11/22/2010 1 Copyright 2010 Lockheed Martin Aeronautics Company Name: William Golaz Title: LM Fellow & LM Aero Measurement and Analysis Lead Deploying the Measurement and Analysis Process
Transcript
Page 1: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

11/22/2010 1Copyright 2010 Lockheed Martin Aeronautics Company

Name: William GolazTitle: LM Fellow & LM Aero Measurement and Analysis Lead

Deploying the Measurement and Analysis Process

Page 2: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

2Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Topics

• Background• Problem• Approach• Experience• Resources• Results• Summary

11/22/2010

Page 3: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

3Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

3Copyright © 2010 Lockheed Martin Corporation

Fort Worth, TX14,529

Marietta, GA6,864

Palmdale, CA3,834

Pinellas Park, FL - 174

Meridian, MS - 134

Clarksburg, WV - 78Johnstown, PA – 103

YF-22

F-117

U-2

F-16

C-5

C-130J

F-35C CV

F-35A CTOL

F-35B STOVL

F-22

X-35

29,000 employees across the company and around the world

International - 39

Greenville, SC - 3400

Lockheed Martin Aeronautics Overview

Page 4: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

4Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Background

• Lockheed Martin Aeronautics measurement process improvements– SEI CMM Level 3 for software – 1993

• SW Standard Metrics– SEI CMM Level 4 for software – 1999

• SW Quantitative Management– SEI CMMI Level 3 at company level – 2007 & 2010

• Company wide measurement process

11/22/2010

Page 5: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

5Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Problem• How to deploy the company Measurement and

Analysis process across multiple programs and geographical sites?– Institutionalize the M&A process

• Georgia, Texas, and California– Incorporate M&A planning into the program

planning– Identify and deploy M&A related training– Programs already doing most of M&A process

11/22/2010

Change company culture

Page 6: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

6Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Approach• Take the Measurement and Analysis process to

the programs– M&A planning workshops on site with the

programs– Facilitated by small team of M&A experts– Pre-populated M&A planning templates– M&A process awareness training prerequisite

for participants– Met with program management– Include current program SMEs and middle

management

11/22/2010

Page 7: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

7Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Approach (cont.)• Objective: Develop a 70-80% complete M&A Plan

for the program by end of 3 day workshop• Preparation

– Schedule workshop with program POC• Coordinate appropriate participants

– Pre-populated plan template with standard content• Boiler plate material• General measurement traceability data• Measurement specification data for standard

measures• Standard reference to M&A training• Place holders for required content

11/22/2010

Page 8: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

8Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Approach (cont.)• Objective: Develop a 70-80% complete M&A Plan for the

program by end of 3 day workshop• Onsite

– Obtain buy-in from program manager– Identify current Information Needs with middle

management– Review current measures with program SMEs

• Match to the Information Needs• Identify any gaps or duplications

– Load program data in organizational database– Generate plan tables from the database– Identify and fill in program specific information in the

plan– Identify remaining tasks for program POC

11/22/2010

Page 9: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

9Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Workshop activities

11/22/2010

Pre-populate template & database

M&A Team

Program POC

Program Mid Mgmt

Program SMEs

Program Mgr

Schedule workshop

Complete initial M&A training

Review plantemplate

Detail info from Prog SMEs•Objectives•info needs & gaps•Current Measures•Reporting mechanisms

Collect information from Middle Mgmt•Objectives•Information needs & gaps•Current Measures•Reporting mechanisms

Initial buy in

Page 10: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

10Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Workshop activities (cont.)

11/22/2010

Populate database Generate draft plan

Review draft plan with program POC

Hand off plan to program POC

M&A Team

Program POC

Program Mid Mgmt

Program SMEs

Program Mgr

Collect Reporting and other program specifics

Complete Plan

Notice this frees up the program to continue working

Page 11: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

11Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Experiences• Programs appreciated the help

– Going to the program minimized impact to the program• Distributed planning experience across company

– M&A Team could take best practices & lessons learned from program to program

• Planning made workshop go smoother– Clear expectations and objectives

• Flexibility in execution fit better with program availability– Meet with management in a CR or go to their offices

• Meet with program manager helped gain buy in and visibility of M&A planning

• Many times program had been requested to improve their measures just before we arrived

11/22/2010

Page 12: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

12Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Program A Program B Program Z

Distribution of Lessons Learned

11/22/2010

M&A Planning experience

M&A Team & Plan Template

Page 13: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

13Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Experiences (cont.)

• Program follow up to complete the plan sometimes became low priority after we left – Took long time to complete

• Program personnel assigned to complete plan sometimes were re-assigned

• Program later did not recognize M&A planning as significant portion of program planning

• Program didn’t want to include all measures in their plan• Program didn’t use the plan to mange their measures with

– tendency to do it like they always have• Difficult identifying various reporting mechanisms using

measures

11/22/2010

Page 14: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

14Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Resources• Resources:

– Pre-populated M&A plan template• Common objectives, information needs and

measures• Boiler plate information• Training references• References to standard process

– Measurement Model Database• Specification data for standard measures• Common objectives and information needs• Able to generate tables for M&A plan

11/22/2010

Page 15: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

15Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Results• Began culture change about use of measurement

– Everyone uses measurement but they don’t plan how they use them or link them to specific information needs

– Understand the need to document analysis and actions in preparation for management consumption

– Concept to plan their measurement activities – Expanded awareness of M&A infrastructure

11/22/2010

Page 16: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

16Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Summary

• Institutionalization of the measurement and analysis process

• Culture change• Take the process to the programs• Assisted the programs in measurement planning

11/22/2010

Page 17: Deploying the Measurement and Analysis Process · Lockheed Martin Aeronautics measurement process improvements – SEI CMM Level 3 for software – 1993 • SW Standard Metrics –

17Lockheed Martin Aeronautics Company© 2010 Lockheed Martin Aeronautics Company

Contact Information

• William H. Golaz– LM Fellow– Lockheed Martin Aeronautics– 817-935-5701– [email protected]