# Activity ID Activity Name Original Duration Start Finish
1 EXCHANGEREXCHANGER 560h 06-Feb-15 06:00 AM 01-Mar-15 02:00 PM
2 INSP-EXCH-FIX-D/N01INSP-EXCH-FIX-D/N01 473h 09-Feb-15 06:00 AM 28-Feb-15 11:00 PM
3 R15E-310-021 RC2-32-310-41-E-303 EXCHANGER - INT, EXT INSPECTIONR15E-310-021 RC2-32-310-41-E-303 EXCHANGER - INT, EXT INSPECTION 413h 11-Feb-15 06:00 PM 28-Feb-15 11:00 PM
4 SHUTDOWNSHUTDOWN 413h 11-Feb-15 06:00 PM 28-Feb-15 11:00 PM
5 IM110410 Purging, Flushing & Gas test, LEL checking 4h 11-Feb-15 06:00 PM 11-Feb-15 10:00 PM
6 IM110415 Verify LT&T and Obtain PTW 2h 11-Feb-15 10:00 PM 12-Feb-15 12:00 AM
7 IM110420 Drop spools & blind as per blindlist 15h 12-Feb-15 12:00 AM 12-Feb-15 03:00 PM
8 IM110425 Remove channel covers & distribution plate 10h 12-Feb-15 03:00 PM 13-Feb-15 01:00 AM
9 IM110430 Carryout prelim. inspn. & Offer for AFI 3h 13-Feb-15 01:00 AM 13-Feb-15 04:00 AM
10 IM110435 100% hydrojetting of tube internals 90h 17-Feb-15 06:00 AM 21-Feb-15 12:00 AM
11 IM110440 Hydrojetting of tubesheet & channel covers 5h 21-Feb-15 12:00 AM 21-Feb-15 05:00 AM
12 IM110445 Carryout detailed inspn. 3h 21-Feb-15 05:00 AM 21-Feb-15 08:00 AM
13 IM110450 RFECT inspn. on 471 tubes (Confirm via IRIS) 82h 22-Feb-15 07:00 PM 26-Feb-15 05:00 AM
14 IM110455 Boroscopic test & thickness monitoring 3h 26-Feb-15 05:00 AM 26-Feb-15 08:00 AM
15 IM110460 NDT of welds 3h 26-Feb-15 08:00 AM 26-Feb-15 11:00 AM
16 IM110465 Hydrotest on shell & tube side 10h 26-Feb-15 11:00 AM 26-Feb-15 09:00 PM
17 IM110470 Repairs & retest as per inspn. report 20h 26-Feb-15 09:00 PM 27-Feb-15 05:00 PM
18 IM110475 Final Inspection 2h 27-Feb-15 05:00 PM 27-Feb-15 07:00 PM
19 IM110480 Reinstall distribution plate & channel covers 12h 27-Feb-15 07:00 PM 28-Feb-15 07:00 AM
20 IM110485 Reinstall spools & Deblinding 16h 28-Feb-15 07:00 AM 28-Feb-15 11:00 PM
21 R15E-810-019 RC2-32-810-41-E-807 EXCHANGER - INT, EXT INSPECTIONR15E-810-019 RC2-32-810-41-E-807 EXCHANGER - INT, EXT INSPECTION 410h 09-Feb-15 06:00 AM 26-Feb-15 08:00 AM
22 SHUTDOWNSHUTDOWN 410h 09-Feb-15 06:00 AM 26-Feb-15 08:00 AM
23 IM111125 Purging, Flushing & Gas test, LEL checking 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM
24 IM111130 Verify LT&T and Obtain PTW 2h 09-Feb-15 10:00 AM 09-Feb-15 12:00 PM
25 IM111135 Drop spools & blind as per blindlist 25h 09-Feb-15 12:00 PM 10-Feb-15 01:00 PM
26 IM111140 Remove both channel covers 20h 10-Feb-15 01:00 PM 11-Feb-15 09:00 AM
27 IM111145 Carryout prelim. inspn. & Offer for AFI 3h 11-Feb-15 09:00 AM 11-Feb-15 12:00 PM
28 IM111150 100% hydrojetting of tube internals 130h 11-Feb-15 12:00 PM 16-Feb-15 10:00 PM
29 IM111155 Hydrojetting of tubesheet & channel covers 5h 16-Feb-15 10:00 PM 17-Feb-15 03:00 AM
30 IM111160 Carryout detailed inspn. 3h 17-Feb-15 03:00 AM 17-Feb-15 06:00 AM
31 IM111165 ECT on 780 tubes (Confirm via IRIS) 130h 17-Feb-15 06:00 AM 22-Feb-15 04:00 PM
32 IM111170 Boroscopic test & thickness monitoring 3h 22-Feb-15 04:00 PM 22-Feb-15 07:00 PM
33 IM111175 NDT of welds 3h 22-Feb-15 07:00 PM 22-Feb-15 10:00 PM
34 IM111180 Hydrostatic test on shell & tube side 12h 22-Feb-15 10:00 PM 23-Feb-15 10:00 AM
35 IM111185 Repairs & retest as per inspn. report 20h 23-Feb-15 10:00 AM 24-Feb-15 06:00 AM
36 IM111190 Final Inspection 2h 24-Feb-15 06:00 AM 24-Feb-15 08:00 AM
37 IM111195 Reinstall channel covers 20h 24-Feb-15 08:00 AM 25-Feb-15 04:00 AM
38 IM111200 Reinstall spools & Deblinding 28h 25-Feb-15 04:00 AM 26-Feb-15 08:00 AM
39 INSP-EXCH-FIX-D/N02INSP-EXCH-FIX-D/N02 536h 07-Feb-15 06:00 AM 01-Mar-15 02:00 PM
40 R15E-310-019 RC2-32-310-41-E-301 EXCHANGER - INT, EXT INSPECTIONR15E-310-019 RC2-32-310-41-E-301 EXCHANGER - INT, EXT INSPECTION 464h 10-Feb-15 06:00 AM 01-Mar-15 02:00 PM
41 SHUTDOWNSHUTDOWN 464h 10-Feb-15 06:00 AM 01-Mar-15 02:00 PM
42 IM110170 Purging, Flushing & Gas test, LEL checking 4h 10-Feb-15 06:00 AM 10-Feb-15 10:00 AM
43 IM110175 Verify LT&T and Obtain PTW 2h 10-Feb-15 10:00 AM 10-Feb-15 12:00 PM
44 IM110180 Drop spools & blind as per blindlist 15h 10-Feb-15 12:00 PM 11-Feb-15 03:00 AM
45 IM110185 Remove channel covers & distribution plate 10h 11-Feb-15 03:00 AM 11-Feb-15 01:00 PM
46 IM110190 Carryout prelim. inspn. & Offer for AFI 3h 11-Feb-15 01:00 PM 11-Feb-15 04:00 PM
47 IM110195 100% hydrojetting of tube internals 120h 16-Feb-15 08:00 PM 21-Feb-15 08:00 PM
48 IM110200 Hydrojetting of tubesheet & channel covers 5h 21-Feb-15 08:00 PM 22-Feb-15 01:00 AM
49 IM110205 Carryout detailed inspn. 3h 22-Feb-15 01:00 AM 22-Feb-15 04:00 AM
50 IM110210 RFECT inspn. on 557 tubes (Confirm via IRIS) 100h 22-Feb-15 04:00 AM 26-Feb-15 08:00 AM
51 IM110215 Boroscopic test & thickness monitoring 3h 26-Feb-15 08:00 AM 26-Feb-15 11:00 AM
52 IM110220 NDT of welds 3h 26-Feb-15 11:00 AM 26-Feb-15 02:00 PM
53 IM110225 Hydrotest on shell & tube side 10h 26-Feb-15 02:00 PM 27-Feb-15 12:00 AM
54 IM110230 Repairs & retest as per inspn. report 20h 27-Feb-15 12:00 AM 27-Feb-15 08:00 PM
55 IM110235 Final Inspection 2h 27-Feb-15 08:00 PM 27-Feb-15 10:00 PM
56 IM110240 Reinstall distribution plate & channel covers 12h 28-Feb-15 10:00 AM 28-Feb-15 10:00 PM
57 IM110245 Reinstall spools & Deblinding 16h 28-Feb-15 10:00 PM 01-Mar-15 02:00 PM
58 R15E-310-024 RC2-32-310-41-E-305 EXCHANGER - INT, EXT INSPECTIONR15E-310-024 RC2-32-310-41-E-305 EXCHANGER - INT, EXT INSPECTION 288h 07-Feb-15 06:00 AM 19-Feb-15 06:00 AM
59 SHUTDOWNSHUTDOWN 288h 07-Feb-15 06:00 AM 19-Feb-15 06:00 AM
60 IM110650 Purging, Flushing & Gas test, LEL checking 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM
61 IM110655 Verify LT&T and Obtain PTW 2h 07-Feb-15 10:00 AM 07-Feb-15 12:00 PM
62 IM110660 Drop spools & blind as per blindlist 15h 07-Feb-15 12:00 PM 08-Feb-15 03:00 AM
63 IM110665 Remove channel covers & distribution plate 10h 08-Feb-15 03:00 AM 08-Feb-15 01:00 PM
64 IM110670 Carryout prelim. inspn. & Offer for AFI 3h 08-Feb-15 01:00 PM 08-Feb-15 04:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 1 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
65 IM110675 100% hydrojetting of tube internals 90h 08-Feb-15 04:00 PM 12-Feb-15 10:00 AM
66 IM110680 Hydrojetting of tubesheet & channel covers 5h 12-Feb-15 10:00 AM 12-Feb-15 03:00 PM
67 IM110685 Carryout detailed inspn. 3h 12-Feb-15 03:00 PM 12-Feb-15 06:00 PM
68 IM110690 RFECT inspn. on 348 tubes (Confirm via IRIS) 90h 12-Feb-15 06:00 PM 16-Feb-15 12:00 PM
69 IM110695 Boroscopic test & thickness monitoring 3h 16-Feb-15 12:00 PM 16-Feb-15 03:00 PM
70 IM110700 NDT of welds 3h 16-Feb-15 03:00 PM 16-Feb-15 06:00 PM
71 IM110705 Hydrotest on shell & tube side 10h 16-Feb-15 06:00 PM 17-Feb-15 04:00 AM
72 IM110710 Repairs & retest as per inspn. report 20h 17-Feb-15 04:00 AM 18-Feb-15 12:00 AM
73 IM110715 Final Inspection 2h 18-Feb-15 12:00 AM 18-Feb-15 02:00 AM
74 IM110720 Reinstall distribution plate & channel covers 12h 18-Feb-15 02:00 AM 18-Feb-15 02:00 PM
75 IM110725 Reinstall spools & Deblinding 16h 18-Feb-15 02:00 PM 19-Feb-15 06:00 AM
76 R15E-310-025 RC2-32-310-41-E-306 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-310-025 RC2-32-310-41-E-306 EXCHANGER - INT, EXT, CUI INSPECTION 488h 08-Feb-15 06:00 PM 01-Mar-15 02:00 AM
77 SHUTDOWNSHUTDOWN 488h 08-Feb-15 06:00 PM 01-Mar-15 02:00 AM
78 IM110775 Purging, Flushing & Gas test, LEL checking 4h 08-Feb-15 06:00 PM 08-Feb-15 10:00 PM
79 IM110780 Verify LT&T and Obtain PTW 2h 08-Feb-15 10:00 PM 09-Feb-15 12:00 AM
80 IM110785 Drop spools & blind as per blindlist 15h 09-Feb-15 12:00 AM 09-Feb-15 03:00 PM
81 IM110790 Remove channel covers 10h 09-Feb-15 03:00 PM 10-Feb-15 01:00 AM
82 IM110795 Carryout prelim. inspn. & Offer for AFI 3h 10-Feb-15 01:00 AM 10-Feb-15 04:00 AM
83 IM110800 100% hydrojetting of tube internals 90h 12-Feb-15 06:00 PM 16-Feb-15 12:00 PM
84 IM110805 Hydrojetting of tubesheet & channel covers 5h 16-Feb-15 12:00 PM 16-Feb-15 05:00 PM
85 IM110810 Carryout detailed inspn. 3h 16-Feb-15 05:00 PM 16-Feb-15 08:00 PM
86 IM110815 RFECT inspn. on 271 tubes (Confirm via IRIS) 90h 16-Feb-15 08:00 PM 20-Feb-15 02:00 PM
87 IM110820 Boroscopic test & thickness monitoring 3h 20-Feb-15 02:00 PM 20-Feb-15 05:00 PM
88 IM110825 NDT of welds & CUI inspection 6h 20-Feb-15 05:00 PM 20-Feb-15 11:00 PM
89 IM110830 Hydrotest on shell & tube side 10h 20-Feb-15 11:00 PM 21-Feb-15 09:00 AM
90 IM110835 Repairs & retest as per inspn. report 20h 21-Feb-15 09:00 AM 22-Feb-15 05:00 AM
91 IM110840 Final Inspection 2h 22-Feb-15 05:00 AM 22-Feb-15 07:00 AM
92 IM110845 Reinstall channel covers 12h 27-Feb-15 10:00 PM 28-Feb-15 10:00 AM
93 IM110850 Reinstall spools & Deblinding 16h 28-Feb-15 10:00 AM 01-Mar-15 02:00 AM
94 INSP-EXCH-FIX-D/N03INSP-EXCH-FIX-D/N03 448h 07-Feb-15 06:00 AM 25-Feb-15 10:00 PM
95 R15E-310-020 RC2-32-310-41-E-302 EXCHANGER - INT, EXT INSPECTIONR15E-310-020 RC2-32-310-41-E-302 EXCHANGER - INT, EXT INSPECTION 305h 07-Feb-15 06:00 AM 19-Feb-15 11:00 PM
96 SHUTDOWNSHUTDOWN 305h 07-Feb-15 06:00 AM 19-Feb-15 11:00 PM
97 IM110290 Purging, Flushing & Gas test, LEL checking 6h 07-Feb-15 06:00 AM 07-Feb-15 12:00 PM
98 IM110295 Verify LT&T and Obtain PTW 2h 07-Feb-15 12:00 PM 07-Feb-15 02:00 PM
99 IM110300 Drop spools & blind as per blindlist 15h 07-Feb-15 02:00 PM 08-Feb-15 05:00 AM
100 IM110305 Remove channel covers & distribution plate 10h 08-Feb-15 05:00 AM 08-Feb-15 03:00 PM
101 IM110310 Carryout prelim. inspn. & Offer for AFI 3h 08-Feb-15 03:00 PM 08-Feb-15 06:00 PM
102 IM110315 100% hydrojetting of tube internals 120h 08-Feb-15 06:00 PM 13-Feb-15 06:00 PM
103 IM110320 Hydrojetting of tubesheet & channel covers 5h 13-Feb-15 06:00 PM 13-Feb-15 11:00 PM
104 IM110325 Carryout detailed inspn. 3h 13-Feb-15 11:00 PM 14-Feb-15 02:00 AM
105 IM110330 RFECT inspn. on 423 tubes (Confirm via IRIS) 75h 14-Feb-15 02:00 AM 17-Feb-15 05:00 AM
106 IM110335 Boroscopic test & thickness monitoring 3h 17-Feb-15 05:00 AM 17-Feb-15 08:00 AM
107 IM110340 NDT of welds 3h 17-Feb-15 08:00 AM 17-Feb-15 11:00 AM
108 IM110345 Hydrotest on shell & tube side 10h 17-Feb-15 11:00 AM 17-Feb-15 09:00 PM
109 IM110350 Repairs & retest as per inspn. report 20h 17-Feb-15 09:00 PM 18-Feb-15 05:00 PM
110 IM110355 Final Inspection 2h 18-Feb-15 05:00 PM 18-Feb-15 07:00 PM
111 IM110360 Reinstall distribution plate & channel covers 12h 18-Feb-15 07:00 PM 19-Feb-15 07:00 AM
112 IM110365 Reinstall spools & Deblinding 16h 19-Feb-15 07:00 AM 19-Feb-15 11:00 PM
113 R15E-310-022 RC2-32-310-41-E-304 EXCHANGER - INT, EXT INSPECTIONR15E-310-022 RC2-32-310-41-E-304 EXCHANGER - INT, EXT INSPECTION 388h 09-Feb-15 06:00 PM 25-Feb-15 10:00 PM
114 SHUTDOWNSHUTDOWN 388h 09-Feb-15 06:00 PM 25-Feb-15 10:00 PM
115 IM110530 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 06:00 PM 10-Feb-15 12:00 AM
116 IM110535 Verify LT&T and Obtain PTW 2h 10-Feb-15 12:00 AM 10-Feb-15 02:00 AM
117 IM110540 Drop spools & blind as per blindlist 15h 10-Feb-15 02:00 AM 10-Feb-15 05:00 PM
118 IM110545 Remove channel covers & distribution plate 10h 10-Feb-15 05:00 PM 11-Feb-15 03:00 AM
119 IM110550 Carryout prelim. inspn. & Offer for AFI 3h 11-Feb-15 03:00 AM 11-Feb-15 06:00 AM
120 IM110555 100% hydrojetting of tube internals 120h 14-Feb-15 02:00 AM 19-Feb-15 02:00 AM
121 IM110560 Hydrojetting of tubesheet & channel covers 5h 19-Feb-15 02:00 AM 19-Feb-15 07:00 AM
122 IM110565 Carryout detailed inspn. 3h 19-Feb-15 07:00 AM 19-Feb-15 10:00 AM
123 IM110570 RFECT inspn. on 512 tubes (Confirm via IRIS) 90h 19-Feb-15 10:00 AM 23-Feb-15 04:00 AM
124 IM110575 Boroscopic test & thickness monitoring 3h 23-Feb-15 04:00 AM 23-Feb-15 07:00 AM
125 IM110580 NDT of welds 3h 23-Feb-15 07:00 AM 23-Feb-15 10:00 AM
126 IM110585 Hydrotest on shell & tube side 10h 23-Feb-15 10:00 AM 23-Feb-15 08:00 PM
127 IM110590 Repairs & retest as per inspn. report 20h 23-Feb-15 08:00 PM 24-Feb-15 04:00 PM
128 IM110595 Final Inspection 2h 24-Feb-15 04:00 PM 24-Feb-15 06:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 2 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
129 IM110600 Reinstall distribution plate & channel covers 12h 24-Feb-15 06:00 PM 25-Feb-15 06:00 AM
130 IM110605 Reinstall spools & Deblinding 16h 25-Feb-15 06:00 AM 25-Feb-15 10:00 PM
131 INSP-EXCH-FIX-D/N04INSP-EXCH-FIX-D/N04 370h 06-Feb-15 06:00 AM 21-Feb-15 04:00 PM
