1.3 100
1 Shipping: Road-Short Sea 0.7 200
2 Shippings: Road-Rail + Rail-Rail 3.7 95
2 Shippings: Road-Rail + Barge 0.1 125
2 Shippings: Road-Rail + Short Sea 0.6 225
2 Shippings: Barge + Short Sea 0.1 250
Other 0 0
Total Costs (€/a) 2,478
The annual cost of the three solutions for maintenance and repair differs according to the
values of the NOWS-Workshop (Table 5-4).
Table 5-4: Annual costs for maintenance and repair
Solution Type of Cost
AirTech-Box Fala-EC-Box Shoe-Box
Maintenance costs (€/a) 1040 800 800
Repair costs (€/a) 1220 300 760
The expenses for capital commitment arise from about the year seen on an average in the
transport bearer engaged goods value and the cost-accounting interest for the TelliBox.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
39
The calculated value for a container is 25,000 €. The expenses for capital commitment
arise from the product of this value and the interest of 6% to 25,000 € x 6% = 1,500 €.
Because still no numerical values for the TelliBox exist, the cost advantages and
disadvantages towards the Megatrailer are gathered for the calculation of ROI and NPV. It
is needed to equalize general conditions for the mileage and weight. The annual total
costs are 63,661 € for the AirTech-Box, 62,473 € for the Fala-EC-Box and 62,944 € for the
Shoe-Box (Table 5-5). The annual total are 67,496 € for a modified Megatrailer (Table
5-5). The modification calculates the mileage of the Megatrailer equal to the TelliBox
solutions to make them comparable.
Table 5-5 Overview over all annual operative costs
Solution Type of Cost
AirTech-Box Fala-EC-Box Shoe-Box Megatrailer
modificated for 52000 km/a
Transport Charges 55,917 55,917 55,917 67,496
Transshipment Costs 2,478 2,478 2,478 -
Maintenance Costs 1040 800 800 2,000
Repair Costs 1220 300 760 -
expenses for capital commitment 1,500 1,500 1,500 1,500
Insurance Costs - - - -
Costs trough Theft - - -
Factor of Equalization (Capacity) 1.03 1.03 1.03 -
Annual Total Costs (OPEX) 63,661 62,473 62,944 67,496
The net present value is calculated with the following formula 6-1:
∑=
−−+−++−=
T
1t
Tt )i1(*L)i1(*BINPV
I = Invest
B = Benefit
i = Interest
L = Liquidation Proceeds
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
40
Formula 5-1
If you put the cost for investments and liquidation by hand into a timetable and calculate
your benefits from the annual costs for the Megatrailer minus the annual costs for the
TelliBox you get the formula 6-2.
tTelliBox10t
0t
rMegatraile)i1(*)
a
]t[Costs
a
]t[Costs(NPV −
=
=
+−= ∑
Formula 5-2
The Megatrailer has a lifetime about five years and will be sold after this period. The
TelliBox is calculated to stay in traffic for ten years. Therefore it’s needed to calculate the
NPV with two fit Megatrailers with their investment and liquidation proceeds. After the
insertion of these parameters formula 6-3 arises.
10M
5M
10TB
tTelliBox10t
1t
rMegatraile5MTBM
)i1(L)i1(L)i1(L
)i1(*)a
Costs
a
Costs())i1(III(NPV
−−−
−
=
=
−
+−+−++
+−+++−−= ∑
M = Megatrailer
TB = TelliBox
Formula 5-3
The result of the net present value doesn’t show the absolute profit of the investment, but
the profit in relationship to the Megatrailer. In this calculation the NPV of the Megatrailer is
set to 0 €. The absolute net present value of the TelliBox solutions is higher, because it is
assumed that the Megatrailer is economical, too.
The following figures and formulas visualize the single steps on the calculation of the NPV.
The Formula 5-4, Formula 5-5, Formula 5-6 and it legends below are for the calculation of
the NPV. On the top of Figure 5-1, Figure 5-2 and Figure 5-3, are timelines from t0 (now)
until t10 (after 10 years). Below is the benefit in the single years but t0 shows the first
investment on the product. Afterwards the values are calculated with the interest rate, later
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
41
invests and liquidation proceeds. On the left side are the single net present values which
are summed on the bottom to the NPV for the solution.
10M
5M
10A
t10t
1t
5MAMA )i1(L)i1(L)i1(L)i1(*B))i1(III(NPV −−−−
=
=
−
+−+−++++++−−= ∑
M = Megatrailer
A = AirTech-Box
B = Benefit
I = Investment
L = Liquidation Proceeds
i = Discount Rate
Formula 5-4: Calculation formula for the AirTech-Box
t0 t1 t2 t3 t4 t5 t6 t7 t8 t9 t10
AMII −−
-29881
3618
3413
3220
3037
7828
2703
2550
2406
2270
2310
+
+
+
+
+
+
+
+
+
+
= 3473
2)1*(
−
+i
9)1*(−
+i
3)1*(−
+i
6)1*(−
+i
4)1*(
−
+i
8)1*(
−
+i
5)1*(
−
+i
7)1*(−
+i
1)1*(
−
+i
10)1*(−
+i
3834,56 3834,563834,563834,563834,563834,563834,563834,563834,563834,56-29881
5)1(
−
+− iLM
10)1(
−
+− iLM
10)1(
−
++ iLA
5)1(
−
++ iIM
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
42
Figure 5-1: Description of the NPV calculation for the Air-Tech-Box
The calculated result of the NPV for the AirTech-Box is 3,473 €.
10M
5M
10F
t10t
1t
5MFMF )i1(L)i1(L)i1(L)i1(*B))i1(III(NPV −−−−
=
=
−
+−+−++++++−−= ∑
M = Megatrailer
F = Fala-EC-Box
B = Benefit
I = Investment
L = Liquidation Proceeds
i = Discount Rate
Formula 5-5: Calculation formula for the Fala-EC-Box
t0 t1 t2 t3 t4 t5 t6 t7 t8 t9 t10
FMII −−
-21581
4738
4470
4217
3978
8716
3541
3340
3151
2973
3085
+
+
+
+
+
+
+
+
+
+
= 20630
2)1*(
−
+i
9)1*(−
+i
3)1*(−
+i
6)1*(−
+i
4)1*(
−
+i
8)1*(
−
+i
5)1*(
−
+ i
7)1*(−
+i
1)1*(
−
+i
10)1*(−
+i
5022,68 5022,685022,685022,685022,685022,685022,685022,685022,685022,68-21581
5)1(
−
+− iLM
10)1(
−
+− iLM
10)1(
−
++ iLF
5)1(
−
++ iIM
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
43
Figure 5-2: Description of the NPV calculation for the Fala-EC-Box
The calculated result of the NPV for the Fala-EC-Box is 20,630 €.
