DEPT OF PUBLIC ENTERPRISES
CAPEX UPDATE
PRESENTATION TO THE PORTFOLIO COMMITTEE ON PUBLIC ENTERPRISES
16 AUGUST 2006
CONTENTS
• Progress Eskom’s Build Programme Overall spent to date
Supplier Development (SD)
Jobs created
• Progress on the Integrated National
Electrification Programme (INEP)
• Progress Transnet Build Programme
2
3
Progress on Eskom Build Programme
4
Progress on Eskom Build Programme (Cont)
5
Progress on Eskom Build Programme (Cont)
6
Progress on Eskom Build Programme (Cont)
7 7
Build Programme & SD
• Maximise SD & industry wide initiatives
• SD with major focus on Small enterprise (SE)with turnover of up to R25m
Medium enterprises (ME) with turnover between R25m & R100m
Black Women Owned Business (BWOB) including both Small & Medium enterprises
8 8
Build Programme & SD
• Opportunities are explored to contract directly with the above group Suppliers Engagement Where direct contracting is not practical, large
suppliers to subcontract a substantial amount of the contract to SE, ME & BWOBs
Include skills transfer & programme, to be audited by Eskom (including classroom content)
In service training & learnerships to students
9 9
BP & HR Capacity building
• Target 4 000 by March 2007 year-end through: Providing them with skills for either employability
or to be self employed Identifying & developing critical skills for Eskom &
the industry future requirements Engineers, artisans, technicians & graduates-in
training will be targeted Expansion & central coordination of learnership
programmes, with funding from the Energy Sector Training Authority (ESETA) grant; currently Eskom has 1127 students in the programme
10 10
Progress on INEP
• The DME is reponsible for planning, coordination, administration, monitoring & evaluation of the INEP
• The year 2012 is targeted for universal access
• 3.2 million households have been electrified since 1991
• 3.4 million households are un-electrified
11 11
HOUSEHOLD ELECTRIFICATION - HISTORY
SOUTH AFRICACOST PER
CONNECTIONRURAL
CONNECTIONSURBAN
CONNECTIONSTOTAL
CONNECTIONS
1991 - 1994 3,176 572,441 66,853 639,294
1995 3,370 226,065 87,114 313,179
1996 3,417 261,438 45,609 307,047
1997 3,159 241,880 43,662 285,542
1998 3,008 198,197 93,155 291,352
1999 2,899 173,625 125,622 299,247
2000 2,647 133,672 122,351 256,023
2001 2,532 105,587 103,948 209,535
2002 2,614 107,718 103,910 211,628
2003 3,384 117,108 58,288 175,396
2004 4,207 126,477 43,893 170,370
2005 (March) 38,920 12,974 51,894
2005/6 4,137 119,077 16,791 135,868
GRAND TOTAL 2,422,205 924,170 3,346,375
12 12
Progress on INEP
• Annual funding is R1.39 billion and 230 000 hhlds are connected
• In order to achieve the target annual funding should be R3.6 billion and 500 000 hhlds should be connected
• Should the above happen the programme could create 10 000 jobs per annum (according to the DME).
13 13
Transnet core businesses: 5 year investment plan
• 5 Year investment plan R64.5bn – Rail R34.1bn– Ports R24.8bn– Pipeline R4.9bn
• Major investments: To sustain and expand operations – Export lines: Iron ore and Coal lines to increase capacity and major
refurbishment costs– Port infrastructure and terminals – General freight business: Replacement of assets; major refurbishment
costs– Pipeline (Multi product) from Durban to Johannesburg to create
capacity
14 14
Corporate plan: Capex 2006/07 and 5 year plan
Total 5 year Capital Investment Plan: R64.5bn
R11.4bn R15.3bn R14.7bn R12.0bn R11.1bn
Rail
R31.5bn
Ports Pipeline Other
R24.8bn R4.9bn R3.3bn
5 year investment plan
2006/07 2007/08 2008/09 2009/10 2010/11
18% 24% 23% 18% 17%
Roll out plan
15 15
Transnet capital projects
•To ensure effective implementation of investment plan:– Appointed new focused, centralised and experienced project team
– Centralised control over projects in excess of R 300 million
– Access to high quality skills for managing risk and delivery on
•Major projects–Transnet Capital Projects responsible for entire project value chain –
feasibility to execution
– Agreement with Hatch/Mott MacDondald/Goba (International project
management consultants with local representation)
16 16
Progress to date – July 2006
• Most of projects have commenced
• Spending to date R2.0bn vs budget of R3.1bn
– Spoornet underspending R0.8bn
– NPA underspending R0.3bn
• Spending behind schedule mainly due to:-
– Delays in the approvals of EIA’s (mainly NPA)
– Delivery of imported supplies (eg. wheel centres for Spoornet which is
the major cause of Spoornet being behind budget. This underspending
will be progressively caught up)
• Plans in place to accelerate implementation over remaining months
CORE BUSINESSES
17 17
Transnet core businesses: Capital expenditure 2006/07
3.1
8.3
11.4
2.0
9.4
0
2
4
6
8
10
12
April to July2006
August 06 toMarch 07
Estimate2006/07
Ra
nd
Bil
lio
n
Budget Actual / Estimate
18 18
Progress on major projects – July 2006
Saldanha Port/Rail line
- Total cost of project is R3bn and the budget for 2006/07 is R1.1bn
- Spending to date R134m against budget of R325m (mainly due to revision of
engineering design)
Cape Town Container terminal
- ETC of R2.4bn with R160m budgeted for 2006/07
- EIA approval outstanding
- Project essential to create required capacity for container handling
19 19
Progress on major projects – July 2006 (cont.)
Durban Pier 1: Resurfacing
• Total cost of R1.4bn
− Civil contracts already awarded
• Spending to date: R68m vs budget of R108m
Durban Harbour Entrance Widening
• Total cost of project is R1.7bn
• Feasibility study underway
• Detail engineering in progress which includes breakwater and
deepening of channel
• Spending to date: R16m vs budget of R25m
20 20
Progress on major projects – July 2006 (cont.)
Port of Ngqura
• Will conclude phase 1 of the project in 2006/07 (total cost of R3.5bn)
• Feasibilities undertaken to construct a container terminal at port
• Experiencing delays in land surveys
• Spending to date 2006/07 on Nqgura is R26m vs budget of R82m
21 21
Progress on major projects – July 2006 (cont.)
OTHER PROJECTS
Wagon fleet renewal and modernisation
• Budget 2006/07: R900m, actual spending to date R278m vs budget of
• R241m
Coal line capacity expansion from 71mtpa to 78mtpa
• Budget 2006/07 of R119m, actual spending to date R90m vs budget of
• R24m
Projects between R20m – R300m
•Specific focus and action plans to address projects behind schedule
22 22
Major risks in roll out of investment plan
Delay in EIA approvals
Claims and other legal challenges
Delivery of imported equipment
23 23
Projections: Capex spending
Transnet committed to roll out the 5 year plan
Core businesses confident that approved budget for 2006/07 will be
largely achieved
Resources allocated to ensure successful implementation of planned
projects