132 R15E-510-008 RC2-32-510-41-E-502 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-510-008 RC2-32-510-41-E-502 EXCHANGER - INT, EXT, CUI INSPECTION 179h 06-Feb-15 06:00 AM 13-Feb-15 05:00 PM
133 SHUTDOWNSHUTDOWN 179h 06-Feb-15 06:00 AM 13-Feb-15 05:00 PM
134 IM109930 Purging, Flushing & Gas test, LEL checking 6h 06-Feb-15 06:00 AM 06-Feb-15 12:00 PM
135 IM109935 Verify LT&T and Obtain PTW 2h 06-Feb-15 12:00 PM 06-Feb-15 02:00 PM
136 IM109940 Drop spools & blind as per blindlist 14h 06-Feb-15 02:00 PM 07-Feb-15 04:00 AM
137 IM109945 Remove channel covers 8h 07-Feb-15 04:00 AM 07-Feb-15 12:00 PM
138 IM109950 Carryout prelim. inspn. & Offer for AFI 2h 07-Feb-15 12:00 PM 07-Feb-15 02:00 PM
139 IM109955 100% hydrojetting of tube internals 50h 07-Feb-15 02:00 PM 09-Feb-15 04:00 PM
140 IM109960 Hydrojetting of tubesheet & channel covers 6h 09-Feb-15 04:00 PM 09-Feb-15 10:00 PM
141 IM109965 Carryout detailed inspn. 3h 09-Feb-15 10:00 PM 10-Feb-15 01:00 AM
142 IM109970 RFECT inspn. on 133 tubes (Confirm via IRIS) 25h 10-Feb-15 01:00 AM 11-Feb-15 02:00 AM
143 IM109975 Boroscopic test & thickness monitoring 3h 11-Feb-15 02:00 AM 11-Feb-15 05:00 AM
144 IM109980 NDT of welds & CUI inspection 6h 11-Feb-15 05:00 AM 11-Feb-15 11:00 AM
145 IM109985 Hydrotest on shell & tube side 9h 11-Feb-15 11:00 AM 11-Feb-15 08:00 PM
146 IM109990 Repairs & retest as per inspn. report 20h 11-Feb-15 08:00 PM 12-Feb-15 04:00 PM
147 IM109995 Final Inspection 2h 12-Feb-15 04:00 PM 12-Feb-15 06:00 PM
148 IM110000 Reinstall channel covers 8h 12-Feb-15 06:00 PM 13-Feb-15 02:00 AM
149 IM110005 Reinstall spools & Deblinding 15h 13-Feb-15 02:00 AM 13-Feb-15 05:00 PM
150 R15E-510-014 RC2-32-510-41-E-504 EXCHANGER - EXT, CUI INSPECTIONR15E-510-014 RC2-32-510-41-E-504 EXCHANGER - EXT, CUI INSPECTION 194h 08-Feb-15 06:00 PM 16-Feb-15 08:00 PM
151 SHUTDOWNSHUTDOWN 194h 08-Feb-15 06:00 PM 16-Feb-15 08:00 PM
152 IM111370 Purging, Flushing & Gas test, LEL checking 6h 08-Feb-15 06:00 PM 09-Feb-15 12:00 AM
153 IM111375 Verify LT&T and Obtain PTW 2h 09-Feb-15 12:00 AM 09-Feb-15 02:00 AM
154 IM111380 Drop spools & blind as per blindlist 10h 09-Feb-15 02:00 AM 09-Feb-15 12:00 PM
155 IM111385 Remove channel covers 8h 09-Feb-15 12:00 PM 09-Feb-15 08:00 PM
156 IM111390 Carryout prelim. inspn. & Offer for AFI 3h 09-Feb-15 08:00 PM 09-Feb-15 11:00 PM
157 IM111395 100% hydrojetting of tube internals 40h 10-Feb-15 01:00 AM 11-Feb-15 05:00 PM
158 IM111400 Hydrojetting of tubesheet & channel covers 5h 11-Feb-15 05:00 PM 11-Feb-15 10:00 PM
159 IM111405 Carryout detailed inspn. 3h 11-Feb-15 10:00 PM 12-Feb-15 01:00 AM
160 IM111410 RFECT inspn. on 258 tubes (Confirm via IRIS) 52h 12-Feb-15 01:00 AM 14-Feb-15 05:00 AM
161 IM111415 Boroscopic test & thickness monitoring 3h 14-Feb-15 05:00 AM 14-Feb-15 08:00 AM
162 IM111420 NDT of welds & CUI inspection 6h 14-Feb-15 08:00 AM 14-Feb-15 02:00 PM
163 IM111425 Hydrotest on shell & tube side 10h 14-Feb-15 02:00 PM 15-Feb-15 12:00 AM
164 IM111430 Repairs & retest as per inspn. report 20h 15-Feb-15 12:00 AM 15-Feb-15 08:00 PM
165 IM111435 Final Inspection 2h 15-Feb-15 08:00 PM 15-Feb-15 10:00 PM
166 IM111440 Reinstall channel covers 10h 15-Feb-15 10:00 PM 16-Feb-15 08:00 AM
167 IM111445 Reinstall spools & Deblinding 12h 16-Feb-15 08:00 AM 16-Feb-15 08:00 PM
168 R15E-510-064 RC2-32-510-41-E-505 EXCHANGER - INT, EXT INSPECTIONR15E-510-064 RC2-32-510-41-E-505 EXCHANGER - INT, EXT INSPECTION 262h 10-Feb-15 06:00 PM 21-Feb-15 04:00 PM
169 SHUTDOWNSHUTDOWN 262h 10-Feb-15 06:00 PM 21-Feb-15 04:00 PM
170 IM114420 Purging, Flushing & Gas test, LEL checking 6h 10-Feb-15 06:00 PM 11-Feb-15 12:00 AM
171 IM114425 Verify LT&T and Obtain PTW 2h 11-Feb-15 12:00 AM 11-Feb-15 02:00 AM
172 IM114430 Drop spools & blind as per blindlist 10h 11-Feb-15 02:00 AM 11-Feb-15 12:00 PM
173 IM114435 Remove channel covers 8h 11-Feb-15 12:00 PM 11-Feb-15 08:00 PM
174 IM114440 Carryout prelim. inspn. & Offer for AFI 3h 11-Feb-15 08:00 PM 11-Feb-15 11:00 PM
175 IM114445 100% hydrojetting of tube internals 90h 12-Feb-15 01:00 AM 15-Feb-15 07:00 PM
176 IM114450 Hydrojetting of tubesheet & channel covers 5h 15-Feb-15 07:00 PM 16-Feb-15 12:00 AM
177 IM114455 Carryout detailed inspn. 3h 16-Feb-15 12:00 AM 16-Feb-15 03:00 AM
178 IM114460 RFECT inspn. on 264 tubes (Confirm via IRIS) 70h 16-Feb-15 03:00 AM 19-Feb-15 01:00 AM
179 IM114465 Boroscopic test & thickness monitoring 3h 19-Feb-15 01:00 AM 19-Feb-15 04:00 AM
180 IM114470 NDT of welds & CUI inspection 6h 19-Feb-15 04:00 AM 19-Feb-15 10:00 AM
181 IM114475 Hydrotest on shell & tube side 10h 19-Feb-15 10:00 AM 19-Feb-15 08:00 PM
182 IM114480 Repairs & retest as per inspn. report 20h 19-Feb-15 08:00 PM 20-Feb-15 04:00 PM
183 IM114485 Final Inspection 2h 20-Feb-15 04:00 PM 20-Feb-15 06:00 PM
184 IM114490 Reinstall channel covers 10h 20-Feb-15 06:00 PM 21-Feb-15 04:00 AM
185 IM114495 Reinstall spools & Deblinding 12h 21-Feb-15 04:00 AM 21-Feb-15 04:00 PM
186 R15E-710-025 RC2-32-710-41-E-708 EXCHANGER - INT, EXT INSPECTIONR15E-710-025 RC2-32-710-41-E-708 EXCHANGER - INT, EXT INSPECTION 115h 12-Feb-15 06:00 PM 17-Feb-15 01:00 PM
187 SHUTDOWNSHUTDOWN 115h 12-Feb-15 06:00 PM 17-Feb-15 01:00 PM
188 IM110050 Purging, Flushing & Gas test, LEL checking 6h 12-Feb-15 06:00 PM 13-Feb-15 12:00 AM
189 IM110055 Verify LT&T and Obtain PTW 2h 13-Feb-15 12:00 AM 13-Feb-15 02:00 AM
190 IM110060 Drop spools & blind as per blindlist 10h 13-Feb-15 02:00 AM 13-Feb-15 12:00 PM
191 IM110065 Remove both channel covers 8h 13-Feb-15 12:00 PM 13-Feb-15 08:00 PM
192 IM110070 Carryout prelim. inspn. & Offer for AFI 3h 13-Feb-15 08:00 PM 13-Feb-15 11:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 3 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
193 IM110075 100% hydrojetting of tube internals 10h 13-Feb-15 11:00 PM 14-Feb-15 09:00 AM
194 IM110080 Hydrojetting of tubesheet & channel covers 5h 14-Feb-15 09:00 AM 14-Feb-15 02:00 PM
195 IM110085 Carryout detailed inspn. 3h 14-Feb-15 02:00 PM 14-Feb-15 05:00 PM
196 IM110090 RFECT inspn. on 50 tubes (Confirm via IRIS) 10h 14-Feb-15 05:00 PM 15-Feb-15 03:00 AM
197 IM110095 Boroscopic test & thickness monitoring 3h 15-Feb-15 03:00 AM 15-Feb-15 06:00 AM
198 IM110100 NDT of welds 3h 15-Feb-15 06:00 AM 15-Feb-15 09:00 AM
199 IM110105 Hydrotest on shell & tube side 8h 15-Feb-15 09:00 AM 15-Feb-15 05:00 PM
200 IM110110 Repairs & retest as per inspn. report 20h 15-Feb-15 05:00 PM 16-Feb-15 01:00 PM
201 IM110115 Final Inspection 2h 16-Feb-15 01:00 PM 16-Feb-15 03:00 PM
202 IM110120 Reinstall channel covers 10h 16-Feb-15 03:00 PM 17-Feb-15 01:00 AM
203 IM110125 Reinstall spools & Deblinding 12h 17-Feb-15 01:00 AM 17-Feb-15 01:00 PM
204 INSP-EXCH-FIX-D/N05INSP-EXCH-FIX-D/N05 372h 08-Feb-15 06:00 AM 23-Feb-15 06:00 PM
205 R15E-420-002 RC2-32-420-41-E-401 EXCHANGER - INT, EXT INSPECTIONR15E-420-002 RC2-32-420-41-E-401 EXCHANGER - INT, EXT INSPECTION 372h 08-Feb-15 06:00 AM 23-Feb-15 06:00 PM
206 SHUTDOWNSHUTDOWN 372h 08-Feb-15 06:00 AM 23-Feb-15 06:00 PM
207 IM114540 Purging, Flushing & Gas test, LEL checking 6h 08-Feb-15 06:00 AM 08-Feb-15 12:00 PM
208 IM114545 Verify LT&T and Obtain PTW 2h 08-Feb-15 12:00 PM 08-Feb-15 02:00 PM
209 IM114550 Drop spools & blind as per blindlist 15h 08-Feb-15 02:00 PM 09-Feb-15 05:00 AM
210 IM114555 Remove channel covers 10h 09-Feb-15 05:00 AM 09-Feb-15 03:00 PM
211 IM114560 Carryout prelim. inspn. & Offer for AFI 3h 09-Feb-15 03:00 PM 09-Feb-15 06:00 PM
212 IM114565 100% hydrojetting of tube internals 90h 09-Feb-15 06:00 PM 13-Feb-15 12:00 PM
213 IM114570 Hydrojetting of tubesheet & channel covers 5h 13-Feb-15 12:00 PM 13-Feb-15 05:00 PM
214 IM114575 Carryout detailed inspn. 3h 13-Feb-15 05:00 PM 13-Feb-15 08:00 PM
215 IM114580 RFECT inspn. on 348 tubes (Confirm via IRIS) 90h 13-Feb-15 08:00 PM 17-Feb-15 02:00 PM
216 IM114585 Boroscopic test & thickness monitoring 3h 17-Feb-15 02:00 PM 17-Feb-15 05:00 PM
217 IM114590 NDT of welds 3h 17-Feb-15 05:00 PM 17-Feb-15 08:00 PM
218 IM114595 Carryout Helium test 24h 17-Feb-15 08:00 PM 18-Feb-15 08:00 PM
219 IM114600 Repairs & retest as per inspn. report 36h 18-Feb-15 08:00 PM 20-Feb-15 08:00 AM
220 IM114605 Final Inspection 2h 20-Feb-15 08:00 AM 20-Feb-15 10:00 AM
221 IM114610 Reinstall channel covers 12h 20-Feb-15 10:00 AM 20-Feb-15 10:00 PM
222 IM114615 Reinstall spools & Deblinding 16h 23-Feb-15 02:00 AM 23-Feb-15 06:00 PM
223 R15E-610-001 RC2-32-610-41-E-601 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-610-001 RC2-32-610-41-E-601 EXCHANGER - INT, EXT, CUI INSPECTION 302h 09-Feb-15 06:00 PM 22-Feb-15 08:00 AM
224 SHUTDOWNSHUTDOWN 302h 09-Feb-15 06:00 PM 22-Feb-15 08:00 AM
225 IM110900 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 06:00 PM 10-Feb-15 12:00 AM
226 IM110905 Verify LT&T and Obtain PTW 2h 10-Feb-15 12:00 AM 10-Feb-15 02:00 AM
227 IM110910 Drop spools & blind as per blindlist 5h 10-Feb-15 02:00 AM 10-Feb-15 07:00 AM
228 IM110915 Remove top channel cover 4h 10-Feb-15 07:00 AM 10-Feb-15 11:00 AM
229 IM110920 Carryout prelim. inspn. & Offer for AFI 2h 10-Feb-15 11:00 AM 10-Feb-15 01:00 PM
230 IM110925 100% hydrojetting of tube internals 30h 13-Feb-15 08:00 PM 15-Feb-15 02:00 AM
231 IM110930 Hydrojetting of tubesheet & channel covers 4h 15-Feb-15 02:00 AM 15-Feb-15 06:00 AM
232 IM110935 Carryout detailed inspn. 3h 15-Feb-15 06:00 AM 15-Feb-15 09:00 AM
233 IM110940 RFECT inspn. on 130 tubes (Confirm via IRIS) 12h 17-Feb-15 05:00 PM 18-Feb-15 05:00 AM
234 IM110945 Boroscopic test & thickness monitoring 3h 18-Feb-15 05:00 AM 18-Feb-15 08:00 AM
235 IM110950 NDT of welds & CUI inspection 4h 20-Feb-15 10:00 AM 20-Feb-15 02:00 PM
236 IM110955 Hydrotest on shell side 8h 20-Feb-15 02:00 PM 20-Feb-15 10:00 PM
237 IM110960 Repairs & retest as per inspn. report 20h 20-Feb-15 10:00 PM 21-Feb-15 06:00 PM
238 IM110965 Final Inspection 2h 21-Feb-15 06:00 PM 21-Feb-15 08:00 PM
239 IM110970 Reinstall channel cover 5h 21-Feb-15 08:00 PM 22-Feb-15 01:00 AM
240 IM110975 Reinstall spools & Deblinding 7h 22-Feb-15 01:00 AM 22-Feb-15 08:00 AM
241 INSP-EXCH-FIX-D/N06INSP-EXCH-FIX-D/N06 419h 09-Feb-15 06:00 AM 26-Feb-15 05:00 PM
242 R15E-810-014 RC2-32-810-41-E-801A EXCHANGER - INT, EXT INSPECTIONR15E-810-014 RC2-32-810-41-E-801A EXCHANGER - INT, EXT INSPECTION 301h 09-Feb-15 06:00 AM 21-Feb-15 07:00 PM
243 SHUTDOWNSHUTDOWN 301h 09-Feb-15 06:00 AM 21-Feb-15 07:00 PM
244 IM114800 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
245 IM114805 Verify LT&T and Obtain PTW 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM
246 IM114810 Drop spools & blind as per blindlist 16h 09-Feb-15 02:00 PM 10-Feb-15 06:00 AM
247 IM114815 Remove both channel covers 10h 10-Feb-15 06:00 AM 10-Feb-15 04:00 PM
248 IM114820 Carryout prelim. inspn. & Offer for AFI 3h 10-Feb-15 04:00 PM 10-Feb-15 07:00 PM
249 IM114825 100% hydrojetting of tube internals 110h 10-Feb-15 07:00 PM 15-Feb-15 09:00 AM
250 IM114830 Hydrojetting of tubesheet & channel covers 5h 15-Feb-15 09:00 AM 15-Feb-15 02:00 PM
251 IM114835 Carryout detailed inspn. 3h 15-Feb-15 02:00 PM 15-Feb-15 05:00 PM
252 IM114840 IRIS on 417 tubes 70h 15-Feb-15 05:00 PM 18-Feb-15 03:00 PM
253 IM114845 Boroscopic test & thickness monitoring 3h 18-Feb-15 03:00 PM 18-Feb-15 06:00 PM
254 IM114850 NDT of welds 3h 18-Feb-15 06:00 PM 18-Feb-15 09:00 PM
255 IM114855 Carryout Helium test 24h 18-Feb-15 09:00 PM 19-Feb-15 09:00 PM
256 IM114860 Repairs & retest as per inspn. Report 20h 19-Feb-15 09:00 PM 20-Feb-15 05:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 4 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
257 IM114865 Final Inspection 2h 20-Feb-15 05:00 PM 20-Feb-15 07:00 PM
258 IM114870 Reinstall channel covers 12h 20-Feb-15 07:00 PM 21-Feb-15 07:00 AM
259 IM114875 Reinstall spools & Deblinding 12h 21-Feb-15 07:00 AM 21-Feb-15 07:00 PM
260 R15E-810-015 RC2-32-810-41-E-801B EXCHANGER - INT, EXT INSPECTIONR15E-810-015 RC2-32-810-41-E-801B EXCHANGER - INT, EXT INSPECTION 395h 10-Feb-15 06:00 AM 26-Feb-15 05:00 PM
261 SHUTDOWNSHUTDOWN 395h 10-Feb-15 06:00 AM 26-Feb-15 05:00 PM
262 IM114920 Purging, Flushing & Gas test, LEL checking 6h 10-Feb-15 06:00 AM 10-Feb-15 12:00 PM
263 IM114925 Verify LT&T and Obtain PTW 2h 10-Feb-15 12:00 PM 10-Feb-15 02:00 PM