10M
5M
10S
t10t
1t
5MSMS )i1(L)i1(L)i1(L)i1(*B))i1(III(NPV −−−−
=
=
−
+−+−++++++−−= ∑
M = Megatrailer
S = Shoe-Box
B = Benefit
I = Investment
L = Liquidation Proceeds
i = Discount Rate
Formula 5-6: Calculation formula for the Shoe-Box
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
44
SMII −−
+
+
+
+
+
+
+
+
+
+
=
2)1*(−
+i
9)1*(−
+i
3)1*(−
+i
6)1*(−
+i
4)1*(−
+i
8)1*(−
+i
5)1*(−
+i
7)1*(−
+i
1)1*(
−
+i
10)1*(−
+i
5)1(
−
+− iLM
10)1(
−
+− iLM
10)1(
−
++ iLS
5)1(
−
++ iIM
Figure 5-3: Description of the NPV calculation for the Shoe-Box
The calculated result of the NPV for the Shoe-Box is 13,012 €.
The ROI for the TelliBox is calculated with the following formula 6-4:
%100*Invest
BenefitROI =
Formula 5-7
The calculation on the ROI is set in relationship to the Megatrailer. It turns out whether the
TelliBox is more profitable as the Megatrailer. The solution which would be as profitable as
the Megatrailer would have a ROI about 100%. If the ROI turns out above this value it
shows the volume of profit in percentage. On the given values it is useful to transform this
formula to 6-5:
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
45
%100*Invest
Investa10*a/BenefitROI
−=
Formula 5-8
With:
Benefit = Transport Costs Megatrailer / 175000 * 52000 – Transport Costs TelliBox *
34/33
Invest = Costs TelliBox + 0.3 * Chassis – Costs Megatrailer / 875,000 * 520,000 –
Liquidation TelliBox - Liquidation 0.3 * Chassis + Liquidation Megatrailer / 875,000 *
520,000
The calculated benefits for the different TelliBox solutions are the minor transport costs in
relation to the Megatrailer. It is the fact that the Megatrailer has a total mileage of 875,000
km in 5 years and the TelliBox is calculated to have a total mileage of 520,000 in 10 years.
Besides the TelliBox can only carry 33 instead of 34 pallets and needs 0.3 chassis for the
road transport.
The results of the ROI for the different solutions are shown in Figure 5-4:
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
46
67%ROI =−
=
=
+−−+=
=
−=
100%*22937.14€
22937.14€10*3834.56€
22937.14€875000km
520000km*600€480€
875000km
520000km*22950€15000€*0.332200€Invest
3834.56€33
34*44€.63661
175000km
52000km*223650€a
Benefit
-BoxAirTech
-BoxAirTech
-BoxAirTech
%248=−
=
=
+−−+=
=
−=
−−
−−
−−
%100*€71.14437
€71.1443710*€68.5022
€71.14437km875000
km520000*€600€680
km875000
km520000*€22950€18000*3.0€23000Invest
€5022.6833
34*€62473.32
km175000
km52000*€223650Benefit
BoxECFala
BoxECFala
aBoxECFala
ROI
ROI
ROI
ROI
145%=−
=
=
+−−+=
=
−=
−
−
−
%100*€71.18587
€71.1858710*€53.4551
€71.18587km875000
km520000*€600€680
km875000
km520000*€22950€16500*3.0€27600Invest
€4551.5333
34*€62944.47
km175000
km52000*€223650Benefit
BoxShoe
BoxShoe
aBoxShoe
ROI
ROI
ROI
ROI
Figure 5-4: Results of ROI
According to the values of NPV and ROI of the three solutions they turn out as a
worthwhile investment. The AirTech-Box has a ROI of 67% and a NPV of 3,473 €. The
Fala-EC-Box has a ROI of 248% and a NPV of 20,630 €. The Shoe-Box has a ROI of
145% and a NPV of 13,012 €.
Hence, if one supposes that the income depend for all TelliBox solutions only on transport
distance and not on transport time, the investment turns out as worthwhile.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
47
5.2 Life Cycle Costing (LCC)
In this chapter the results for the TelliBox solutions of the Life-Cycle costing analysis are
shown in different units of meaning. The basis e.g the best solution of the three solutions is
illustrated with 100%. The more expensive ones are for example described like 110% etc.
Investments:
The investments are divided into initial invest, training and liquidation proceeds. The initial
invest for the Shoe-Box is 20% higher than the Fala-EC-Box, because of a higher
technical complexity. The AirTech-Box consists of a complicated lifting mechanism and is
therefore about 40% more expensive than the Fala-EC-Box. The training of employees of
the Shoe-Box is 40% and the AirTech-Box 100% above the costs of the Fala-EC-Box,
because the operating time is longer and more complex. It would only be done once. The
liquidation proceeds mean only the effort of sold resources without transport costs or costs
for material separation. The proceeds for the AirTech-Box are the slightest and the Shoe-
Box as well as the Fala-EC-Box are 71% higher (Table 5-6).
Table 5-6 Overview of investments
Solution Type of Cost
Shoe-Box AirTech-Box Fala-EC-Box
Invest
Initial Invest 120% 140% 100%
Training 140% 200% 100%
Liquidation Proceeds -171% -100% -171%
Operational Costs
The operational costs are divided in operating time and energy costs. The operating time
is the slightest for the Fala-EC-Box and is as for the Shoe-Box as the AirTech-Box 40%
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
48
higher. While energy costs for the Shoe-Box and the Fala-EC-Box are negligible, they are
about 0.04€/lifting for the AirTech-Box (Table 5-7).
Table 5-7: Overview of operational costs
Solution Type of Cost
Shoe-Box AirTech-Box Fala-EC-Box
Operational Costs
Operating Time 140% 140% 100%
Energy Costs none about 0.04€/lifting none
Maintenance
The maintenance is divided into door, hinge, lifting, roof, floor, corrosion protection and
sealing for one year. The maintenance costs for doors are the slightest for the AirTech-
Box. The costs are 110% for the Shoe-Box and 120% for the Fala-EC-Box. The costs for
hinge are at 100% for the AirTech-Box, 120% for the Fala-EC-Box and 165% for the Shoe-
Box. The lifting of the Shoe-Box and the AirTech-Box is equal, but twice as expensive as
the Fala-EC-Box. All values for the roof are equal. The maintenance costs for the floor of
the AirTech-Box is about 250€. There are no costs for the Shoe-Box or Fala-EC-Box. And
therefore no percentage can be given. All values for the corrosion protection are equal.
The maintenance costs for sealing are the slightest for the AirTech-Box. The costs are at
110% for the Shoe-Box and 120% for the Fala-EC-Box (Table 5-8).
Table 5-8: Overview of maintenance
Solution Type of Cost
Shoe-Box AirTech-Box Fala-EC-Box
Maintenance
Door 110% 100% 120%
Hinge 165% 100% 120%
Lifting 200% 200% 100%
Roof 100% 100% 100%
Floor none 250 Euro none
Corrosion Protection 100% 100% 100%
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
49
Sealing 110% 100% 120%
Cost of Repair
The costs of repair are the costs for personal and they are as for the Shoe-Box as for the
AirTech-Box twice as expensive as for the Fala-EC-Box (Table 5-9).
Table 5-9: Overview of costs of repair
Solution Type of Cost
Shoe-Box AirTech-Box Fala-EC-Box
Cost of Repair
Personal 200% 200% 100%
Transport costs
The transport costs are divided in handling costs and storage costs. All values are equal
for the three solutions (Table 5-10).
Table 5-10: Overview of transport costs
Solution Type of Cost
Shoe-Box AirTech-Box Fala-EC-Box
Transport
Handling Costs 100% 100% 100%
Storage Costs 100% 100% 100%
Other Costs
The other costs are divided in chassis, cancellation costs and cargo securing. The costs
for the chassis are the slightest for the AirTech-Box because it just needs a simple one.
The Chassis is needs modifications for the other solutions and therefore the Shoe-Box is
about ten percent and the Fala-EC-Box about 20% more expensive. The costs for
cancellation are 20% higher for the AirTech-Box as for the Fala-EC-Box and 40% higher
for the Shoe-Box as for the Fala-EC-Box. The costs for cargo securing are the slightest for
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
50
the AirTech-Box because there is no need of special tools to secure the cargo. The Shoe-
Box needs twice effort to secure the loading and five times sophisticated to secure the
cargo on the Fala-EC-Box (Table 5-11).
Table 5-11: Overview of other costs
Solution Type of Cost
Shoe-Box AirTech-Box Fala-EC-Box
Other Costs
Chassis 110% 100% 120%
Cancellation Costs 140% 120% 100%
Cargo Securing 200% 100% 500%
5.3 Value oriented cost-effectiveness estimation (NOWS)
Figure 5-5 - Figure 5-9 illustrate the NOWS-graph for the three designs named “AirTech-
Box”, “Fala-EC-Box” and “Shoe-Box” respectively. The derivation of several benefit and
cost aspects is shown in the following. A complete list of all identified aspects in the course
of the workshop can be found in the appendix. As a main direct benefit with high
occurrence, a reduction of transport costs was identified by the participants of the
workshop. Referring to a test track, it was agreed that an intermodal transport with the
TelliBox has an advantage, when compared with a swap-body of 0,37 €/km regardless the
design of the TelliBox. Consequently, when the test track accounts one way with 1,300 km
and 20 cycles/TelliBox and year are assumed, a benefit of 19,240 € occurs.
Another benefit which can be stated independent of the design is the volume of 100 m³ of
the TelliBox. Compared to a swap-body with a transport volume of only 80 m3 this is a gain
of 20 %. This increase in volume will result in a decrease of necessary traffic and therefore
transport costs.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
51
The participants assumed a yearly mileage in kilometers of about 52,000 km for a swap-
body. The variable operating costs for the swap-body were assessed as 1.00 €/km.
Furthermore it was not regarded as realistic that the freight forwarder can keep this benefit
himself but would pass on one third to his customers. This results in an overall benefit due
to an increase in volume of 6,968 € per year for every TelliBox in use.
27,652.30 €
0,00 €
invest positive trend indifferent negative trend divest
27,652.30 €
0,00 €
invest positive trend indifferent negative trend divestinvest positive trend indifferent negative trend divest
Figure 5-5: NOWS-graph of AirTech-Box
Two further common identified advantages of the TelliBox are its stackability and the ability
for transsiberian transport. The TelliBox can be stapled fourfold in contrast to the swap-
body which is not stapable at all. Therefore four TelliBoxes can be stored on one slot
whereas every swap-body needs a separate slot. The fees for one slot account to
10 €/day, resulting in a benefit of 7.50 €/day for the TelliBox when compared to the swap-
body. It was assumed that a transport unit is stored on average 37 days per year, being
approximately 10 % per year. This leads to a benefit of 277.50 €.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
52
Figure 5-6: Air-Tech-Box results of the NOWS-Workshop
The TelliBox can be transported to Asia via train with less thievery than today. This comes
along with a saving of ten days per cycle for the transport when compared to the longer
ocean route. Assuming eight cycles per year, capital costs of 80 days can be saved. Given
an interest rate of 6 %, this benefit therefore adds up to 263 € per year.
Differences in the monetization for all designs were found in the amortization period in
relation to the swap body reference model. The workshop-participants agreed that for all
three designs of the TelliBox an amortization period of ten years is realistic in contrast to
an amortization period of six years for a swap-body. For the monetization, a linear
depreciation is assumed. In order to calculate the benefit due to a longer lifetime, the
acquisition costs of the TelliBox designs are needed. The different acquisition costs were
discussed by the participants. Table 5-12 shows the result.
Table 5-12: Acquisition costs of the TelliBox designs
Swap-body Fala-Ec-Box Shoe-Box Air-Tech-Box
87% 100% 120% 140%
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
53
20.000 € 23.000 € 27.600 € 32.200 €
Given an interest rate of 6 % an amortization rate of 3,533 € per year can be calculated for
the swap-body over six years. In contrast the longer life time of the three TelliBox designs
lead to less annually amortization costs. This results in a monetary benefit of 1,095 € for
the Fala-EC-Box, 607.40 € for the Shoe-Box and 119.80 € for the AirTech-Box.