264 IM114930 Drop spools & blind as per blindlist 16h 10-Feb-15 07:00 PM 11-Feb-15 11:00 AM
265 IM114935 Remove both channel covers 10h 11-Feb-15 11:00 AM 11-Feb-15 09:00 PM
266 IM114940 Carryout prelim. inspn. & Offer for AFI 3h 11-Feb-15 09:00 PM 12-Feb-15 12:00 AM
267 IM114945 100% hydrojetting of tube internals 110h 15-Feb-15 05:00 PM 20-Feb-15 07:00 AM
268 IM114950 Hydrojetting of tubesheet & channel covers 5h 20-Feb-15 07:00 AM 20-Feb-15 12:00 PM
269 IM114955 Carryout detailed inspn. 3h 20-Feb-15 12:00 PM 20-Feb-15 03:00 PM
270 IM114960 IRIS on 417 tubes 70h 20-Feb-15 03:00 PM 23-Feb-15 01:00 PM
271 IM114965 Boroscopic test & thickness monitoring 3h 23-Feb-15 01:00 PM 23-Feb-15 04:00 PM
272 IM114970 NDT of welds 3h 23-Feb-15 04:00 PM 23-Feb-15 07:00 PM
273 IM114975 Carryout Helium test 24h 23-Feb-15 07:00 PM 24-Feb-15 07:00 PM
274 IM114980 Repairs & retest as per inspn. Report 20h 24-Feb-15 07:00 PM 25-Feb-15 03:00 PM
275 IM114985 Final Inspection 2h 25-Feb-15 03:00 PM 25-Feb-15 05:00 PM
276 IM114990 Reinstall channel covers 12h 25-Feb-15 05:00 PM 26-Feb-15 05:00 AM
277 IM114995 Reinstall spools & Deblinding 12h 26-Feb-15 05:00 AM 26-Feb-15 05:00 PM
278 INSP-EXCH-FIX-D/N07INSP-EXCH-FIX-D/N07 302h 09-Feb-15 06:00 AM 21-Feb-15 08:00 PM
279 R15E-151-002 RC2-32-151-41-E-201 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-151-002 RC2-32-151-41-E-201 EXCHANGER - INT, EXT, CUI INSPECTION 240h 09-Feb-15 06:00 AM 19-Feb-15 06:00 AM
280 SHUTDOWNSHUTDOWN 240h 09-Feb-15 06:00 AM 19-Feb-15 06:00 AM
281 IM109805 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
282 IM109810 Verify LT&T and Obtain PTW 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM
283 IM109815 Drop spools & blind as per blindlist 12h 09-Feb-15 02:00 PM 10-Feb-15 02:00 AM
284 IM109820 Remove both channel covers 10h 10-Feb-15 02:00 AM 10-Feb-15 12:00 PM
285 IM109825 Carryout prelim. inspn. & Offer for AFI 3h 10-Feb-15 12:00 PM 10-Feb-15 03:00 PM
286 IM109830 100% hydrojetting of tube internals 50h 10-Feb-15 03:00 PM 12-Feb-15 05:00 PM
287 IM109835 Hydrojetting of tubesheet & channel covers 5h 12-Feb-15 05:00 PM 12-Feb-15 10:00 PM
288 IM109840 Carryout detailed inspn. 3h 12-Feb-15 10:00 PM 13-Feb-15 01:00 AM
289 IM109845 RFECT inspn. on 540 tubes (Confirm via IRIS) 90h 13-Feb-15 01:00 AM 16-Feb-15 07:00 PM
290 IM109850 Boroscopic test & thickness monitoring 3h 16-Feb-15 07:00 PM 16-Feb-15 10:00 PM
291 IM109855 NDT of welds & CUI inspection 3h 16-Feb-15 10:00 PM 17-Feb-15 01:00 AM
292 IM109860 Hydrotest on shell & tube side 9h 17-Feb-15 01:00 AM 17-Feb-15 10:00 AM
293 IM109865 Repairs & retest as per inspn. report 20h 17-Feb-15 10:00 AM 18-Feb-15 06:00 AM
294 IM109870 Final Inspection 2h 18-Feb-15 06:00 AM 18-Feb-15 08:00 AM
295 IM109875 Reinstall channel covers 10h 18-Feb-15 08:00 AM 18-Feb-15 06:00 PM
296 IM109880 Reinstall spools & Deblinding 12h 18-Feb-15 06:00 PM 19-Feb-15 06:00 AM
297 R15E-810-016 RC2-32-810-41-E-802 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-810-016 RC2-32-810-41-E-802 EXCHANGER - INT, EXT, CUI INSPECTION 230h 12-Feb-15 06:00 AM 21-Feb-15 08:00 PM
298 SHUTDOWNSHUTDOWN 230h 12-Feb-15 06:00 AM 21-Feb-15 08:00 PM
299 IM111245 Purging, Flushing & Gas test, LEL checking 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM
300 IM111250 Verify LT&T and Obtain PTW 2h 12-Feb-15 12:00 PM 12-Feb-15 02:00 PM
301 IM111255 Drop spools & blind as per blindlist 8h 12-Feb-15 02:00 PM 12-Feb-15 10:00 PM
302 IM111260 Remove channel covers 8h 12-Feb-15 10:00 PM 13-Feb-15 06:00 AM
303 IM111265 Carryout prelim. inspn. & Offer for AFI 3h 13-Feb-15 06:00 AM 13-Feb-15 09:00 AM
304 IM111270 100% hydrojetting of tube internals 75h 13-Feb-15 09:00 AM 16-Feb-15 12:00 PM
305 IM111275 Hydrojetting of tubesheet & channel covers 5h 16-Feb-15 12:00 PM 16-Feb-15 05:00 PM
306 IM111280 Carryout detailed inspn. 3h 16-Feb-15 05:00 PM 16-Feb-15 08:00 PM
307 IM111285 RFECT inspn. on 193 tubes (Confirm via IRIS) 55h 16-Feb-15 10:00 PM 19-Feb-15 05:00 AM
308 IM111290 Boroscopic test & thickness monitoring 3h 19-Feb-15 05:00 AM 19-Feb-15 08:00 AM
309 IM111295 NDT of welds & CUI inspection 6h 19-Feb-15 08:00 AM 19-Feb-15 02:00 PM
310 IM111300 Hydrotest on shell & tube side 10h 19-Feb-15 02:00 PM 20-Feb-15 12:00 AM
311 IM111305 Repairs & retest as per inspn. report 20h 20-Feb-15 12:00 AM 20-Feb-15 08:00 PM
312 IM111310 Final Inspection 2h 20-Feb-15 08:00 PM 20-Feb-15 10:00 PM
313 IM111315 Reinstall channel covers 10h 20-Feb-15 10:00 PM 21-Feb-15 08:00 AM
314 IM111320 Reinstall spools & Deblinding 12h 21-Feb-15 08:00 AM 21-Feb-15 08:00 PM
315 INSP-EXCH-FIX-D/N08INSP-EXCH-FIX-D/N08 330h 08-Feb-15 06:00 AM 22-Feb-15 12:00 AM
316 R15E-310-029 RC2-32-310-41-E-316 EXCHANGER - INT, EXT INSPECTIONR15E-310-029 RC2-32-310-41-E-316 EXCHANGER - INT, EXT INSPECTION 330h 08-Feb-15 06:00 AM 22-Feb-15 12:00 AM
317 SHUTDOWNSHUTDOWN 330h 08-Feb-15 06:00 AM 22-Feb-15 12:00 AM
318 IM111015 Purging, Flushing & Gas test, LEL checking 6h 08-Feb-15 06:00 AM 08-Feb-15 12:00 PM
319 IM111020 Verify LT&T and Obtain PTW 2h 08-Feb-15 12:00 PM 08-Feb-15 02:00 PM
320 IM111025 Drop spools & blind as per blindlist 24h 08-Feb-15 02:00 PM 09-Feb-15 02:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 5 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
321 IM111030 Remove end covers 15h 09-Feb-15 02:00 PM 10-Feb-15 05:00 AM
322 IM111035 Carryout prelim. inspn. & Offer for AFI, CSE required. 3h 10-Feb-15 09:00 AM 10-Feb-15 12:00 PM
323 IM111040 100% hydrojetting of tube internals 100h 10-Feb-15 12:00 PM 14-Feb-15 04:00 PM
324 IM111045 Hydrojetting of tubesheet & channel covers 5h 14-Feb-15 04:00 PM 14-Feb-15 09:00 PM
325 IM111050 Carryout detailed inspn. 3h 14-Feb-15 09:00 PM 15-Feb-15 12:00 AM
326 IM111055 ECT on 347 tubes (Confirm via IRIS) 70h 15-Feb-15 12:00 AM 17-Feb-15 10:00 PM
327 IM111060 Boroscopic test & thickness monitoring 5h 17-Feb-15 10:00 PM 18-Feb-15 03:00 AM
328 IM111065 NDT of welds 5h 18-Feb-15 03:00 AM 18-Feb-15 08:00 AM
329 IM111070 Hydrostatic test on shell & tube side 20h 18-Feb-15 08:00 AM 19-Feb-15 04:00 AM
330 IM111075 Repairs & retest as per inspn. report 24h 19-Feb-15 04:00 AM 20-Feb-15 04:00 AM
331 IM111080 Final Inspection 2h 20-Feb-15 04:00 AM 20-Feb-15 06:00 AM
332 IM111085 Reinstall end covers 18h 20-Feb-15 06:00 AM 21-Feb-15 12:00 AM
333 IM111090 Reinstall spools & Deblinding 24h 21-Feb-15 12:00 AM 22-Feb-15 12:00 AM
334 INSP-EXCH-U-D/N09INSP-EXCH-U-D/N09 384h 07-Feb-15 06:00 AM 23-Feb-15 06:00 AM
335 R15E-320-016 RC2-32-320-41-E-307 EXCHANGER - INT, EXT INSPECTIONR15E-320-016 RC2-32-320-41-E-307 EXCHANGER - INT, EXT INSPECTION 147h 15-Feb-15 10:00 AM 21-Feb-15 01:00 PM
336 SHUTDOWNSHUTDOWN 147h 15-Feb-15 10:00 AM 21-Feb-15 01:00 PM
337 IM111485 Purging, Flushing & Gas test, LEL checking 6h 15-Feb-15 10:00 AM 15-Feb-15 04:00 PM
338 IM111490 Verify LT&T and Obtain PTW 2h 15-Feb-15 04:00 PM 15-Feb-15 06:00 PM
339 IM111495 Drop spools & blind as per blindlist 8h 15-Feb-15 06:00 PM 16-Feb-15 02:00 AM
340 IM111500 Remove channel head 5h 16-Feb-15 02:00 AM 16-Feb-15 07:00 AM
341 IM111505 Carryout prelim. inspn. & Offer for AFI 2h 16-Feb-15 07:00 AM 16-Feb-15 09:00 AM
342 IM111510 Pull out the tube bundle 5h 16-Feb-15 09:00 AM 16-Feb-15 02:00 PM
343 IM111515 Perform AFI on tube bundle, shell & channel head 2h 16-Feb-15 02:00 PM 16-Feb-15 04:00 PM
344 IM111520 Shift tube bundle to jetting area 2h 16-Feb-15 04:00 PM 16-Feb-15 06:00 PM
345 IM111525 100% hydrojetting of tube external & internal 10h 16-Feb-15 06:00 PM 17-Feb-15 04:00 AM
346 IM111530 Hydrojetting of shell & channel covers 4h 17-Feb-15 04:00 AM 17-Feb-15 08:00 AM
347 IM111535 Perform detailed inspn. 3h 17-Feb-15 08:00 AM 17-Feb-15 11:00 AM
348 IM111540 RFECT inspn. on 178U tubes (Confirm via IRIS) 33h 17-Feb-15 11:00 AM 18-Feb-15 08:00 PM
349 IM111545 NDT of welds & thickness monitoring 6h 18-Feb-15 08:00 PM 19-Feb-15 02:00 AM
350 IM111550 Shift back tube bundle to site 3h 19-Feb-15 02:00 AM 19-Feb-15 05:00 AM
351 IM111555 Reinstall tube bundle 4h 19-Feb-15 05:00 AM 19-Feb-15 09:00 AM
352 IM111560 Hydrotest shell with test ring,shell & tube side 15h 19-Feb-15 09:00 AM 20-Feb-15 12:00 AM
353 IM111565 Repairs & retest as per inspn. report 20h 20-Feb-15 12:00 AM 20-Feb-15 08:00 PM
354 IM111570 Final Inspection 2h 20-Feb-15 08:00 PM 20-Feb-15 10:00 PM
355 IM111575 Reinstall channel head 5h 20-Feb-15 10:00 PM 21-Feb-15 03:00 AM
356 IM111580 Reinstall spools & Deblinding 10h 21-Feb-15 03:00 AM 21-Feb-15 01:00 PM
357 R15E-320-018 RC2-32-320-41-E-308 EXCHANGER - INT, EXT INSPECTIONR15E-320-018 RC2-32-320-41-E-308 EXCHANGER - INT, EXT INSPECTION 152h 16-Feb-15 10:00 PM 23-Feb-15 06:00 AM
358 SHUTDOWNSHUTDOWN 152h 16-Feb-15 10:00 PM 23-Feb-15 06:00 AM
359 IM112750 Purging, Flushing & Gas test, LEL checking 6h 16-Feb-15 10:00 PM 17-Feb-15 04:00 AM
360 IM112755 Verify LT&T and Obtain PTW 2h 17-Feb-15 04:00 AM 17-Feb-15 06:00 AM
361 IM112760 Drop spools & blind as per blindlist 12h 17-Feb-15 06:00 AM 17-Feb-15 06:00 PM
362 IM112765 Remove channel head 5h 17-Feb-15 06:00 PM 17-Feb-15 11:00 PM
363 IM112770 Carryout prelim. inspn. & Offer for AFI 2h 17-Feb-15 11:00 PM 18-Feb-15 01:00 AM
364 IM112775 Pull out the tube bundle 5h 18-Feb-15 01:00 AM 18-Feb-15 06:00 AM
365 IM112780 Perform AFI on tube bundle & shell 2h 18-Feb-15 06:00 AM 18-Feb-15 08:00 AM
366 IM112785 Shift tube bundle to jetting area 2h 18-Feb-15 08:00 AM 18-Feb-15 10:00 AM
367 IM112790 100% hydrojetting of tube external & internal 12h 18-Feb-15 10:00 AM 18-Feb-15 10:00 PM
368 IM112795 Hydrojetting of shell & channel head 4h 18-Feb-15 10:00 PM 19-Feb-15 02:00 AM
369 IM112800 Perform detailed inspn. 3h 19-Feb-15 02:00 AM 19-Feb-15 05:00 AM
370 IM112805 RFECT inspn. on 256U tubes (Confirm via IRIS) 32h 19-Feb-15 05:00 AM 20-Feb-15 01:00 PM
371 IM112810 NDT of welds, visual insp. & thickness monitoring 6h 20-Feb-15 01:00 PM 20-Feb-15 07:00 PM
372 IM112815 Shift back tube bundle to site 2h 20-Feb-15 07:00 PM 20-Feb-15 09:00 PM
373 IM112820 Reinstall tube bundle 5h 20-Feb-15 09:00 PM 21-Feb-15 02:00 AM
374 IM112825 Hydrotest shell with test ring, shell & tube side 15h 21-Feb-15 02:00 AM 21-Feb-15 05:00 PM
375 IM112830 Repairs & retest as per inspn. Report 20h 21-Feb-15 05:00 PM 22-Feb-15 01:00 PM
376 IM112835 Final Inspection 2h 22-Feb-15 01:00 PM 22-Feb-15 03:00 PM
377 IM112840 Reinstall channel head 5h 22-Feb-15 03:00 PM 22-Feb-15 08:00 PM
378 IM112845 Reinstall spools & Deblinding 10h 22-Feb-15 08:00 PM 23-Feb-15 06:00 AM
379 R15E-610-004 RC2-32-610-41-E-603A EXCHANGER - INT, EXT INSPECTIONR15E-610-004 RC2-32-610-41-E-603A EXCHANGER - INT, EXT INSPECTION 115h 13-Feb-15 02:00 AM 17-Feb-15 09:00 PM
380 SHUTDOWNSHUTDOWN 115h 13-Feb-15 02:00 AM 17-Feb-15 09:00 PM
381 IM112180 Purging, Flushing & Gas test, LEL checking 6h 13-Feb-15 02:00 AM 13-Feb-15 08:00 AM
382 IM112185 Verify LT&T and Obtain PTW 2h 13-Feb-15 08:00 AM 13-Feb-15 10:00 AM
383 IM112190 Drop spools & blind as per blindlist 4h 13-Feb-15 10:00 AM 13-Feb-15 02:00 PM
384 IM112195 Open stub end & return bend housing flanges 4h 13-Feb-15 02:00 PM 13-Feb-15 06:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 6 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
385 IM112200 Carryout prelim. inspn. & Offer for AFI 2h 13-Feb-15 06:00 PM 13-Feb-15 08:00 PM
386 IM112205 Pull out the tube bundle 4h 13-Feb-15 08:00 PM 14-Feb-15 12:00 AM
387 IM112210 Perform AFI on tube bundle, shell & channel head 2h 14-Feb-15 12:00 AM 14-Feb-15 02:00 AM
388 IM112215 Shift tube bundle to jetting area 2h 14-Feb-15 02:00 AM 14-Feb-15 04:00 AM
389 IM112220 100% hydrojetting of tube external & internal 6h 14-Feb-15 04:00 AM 14-Feb-15 10:00 AM
390 IM112225 Hydrojetting of shell & channel covers 3h 14-Feb-15 10:00 AM 14-Feb-15 01:00 PM
391 IM112230 Perform detailed inspn. 2h 14-Feb-15 01:00 PM 14-Feb-15 03:00 PM
392 IM112235 RFECT inspn. on 14 tubes (Confirm via IRIS) 8h 14-Feb-15 03:00 PM 14-Feb-15 11:00 PM
393 IM112240 NDT of welds 3h 14-Feb-15 11:00 PM 15-Feb-15 02:00 AM
394 IM112245 Visual inspn. & thickness monitoring 3h 15-Feb-15 02:00 AM 15-Feb-15 05:00 AM
395 IM112250 Shift back tube bundle to site 2h 15-Feb-15 05:00 AM 15-Feb-15 07:00 AM