The identification of cost aspects showed that there are also common aspects over all
three designs. However in contrast to the common beneficial aspects most of the costs
aspects differ in the monetary value assigned to them. The reason for this is that all
designs are developed to fulfil the same defined requirements leading to the same
monetary values. However this is realized by different technical concepts leading to
different monetary values for the cost aspects.
28,647.50 €
invest positive trend indifferent negative trend divest
0,00 €
28,647.50 €
invest positive trend indifferent negative trend divest
28,647.50 €
invest positive trend indifferent negative trend divestinvest positive trend indifferent negative trend divest
0,00 €
Figure 5-7: NOWS-graph of Fala-EC-Box
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
54
As one main cost aspect repair costs were identified by the workshop-participants. For the
Fala-EC-Box as for the Shoe-Box the repair costs were classified as direct costs with a low
probability.
Figure 5-8: Fala-EC-Box results of the NOWS-Workshop
As the AirTech-Box possesses more technical components the probability of failure was
rated medium. For the monetization it was assumed that over the lifeduration of ten
yearsall movable parts of a TelliBox need to be renewed once. The monetary value of the
moving parts in a TelliBox-design was set to the difference in acquisition costs of each
design relative to the swap-body. Hence, the annually averaged repair costs of 1,220 €,
300 €, 760 € arise for the AirTech-Box, the Fala-EC-Box and the Shoe-Box respectively.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
55
0,00 €
28,159.90 €
invest positive trend indifferent negative trend divest
0,00 €
28,159.90 €
0,00 €
28,159.90 €
invest positive trend indifferent negative trend divestinvest positive trend indifferent negative trend divest
Figure 5-9: NOWS-graph of Shoe-Box
Next to the repair costs, general maintenance costs arise on a yearly basis. For the Fala-
EC-Box and the Shoe-Box the same efforts are required as for the swap-body. Again, due
to the greater number of technical components of the AirTech-Box, higher costs for
maintenance, namely 240 € per year, arise.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
56
Figure 5-10: Shoe-Box results of the NOWS-Workshop
On the other hand the AirTech-Box faces no issues overcoming a low sill due to its lifting
device. However, the Fala-EC-Box and the Shoe-Box need specific modifications to the
chassis. These modifications were monetized in the workshop with 5,000 €. When taking a
life duration of six years and given the fact that four TelliBoxes can be handled with one
chassis, “low sill” costs of 208 € occur. The participants rated this cost aspect as difficult to
ascertain with low probability.
In the course of the workshop other benefit and cost aspects were identified and partly
monetized which were not described above as these aspects only have a marginal effect
on the general statement of the value orientated cost-effectiveness estimation.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
57
6. Conclusion
Within the NOWS workshop, an estimation of the value orientated cost-effectiveness was
conducted for three alternative designs of the TelliBox. Participants of the workshop were
members of the project consortia of TelliBox. The cost-effectiveness was evaluated for
each design relative to today used swap-bodies. The Life Cycle Cost Analysis also
regarded the three TelliBox solutions and the LCC workshop was conducted with the three
leaders of each TelliBox concept. The ROI and NPV were determined for each of the three
TelliBox solutions. As baseline for the calculation, due to not yet completely definable
assets, a modified Megatrailer was used. The comparison with swap-bodies and
Megatrailer additionally shows the profitability compared to current solutions.
Generally it could be shown that the benefits for each design strongly dominate the costs
independent of the risk attitude of the decision maker. This means that even when all costs
of any type and with any probability are aggregated and compared with only direct benefits
with a high probability, the benefits still exceed the arising costs.
After evaluating the results of the NOWS-method and the ROI & NPV, it can be stated that
an investment for any TelliBox can be recommended. However, the evaluation of the
results almost gives no preference for any design variant of the TelliBox as with NOWS for
any scenario only a tendency can be given. The tendency is for NOWS, LCC and ROI &
NPV the same:
4. Fala-EC-Box
5. Shoe-Box
6. AirTech-Box
For an economic evaluation it is recommended that an ex-post NOWS-workshop and ROI
& NPV calculation is to be conducted. At this time the remaining designs should then be
finalized. On this basis an even more profound statement on the cost-effectiveness of the
TelliBox can be expected.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
58
7. Bibliography
Breuer, W. (2000): Investition I, 1.Auflage, Gabler
Breuer, W. (2006): Vorlesungsunterlagen „Investition und Finanzierung“
Bundesministerium für Wirtschaft und Technologie (2007): Projekt GZ 1000
Bundesverband Güterkraftverkehr Logistik und Entsorgung (BGL) e.V. (2009 A):
Branchenkostenentwicklung. Online Internet, URL:
http://www.bgl-ev.de/web/initiativen/kosten_kalkulator.htm&v=2 [Stand: 29.07.010]
Bundesverband Güterkraftverkehr Logistik und Entsorgung (BGL) e.V. (2009 B):
Dieselpreis für Großverbraucher. Online Internet, URL: http://www.bgl-
ev.de/images/downloads/initiativen/ dieselpreisinformation.pdf?ms=845 [Stand: 29.07.010]
Bundesverband Güterkraftverkehr Logistik und Entsorgung (BGL) e.V. (2009 C):
Dieselpreis an Tankstellen. Online Internet, URL: http://www.bgl-
ev.de/images/downloads/initiativen/ dieselpreisinformation_tankstelle.pdf?ms=853 [Stand:
29.07.010]
Bundesverband Güterkraftverkehr Logistik und Entsorgung (BGL) e.V. (2009 D):
Marktanteile deutscher und ausländischer LKW in Deutschland. Online Internet, URL:
http://www.bgl-ev.de/web/daten/grenz_lkwind.htm [Stand: 10.08.009]
Containerportal (2009): Containertypen. Online Internet, URL:
http://www.containerportal.de/content/containertypen.htm [Stand: 10.08.009]
Contargo (2009): Bunkerzuschlag. Online im Internet, URL:
http://www.contargo.net/index.php?option=com_content&task=view&id=136&Itemid=208
[Stand: 10.08.009]
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
59
Deutsche Umschlaggesellschft Schiene-Straße (DUSS) mbH (2009 A): Entgeltliste vom
01.04.2009.
Deutsche Umschlaggesellschft Schiene-Straße (DUSS) mbH (2009 B):
Nutzungsbedingungen für Serviceeinrichtungen
EU-Kommission (17.06.2009): Verkehrs-Herausforderungen für das nächste Jahrzehnt
Frankfurter Allgemeine Sonntagszeitung (2008): Kampf ums Streckennetz [Artikel vom
05.10.2008]
Fraunhofer-Institut für Materialfluss und Logistik (2006): Hinterland-Terminals: Typen und
Umsetzung Online im Internet, URL:http://www.hebezeuge-foerdermittel.de/hf_magazin/
artikel/pdfs/2006/HF1106_580-583.pdf [Stand: 10.08.2009]
Ifo-Institut (1996): ifo-Studie 1996. Online im Internet, URL:
http://www.lbst.de/publications/books__d/co2/Teil1/4_2.html#punkt4_23 [Stand:
10.08.2009]
Kögel (2009): Big-maxx. Online im Internet, URL: http://www.big-maxx.com [Stand:
10.08.2009]
Niedersächsiches Ministerium für Witschaft, Arbeit und Verkehr (2007): Auswertung des
niedersächsischen Modellversuchs zum Thema „Gigaliner“, URL:
http://cdl.niedersachsen.de/blob/images/C40627922_L20.pdf
Krone (2009): EuroCombi. Online im Internet, URL:
http://www.nutzfahrzeuge.krone.de/de/index/gigaliner.html [Stand: 10.08.2009]
Pahl, G.; Beitz, W.; Feldhusen. J.; Grote, K.H. (2005): Konstruktionslehre – Grundlagen
erfolgreicher Produktentwicklung, Methoden und Anwendungen. Heidelberg.
Savelsberg, E. (2008): Innovation in European Freight Transportation – Basics,
Methodology and Case Studies fort he European Markets. Berlin, Heidelberg.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
60
Schweiger, S. (2009): Lebenszykluskosten optimieren – Paradigmenwechsel für Anbieter
und Nutzer von Investitionsgütern.
Statistisches Bundesamt (2009):Dieselpreis. Online im Internet, URL:
http://de.statista.com/statistik/daten/studie/1691/umfrage/preis-fuer-einen-liter-diesel-
monatsdurchschnittswerte [Stand: 10.08.2009]
Strina, Giuseppe; Uribe, Jaime: Participative pre-evaluation of the profitability of
operational investments - NOWS approach - A process and involvement oriented
evaluation method. In: Applied Participation and Empowerment at Work - Methods, Tools
and Case Studies. Hrsg. v. Johansson, C.R.; Frevel, A.; Geißler-Gruber, B.; Strina,
Giuseppe: Lund, Sweden: Studentenliteratur, 2004: 81-92.
Strina, Giuseppe; Uribe, Jaime; Henning, Klaus: NOWS Technique: Participation oriented
Evalution of further Education Strategies and Measures. In: Proceedings of E-Learn 2003.
World Conference on E-learning in Corporate, Government, Healthcare & Higher
Education, Association for the Advancement of Computing in Education(AACE). Hrsg. v.
Rossett, A.: Phoenix, Arizona, USA: AACE, 2003: 331 ff.
Stumpe, F. (2003): Entwickling und Betrieb von neuen Sattelanhänger-Waggon
Kombinationen für zukunftsfähige Transportketten in Europa
Schulte, G. (2007): Investition, Oldenbourg Wissenschaftsverlag
Stopford, M. (2009): Maritime Economics, 3. Ausgabe, London
Unger, H. (1998): Organisationales Lernen durch Teams - Methode und Umsetzung eines
teambasierten Projektsmanagements. Rainer Hampp Verlag, München und Mering.
Uribe, Jaime; Henning, Klaus; Strina, Giuseppe: Measurement of Participation-oriented
Evaluation: NOWS. In: Knowledge is Orange - Industry-Focused Applications of
Knowledge Management across Germany. 2004.
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
61
Weydant, Dirk: Beteiligungsorientierte wirtschaftliche Bewertung von technischen
Investitionen für prozessorientierte Fertigungsinseln. Unternehmenskybernetik in der
Praxis, Band 2. Aachen: Shaker-Verlag, 2000.
Worldcargonews (2009): Rotterdam’s modal split. Online im Internet, URL:
http://www.worldcargonews.com/htm/w20080621.667714.htm [Stand: 10.08.009]
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
62
8. Appendix
8.1 Cost aspects of AirTech-Box
Box Cost Aspect Probability Type Quadrant Value(€) Derivation
AirTech-Box Maintenance Costs high direct 1 240,00 Swap body 800 €/a;Fala: 800 €/a;Shoe: 800 €/a
Air-Tech: 1040€/a because it has more moving parts and more complex technique (30% more)
AirTech-Box Destination Charges high indirect 2 0,00 insignificant difference to swap bodyAirTech-Box External Energy and
Air Supplyhigh indirect 2 3,84 0,04€/lift; 24circulations * charge/discahrge (2*2) =
96; 96*0,04= 3,84€AirTech-Box Marketing Costs high indirect 2 13,33 10.000€ overall marketing cotsts (approx.) ; 250
boxes; 3 years project duration: 10.000/250/3= 13,33
AirTech-Box Repair Costs medium direct 3 1.220,00 Basic Assumtion: 1x per lifeduration substitution of the movable parts. Value for the moveable parts is based on the difference of the initial value of the
box in relation to a swap body. Fala: 3000/10a =300€; Shoe: 7600/10a= 760€; Air-Tech: 12200/10a = 1220€
AirTech-Box Training Costs high difficult to ascertain
4 24,00 training materials/information on Box: 1pce./circulation a 1€; 1€ *24 circulations p.a. = 24€
AirTech-Box Cancelations Expansions
medium indirect 5 0,00 insignificant
AirTech-Box High Sill, Hight of Chassis and Cam
Distance
medium difficult to ascertain
7 0,00 lift charge
AirTech-Box Changeover Costs low difficult to
ascertain
9 0,80 external compressor= 1000€ 250 usages
40€/Usage, duration 5 years => 0.8€
AirTech-Box Empty Trips low difficult to ascertain
9 0,00 -