396 IM112255 Reinstall tube bundle 5h 15-Feb-15 06:00 PM 15-Feb-15 11:00 PM
397 IM112260 Hydrotest on shell & tube side 5h 15-Feb-15 11:00 PM 16-Feb-15 04:00 AM
398 IM112265 Repairs & retest as per inspn. Report 20h 16-Feb-15 04:00 AM 17-Feb-15 12:00 AM
399 IM112270 Final Inspection 2h 17-Feb-15 12:00 AM 17-Feb-15 02:00 AM
400 IM112275 Boxup the exchanger 4h 17-Feb-15 02:00 AM 17-Feb-15 06:00 AM
401 IM112280 Reinstall spools & Deblinding 5h 17-Feb-15 04:00 PM 17-Feb-15 09:00 PM
402 R15E-610-006 RC2-32-610-41-E-603B EXCHANGER - INT, EXT INSPECTIONR15E-610-006 RC2-32-610-41-E-603B EXCHANGER - INT, EXT INSPECTION 107h 13-Feb-15 10:00 AM 17-Feb-15 09:00 PM
403 SHUTDOWNSHUTDOWN 107h 13-Feb-15 10:00 AM 17-Feb-15 09:00 PM
404 IM112320 Purging, Flushing & Gas test, LEL checking 6h 13-Feb-15 10:00 AM 13-Feb-15 04:00 PM
405 IM112325 Verify LT&T and Obtain PTW 2h 13-Feb-15 04:00 PM 13-Feb-15 06:00 PM
406 IM112330 Drop spools & blind as per blindlist 4h 13-Feb-15 06:00 PM 13-Feb-15 10:00 PM
407 IM112335 Open stub end & return bend housing flanges 4h 13-Feb-15 10:00 PM 14-Feb-15 02:00 AM
408 IM112340 Carryout prelim. inspn. & Offer for AFI 2h 14-Feb-15 02:00 AM 14-Feb-15 04:00 AM
409 IM112345 Pull out the tube bundle 4h 14-Feb-15 04:00 AM 14-Feb-15 08:00 AM
410 IM112350 Perform AFI on tube bundle, shell & channel head 2h 14-Feb-15 08:00 AM 14-Feb-15 10:00 AM
411 IM112355 Shift tube bundle to jetting area 2h 14-Feb-15 10:00 AM 14-Feb-15 12:00 PM
412 IM112360 100% hydrojetting of tube external & internal 6h 14-Feb-15 12:00 PM 14-Feb-15 06:00 PM
413 IM112365 Hydrojetting of shell & channel covers 3h 14-Feb-15 06:00 PM 14-Feb-15 09:00 PM
414 IM112370 Perform detailed inspn. 2h 14-Feb-15 09:00 PM 14-Feb-15 11:00 PM
415 IM112375 RFECT inspn. on 14 tubes (Confirm via IRIS) 8h 15-Feb-15 05:00 AM 15-Feb-15 01:00 PM
416 IM112380 NDT of welds 3h 15-Feb-15 01:00 PM 15-Feb-15 04:00 PM
417 IM112385 Visual inspn. & thickness monitoring 3h 15-Feb-15 04:00 PM 15-Feb-15 07:00 PM
418 IM112390 Shift back tube bundle to site 2h 15-Feb-15 07:00 PM 15-Feb-15 09:00 PM
419 IM112395 Reinstall tube bundle 5h 16-Feb-15 04:00 AM 16-Feb-15 09:00 AM
420 IM112400 Hydrotest on shell & tube side 5h 16-Feb-15 09:00 AM 16-Feb-15 02:00 PM
421 IM112405 Repairs & retest as per inspn. Report 20h 16-Feb-15 02:00 PM 17-Feb-15 10:00 AM
422 IM112410 Final Inspection 2h 17-Feb-15 10:00 AM 17-Feb-15 12:00 PM
423 IM112415 Boxup the exchanger 4h 17-Feb-15 12:00 PM 17-Feb-15 04:00 PM
424 IM112420 Reinstall spools & Deblinding 5h 17-Feb-15 04:00 PM 17-Feb-15 09:00 PM
425 R15E-620-007 RC2-32-620-41-E-607 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-620-007 RC2-32-620-41-E-607 EXCHANGER - INT, EXT, CUI INSPECTION 135h 10-Feb-15 02:00 PM 16-Feb-15 05:00 AM
426 SHUTDOWNSHUTDOWN 135h 10-Feb-15 02:00 PM 16-Feb-15 05:00 AM
427 IM113890 Purging, Flushing & Gas test, LEL checking 6h 10-Feb-15 02:00 PM 10-Feb-15 08:00 PM
428 IM113895 Verify LT&T and Obtain PTW 2h 10-Feb-15 08:00 PM 10-Feb-15 10:00 PM
429 IM113900 Drop spools & blind as per blindlist 4h 10-Feb-15 10:00 PM 11-Feb-15 02:00 AM
430 IM113905 Remove channel head 4h 11-Feb-15 02:00 AM 11-Feb-15 06:00 AM
431 IM113910 Carryout prelim. inspn. & Offer for AFI 2h 11-Feb-15 06:00 AM 11-Feb-15 08:00 AM
432 IM113915 Pull out the tube bundle 3h 11-Feb-15 08:00 AM 11-Feb-15 11:00 AM
433 IM113920 Perform AFI on tube bundle & shell 10h 11-Feb-15 11:00 AM 11-Feb-15 09:00 PM
434 IM113925 Shift tube bundle to jetting area 4h 11-Feb-15 09:00 PM 12-Feb-15 01:00 AM
435 IM113930 100% hydrojetting of tube external & internal 2h 12-Feb-15 01:00 AM 12-Feb-15 03:00 AM
436 IM113935 Hydrojetting of shell & channel head 5h 12-Feb-15 03:00 AM 12-Feb-15 08:00 AM
437 IM113940 Perform detailed inspn. 8h 12-Feb-15 08:00 AM 12-Feb-15 04:00 PM
438 IM113945 RFECT inspn. on 96 tubes (Confirm via IRIS) 25h 12-Feb-15 04:00 PM 13-Feb-15 05:00 PM
439 IM113950 NDT of welds & CUI inspection 7h 13-Feb-15 05:00 PM 14-Feb-15 12:00 AM
440 IM113955 Shift back tube bundle to site 2h 14-Feb-15 12:00 AM 14-Feb-15 02:00 AM
441 IM113960 Reinstall tube bundle 4h 14-Feb-15 03:00 AM 14-Feb-15 07:00 AM
442 IM113965 Hydrotest on shell with test ring, shell & tube side test 15h 14-Feb-15 07:00 AM 14-Feb-15 10:00 PM
443 IM113970 Repairs & retest as per inspn. Report 20h 14-Feb-15 10:00 PM 15-Feb-15 06:00 PM
444 IM113975 Final Inspection 2h 15-Feb-15 06:00 PM 15-Feb-15 08:00 PM
445 IM113980 Reinstall channel head 4h 15-Feb-15 08:00 PM 16-Feb-15 12:00 AM
446 IM113985 Reinstall spools & Deblinding 5h 16-Feb-15 12:00 AM 16-Feb-15 05:00 AM
447 R15E-710-008 RC2-32-710-41-E-701 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-710-008 RC2-32-710-41-E-701 EXCHANGER - INT, EXT, CUI INSPECTION 131h 07-Feb-15 06:00 AM 12-Feb-15 05:00 PM
448 SHUTDOWNSHUTDOWN 131h 07-Feb-15 06:00 AM 12-Feb-15 05:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 7 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
449 IM114030 Purging, Flushing & Gas test, LEL checking 6h 07-Feb-15 06:00 AM 07-Feb-15 12:00 PM
450 IM114035 Verify LT&T and Obtain PTW 2h 07-Feb-15 12:00 PM 07-Feb-15 02:00 PM
451 IM114040 Drop spools & blind as per blindlist 5h 07-Feb-15 02:00 PM 07-Feb-15 07:00 PM
452 IM114045 Remove channel cover, head, shell cover 6h 07-Feb-15 07:00 PM 08-Feb-15 01:00 AM
453 IM114050 Open the floating head 3h 08-Feb-15 01:00 AM 08-Feb-15 04:00 AM
454 IM114055 Carryout prelim. inspn. & Offer for AFI 2h 08-Feb-15 04:00 AM 08-Feb-15 06:00 AM
455 IM114060 Pull out the tube bundle 5h 08-Feb-15 06:00 AM 08-Feb-15 11:00 AM
456 IM114065 Perform AFI on tube bundle & shell 2h 08-Feb-15 11:00 AM 08-Feb-15 01:00 PM
457 IM114070 Shift tube bundle to jetting area 2h 08-Feb-15 01:00 PM 08-Feb-15 03:00 PM
458 IM114075 100% hydrojetting of tube external & internal 15h 08-Feb-15 03:00 PM 09-Feb-15 06:00 AM
459 IM114080 Hydrojeting of shell, channel head, cover 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM
460 IM114085 Perform detailed inspn. 3h 09-Feb-15 10:00 AM 09-Feb-15 01:00 PM
461 IM114090 RFECT inspn. on 65 tubes (Confirm via IRIS) 12h 09-Feb-15 01:00 PM 10-Feb-15 01:00 AM
462 IM114095 Visual inspn, NDT of welds & CUI inspn. 6h 10-Feb-15 01:00 AM 10-Feb-15 07:00 AM
463 IM114100 Shift back tube bundle to site 2h 10-Feb-15 07:00 AM 10-Feb-15 09:00 AM
464 IM114105 Reinstall tube bundle 5h 10-Feb-15 09:00 AM 10-Feb-15 02:00 PM
465 IM114110 Hydrotest shell with test ring, shell & tube side test 15h 10-Feb-15 02:00 PM 11-Feb-15 05:00 AM
466 IM114115 Repairs & retest as per inspn. Report 20h 11-Feb-15 05:00 AM 12-Feb-15 01:00 AM
467 IM114120 Final Inspection 2h 12-Feb-15 01:00 AM 12-Feb-15 03:00 AM
468 IM114125 Reinstall floating & channel heads 8h 12-Feb-15 03:00 AM 12-Feb-15 11:00 AM
469 IM114130 Reinstall spools & Deblinding 6h 12-Feb-15 11:00 AM 12-Feb-15 05:00 PM
470 R15E-710-014 RC2-32-710-41-E-704A EXCHANGER - INT, EXT INSPECTIONR15E-710-014 RC2-32-710-41-E-704A EXCHANGER - INT, EXT INSPECTION 126h 09-Feb-15 06:00 AM 14-Feb-15 12:00 PM
471 SHUTDOWNSHUTDOWN 126h 09-Feb-15 06:00 AM 14-Feb-15 12:00 PM
472 IM111900 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
473 IM111905 Verify LT&T and Obtain PTW 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM
474 IM111910 Drop spools & blind as per blindlist 5h 09-Feb-15 02:00 PM 09-Feb-15 07:00 PM
475 IM111915 Open stub end & return bend housing flanges 4h 09-Feb-15 07:00 PM 09-Feb-15 11:00 PM
476 IM111920 Carryout prelim. inspn. & Offer for AFI 2h 09-Feb-15 11:00 PM 10-Feb-15 01:00 AM
477 IM111925 Pull out the tube bundle 4h 10-Feb-15 01:00 AM 10-Feb-15 05:00 AM
478 IM111930 Perform AFI on tube bundle, shell & channel head 2h 10-Feb-15 05:00 AM 10-Feb-15 07:00 AM
479 IM111935 Shift tube bundle to jetting area 2h 10-Feb-15 05:00 PM 10-Feb-15 07:00 PM
480 IM111940 100% hydrojetting of tube external & internal 6h 10-Feb-15 07:00 PM 11-Feb-15 01:00 AM
481 IM111945 Hydrojetting of shell & channel covers 3h 11-Feb-15 01:00 AM 11-Feb-15 04:00 AM
482 IM111950 Perform detailed inspn. 2h 11-Feb-15 04:00 AM 11-Feb-15 06:00 AM
483 IM111955 RFECT inspn. on 50 tubes (Confirm via IRIS) 12h 11-Feb-15 06:00 AM 11-Feb-15 06:00 PM
484 IM111960 NDT of welds 3h 11-Feb-15 06:00 PM 11-Feb-15 09:00 PM
485 IM111965 Visual inspn. & thickness monitoring 3h 11-Feb-15 09:00 PM 12-Feb-15 12:00 AM
486 IM111970 Shift back tube bundle to site 2h 12-Feb-15 12:00 PM 12-Feb-15 02:00 PM
487 IM111975 Reinstall tube bundle 5h 12-Feb-15 02:00 PM 12-Feb-15 07:00 PM
488 IM111980 Hydrotest on shell & tube side 5h 13-Feb-15 12:00 AM 13-Feb-15 05:00 AM
489 IM111985 Repairs & retest as per inspn. Report 20h 13-Feb-15 05:00 AM 14-Feb-15 01:00 AM
490 IM111990 Final Inspection 2h 14-Feb-15 01:00 AM 14-Feb-15 03:00 AM
491 IM111995 Boxup the exchanger 4h 14-Feb-15 03:00 AM 14-Feb-15 07:00 AM
492 IM112000 Reinstall spools & Deblinding 5h 14-Feb-15 07:00 AM 14-Feb-15 12:00 PM
493 R15E-710-015 RC2-32-710-41-E-704B EXCHANGER - INT, EXT INSPECTIONR15E-710-015 RC2-32-710-41-E-704B EXCHANGER - INT, EXT INSPECTION 122h 09-Feb-15 02:00 PM 14-Feb-15 04:00 PM
494 SHUTDOWNSHUTDOWN 122h 09-Feb-15 02:00 PM 14-Feb-15 04:00 PM
495 IM112040 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 02:00 PM 09-Feb-15 08:00 PM
496 IM112045 Verify LT&T and Obtain PTW 2h 09-Feb-15 08:00 PM 09-Feb-15 10:00 PM
497 IM112050 Drop spools & blind as per blindlist 5h 09-Feb-15 10:00 PM 10-Feb-15 03:00 AM
498 IM112055 Open stub end & return bend housing flanges 4h 10-Feb-15 05:00 AM 10-Feb-15 09:00 AM
499 IM112060 Carryout prelim. inspn. & Offer for AFI 2h 10-Feb-15 09:00 AM 10-Feb-15 11:00 AM
500 IM112065 Pull out the tube bundle 4h 10-Feb-15 11:00 AM 10-Feb-15 03:00 PM
501 IM112070 Perform AFI on tube bundle, shell & channel head 2h 10-Feb-15 03:00 PM 10-Feb-15 05:00 PM
502 IM112075 Shift tube bundle to jetting area 2h 10-Feb-15 05:00 PM 10-Feb-15 07:00 PM
503 IM112080 100% hydrojetting of tube external & internal 6h 11-Feb-15 06:00 AM 11-Feb-15 12:00 PM
504 IM112085 Hydrojetting of shell & channel covers 3h 11-Feb-15 12:00 PM 11-Feb-15 03:00 PM
505 IM112090 Perform detailed inspn. 2h 11-Feb-15 03:00 PM 11-Feb-15 05:00 PM
506 IM112095 RFECT inspn. on 50 tubes (Confirm via IRIS) 12h 11-Feb-15 06:00 PM 12-Feb-15 06:00 AM
507 IM112100 NDT of welds 3h 12-Feb-15 06:00 AM 12-Feb-15 09:00 AM
508 IM112105 Visual inspn. & thickness monitoring 3h 12-Feb-15 09:00 AM 12-Feb-15 12:00 PM
509 IM112110 Shift back tube bundle to site 2h 12-Feb-15 12:00 PM 12-Feb-15 02:00 PM
510 IM112115 Reinstall tube bundle 5h 12-Feb-15 07:00 PM 13-Feb-15 12:00 AM
511 IM112120 Hydrotest on shell & tube side 5h 13-Feb-15 12:00 AM 13-Feb-15 05:00 AM
512 IM112125 Repairs & retest as per inspn. Report 20h 13-Feb-15 05:00 AM 14-Feb-15 01:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 8 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
513 IM112130 Final Inspection 2h 14-Feb-15 01:00 AM 14-Feb-15 03:00 AM
514 IM112135 Boxup the exchanger 4h 14-Feb-15 07:00 AM 14-Feb-15 11:00 AM
515 IM112140 Reinstall spools & Deblinding 5h 14-Feb-15 11:00 AM 14-Feb-15 04:00 PM
516 INSP-EXCH-U-D/N10INSP-EXCH-U-D/N10 346h 09-Feb-15 06:00 AM 23-Feb-15 04:00 PM
517 R15E-071-001 RC2-31-071-41-E-1101 EXCHANGER - INT, EXT INSPECTIONR15E-071-001 RC2-31-071-41-E-1101 EXCHANGER - INT, EXT INSPECTION 346h 09-Feb-15 06:00 AM 23-Feb-15 04:00 PM
518 SHUTDOWNSHUTDOWN 346h 09-Feb-15 06:00 AM 23-Feb-15 04:00 PM
519 IM113170 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
520 IM113175 Verify LT&T and Obtain PTW 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM
521 IM113180 Drop spools & blind as per blindlist 12h 09-Feb-15 02:00 PM 10-Feb-15 02:00 AM
522 IM113185 Remove channel head 5h 10-Feb-15 02:00 AM 10-Feb-15 07:00 AM
523 IM113190 Carryout prelim. inspn. & Offer for AFI 2h 10-Feb-15 07:00 AM 10-Feb-15 09:00 AM
524 IM113195 Pull out the tube bundle 5h 10-Feb-15 09:00 AM 10-Feb-15 02:00 PM
525 IM113200 Perform AFI on tube bundle & shell 2h 10-Feb-15 02:00 PM 10-Feb-15 04:00 PM
526 IM113205 Shift tube bundle to jetting area 2h 10-Feb-15 04:00 PM 10-Feb-15 06:00 PM
527 IM113210 100% hydrojetting of tube external & internal 30h 10-Feb-15 06:00 PM 12-Feb-15 12:00 AM
528 IM113215 Hydrojetting of shell & channel head 4h 12-Feb-15 12:00 AM 12-Feb-15 04:00 AM