AirTech-Box Higher Risk of Injuries low difficult to ascertain
9 0,00 aspect was discussed but no consensus was found; it was said, that it is too early to actually define those costs
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
63
8.2 Benefit aspects AirTech-Box
Box Benefit Aspect Probability Type Quadrant Value(€) Derivation
AirTech-Box 100m³ Capacity and 3 Meters Loading Heigth
high direct 1 6.968,00 Tellibox: 100m³; swap body 80m³ effective = 20% more capacity = 20% less transport costs. Customer gets 1/3 of the benefit; 52.000km/a for 1€ each *0.2 = 10400 *2/3 = 6968€
AirTech-Box Amortization Period high direct 1 119,80 Swap body : 20.000€; Fala-Ec: 115% of swap body; Shoe: 120% of Fala-Ec; Air-Tech: 140% of Fala-Ec; cost value/10 years *1,06 ( 6% interest) Swap body 3533 €; Fala: 2438 € / Shoe:2925,6€/
Air-Tech: 3413,2€; Fala: 3533€-2438€ = 1095€/Shoe: 607,40€/ Air-Tech:119,8€
AirTech-Box Door Opening Conception
high direct 1 not monetized
AirTech-Box Grasp Flange high direct 1 not monetizedAirTech-Box Liqudation Proceeds high direct 1 28,00 discarded metal valued 85€/1000kg transfercosts
to junk yard = 200€; 8000 kg discarded metal from
a TelliBox= 480€/10years = 48€ -20€ disposal fee for the airbags = 28€
AirTech-Box Lower Transport Costs high direct 1 19.240,00 testrack: Tellibox has an cost advantage of 0,37€/km 20 circulations per year *2 trips
1trip=1300km 20*2*1300=19240€AirTech-Box Stackability high direct 1 277,50 recent options are not stackable, storage fee is
based on stack hight. 1st attempt: 24 days
circulation + 1day 2nd attempt: 10% (~37days)of all calendardays the container is stored. This costs approx. 10€ per day = 370€. TelliBox is four times stackable. This would be only 2,5€ for a TelliBox =>
277,5€ benefitAirTech-Box Standard Handling,
Top Crane Handlinghigh direct 1 not monetized
AirTech-Box Transsiberian Transport
high direct 1 263,00 Time savings vs. Shipping: 10 days. Average value per Container: 20.000€; interest: 6% p.a.; 8 circulations p.a 20.000*0,06/356*10 *8=
263€AirTech-Box Trimodal high direct 1 not monetizedAirTech-Box Abilitiy to use Eco-
friendly Carriershigh indirect 2 not monetized
AirTech-Box Easy Handling high indirect 2 not monetizedAirTech-Box Integrated Tie-Down high indirect 2 756,00 staff saving and material saving: Material: 12
lashing straps for 15€ ea. *20% abrasion= 36€ staff: 0.5 h work time
AirTech-Box Tailgate high indirect 2 not monetizedAirTech-Box Robust, Low
Reparation Costsmedium indirect 5 not monetized
AirTech-Box Weatherproof medium indirect 5 not monetizedAirTech-Box Marketingtool medium difficult to
ascertain7 not monetized
AirTech-Box Sustainable medium difficult to ascertain
7 not monetized
AirTech-Box Flexible on Ramps low indirect 8 not monetizedAirTech-Box High Protection
Against Theftlow difficult to
ascertain9 not monetized
AirTech-Box Less Hazards for Staff low difficult to ascertain
9 not monetized
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
64
8.3 Cost aspects Fala-EC-Box
Box Cost Aspect Probability Type Quadrant Value(€) Derivation
Fala-EC-Box Maintenance Costs high direct 1 0,00 Swap body 800 €/a;Fala: 800 €/a;Shoe: 800 €/a
Air-Tech: 1040€/a because it has more moving parts and more complex technique (30% more)
Fala-EC-Box Destination Charges high indirect 2 0,00 insignificant difference to swap bodyFala-EC-Box Repair Costs low direct 6 300,00 Basic Assumtion: 1x per lifeduration substitution of
the movable parts. Value for the moveable parts is based on the difference of the initial value of the box in relation to a swap body. Fala: 3000/10a
=300€; Shoe: 7600/10a= 760€; Air-Tech: 12200/10a = 1220€
Fala-EC-Box Cancelations
Expansions
low indirect 8 0,00 insignificant
Fala-EC-Box Low Sill low difficult to ascertain
9 208,00 Chassis costs = 5000€; 4Boxes, deprication: 6 years; 5000€/ 4*6= 208,33€
Fala-EC-Box Marketing Costs low difficult to ascertain
9 13,33 10.000€ overall marketing cotsts (approx.) ; 250 boxes; 3 years project duration: 10.000/250/3= 13,33
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
65
8.4 Benefit aspects Fala-EC-Box
Box Benefit Aspect Probability Type Quadrant Value(€) Derivation
Fala-Ec-Box 100m³ Capacity and 3 Meters Loading Heigth
high direct 1 6.968,00 Tellibox: 100m³; swap body 80m³ effective = 20% more capacity = 20% less transport costs. Customer gets 1/3 of the benefit; 52.000km/a for 1€ each *0.2 = 10400 *2/3 = 6968€
Fala-Ec-Box Amortization Period high direct 1 1.095,00 Swap body : 20.000€; Fala-Ec: 115% of swap body; Shoe: 120% of Fala-Ec; Air-Tech: 140% of Fala-Ec; cost value/10 years *1,06 ( 6% interest) Swap body 3533 €; Fala: 2438 € / Shoe:2925,6€/
Air-Tech: 3413,2€; Fala: 3533€-2438€ = 1095€/Shoe: 607,40€/ Air-Tech:119,8€
Fala-Ec-Box Grasp Flange high direct 1 not monetizedFala-Ec-Box Liqudation Proceeds high direct 1 48,00 discarded metal valued 85€/1000kg transfercosts
to junk yard = 200€ 8000 kg discarded metal from a
TelliBox= 480€/10years = 48€
Fala-Ec-Box Lower Transport Costs high direct 1 19.240,00 testrack: Tellibox has an cost advantage of 0,37€/km 20 circulations per year *2 trips
1trip=1300km 20*2*1300=19240€Fala-Ec-Box One Open Side high direct 1 not monetizedFala-Ec-Box Stackability high direct 1 277,50 recent options are not stackable, storage fee is