529 IM113220 Perform detailed inspn. 3h 12-Feb-15 04:00 AM 12-Feb-15 07:00 AM
530 IM113225 RFECT inspn. on 147U tubes (Confirm via IRIS) 38h 12-Feb-15 07:00 AM 13-Feb-15 09:00 PM
531 IM113230 NDT of welds, visual insp. & thickness monitoring 6h 13-Feb-15 09:00 PM 14-Feb-15 03:00 AM
532 IM113235 Shift back tube bundle to site 2h 14-Feb-15 03:00 AM 14-Feb-15 05:00 AM
533 IM113240 Reinstall tube bundle 5h 14-Feb-15 05:00 AM 14-Feb-15 10:00 AM
534 IM113245 Hydrotest shell with test ring, shell & tube side 18h 14-Feb-15 10:00 AM 15-Feb-15 04:00 AM
535 IM113250 Repairs & retest as per inspn. Report 20h 15-Feb-15 04:00 AM 16-Feb-15 12:00 AM
536 IM113255 Final Inspection 2h 16-Feb-15 12:00 AM 16-Feb-15 02:00 AM
537 IM113260 Reinstall channel head 5h 16-Feb-15 02:00 AM 16-Feb-15 07:00 AM
538 IM113265 Reinstall spools & Deblinding 12h 23-Feb-15 04:00 AM 23-Feb-15 04:00 PM
539 R15E-820-009 RC2-32-820-41-E-804 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-820-009 RC2-32-820-41-E-804 EXCHANGER - INT, EXT, CUI INSPECTION 168h 10-Feb-15 06:00 PM 17-Feb-15 06:00 PM
540 SHUTDOWNSHUTDOWN 168h 10-Feb-15 06:00 PM 17-Feb-15 06:00 PM
541 IM114660 Purging, Flushing & Gas test, LEL checking 6h 10-Feb-15 06:00 PM 11-Feb-15 12:00 AM
542 IM114665 Verify LT&T and Obtain PTW 2h 11-Feb-15 12:00 AM 11-Feb-15 02:00 AM
543 IM114670 Drop spools & blind as per blindlist 8h 11-Feb-15 02:00 AM 11-Feb-15 10:00 AM
544 IM114675 Remove channel head 4h 11-Feb-15 10:00 AM 11-Feb-15 02:00 PM
545 IM114680 Carryout prelim. inspn. & Offer for AFI 2h 11-Feb-15 02:00 PM 11-Feb-15 04:00 PM
546 IM114685 Pull out the tube bundle 4h 11-Feb-15 04:00 PM 11-Feb-15 08:00 PM
547 IM114690 Perform AFI on tube bundle & shell 2h 11-Feb-15 08:00 PM 11-Feb-15 10:00 PM
548 IM114695 Shift tube bundle to jetting area 2h 11-Feb-15 10:00 PM 12-Feb-15 12:00 AM
549 IM114700 100% hydrojetting of tube external & internal 30h 12-Feb-15 07:00 AM 13-Feb-15 01:00 PM
550 IM114705 Hydrojetting of shell & channel head 5h 13-Feb-15 01:00 PM 13-Feb-15 06:00 PM
551 IM114710 Perform detailed inspn. 2h 13-Feb-15 06:00 PM 13-Feb-15 08:00 PM
552 IM114715 RFECT inspn. on 151 tubes (Confirm via IRIS) 28h 14-Feb-15 03:00 AM 15-Feb-15 07:00 AM
553 IM114720 NDT of welds & CUI inspection 6h 15-Feb-15 07:00 AM 15-Feb-15 01:00 PM
554 IM114725 Shift back tube bundle to site 2h 15-Feb-15 01:00 PM 15-Feb-15 03:00 PM
555 IM114730 Reinstall tube bundle 4h 15-Feb-15 03:00 PM 15-Feb-15 07:00 PM
556 IM114735 Carryout Helium test 10h 15-Feb-15 07:00 PM 16-Feb-15 05:00 AM
557 IM114740 Repairs & retest as per inspn. Report 20h 16-Feb-15 05:00 AM 17-Feb-15 01:00 AM
558 IM114745 Final Inspection 2h 17-Feb-15 01:00 AM 17-Feb-15 03:00 AM
559 IM114750 Boxup the exchanger 5h 17-Feb-15 03:00 AM 17-Feb-15 08:00 AM
560 IM114755 Reinstall spools & Deblinding 10h 17-Feb-15 08:00 AM 17-Feb-15 06:00 PM
561 R15E-820-014 RC2-32-820-41-E-806 EXCHANGER - He LEAK TEST & INSPECTIONR15E-820-014 RC2-32-820-41-E-806 EXCHANGER - He LEAK TEST & INSPECTION 185h 12-Feb-15 06:00 AM 19-Feb-15 11:00 PM
562 SHUTDOWNSHUTDOWN 185h 12-Feb-15 06:00 AM 19-Feb-15 11:00 PM
563 IM114170 Purging, Flushing & Gas test, LEL checking 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM
564 IM114175 Verify LT&T and Obtain PTW 1h 12-Feb-15 12:00 PM 12-Feb-15 01:00 PM
565 IM114180 Drop spools & blind as per blindlist 5h 12-Feb-15 01:00 PM 12-Feb-15 06:00 PM
566 IM114185 Remove channel head 4h 12-Feb-15 06:00 PM 12-Feb-15 10:00 PM
567 IM114190 Carryout prelim. inspn. & Offer for AFI 2h 12-Feb-15 10:00 PM 13-Feb-15 12:00 AM
568 IM114195 Pull out the tube bundle 3h 13-Feb-15 12:00 AM 13-Feb-15 03:00 AM
569 IM114200 Perform AFI on tube bundle & shell 2h 13-Feb-15 03:00 AM 13-Feb-15 05:00 AM
570 IM114205 Shift tube bundle to jetting area 2h 13-Feb-15 05:00 AM 13-Feb-15 07:00 AM
571 IM114210 100% hydrojetting of tube external & internal 30h 13-Feb-15 08:00 PM 15-Feb-15 02:00 AM
572 IM114215 Hydrojetting of shell & channel head 3h 15-Feb-15 02:00 AM 15-Feb-15 05:00 AM
573 IM114220 Perform detailed inspn. 2h 15-Feb-15 05:00 AM 15-Feb-15 07:00 AM
574 IM114225 RFECT inspn. on 239 tubes (Confirm via IRIS) 45h 15-Feb-15 01:00 PM 17-Feb-15 10:00 AM
575 IM114230 NDT of welds 3h 17-Feb-15 10:00 AM 17-Feb-15 01:00 PM
576 IM114235 Shift back tube bundle to site 3h 17-Feb-15 01:00 PM 17-Feb-15 04:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 9 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
577 IM114240 Reinstall tube bundle 4h 17-Feb-15 04:00 PM 17-Feb-15 08:00 PM
578 IM114245 Carryout Helium test 20h 17-Feb-15 08:00 PM 18-Feb-15 04:00 PM
579 IM114250 Repairs & retest as per inspn. Report 20h 18-Feb-15 04:00 PM 19-Feb-15 12:00 PM
580 IM114255 Final Inspection 2h 19-Feb-15 12:00 PM 19-Feb-15 02:00 PM
581 IM114260 Reinstall channel head 4h 19-Feb-15 02:00 PM 19-Feb-15 06:00 PM
582 IM114265 Reinstall spools & Deblinding 5h 19-Feb-15 06:00 PM 19-Feb-15 11:00 PM
583 R15E-820-015 RC2-32-820-41-E-812A EXCHANGER - INT, EXT INSPECTIONR15E-820-015 RC2-32-820-41-E-812A EXCHANGER - INT, EXT INSPECTION 197h 13-Feb-15 06:00 PM 21-Feb-15 11:00 PM
584 SHUTDOWNSHUTDOWN 197h 13-Feb-15 06:00 PM 21-Feb-15 11:00 PM
585 IM113300 Purging, Flushing & Gas test, LEL checking 6h 13-Feb-15 06:00 PM 14-Feb-15 12:00 AM
586 IM113305 Verify LT&T and Obtain PTW 2h 14-Feb-15 12:00 AM 14-Feb-15 02:00 AM
587 IM113310 Drop spools & blind as per blindlist 5h 14-Feb-15 02:00 AM 14-Feb-15 07:00 AM
588 IM113315 Remove channel cover, head, shell cover 6h 14-Feb-15 07:00 AM 14-Feb-15 01:00 PM
589 IM113320 Open the floating head 3h 14-Feb-15 01:00 PM 14-Feb-15 04:00 PM
590 IM113325 Carryout prelim. inspn. & Offer for AFI 2h 14-Feb-15 04:00 PM 14-Feb-15 06:00 PM
591 IM113330 Pull out the tube bundle 5h 14-Feb-15 06:00 PM 14-Feb-15 11:00 PM
592 IM113335 Perform AFI on tube bundle & shell 2h 14-Feb-15 11:00 PM 15-Feb-15 01:00 AM
593 IM113340 Shift tube bundle to jetting area 2h 15-Feb-15 10:00 AM 15-Feb-15 12:00 PM
594 IM113345 100% hydrojetting of tube external & internal 10h 15-Feb-15 12:00 PM 15-Feb-15 10:00 PM
595 IM113350 Hydrojeting of shell, channel head, cover 4h 15-Feb-15 10:00 PM 16-Feb-15 02:00 AM
596 IM113355 Perform detailed inspn. 3h 16-Feb-15 02:00 AM 16-Feb-15 05:00 AM
597 IM113360 ECT inspn. on 50 tubes (Confirm via IRIS) 12h 17-Feb-15 01:00 PM 18-Feb-15 01:00 AM
598 IM113365 Visual insp. & NDT of welds 4h 18-Feb-15 01:00 AM 18-Feb-15 05:00 AM
599 IM113370 Shift back tube bundle to site 2h 18-Feb-15 05:00 AM 18-Feb-15 07:00 AM
600 IM113375 Reinstall tube bundle 5h 19-Feb-15 02:00 PM 19-Feb-15 07:00 PM
601 IM113380 Hydrotest on shell & tube side 8h 19-Feb-15 07:00 PM 20-Feb-15 03:00 AM
602 IM113385 Repairs & retest as per inspn. Report 20h 20-Feb-15 03:00 AM 20-Feb-15 11:00 PM
603 IM113390 Final Inspection 2h 20-Feb-15 11:00 PM 21-Feb-15 01:00 AM
604 IM113395 Reinstall floating & channel heads 8h 21-Feb-15 01:00 AM 21-Feb-15 09:00 AM
605 IM113400 Reinstall spools & Deblinding 6h 21-Feb-15 05:00 PM 21-Feb-15 11:00 PM
606 R15E-820-016 RC2-32-820-41-E-812B EXCHANGER - INT, EXT INSPECTIONR15E-820-016 RC2-32-820-41-E-812B EXCHANGER - INT, EXT INSPECTION 197h 13-Feb-15 06:00 PM 21-Feb-15 11:00 PM
607 SHUTDOWNSHUTDOWN 197h 13-Feb-15 06:00 PM 21-Feb-15 11:00 PM
608 IM113430 Purging, Flushing & Gas test, LEL checking 6h 13-Feb-15 06:00 PM 14-Feb-15 12:00 AM
609 IM113435 Verify LT&T and Obtain PTW 2h 14-Feb-15 12:00 AM 14-Feb-15 02:00 AM
610 IM113440 Drop spools & blind as per blindlist (R15E-820-015) 5h 14-Feb-15 07:00 AM 14-Feb-15 12:00 PM
611 IM113445 Remove channel cover, head, shell cover 6h 14-Feb-15 04:00 PM 14-Feb-15 10:00 PM
612 IM113450 Open the floating head 3h 14-Feb-15 10:00 PM 15-Feb-15 01:00 AM
613 IM113455 Carryout prelim. inspn. & Offer for AFI 2h 15-Feb-15 01:00 AM 15-Feb-15 03:00 AM
614 IM113460 Pull out the tube bundle 5h 15-Feb-15 03:00 AM 15-Feb-15 08:00 AM
615 IM113465 Perform AFI on tube bundle & shell 2h 15-Feb-15 08:00 AM 15-Feb-15 10:00 AM
616 IM113470 Shift tube bundle to jetting area 2h 15-Feb-15 10:00 AM 15-Feb-15 12:00 PM
617 IM113475 100% hydrojetting of tube external & internal 10h 16-Feb-15 05:00 AM 16-Feb-15 03:00 PM
618 IM113480 Hydrojeting of shell, channel head, cover 4h 16-Feb-15 03:00 PM 16-Feb-15 07:00 PM
619 IM113485 Perform detailed inspn. 3h 16-Feb-15 07:00 PM 16-Feb-15 10:00 PM
620 IM113490 ECT inspn. on 50 tubes (Confirm via IRIS) 12h 18-Feb-15 07:00 AM 18-Feb-15 07:00 PM
621 IM113495 Visual insp. & NDT of welds 4h 18-Feb-15 07:00 PM 18-Feb-15 11:00 PM
622 IM113500 Shift back tube bundle to site 2h 18-Feb-15 11:00 PM 19-Feb-15 01:00 AM
623 IM113505 Reinstall tube bundle 5h 19-Feb-15 02:00 PM 19-Feb-15 07:00 PM
624 IM113510 Hydrotest on shell & tube side 8h 19-Feb-15 07:00 PM 20-Feb-15 03:00 AM
625 IM113515 Repairs & retest as per inspn. Report 20h 20-Feb-15 03:00 AM 20-Feb-15 11:00 PM
626 IM113520 Final Inspection 2h 20-Feb-15 11:00 PM 21-Feb-15 01:00 AM
627 IM113525 Reinstall floating & channel heads 8h 21-Feb-15 09:00 AM 21-Feb-15 05:00 PM
628 IM113530 Reinstall spools & Deblinding 6h 21-Feb-15 05:00 PM 21-Feb-15 11:00 PM
629 INSP-EXCH-U-D/N11INSP-EXCH-U-D/N11 191h 12-Feb-15 06:00 AM 20-Feb-15 05:00 AM
630 R15U-020-003 RC2-31-020-41-E-1205 EXCHANGER - INT, EXT INSPECTIONR15U-020-003 RC2-31-020-41-E-1205 EXCHANGER - INT, EXT INSPECTION 107h 15-Feb-15 06:00 PM 20-Feb-15 05:00 AM
631 SHUTDOWNSHUTDOWN 107h 15-Feb-15 06:00 PM 20-Feb-15 05:00 AM
632 OM105565 Purging to be carried out 6h 15-Feb-15 06:00 PM 16-Feb-15 12:00 AM
633 OM105570 Verify LT&T and Obtain PTW 2h 16-Feb-15 12:00 AM 16-Feb-15 02:00 AM
634 OM105575 Drop spools & carryout blinding. 4h 16-Feb-15 02:00 AM 16-Feb-15 06:00 AM
635 OM105580 Open stub end & return bend housing flanges 3h 16-Feb-15 06:00 AM 16-Feb-15 09:00 AM
636 OM105585 Carryout prelim. inspn & Offer for AFI 2h 16-Feb-15 09:00 AM 16-Feb-15 11:00 AM
637 OM105590 Pull out tube bundle & perform AFI 6h 16-Feb-15 11:00 AM 16-Feb-15 05:00 PM
638 OM105595 Shift tube bundle to jetting area 2h 16-Feb-15 05:00 PM 16-Feb-15 07:00 PM
639 OM105600 100% Hydrojetting of tube external & internal 8h 16-Feb-15 07:00 PM 17-Feb-15 03:00 AM
640 OM105605 Hydrojetting of shell, channel cover & flange 3h 17-Feb-15 03:00 AM 17-Feb-15 06:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 10 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
641 OM105610 Inspn. of tube bundle, channel head & shell 3h 17-Feb-15 06:00 AM 17-Feb-15 09:00 AM
642 OM105615 Carryout RFECT inspection on 50 tubes. 10h 17-Feb-15 09:00 AM 17-Feb-15 07:00 PM
643 OM105620 NDT as per ERG recommendation 3h 17-Feb-15 07:00 PM 17-Feb-15 10:00 PM
644 OM105625 Visual inspection & Thickness monitoring 3h 17-Feb-15 10:00 PM 18-Feb-15 01:00 AM
645 OM105630 Shift back tube bundle to the locaton 2h 18-Feb-15 01:00 AM 18-Feb-15 03:00 AM
646 OM105635 Reinstallation of tube bundle 5h 18-Feb-15 10:00 AM 18-Feb-15 03:00 PM
647 OM105640 Hydrotest both shell side & tube side 5h 18-Feb-15 03:00 PM 18-Feb-15 08:00 PM
648 OM105645 Inspection report and repairs, if any 20h 18-Feb-15 08:00 PM 19-Feb-15 04:00 PM
649 OM105650 Final inspection 2h 19-Feb-15 04:00 PM 19-Feb-15 06:00 PM
650 OM105655 Boxup the exchanger tighten the bolts. 5h 19-Feb-15 06:00 PM 19-Feb-15 11:00 PM
651 OM105660 De-Blinding & Reinstall spools 6h 19-Feb-15 11:00 PM 20-Feb-15 05:00 AM
652 R15U-020-005 RC2-31-020-41-E-1211 EXCHANGER - INT, EXT, CUI INSPECTIONR15U-020-005 RC2-31-020-41-E-1211 EXCHANGER - INT, EXT, CUI INSPECTION 138h 12-Feb-15 06:00 AM 18-Feb-15 12:00 AM
653 SHUTDOWNSHUTDOWN 138h 12-Feb-15 06:00 AM 18-Feb-15 12:00 AM
654 OM105840 Purging to be carried out 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM
655 OM105845 Verify LT&T and Obtain PTW 2h 12-Feb-15 12:00 PM 12-Feb-15 02:00 PM
656 OM105850 Drop spools & carryout blinding. 10h 12-Feb-15 02:00 PM 13-Feb-15 12:00 AM
657 OM105855 Detorque, & remove the channel cover 5h 13-Feb-15 12:00 AM 13-Feb-15 05:00 AM
658 OM105860 Carryout prelim. inspn & Offer for AFI 2h 13-Feb-15 05:00 AM 13-Feb-15 07:00 AM
659 OM105865 Pull out tube bundle & perform AFI 7h 13-Feb-15 07:00 AM 13-Feb-15 02:00 PM
660 OM105870 Shift tube bundle to jetting area 2h 13-Feb-15 02:00 PM 13-Feb-15 04:00 PM
661 OM105875 100% Hydrojetting of tube external & internal 18h 13-Feb-15 04:00 PM 14-Feb-15 10:00 AM
662 OM105880 Hydrojetting of shell, channel cover & flange 4h 14-Feb-15 10:00 AM 14-Feb-15 02:00 PM
663 OM105885 Inspn. of tube bundle, channel head & shell 2h 14-Feb-15 02:00 PM 14-Feb-15 04:00 PM
664 OM105890 Carryout RFECT inspection on 125 tubes. 16h 14-Feb-15 04:00 PM 15-Feb-15 08:00 AM
665 OM105895 NDT of welds & suspected areas 3h 15-Feb-15 08:00 AM 15-Feb-15 11:00 AM
666 OM105900 Thickness monitoring & CUI 6h 15-Feb-15 11:00 AM 15-Feb-15 05:00 PM
667 OM105905 Shift back tube bundle to the locaton 2h 15-Feb-15 05:00 PM 15-Feb-15 07:00 PM
668 OM105910 Reinstallation of tube bundle 5h 15-Feb-15 07:00 PM 16-Feb-15 12:00 AM
669 OM105915 Hydrotest shell with test flange, shell & tube side 8h 16-Feb-15 12:00 AM 16-Feb-15 08:00 AM
670 OM105920 Inspection report and repairs, if any 20h 16-Feb-15 08:00 AM 17-Feb-15 04:00 AM
671 OM105925 Final inspection 2h 17-Feb-15 04:00 AM 17-Feb-15 06:00 AM
672 OM105930 Box up and tighten the bolts. 6h 17-Feb-15 06:00 AM 17-Feb-15 12:00 PM
673 OM105935 De-Blinding & Reinstall spools 12h 17-Feb-15 12:00 PM 18-Feb-15 12:00 AM
674 R15U-024-013 RC2-31-024-41-E-1201 EXCHANGER - INT, EXT INSPECTIONR15U-024-013 RC2-31-024-41-E-1201 EXCHANGER - INT, EXT INSPECTION 113h 14-Feb-15 06:00 AM 18-Feb-15 11:00 PM
675 SHUTDOWNSHUTDOWN 113h 14-Feb-15 06:00 AM 18-Feb-15 11:00 PM
676 OM105700 Purging to be carried out 6h 14-Feb-15 06:00 AM 14-Feb-15 12:00 PM
677 OM105705 Verify LT&T and Obtain PTW 2h 14-Feb-15 12:00 PM 14-Feb-15 02:00 PM
678 OM105710 Drop spools & carryout blinding. 4h 14-Feb-15 02:00 PM 14-Feb-15 06:00 PM
679 OM105715 Open stub end & return bend housing flanges 3h 14-Feb-15 06:00 PM 14-Feb-15 09:00 PM
680 OM105720 Carryout prelim. inspn & Offer for AFI 2h 14-Feb-15 09:00 PM 14-Feb-15 11:00 PM
681 OM105725 Pull out tube bundle & perform AFI 6h 14-Feb-15 11:00 PM 15-Feb-15 05:00 AM
682 OM105730 Shift tube bundle to jetting area 2h 15-Feb-15 05:00 AM 15-Feb-15 07:00 AM
683 OM105735 100% Hydrojetting of tube external & internal 8h 15-Feb-15 07:00 AM 15-Feb-15 03:00 PM
684 OM105740 Hydrojetting of shell, channel cover & flange 3h 15-Feb-15 03:00 PM 15-Feb-15 06:00 PM
685 OM105745 Inspn. of tube bundle, channel head & shell 3h 15-Feb-15 06:00 PM 15-Feb-15 09:00 PM
686 OM105750 Carryout RFECT inspection on 48 tubes. 10h 15-Feb-15 09:00 PM 16-Feb-15 07:00 AM
687 OM105755 NDT as per ERG recommendation 3h 16-Feb-15 07:00 AM 16-Feb-15 10:00 AM
688 OM105760 Visual inspection & Thickness monitoring 3h 16-Feb-15 10:00 AM 16-Feb-15 01:00 PM
689 OM105765 Shift back tube bundle to the locaton 2h 16-Feb-15 01:00 PM 16-Feb-15 03:00 PM
690 OM105770 Reinstallation of tube bundle 5h 17-Feb-15 04:00 AM 17-Feb-15 09:00 AM
691 OM105775 Hydrotest both shell side & tube side 5h 17-Feb-15 09:00 AM 17-Feb-15 02:00 PM
692 OM105780 Inspection report and repairs, if any 20h 17-Feb-15 02:00 PM 18-Feb-15 10:00 AM
693 OM105785 Final inspection 2h 18-Feb-15 10:00 AM 18-Feb-15 12:00 PM
694 OM105790 Boxup the exchanger tighten the bolts. 5h 18-Feb-15 12:00 PM 18-Feb-15 05:00 PM
695 OM105795 De-Blinding & Reinstall spools 6h 18-Feb-15 05:00 PM 18-Feb-15 11:00 PM
696 INSP-EXCH-U-D/N12INSP-EXCH-U-D/N12 282h 07-Feb-15 06:00 AM 19-Feb-15 12:00 AM
697 R15E-710-012 RC2-32-710-41-E-703 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-710-012 RC2-32-710-41-E-703 EXCHANGER - INT, EXT, CUI INSPECTION 107h 09-Feb-15 06:00 AM 13-Feb-15 05:00 PM
698 SHUTDOWNSHUTDOWN 107h 09-Feb-15 06:00 AM 13-Feb-15 05:00 PM
699 IM111625 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
700 IM111630 Verify LT&T and Obtain PTW 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM
701 IM111635 Drop spools & blind as per blindlist 9h 09-Feb-15 02:00 PM 09-Feb-15 11:00 PM
702 IM111640 Open stub end & return bend housing flanges 4h 09-Feb-15 11:00 PM 10-Feb-15 03:00 AM
703 IM111645 Carryout prelim. inspn. & Offer for AFI 2h 10-Feb-15 03:00 AM 10-Feb-15 05:00 AM
704 IM111650 Pull out the tube bundle 4h 10-Feb-15 05:00 AM 10-Feb-15 09:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 11 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
705 IM111655 Perform AFI on tube bundle, shell & channel head 2h 10-Feb-15 09:00 AM 10-Feb-15 11:00 AM
706 IM111660 Shift tube bundle to jetting area 2h 10-Feb-15 11:00 AM 10-Feb-15 01:00 PM
707 IM111665 100% hydrojetting of tube external & internal 6h 10-Feb-15 01:00 PM 10-Feb-15 07:00 PM
708 IM111670 Hydrojetting of shell & channel covers 3h 10-Feb-15 07:00 PM 10-Feb-15 10:00 PM
709 IM111675 Perform detailed inspn. 3h 10-Feb-15 10:00 PM 11-Feb-15 01:00 AM
710 IM111680 RFECT inspn. on 44 tubes (Confirm via IRIS) 10h 11-Feb-15 01:00 AM 11-Feb-15 11:00 AM
711 IM111685 NDT of welds & CUI inspection 5h 11-Feb-15 11:00 AM 11-Feb-15 04:00 PM
712 IM111690 Visual inspn. & thickness monitoring 3h 11-Feb-15 04:00 PM 11-Feb-15 07:00 PM
713 IM111695 Shift back tube bundle to site 2h 11-Feb-15 07:00 PM 11-Feb-15 09:00 PM
714 IM111700 Reinstall tube bundle 5h 11-Feb-15 09:00 PM 12-Feb-15 02:00 AM
715 IM111705 Hydrotest on shell & tube side 5h 12-Feb-15 02:00 AM 12-Feb-15 07:00 AM
716 IM111710 Repairs & retest as per inspn. report 20h 12-Feb-15 07:00 AM 13-Feb-15 03:00 AM
717 IM111715 Final Inspection 2h 13-Feb-15 03:00 AM 13-Feb-15 05:00 AM
718 IM111720 Boxup the exchanger 4h 13-Feb-15 05:00 AM 13-Feb-15 09:00 AM
719 IM111725 Reinstall spools & Deblinding 8h 13-Feb-15 09:00 AM 13-Feb-15 05:00 PM
720 R15E-710-020 RC2-32-710-41-E-706 EXCHANGER - INT, EXT INSPECTIONR15E-710-020 RC2-32-710-41-E-706 EXCHANGER - INT, EXT INSPECTION 125h 07-Feb-15 06:00 AM 12-Feb-15 11:00 AM
721 SHUTDOWNSHUTDOWN 125h 07-Feb-15 06:00 AM 12-Feb-15 11:00 AM
722 IM111765 Purging, Flushing & Gas test, LEL checking 6h 07-Feb-15 06:00 AM 07-Feb-15 12:00 PM
723 IM111770 Verify LT&T and Obtain PTW 2h 07-Feb-15 12:00 PM 07-Feb-15 02:00 PM
724 IM111775 Drop spools & blind as per blindlist 10h 07-Feb-15 02:00 PM 08-Feb-15 12:00 AM
725 IM111780 Remove channel covers 5h 08-Feb-15 12:00 AM 08-Feb-15 05:00 AM
726 IM111785 Carryout prelim. inspn. & Offer for AFI 2h 08-Feb-15 05:00 AM 08-Feb-15 07:00 AM
727 IM111790 Pull out the tube bundle 5h 08-Feb-15 07:00 AM 08-Feb-15 12:00 PM
728 IM111795 Perform AFI on tube bundle & shell 2h 08-Feb-15 12:00 PM 08-Feb-15 02:00 PM
729 IM111800 Shift tube bundle to jetting area 2h 08-Feb-15 02:00 PM 08-Feb-15 04:00 PM
730 IM111805 100% hydrojetting of tube external & internal 10h 08-Feb-15 04:00 PM 09-Feb-15 02:00 AM
731 IM111810 Hydrojetting of shell & channel covers 4h 09-Feb-15 02:00 AM 09-Feb-15 06:00 AM
732 IM111815 Perform detailed inspn. 2h 09-Feb-15 06:00 AM 09-Feb-15 08:00 AM
733 IM111820 RFECT inspn. on 50 tubes (Confirm via IRIS) 12h 09-Feb-15 08:00 AM 09-Feb-15 08:00 PM
734 IM111825 NDT of welds 3h 09-Feb-15 08:00 PM 09-Feb-15 11:00 PM
735 IM111830 Shift back tube bundle to site 2h 09-Feb-15 11:00 PM 10-Feb-15 01:00 AM
736 IM111835 Reinstall tube bundle 5h 10-Feb-15 01:00 AM 10-Feb-15 06:00 AM
737 IM111840 Hydrotest shell with test ring, shell & tube hydrotest. 15h 10-Feb-15 06:00 AM 10-Feb-15 09:00 PM
738 IM111845 Repairs & retest as per inspn. Report 20h 10-Feb-15 09:00 PM 11-Feb-15 05:00 PM
739 IM111850 Final Inspection 2h 11-Feb-15 05:00 PM 11-Feb-15 07:00 PM
740 IM111855 Boxup the exchanger 6h 11-Feb-15 07:00 PM 12-Feb-15 01:00 AM
741 IM111860 Reinstall spools & Deblinding 10h 12-Feb-15 01:00 AM 12-Feb-15 11:00 AM
742 R15E-710-021 RC2-32-710-41-E-707A EXCHANGER - INT, EXT, CUI INSPECTIONR15E-710-021 RC2-32-710-41-E-707A EXCHANGER - INT, EXT, CUI INSPECTION 168h 11-Feb-15 06:00 AM 18-Feb-15 06:00 AM
743 SHUTDOWNSHUTDOWN 168h 11-Feb-15 06:00 AM 18-Feb-15 06:00 AM
744 IM112465 Purging, Flushing & Gas test, LEL checking 6h 11-Feb-15 06:00 AM 11-Feb-15 12:00 PM
745 IM112470 Verify LT&T and Obtain PTW 2h 11-Feb-15 12:00 PM 11-Feb-15 02:00 PM
746 IM112475 Drop spools & blind as per blindlist 5h 11-Feb-15 02:00 PM 11-Feb-15 07:00 PM
747 IM112480 Open stub end & return bend housing flanges 4h 11-Feb-15 07:00 PM 11-Feb-15 11:00 PM
748 IM112485 Carryout prelim. inspn. & Offer for AFI 2h 11-Feb-15 11:00 PM 12-Feb-15 01:00 AM
749 IM112490 Pull out the tube bundle 5h 12-Feb-15 01:00 AM 12-Feb-15 06:00 AM
750 IM112495 Perform AFI on tube bundle, shell & channel head 2h 12-Feb-15 06:00 AM 12-Feb-15 08:00 AM
751 IM112500 Shift tube bundle to jetting area 2h 12-Feb-15 02:00 PM 12-Feb-15 04:00 PM
752 IM112505 100% hydrojetting of tube external & internal 6h 12-Feb-15 04:00 PM 12-Feb-15 10:00 PM
753 IM112510 Hydrojetting of shell & channel covers 3h 12-Feb-15 10:00 PM 13-Feb-15 01:00 AM
754 IM112515 Perform detailed inspn. 2h 13-Feb-15 01:00 AM 13-Feb-15 03:00 AM
755 IM112520 RFECT inspn. on 14 tubes (Confirm via IRIS) 12h 13-Feb-15 03:00 AM 13-Feb-15 03:00 PM
756 IM112525 NDT of welds & CUI inspection 5h 13-Feb-15 03:00 PM 13-Feb-15 08:00 PM
757 IM112530 Visual inspn. & thickness monitoring 3h 13-Feb-15 08:00 PM 13-Feb-15 11:00 PM
758 IM112535 Shift back tube bundle to site 2h 14-Feb-15 07:00 PM 14-Feb-15 09:00 PM
759 IM112540 Reinstall tube bundle 5h 14-Feb-15 09:00 PM 15-Feb-15 02:00 AM
760 IM112545 Hydrotest on shell & tube side 5h 15-Feb-15 07:00 AM 15-Feb-15 12:00 PM
761 IM112550 Repairs & retest as per inspn. Report 20h 15-Feb-15 12:00 PM 16-Feb-15 08:00 AM
762 IM112555 Final Inspection 2h 16-Feb-15 08:00 AM 16-Feb-15 10:00 AM
763 IM112560 Boxup the exchanger 4h 16-Feb-15 10:00 AM 16-Feb-15 02:00 PM
764 IM112565 Reinstall spools & Deblinding 5h 18-Feb-15 01:00 AM 18-Feb-15 06:00 AM
765 R15E-710-023 RC2-32-710-41-E-707B EXCHANGER - INT, EXT, CUI INSPECTIONR15E-710-023 RC2-32-710-41-E-707B EXCHANGER - INT, EXT, CUI INSPECTION 162h 11-Feb-15 12:00 PM 18-Feb-15 06:00 AM
766 SHUTDOWNSHUTDOWN 162h 11-Feb-15 12:00 PM 18-Feb-15 06:00 AM
767 IM112610 Purging, Flushing & Gas test, LEL checking 6h 11-Feb-15 12:00 PM 11-Feb-15 06:00 PM
768 IM112615 Verify LT&T and Obtain PTW 2h 11-Feb-15 06:00 PM 11-Feb-15 08:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 12 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
769 IM112620 Drop spools & blind as per blindlist 5h 11-Feb-15 08:00 PM 12-Feb-15 01:00 AM
770 IM112625 Open stub end & return bend housing flanges 4h 12-Feb-15 01:00 AM 12-Feb-15 05:00 AM
771 IM112630 Carryout prelim. inspn. & Offer for AFI 2h 12-Feb-15 05:00 AM 12-Feb-15 07:00 AM
772 IM112635 Pull out the tube bundle 5h 12-Feb-15 07:00 AM 12-Feb-15 12:00 PM
773 IM112640 Perform AFI on tube bundle, shell & channel head 2h 12-Feb-15 12:00 PM 12-Feb-15 02:00 PM
774 IM112645 Shift tube bundle to jetting area 2h 12-Feb-15 02:00 PM 12-Feb-15 04:00 PM
775 IM112650 100% hydrojetting of tube external & internal 6h 13-Feb-15 03:00 AM 13-Feb-15 09:00 AM
776 IM112655 Hydrojetting of shell & channel covers 3h 13-Feb-15 09:00 AM 13-Feb-15 12:00 PM
777 IM112660 Perform detailed inspn. 2h 13-Feb-15 12:00 PM 13-Feb-15 02:00 PM
778 IM112665 RFECT inspn. on 14 tubes (Confirm via IRIS) 12h 13-Feb-15 11:00 PM 14-Feb-15 11:00 AM
779 IM112670 NDT of welds & CUI inspection 5h 14-Feb-15 11:00 AM 14-Feb-15 04:00 PM
780 IM112675 Visual inspn. & thickness monitoring 3h 14-Feb-15 04:00 PM 14-Feb-15 07:00 PM
781 IM112680 Shift back tube bundle to site 2h 14-Feb-15 07:00 PM 14-Feb-15 09:00 PM
782 IM112685 Reinstall tube bundle 5h 15-Feb-15 02:00 AM 15-Feb-15 07:00 AM
783 IM112690 Hydrotest on shell & tube side 5h 15-Feb-15 07:00 AM 15-Feb-15 12:00 PM
784 IM112695 Repairs & retest as per inspn. Report 20h 15-Feb-15 12:00 PM 16-Feb-15 08:00 AM
785 IM112700 Final Inspection 2h 16-Feb-15 08:00 AM 16-Feb-15 10:00 AM
786 IM112705 Boxup the exchanger 4h 16-Feb-15 02:00 PM 16-Feb-15 06:00 PM
787 IM112710 Reinstall spools & Deblinding 5h 18-Feb-15 01:00 AM 18-Feb-15 06:00 AM
788 R15E-710-026 RC2-32-710-41-E-709 EXCHANGER - INT, EXT, CUI INSPECTIONR15E-710-026 RC2-32-710-41-E-709 EXCHANGER - INT, EXT, CUI INSPECTION 126h 13-Feb-15 06:00 PM 19-Feb-15 12:00 AM
789 SHUTDOWNSHUTDOWN 126h 13-Feb-15 06:00 PM 19-Feb-15 12:00 AM
790 IM113030 Purging, Flushing & Gas test, LEL checking 6h 13-Feb-15 06:00 PM 14-Feb-15 12:00 AM
791 IM113035 Verify LT&T and Obtain PTW 2h 14-Feb-15 12:00 AM 14-Feb-15 02:00 AM
792 IM113040 Drop spools & blind as per blindlist 4h 14-Feb-15 02:00 AM 14-Feb-15 06:00 AM