based on stack hight. 1st attempt: 24 days
circulation + 1day 2nd attempt: 10% of all calendardays the container is stored. This costs approx. 10€ per day = 370€. TelliBox is four times stackable. This would be only 2,5€ for a TelliBox =>
277,5€ benefitFala-Ec-Box Standard Handling,
Top Crane Handlinghigh direct 1 not monetized
Fala-Ec-Box Transsiberian Transport
high direct 1 263,00 Time savings vs. Shipping: 10 days. Average value per Container: 20.000€; interest: 6% p.a.; 8 circulations p.a 20.000*0,06/356*10 *8=
263€Fala-Ec-Box Trimodal high direct 1 not monetizedFala-Ec-Box Abilitiy to use Eco-
friendly Carriershigh indirect 2 not monetized
Fala-Ec-Box Easy Handling high indirect 2 not monetizedFala-Ec-Box Mechanic Lifting
Devicehigh indirect 2 not monetized
Fala-Ec-Box Robust, Low Reparation Costs
high indirect 2 not monetized
Fala-Ec-Box Weatherproof medium indirect 5 not monetizedFala-Ec-Box Marketingtool medium difficult to
ascertain7 not monetized
Fala-Ec-Box Sustainable medium difficult to ascertain
7 not monetized
Fala-Ec-Box Flexible on Ramps low indirect 8 not monetizedFala-Ec-Box Integrated Tie-Down low indirect 8 756,00 staff saving and material saving: Material: 12
lashing straps for 15€ ea. *20% abrasion= 36€ staff: 0.5 h work time
Fala-Ec-Box High Protection Against Theft
low difficult to ascertain
9 not monetized
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
66
8.5 Cost aspects Shoe-Box
Box Cost Aspect Probability Type Quadrant Value(€) Derivation
Shoe-Box Maintenance Costs high direct 1 0,00 Swap body 800 €/a;Fala: 800 €/a;Shoe: 800 €/a
Air-Tech: 1040€/a because it has more moving parts and more complex technique (30% more)
Shoe-Box Destination Charges high indirect 2 0,00 insignificant difference to swap bodyShoe-Box Repair Costs low direct 6 760,00 Basic Assumtion: 1x per lifeduration substitution of
the movable parts. Value for the moveable parts is based on the difference of the initial value of the box in relation to a swap body. Fala: 3000/10a
=300€; Shoe: 7600/10a= 760€; Air-Tech: 12200/10a = 1220€
Shoe-Box Cancelations
Expansions
low indirect 8 0,00 insignificant
Shoe-Box Higher Risk of Injuries low difficult to
ascertain
9 0,00 aspect was discussed but no consensus was
found; it was said, that it is too early to actually define those costs
Shoe-Box Low Sill low difficult to ascertain
9 208,00 Chassis costs = 5000€; 4Boxes, deprication: 6 years; 5000€/ 4*6= 208,33€
Shoe-Box Marketing Costs low difficult to ascertain
9 13,33 10.000€ overall marketing cotsts (approx.) ; 250 boxes; 3 years project duration: 10.000/250/3= 13,33
Shoe-Box Training Costs low difficult to ascertain
9 24,00 training materials/information on Box: 1pce./circulation a 1€; 1€ *24 circulations p.a. = 24€
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
67
8.6 Benefit aspects Shoe-Box
Box Benefit Aspect Probability Type Quadrant Value(€) Derivation
Shoe-Box 100m³ Capacity and 3 Meters Loading Heigth
high direct 1 6.968,00 Tellibox: 100m³; swap body 80m³ effective = 20% more capacity = 20% less transport costs. Customer gets 1/3 of the benefit; 52.000km/a for 1€ each *0.2 = 10400 *2/3 = 6968€
Shoe-Box Amortzation Period high direct 1 607,40 Swap body : 20.000€; Fala-Ec: 115% of swap body; Shoe: 120% of Fala-Ec; Air-Tech: 140% of Fala-Ec; cost value/10 years *1,06 ( 6% interest) Swap body 3533 €; Fala: 2438 € / Shoe:2925,6€/
Air-Tech: 3413,2€; Fala: 3533€-2438€ = 1095€/Shoe: 607,40€/ Air-Tech:119,8€
Shoe-Box Grasp Flange high direct 1 not monetizedShoe-Box Liqudation Proceeds high direct 1 48,00 discarded metal valued 85€/1000kg transfercosts
to junk yard = 200€ 8000 kg discarded metal from a TelliBox= 480€/10years = 48€
Shoe-Box Lower Transport Costs high direct 1 19.240,00 testrack: Tellibox has an cost advantage of
0,37€/km 20 circulations per year *2 trips 1trip=1300km 20*2*1300=19240€
Shoe-Box Stackability high direct 1 277,50 recent options are not stackable, storage fee is based on stack hight. 1st attempt: 24 days circulation + 1day 2nd attempt: 10% of all calendardays the container is stored. This costs
approx. 10€ per day = 370€. TelliBox is four times stackable. This would be only 2,5€ for a TelliBox => 277,5€ benefit
Shoe-Box Standard Handling,
Top Crane Handling
high direct 1 not monetized
Shoe-Box Transsiberian
Transport
high direct 1 263,00 Time savings vs. Shipping: 10 days. Average value
per Container: 20.000€; interest: 6% p.a.; 8 circulations p.a 20.000*0,06/356*10 *8= 263€
Shoe-Box Trimodal high direct 1 not monetizedShoe-Box Abilitiy to use Eco-
friendly Carriers
high indirect 2 not monetized
Shoe-Box Easy Handling high indirect 2 not monetizedShoe-Box Robust, Low
Reparation Costs
high indirect 2 not monetized
Shoe-Box higher Artic Truck Height through Gooseneck
high difficult to ascertain
4 not monetized
Shoe-Box Only One Basic Material
medium indirect 5
Shoe-Box Weatherproof medium indirect 5 not monetizedShoe-Box Marketingtool medium difficult to
ascertain7 not monetized
Shoe-Box Sustainable medium difficult to ascertain
7 not monetized
Shoe-Box Flexible on Ramps low indirect 8 not monetizedShoe-Box Integrated Tie-Down low indirect 8 756,00 staff saving and material saving: Material: 12