793 IM113045 Open stub end & return bend housing flanges 3h 14-Feb-15 06:00 AM 14-Feb-15 09:00 AM
794 IM113050 Carryout prelim. inspn. & Offer for AFI 2h 14-Feb-15 09:00 AM 14-Feb-15 11:00 AM
795 IM113055 Pull out the tube bundle 5h 14-Feb-15 11:00 AM 14-Feb-15 04:00 PM
796 IM113060 Perform AFI on tube bundle, shell & channel head 2h 14-Feb-15 04:00 PM 14-Feb-15 06:00 PM
797 IM113065 Shift tube bundle to jetting area 2h 14-Feb-15 06:00 PM 14-Feb-15 08:00 PM
798 IM113070 100% hydrojetting of tube external & internal 8h 14-Feb-15 08:00 PM 15-Feb-15 04:00 AM
799 IM113075 Hydrojetting of shell & channel covers 3h 15-Feb-15 04:00 AM 15-Feb-15 07:00 AM
800 IM113080 Perform detailed inspn. 3h 15-Feb-15 07:00 AM 15-Feb-15 10:00 AM
801 IM113085 RFECT inspn. on 44 tubes (Confirm via IRIS) 12h 15-Feb-15 01:00 PM 16-Feb-15 01:00 AM
802 IM113090 NDT of welds & CUI inspection 5h 16-Feb-15 01:00 AM 16-Feb-15 06:00 AM
803 IM113095 Visual inspn. & thickness monitoring 3h 16-Feb-15 06:00 AM 16-Feb-15 09:00 AM
804 IM113100 Shift back tube bundle to site 2h 16-Feb-15 03:00 PM 16-Feb-15 05:00 PM
805 IM113105 Reinstall tube bundle 5h 16-Feb-15 08:00 PM 17-Feb-15 01:00 AM
806 IM113110 Hydrotest on shell & tube side 5h 17-Feb-15 01:00 AM 17-Feb-15 06:00 AM
807 IM113115 Repairs & retest as per inspn. Report 20h 17-Feb-15 06:00 PM 18-Feb-15 02:00 PM
808 IM113120 Final Inspection 2h 18-Feb-15 02:00 PM 18-Feb-15 04:00 PM
809 IM113125 Boxup the exchanger 4h 18-Feb-15 04:00 PM 18-Feb-15 08:00 PM
810 IM113130 Reinstall spools & Deblinding 4h 18-Feb-15 08:00 PM 19-Feb-15 12:00 AM
811 R15E-710-028 RC2-32-710-41-E-711 EXCHANGER - INT, EXT INSPECTIONR15E-710-028 RC2-32-710-41-E-711 EXCHANGER - INT, EXT INSPECTION 156h 11-Feb-15 06:00 PM 18-Feb-15 06:00 AM
812 SHUTDOWNSHUTDOWN 156h 11-Feb-15 06:00 PM 18-Feb-15 06:00 AM
813 IM112885 Purging, Flushing & Gas test, LEL checking 6h 11-Feb-15 06:00 PM 12-Feb-15 12:00 AM
814 IM112890 Verify LT&T and Obtain PTW 2h 12-Feb-15 12:00 AM 12-Feb-15 02:00 AM
815 IM112895 Drop spools & blind as per blindlist (R15E-710-023) 4h 12-Feb-15 07:00 AM 12-Feb-15 11:00 AM
816 IM112900 Open stub end & return bend housing flanges 4h 12-Feb-15 11:00 AM 12-Feb-15 03:00 PM
817 IM112905 Carryout prelim. inspn. & Offer for AFI 2h 12-Feb-15 03:00 PM 12-Feb-15 05:00 PM
818 IM112910 Pull out the tube bundle 4h 12-Feb-15 05:00 PM 12-Feb-15 09:00 PM
819 IM112915 Perform AFI on tube bundle, shell & channel head 2h 12-Feb-15 09:00 PM 12-Feb-15 11:00 PM
820 IM112920 Shift tube bundle to jetting area 2h 12-Feb-15 11:00 PM 13-Feb-15 01:00 AM
821 IM112925 100% hydrojetting of tube external & internal 6h 13-Feb-15 02:00 PM 13-Feb-15 08:00 PM
822 IM112930 Hydrojetting of shell & channel covers 3h 13-Feb-15 08:00 PM 13-Feb-15 11:00 PM
823 IM112935 Perform detailed inspn. 3h 13-Feb-15 11:00 PM 14-Feb-15 02:00 AM
824 IM112940 RFECT inspn. on 14 tubes (Confirm via IRIS) 12h 14-Feb-15 07:00 PM 15-Feb-15 07:00 AM
825 IM112945 NDT of welds 3h 15-Feb-15 07:00 AM 15-Feb-15 10:00 AM
826 IM112950 Visual inspn. & thickness monitoring 3h 15-Feb-15 10:00 AM 15-Feb-15 01:00 PM
827 IM112955 Shift back tube bundle to site 2h 15-Feb-15 01:00 PM 15-Feb-15 03:00 PM
828 IM112960 Reinstall tube bundle 5h 16-Feb-15 10:00 AM 16-Feb-15 03:00 PM
829 IM112965 Hydrotest on shell & tube side 5h 16-Feb-15 03:00 PM 16-Feb-15 08:00 PM
830 IM112970 Repairs & retest as per inspn. Report 20h 16-Feb-15 08:00 PM 17-Feb-15 04:00 PM
831 IM112975 Final Inspection 2h 17-Feb-15 04:00 PM 17-Feb-15 06:00 PM
832 IM112980 Boxup the exchanger 4h 17-Feb-15 06:00 PM 17-Feb-15 10:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 13 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
833 IM112985 Reinstall spools & Deblinding 8h 17-Feb-15 10:00 PM 18-Feb-15 06:00 AM
834 INSP-EXCH-CORE-D/N13INSP-EXCH-CORE-D/N13 356h 08-Feb-15 06:00 AM 23-Feb-15 02:00 AM
835 R15E-410-010 RC2-32-410-24-E-404 EXCHANGER - PERLITE LEVEL INSPN. & STRAINER CLEANINGR15E-410-010 RC2-32-410-24-E-404 EXCHANGER - PERLITE LEVEL INSPN. & STRAINER CLEANING 278h 08-Feb-15 06:00 AM 19-Feb-15 08:00 PM
836 SHUTDOWNSHUTDOWN 278h 08-Feb-15 06:00 AM 19-Feb-15 08:00 PM
837 IM115035 Purging, Flushing & Gas test, LEL checking 6h 08-Feb-15 06:00 AM 08-Feb-15 12:00 PM
838 IM115040 Verify LT&T and Obtain PTW 2h 08-Feb-15 12:00 PM 08-Feb-15 02:00 PM
839 IM115045 Remove strainers E,F,H (LT&T R15E-410-010) 15h 08-Feb-15 04:00 PM 09-Feb-15 07:00 AM
840 IM115050 Inspection of strainers 4h 09-Feb-15 07:00 AM 09-Feb-15 11:00 AM
841 IM115055 Cleaning & repair as reqd. 6h 09-Feb-15 11:00 AM 09-Feb-15 05:00 PM
842 IM115060 Remove A strainer (LT&T R15E-810-014) 6h 10-Feb-15 06:00 AM 10-Feb-15 12:00 PM
843 IM115065 Inspection of strainers 1h 10-Feb-15 12:00 PM 10-Feb-15 01:00 PM
844 IM115070 Cleaning & repair as reqd. 3h 10-Feb-15 01:00 PM 10-Feb-15 04:00 PM
845 IM115075 Reinstall A strainer (LT&T R15E-810-014) 6h 10-Feb-15 04:00 PM 10-Feb-15 10:00 PM
846 IM115080 Remove J strainer (LT&T R15E-510-064) 6h 11-Feb-15 12:00 PM 11-Feb-15 06:00 PM
847 IM115085 Inspection of strainers 1h 11-Feb-15 06:00 PM 11-Feb-15 07:00 PM
848 IM115090 Cleaning & repair as reqd. 3h 11-Feb-15 07:00 PM 11-Feb-15 10:00 PM
849 IM115095 Reinstall J strainer (LT& R15E-510-064) 5h 11-Feb-15 10:00 PM 12-Feb-15 03:00 AM
850 IM115100 Remove B,D,L,M,N,O,P,S,T (LT&T R15E-420-001) 35h 12-Feb-15 03:00 AM 13-Feb-15 02:00 PM
851 IM115105 Inspection of strainers 3h 13-Feb-15 02:00 PM 13-Feb-15 05:00 PM
852 IM115110 Cleaning & repair as reqd. 30h 13-Feb-15 05:00 PM 14-Feb-15 11:00 PM
853 IM115115 Reinstall strainers B,D,L,M,N,O,P,S,T (LT&T R15E-420-001) 35h 14-Feb-15 11:00 PM 16-Feb-15 10:00 AM
854 IM115120 Remove strainer C (LT&T R15E-820-009) 6h 16-Feb-15 10:00 AM 16-Feb-15 04:00 PM
855 IM115125 Inspection of strainers 1h 16-Feb-15 04:00 PM 16-Feb-15 05:00 PM
856 IM115130 Cleaning & repair as reqd. 3h 16-Feb-15 05:00 PM 16-Feb-15 08:00 PM
857 IM115135 Reinstall strainer C (LT&T R15E-820-009) 6h 16-Feb-15 08:00 PM 17-Feb-15 02:00 AM
858 IM115140 Remove strainer R,G (LT&T R15E-410-002) 12h 17-Feb-15 02:00 AM 17-Feb-15 02:00 PM
859 IM115145 Inspection of strainers 1h 17-Feb-15 02:00 PM 17-Feb-15 03:00 PM
860 IM115150 Cleaning & repair as reqd. 6h 17-Feb-15 03:00 PM 17-Feb-15 09:00 PM
861 IM115155 Reinstall strainer R,G (LT&T R15E-410-002) 12h 17-Feb-15 09:00 PM 18-Feb-15 09:00 AM
862 IM115160 Remove strainer K (LT&T R15E-410-064) 6h 18-Feb-15 09:00 AM 18-Feb-15 03:00 PM
863 IM115165 Inspection of strainers 1h 18-Feb-15 03:00 PM 18-Feb-15 04:00 PM
864 IM115170 Cleaning & repair as reqd. 3h 18-Feb-15 04:00 PM 18-Feb-15 07:00 PM
865 IM115175 Reinstall strainer K (LT&T R15E-410-064) 6h 18-Feb-15 07:00 PM 19-Feb-15 01:00 AM
866 IM115180 Reinstall strainers E,F,H (LT&T R15E-410-010) 15h 19-Feb-15 01:00 AM 19-Feb-15 04:00 PM
867 IM115185 Open top manway 2h 08-Feb-15 02:00 PM 08-Feb-15 04:00 PM
868 IM115190 Carryout AFI & Perlite level inspn. 4h 08-Feb-15 04:00 PM 08-Feb-15 08:00 PM
869 IM115195 Repair & top-up as reqd. 36h 08-Feb-15 08:00 PM 10-Feb-15 08:00 AM
870 IM115200 Final Inspection 2h 10-Feb-15 08:00 AM 10-Feb-15 10:00 AM
871 IM115205 Boxup manway 2h 10-Feb-15 10:00 AM 10-Feb-15 12:00 PM
872 IM115207 Final Inspection for handing over equipment 4h 19-Feb-15 04:00 PM 19-Feb-15 08:00 PM
873 R15E-820-011 RC2-32-820-41-E-805 EXCHANGER - He LEAK TEST & INSPECTIONR15E-820-011 RC2-32-820-41-E-805 EXCHANGER - He LEAK TEST & INSPECTION 119h 18-Feb-15 03:00 AM 23-Feb-15 02:00 AM
874 SHUTDOWNSHUTDOWN 119h 18-Feb-15 03:00 AM 23-Feb-15 02:00 AM
875 IM113800 Purging, Flushing & Gas test, LEL checking 6h 18-Feb-15 03:00 AM 18-Feb-15 09:00 AM
876 IM113805 Verify LT&T and Obtain PTW 2h 18-Feb-15 09:00 AM 18-Feb-15 11:00 AM
877 IM113810 Drop spools & blind as per blindlist 12h 18-Feb-15 11:00 AM 18-Feb-15 11:00 PM
878 IM113815 Carryout Helium test 24h 18-Feb-15 11:00 PM 19-Feb-15 11:00 PM
879 IM113820 NDT of welds & CUI inspection 3h 19-Feb-15 11:00 PM 20-Feb-15 02:00 AM
880 IM113825 Visual inspn. & thickness monitoring 6h 20-Feb-15 02:00 AM 20-Feb-15 08:00 AM
881 IM113830 Repairs & retest as per inspn. report 48h 20-Feb-15 08:00 AM 22-Feb-15 08:00 AM
882 IM113835 Final Inspection 2h 22-Feb-15 08:00 AM 22-Feb-15 10:00 AM
883 IM113840 Boxup the exchanger 2h 22-Feb-15 10:00 AM 22-Feb-15 12:00 PM
884 IM113845 Reinstall spools & Deblinding 14h 22-Feb-15 12:00 PM 23-Feb-15 02:00 AM
885 INSP-EXCH-HE-D/N14INSP-EXCH-HE-D/N14 364h 06-Feb-15 06:00 AM 21-Feb-15 10:00 AM
886 R15E-520-010 RC2-32-520-41-E-508A EXCHANGER - He LEAK TEST & INSPECTIONR15E-520-010 RC2-32-520-41-E-508A EXCHANGER - He LEAK TEST & INSPECTION 240h 07-Feb-15 06:00 PM 17-Feb-15 06:00 PM
887 SHUTDOWNSHUTDOWN 240h 07-Feb-15 06:00 PM 17-Feb-15 06:00 PM
888 IM113565 Purging, Flushing & Gas test, LEL checking 6h 07-Feb-15 06:00 PM 08-Feb-15 12:00 AM
889 IM113570 Verify LT&T and Obtain PTW 2h 08-Feb-15 12:00 AM 08-Feb-15 02:00 AM
890 IM113575 Drop spools & blind as per blindlist 8h 08-Feb-15 02:00 AM 08-Feb-15 10:00 AM
891 IM113580 Drop & remove the 32" strainer 4h 08-Feb-15 02:00 AM 08-Feb-15 06:00 AM
892 IM113585 Drop & remove the 24" strainer 4h 08-Feb-15 02:00 AM 08-Feb-15 06:00 AM
893 IM113590 Inspection of strainers 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM
894 IM113595 Cleaning & repair as per inspn. findings 3h 08-Feb-15 08:00 AM 08-Feb-15 11:00 AM
895 IM113600 Open top manway 2h 08-Feb-15 10:00 AM 08-Feb-15 12:00 PM
896 IM113605 AFI & Perlite level checking 2h 08-Feb-15 12:00 PM 08-Feb-15 02:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 14 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
897 IM113610 Carryout Helium test 20h 13-Feb-15 02:00 PM 14-Feb-15 10:00 AM
898 IM113615 Repair works / Perlite top up as reqd. 48h 14-Feb-15 10:00 AM 16-Feb-15 10:00 AM
899 IM113620 Carryout Helium test 20h 16-Feb-15 10:00 AM 17-Feb-15 06:00 AM
900 IM113625 Final Inspection 2h 17-Feb-15 06:00 AM 17-Feb-15 08:00 AM
901 IM113630 Boxup top manway 2h 17-Feb-15 08:00 AM 17-Feb-15 10:00 AM
902 IM113635 Reinstall strainers 6h 17-Feb-15 12:00 PM 17-Feb-15 06:00 PM
903 IM113640 Carryout De-Blinding 8h 17-Feb-15 10:00 AM 17-Feb-15 06:00 PM
904 R15E-520-014 RC2-32-520-41-E-508B EXCHANGER - He LEAK TEST & INSPECTIONR15E-520-014 RC2-32-520-41-E-508B EXCHANGER - He LEAK TEST & INSPECTION 292h 09-Feb-15 06:00 AM 21-Feb-15 10:00 AM
905 SHUTDOWNSHUTDOWN 292h 09-Feb-15 06:00 AM 21-Feb-15 10:00 AM
906 IM113680 Purging, Flushing & Gas test, LEL checking 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
907 IM113685 Verify LT&T and Obtain PTW 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM
908 IM113690 Drop spools & blind as per blindlist 8h 09-Feb-15 02:00 PM 09-Feb-15 10:00 PM
909 IM113695 Drop & remove the 32" strainer 4h 09-Feb-15 02:00 PM 09-Feb-15 06:00 PM
910 IM113700 Drop & remove the 24" strainer 4h 09-Feb-15 02:00 PM 09-Feb-15 06:00 PM
911 IM113705 Inspection of strainers 2h 09-Feb-15 06:00 PM 09-Feb-15 08:00 PM
912 IM113710 Cleaning & repair as per inspn. findings 3h 09-Feb-15 08:00 PM 09-Feb-15 11:00 PM
913 IM113715 Open top manway 2h 09-Feb-15 10:00 PM 10-Feb-15 12:00 AM
914 IM113720 AFI & Perlite level checking 2h 10-Feb-15 12:00 AM 10-Feb-15 02:00 AM
915 IM113725 Carryout Helium test 20h 17-Feb-15 06:00 AM 18-Feb-15 02:00 AM
916 IM113730 Repair works / Perlite top up as reqd. 48h 18-Feb-15 02:00 AM 20-Feb-15 02:00 AM
917 IM113735 Carryout Helium test 20h 20-Feb-15 02:00 AM 20-Feb-15 10:00 PM
918 IM113740 Final Inspection 2h 20-Feb-15 10:00 PM 21-Feb-15 12:00 AM
919 IM113745 Boxup top manway 2h 21-Feb-15 12:00 AM 21-Feb-15 02:00 AM
920 IM113750 Reinstall strainers 6h 21-Feb-15 04:00 AM 21-Feb-15 10:00 AM
921 IM113755 Carryout De-Blinding 8h 21-Feb-15 02:00 AM 21-Feb-15 10:00 AM
922 R15E-520-016 RC2-32-520-41-E-509 EXCHANGER - He LEAK TEST & INSPECTIONR15E-520-016 RC2-32-520-41-E-509 EXCHANGER - He LEAK TEST & INSPECTION 204h 06-Feb-15 06:00 AM 14-Feb-15 06:00 PM
923 SHUTDOWNSHUTDOWN 204h 06-Feb-15 06:00 AM 14-Feb-15 06:00 PM
924 IM114305 Purging, Flushing & Gas test, LEL checking 6h 06-Feb-15 06:00 AM 06-Feb-15 12:00 PM
925 IM114310 Verify LT&T and Obtain PTW 3h 06-Feb-15 12:00 PM 06-Feb-15 03:00 PM
926 IM114315 Drop spools & blind as per blindlist 24h 06-Feb-15 03:00 PM 07-Feb-15 03:00 PM