lashing straps for 15€ ea. *20% abrasion= 36€ staff: 0.5 h work time
Shoe-Box High Protection Against Theft
low difficult to ascertain
9 not monetized
Shoe-Box Less Hazards for Staff low difficult to ascertain
9 not monetized
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
68
8.7 Cost Model TelliBox
Cost Model TelliBox
General Key Figures
Gross Vehicle Weight Truck (t) 40
Gross Vehicle Weight (Combined Traffic, t) 44
Gross Vehicle Weight (Container, t) 30,48
Weight Truck (t) 7,48
Interest Rate 6%
Megatrailer (unimodal) AirTech-Box Fala-EC-Box Shoe-Box
Invest (€) 22950 32200 23000 27600
Invest Chassis (€) 0 15000 18000 16500
Weight (t) 6,9 10,5 9 8
Weight Chassis (t) 0
Permitted Vehicle Load Capacity (t) 25,62 20 21,5 23
Number of Pallet Places 34 33 33 33
Lifespan (Years) 5 10 10 10
Lifespan Chassis (Years) 0 10 10 10
Liquidation Proceeds (€) 600 480 680 680
Maintenance. (€/a) 2000 1040 800 800
Repair Costs (€/a) 0 1220 300 760
Insurance (€/a) 0 0 0 0
Average Worth of Loading 25000 25000 25000 25000
Expenses for capital commitment 1500 1500 1500 1500
Travel Costs
Average Transport Lengh (km) 1000 1300 1300 1300
Round Trips per year 88 20 20 20
Annual Mileage (km/a) 175000 52000 52000 52000
Transport Costs Road (€/100km) 127,8 127,8 127,8 127,8
Transport Costs Rail (€/100km) 80 80 80
Transport Costs Barge (€/100km) 60 60 60
Transport Costs Short Sea (€/100km) 100 100 100
Factor of Detour Road 1 1 1 1
Factor of Detour Rail 1,1 1,1 1,1
Factor of Detour Barge 1,2 1,2 1,2
Factor of Detour Short Sea 1 1 1
Transport Costs (Average Truck, BGL) (€/100km)
127,8 127,8 127,8 127,8
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
69
Additional Charge
Transport Costs for Specific Transport Carrier (€/100km) 127,8 127,8 127,8 127,8
Transport Costs Rail effective (€/100km) 0 88 88 88
Transport Costs Barge effektive (€/100km) 0 72 72 72
Transport Costs Short Sea effektive (€/100km) 0 100 100 100
Share of Pre- and Onward Carriage in Short Traffic 0 0,5 0,5 0,5
Average Lengh in Short Traffic (km) 0 100 100 100
Pre- and Onward Carriage in Short Traffic Close Region til 50 km (€)
0 150 150 150
Pre- and Onward Carriage in Short Traffic Local Region till 150 km (€)
0 250 250 250
Average Pre- and Onward Carriage in Short Traffic (€) 0 200 200 200
Costs for Pre- and Onward Carriage in Short Traffic (€) 0 8000 8000 8000
Division of Transport Carriers
Road 1 0,3 0,3 0,3
Rail 0 0,65 0,65 0,65
Barge 0 0,025 0,025 0,025
Short Sea 0 0,025 0,025 0,025
Average Travel Costs (€/100km) 127,8 99,84 99,84 99,84
Annual Transport Costs (€) 223650 55916,8 55916,8 55916,8
Annual Transport Costs (€) mod! 66456
Costs for Transhipment
Road-Rail (€ each Transhipment) 25 25 25
Rail-Rail (€ each Transhipment) 45 45 45
Inland Harbor (€ each Handling) 50 50 50
Seaport (€ each Transhipment)) 100 100 100
Number of Transhipments for one Year (exemplary)
No Transhipment 0 0 0 0
1 Transhipment: Road-Rail 0 33,429 33,429 33,429
1 Transhipment: Road-Barge 0 1,286 1,286 1,286
1 Transhipment: Road-Short Sea 0 0,714 0,714 0,714
2 Transhipments: Road - Rail + Rail - Rail 0 3,714 3,714 3,714
2 Transhipments: Road - Rail + Barge 0 0,143 0,143 0,143
2 Transhipments: Road - Rail + Short Sea 0 0,571 0,571 0,571
2 Transhipments: Barge + Short Sea 0 0,143 0,143 0,143
Other 0 0 0 0
Total (equal to 2 x Round Trips/a) 40 40 40
Loading Charges each One-Way Route
No Transhipment 0 0 0
1 Transhipment: Road-Rail
50 50 50
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
70
1 Transhipment: Road -Barge 100 100 100
1 Transhipment: Road -Short Sea 200 200 200
2 Transhipments: Road - Rail + Rail - Rail 95 95 95
2 Transhipments: Road - Rail + Barge 125 125 125
2 Transhipments: Road - Rail + Short Sea 225 225 225
2 Transhipments: Barge + Short Sea 250 250 250
Other 0 0 0
Annual Transhipment Costs (€/a) 0 2477,857143 2477,857143 2477,857143
Limitation of Loading
None 20% 20% 20%
Capacity 80% 80% 80%
Weight 0% 0% 0%
Factor Disadvantage of Capacity 1,03 1,03 1,03
Factor Disadvantage of Weight 0,000 0,000 0,000
Total Factor of Limitation of Loading 1,0242 1,0242 1,0242
Annual Total Costs (€/a) 227150 63661,43671 62473,3155 62944,46701
Annual Total Costs (€/a) mod! 67496
NPV (€) 22950 3.473,27 € 20.629,63 € 13.011,91 €
ROI (%) 0 67% 248% 145%
TelliBox: x is precursor of y
x y Road Barge Short Sea
Road 0 0,9 0,5
Rail 0 0,1 0,4
Barge 0 0 0,1
Short Sea 0 0 0
1+Interest 1,060
Megatrailer Megatrailer_mod(new) AirTech-Box
Fala-EC-Box
Shoe-Box
Annual Mileage (km/a) 175000 52000 52000,00 52000,00 52000,00
Invest (€) 22950 6819,428571 36700,00 28400,00 32550,00
Annual Total Costs (€/a) 227150 67496 63661,44 62473,32 62944,47
Liquidation Proceeds (€) 600 178 480,00 680,00 680,00
NPV Calculation:
Deliverable_ ProfitabilityOfConcepts _D.10_final
© TelliBox consortium
TelliBox is funded within the Seventh Framework Programme (FP7) of the European Commission
71
Year AirTech-
Box Fala-EC-Box Shoe-Box
0 -29881 -21581 -25731
1 3618 4738 4294
2 3413 4470 4051
3 3220 4217 3822
4 3037 3978 3605
5 7828 8716 8364
6 2703 3541 3209
7 2550 3340 3027
8 2406 3151 2856
9 2270 2973 2694
10 2310 3085 2822
NPV: 3473 20630 13012
ROI: 67% 248% 145%