927 IM114320 Open manway 4h 07-Feb-15 03:00 PM 07-Feb-15 07:00 PM
928 IM114325 Provide air movers & make 100% LEL free 8h 07-Feb-15 07:00 PM 08-Feb-15 03:00 AM
929 IM114330 Obtain CSE permit 4h 08-Feb-15 03:00 AM 08-Feb-15 07:00 AM
930 IM114335 Perform AFI with the vendor 3h 08-Feb-15 07:00 AM 08-Feb-15 10:00 AM
931 IM114340 Carryout leak check 6h 08-Feb-15 10:00 AM 08-Feb-15 04:00 PM
932 IM114345 Repair work as per technical proposal given by vendor 72h 08-Feb-15 04:00 PM 11-Feb-15 04:00 PM
933 IM114350 Carryout testing & inspection after repair work 10h 11-Feb-15 04:00 PM 12-Feb-15 02:00 AM
934 IM114355 Carryout Helium test 24h 12-Feb-15 02:00 AM 13-Feb-15 02:00 AM
935 IM114360 Repairs & retest as per inspn. report 12h 13-Feb-15 02:00 AM 13-Feb-15 02:00 PM
936 IM114365 Boxup the exchanger 4h 13-Feb-15 02:00 PM 13-Feb-15 06:00 PM
937 IM114370 Reinstall spools & Deblinding 24h 13-Feb-15 06:00 PM 14-Feb-15 06:00 PM
938 CUI-EXCH-D15CUI-EXCH-D15 221h 06-Feb-15 06:00 AM 24-Feb-15 11:00 AM
939 R15E-151-005 RC2-32-151-41-E-511 EXCHANGER - EXT, CUI INSPECTIONR15E-151-005 RC2-32-151-41-E-511 EXCHANGER - EXT, CUI INSPECTION 35h 12-Feb-15 11:00 AM 15-Feb-15 10:00 AM
940 SHUTDOWNSHUTDOWN 35h 12-Feb-15 11:00 AM 15-Feb-15 10:00 AM
941 IM109485 Obtain PTW 2h 12-Feb-15 11:00 AM 12-Feb-15 01:00 PM
942 IM109490 Removal of insulation, wherever reqd. 12h 12-Feb-15 01:00 PM 13-Feb-15 01:00 PM
943 IM109495 Inspn. of nozzles, shell & CUI 6h 13-Feb-15 01:00 PM 14-Feb-15 07:00 AM
944 IM109500 Carryout repair works, if any 12h 14-Feb-15 07:00 AM 15-Feb-15 07:00 AM
945 IM109505 Final Inspection & close PTW 3h 15-Feb-15 07:00 AM 15-Feb-15 10:00 AM
946 R15E-310-026 RC2-32-310-41-E-309 EXCHANGER - EXT, CUI INSPECTIONR15E-310-026 RC2-32-310-41-E-309 EXCHANGER - EXT, CUI INSPECTION 84h 17-Feb-15 11:00 AM 24-Feb-15 11:00 AM
947 SHUTDOWNSHUTDOWN 84h 17-Feb-15 11:00 AM 24-Feb-15 11:00 AM
948 IM109535 Obtain PTW 2h 17-Feb-15 11:00 AM 17-Feb-15 01:00 PM
949 IM109540 Removal of insulation, wherever reqd. 5h 21-Feb-15 11:00 AM 21-Feb-15 04:00 PM
950 IM109545 Inspn. of nozzles, shell & CUI 6h 21-Feb-15 04:00 PM 22-Feb-15 10:00 AM
951 IM109550 Carryout repair works, if any 8h 23-Feb-15 01:00 PM 24-Feb-15 09:00 AM
952 IM109555 Final Inspection & close PTW 2h 24-Feb-15 09:00 AM 24-Feb-15 11:00 AM
953 R15E-500-002 RC2-32-500-41-E-512 EXCHANGER - EXT, CUI INSPECTIONR15E-500-002 RC2-32-500-41-E-512 EXCHANGER - EXT, CUI INSPECTION 43h 15-Feb-15 11:00 AM 18-Feb-15 06:00 PM
954 SHUTDOWNSHUTDOWN 43h 15-Feb-15 11:00 AM 18-Feb-15 06:00 PM
955 IM109585 Obtain PTW 2h 15-Feb-15 11:00 AM 15-Feb-15 01:00 PM
956 IM109590 Removal of insulation, wherever reqd. 10h 16-Feb-15 09:00 AM 17-Feb-15 07:00 AM
957 IM109595 Inspn. of nozzles, shell & CUI 6h 17-Feb-15 07:00 AM 17-Feb-15 01:00 PM
958 IM109600 Carryout repair works, if any 15h 17-Feb-15 01:00 PM 18-Feb-15 04:00 PM
959 IM109605 Final Inspection & close PTW 2h 18-Feb-15 04:00 PM 18-Feb-15 06:00 PM
960 R15E-500-004 RC2-32-500-41-E-513 EXCHANGER - EXT, CUI INSPECTIONR15E-500-004 RC2-32-500-41-E-513 EXCHANGER - EXT, CUI INSPECTION 54h 16-Feb-15 07:00 AM 20-Feb-15 01:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 15 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
961 SHUTDOWNSHUTDOWN 54h 16-Feb-15 07:00 AM 20-Feb-15 01:00 PM
962 IM109210 Obtain PTW 2h 16-Feb-15 07:00 AM 16-Feb-15 09:00 AM
963 IM109215 Removal of insulation, wherever reqd. 8h 17-Feb-15 01:00 PM 18-Feb-15 09:00 AM
964 IM109220 Inspn. of nozzles, shell & CUI 12h 18-Feb-15 09:00 AM 19-Feb-15 09:00 AM
965 IM109225 Carryout repair works, if any 8h 19-Feb-15 09:00 AM 19-Feb-15 05:00 PM
966 IM109230 Final Inspection 2h 19-Feb-15 05:00 PM 20-Feb-15 07:00 AM
967 IM109235 Fix back insulation & close PTW 6h 20-Feb-15 07:00 AM 20-Feb-15 01:00 PM
968 R15E-510-005 RC2-32-510-41-E-501 EXCHANGER - EXT, CUI INSPECTIONR15E-510-005 RC2-32-510-41-E-501 EXCHANGER - EXT, CUI INSPECTION 30h 06-Feb-15 06:00 AM 08-Feb-15 12:00 PM
969 SHUTDOWNSHUTDOWN 30h 06-Feb-15 06:00 AM 08-Feb-15 12:00 PM
970 IM109745 Obtain PTW 2h 06-Feb-15 06:00 AM 06-Feb-15 08:00 AM
971 IM109750 Removal of insulation, wherever reqd. 12h 06-Feb-15 08:00 AM 07-Feb-15 08:00 AM
972 IM109755 Inspn. of nozzles, shell & CUI 8h 07-Feb-15 08:00 AM 07-Feb-15 04:00 PM
973 IM109760 Carryout repair works, if any 6h 07-Feb-15 04:00 PM 08-Feb-15 10:00 AM
974 IM109765 Final Inspection & close PTW 2h 08-Feb-15 10:00 AM 08-Feb-15 12:00 PM
975 R15E-510-023 RC2-32-510-41-E-507 EXCHANGER - EXT, CUI INSPECTIONR15E-510-023 RC2-32-510-41-E-507 EXCHANGER - EXT, CUI INSPECTION 58h 07-Feb-15 06:00 AM 11-Feb-15 04:00 PM
976 SHUTDOWNSHUTDOWN 58h 07-Feb-15 06:00 AM 11-Feb-15 04:00 PM
977 IM109320 Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
978 IM109325 Removal of insulation, wherever reqd. 8h 07-Feb-15 04:00 PM 08-Feb-15 12:00 PM
979 IM109330 Inspn. of nozzles, shell & CUI 16h 08-Feb-15 12:00 PM 09-Feb-15 04:00 PM
980 IM109335 Carryout repair works, if any 10h 09-Feb-15 04:00 PM 10-Feb-15 02:00 PM
981 IM109340 Final Inspection 2h 10-Feb-15 02:00 PM 10-Feb-15 04:00 PM
982 IM109345 Fix back insulation & close PTW 12h 10-Feb-15 04:00 PM 11-Feb-15 04:00 PM
983 R15E-520-017 RC2-32-520-41-E-510 EXCHANGER - EXT, CUI INSPECTIONR15E-520-017 RC2-32-520-41-E-510 EXCHANGER - EXT, CUI INSPECTION 82h 16-Feb-15 03:00 PM 23-Feb-15 01:00 PM
984 SHUTDOWNSHUTDOWN 82h 16-Feb-15 03:00 PM 23-Feb-15 01:00 PM
985 IM109265 Obtain PTW 2h 16-Feb-15 03:00 PM 16-Feb-15 05:00 PM
986 IM109270 Removal of insulation, wherever reqd. 10h 19-Feb-15 09:00 AM 20-Feb-15 07:00 AM
987 IM109275 Inspn. of nozzles, shell & CUI 16h 20-Feb-15 07:00 AM 21-Feb-15 11:00 AM
988 IM109280 Carryout repair works, if any 10h 21-Feb-15 11:00 AM 22-Feb-15 09:00 AM
989 IM109285 Final Inspection 2h 22-Feb-15 09:00 AM 22-Feb-15 11:00 AM
990 IM109290 Fix back insulation & close PTW 14h 22-Feb-15 11:00 AM 23-Feb-15 01:00 PM
991 R15E-620-003 RC2-32-620-41-E-606A EXCHANGER - EXT, CUI INSPECTIONR15E-620-003 RC2-32-620-41-E-606A EXCHANGER - EXT, CUI INSPECTION 50h 08-Feb-15 06:00 AM 12-Feb-15 08:00 AM
992 SHUTDOWNSHUTDOWN 50h 08-Feb-15 06:00 AM 12-Feb-15 08:00 AM
993 IM109375 Obtain PTW 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM
994 IM109380 Removal of insulation, wherever reqd. 5h 09-Feb-15 04:00 PM 10-Feb-15 09:00 AM
995 IM109385 Inspn. of nozzles, shell & CUI 4h 10-Feb-15 09:00 AM 10-Feb-15 01:00 PM
996 IM109390 Carryout repair works, if any 8h 10-Feb-15 04:00 PM 11-Feb-15 12:00 PM
997 IM109395 Final Inspection 2h 11-Feb-15 12:00 PM 11-Feb-15 02:00 PM
998 IM109400 Fix back insulation & close PTW 6h 11-Feb-15 02:00 PM 12-Feb-15 08:00 AM
999 R15E-620-005 RC2-32-620-41-E-606B EXCHANGER - EXT, CUI INSPECTIONR15E-620-005 RC2-32-620-41-E-606B EXCHANGER - EXT, CUI INSPECTION 48h 08-Feb-15 12:00 PM 12-Feb-15 12:00 PM
1000 SHUTDOWNSHUTDOWN 48h 08-Feb-15 12:00 PM 12-Feb-15 12:00 PM
1001 IM109430 Obtain PTW 2h 08-Feb-15 12:00 PM 08-Feb-15 02:00 PM
1002 IM109435 Removal of insulation, wherever reqd. 5h 10-Feb-15 01:00 PM 10-Feb-15 06:00 PM
1003 IM109440 Inspn. of nozzles, shell & CUI 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM
1004 IM109445 Carryout repair works, if any 8h 11-Feb-15 02:00 PM 12-Feb-15 10:00 AM
1005 IM109450 Final Inspection & close PTW 2h 12-Feb-15 10:00 AM 12-Feb-15 12:00 PM
1006 R15E-710-010 RC2-32-710-41-E-702 EXCHANGER - EXT, CUI INSPECTIONR15E-710-010 RC2-32-710-41-E-702 EXCHANGER - EXT, CUI INSPECTION 39h 10-Feb-15 09:00 AM 13-Feb-15 12:00 PM
1007 SHUTDOWNSHUTDOWN 39h 10-Feb-15 09:00 AM 13-Feb-15 12:00 PM
1008 IM109640 Obtain PTW 2h 10-Feb-15 09:00 AM 10-Feb-15 11:00 AM
1009 IM109645 Removal of insulation, wherever reqd. 6h 11-Feb-15 10:00 AM 11-Feb-15 04:00 PM
1010 IM109650 Inspn. of nozzles, shell & CUI 6h 11-Feb-15 04:00 PM 12-Feb-15 10:00 AM
1011 IM109655 Carryout repair works, if any 10h 12-Feb-15 12:00 PM 13-Feb-15 10:00 AM
1012 IM109660 Final Inspection & close PTW 2h 13-Feb-15 10:00 AM 13-Feb-15 12:00 PM
1013 R15U-020-004 RC2-31-020-41-E-1210 EXCHANGER - EXT, CUI INSPECTIONR15U-020-004 RC2-31-020-41-E-1210 EXCHANGER - EXT, CUI INSPECTION 34h 14-Feb-15 11:00 AM 17-Feb-15 09:00 AM
1014 SHUTDOWNSHUTDOWN 34h 14-Feb-15 11:00 AM 17-Feb-15 09:00 AM
1015 OM105970 Obtain PTW 2h 14-Feb-15 11:00 AM 14-Feb-15 01:00 PM
1016 OM105975 Remove Insulations as reqd. for inspn. 8h 14-Feb-15 01:00 PM 15-Feb-15 09:00 AM
1017 OM105980 Inspn. of nozzles, shell, suspected areas & CUI 12h 15-Feb-15 09:00 AM 16-Feb-15 09:00 AM
1018 OM105985 Carryout repair. 10h 16-Feb-15 09:00 AM 17-Feb-15 07:00 AM
1019 OM105990 Final inspection and close PTW 2h 17-Feb-15 07:00 AM 17-Feb-15 09:00 AM
1020 TWR D/N91TWR D/N91 376h 07-Feb-15 06:00 AM 22-Feb-15 10:00 PM
1021 R15E-310-028 TWR-32-0153 - REPLACEMENT OF E-310 WITH PROVISION TO BYPASSR15E-310-028 TWR-32-0153 - REPLACEMENT OF E-310 WITH PROVISION TO BYPASS 376h 07-Feb-15 06:00 AM 22-Feb-15 10:00 PM
1022 SHUTDOWNSHUTDOWN 376h 07-Feb-15 06:00 AM 22-Feb-15 10:00 PM
1023 IP100760 LT&T and PTW 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM
1024 IP100765 Insulation removal 16h 08-Feb-15 10:00 AM 09-Feb-15 02:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 16 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1025 IP100770 Marking on existing lines as per approved isometric drawings 16h 09-Feb-15 02:00 AM 09-Feb-15 06:00 PM
1026 IP100775 Cold cutting of the existing lines at tie in points 40h 09-Feb-15 06:00 PM 11-Feb-15 10:00 AM
1027 IP100780 Allignment and fittup of tie in points 40h 12-Feb-15 02:00 AM 13-Feb-15 06:00 PM
1028 IP100785 Inspection of fittup 16h 13-Feb-15 06:00 AM 13-Feb-15 10:00 PM
1029 IP100790 Complete welding of tie in points 56h 13-Feb-15 10:00 PM 16-Feb-15 06:00 AM
1030 IP100795 NDT of all welded tie in joints 24h 15-Feb-15 10:00 PM 16-Feb-15 10:00 PM
1031 IP100800 Hydrotesting 30h 16-Feb-15 10:00 PM 18-Feb-15 04:00 AM
1032 IP100805 Deblinding & reinstatment 24h 18-Feb-15 04:00 AM 19-Feb-15 04:00 AM
1033 IP100810 Paint application to all joints 48h 19-Feb-15 04:00 AM 21-Feb-15 04:00 AM
1034 IP100815 Insulation installation 24h 21-Feb-15 04:00 AM 22-Feb-15 04:00 AM
1035 IP100820 PSSR 6h 22-Feb-15 04:00 AM 22-Feb-15 10:00 AM
1036 IP100825 Rigging of existing lines at tie in points 16h 11-Feb-15 10:00 AM 12-Feb-15 02:00 AM
1037 IP100830 System blinding 24h 07-Feb-15 10:00 AM 08-Feb-15 10:00 AM
1038 IP100835 System deblinding 12h 22-Feb-15 10:00 AM 22-Feb-15 10:00 PM
1039 DRUMDRUM 893h 24-Jan-15 06:00 AM 02-Mar-15 11:00 AM
1040 CSE-MDA-D/N16CSE-MDA-D/N16 868h 24-Jan-15 06:00 AM 01-Mar-15 10:00 AM
1041 R15E-320-001 RC2-32-320-25-D-301A DRYER - DESICCANT REPLACEMENTR15E-320-001 RC2-32-320-25-D-301A DRYER - DESICCANT REPLACEMENT 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1042 SHUTDOWNSHUTDOWN 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1043 IM101110 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM
1044 IM101115 Mechanical Isolation & Blinding 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM
1045 IM101120 Top Manway Opening & screen mesh 6h 07-Feb-15 06:00 PM 08-Feb-15 12:00 AM
1046 IM101125 Removal of Dessicants as per Approved MOS 60h 08-Feb-15 02:00 PM 11-Feb-15 02:00 AM
1047 IM101130 Loading the Dessicants as per Approved MOS 60h 14-Feb-15 08:00 PM 17-Feb-15 08:00 AM
1048 IM101135 Top Manway Box-up 6h 18-Feb-15 02:00 AM 18-Feb-15 08:00 AM
1049 IM101140 De-Blinding 8h 25-Feb-15 08:00 AM 25-Feb-15 04:00 PM
1050 IM101145 Reinstall insulations on vessel 96h 25-Feb-15 08:00 AM 01-Mar-15 08:00 AM
1051 IM101160 Close Work permit 2h 01-Mar-15 08:00 AM 01-Mar-15 10:00 AM
1052 R15E-320-002 RC2-32-320-25-D-301A DRYER - INTERNAL INSPECTION & PAINTINGR15E-320-002 RC2-32-320-25-D-301A DRYER - INTERNAL INSPECTION & PAINTING 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1053 SHUTDOWNSHUTDOWN 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1054 IM101180 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM
1055 IM101185 Obtain Confined space permit 2h 08-Feb-15 12:00 AM 08-Feb-15 02:00 AM
1056 IM101190 Removal of top hold down grids 12h 08-Feb-15 02:00 AM 08-Feb-15 02:00 PM
1057 IM101191 Open side manway 6h 11-Feb-15 02:00 AM 11-Feb-15 08:00 AM
1058 IM101192 Cleaning & Repair & Install of top meshes and grids 12h 17-Feb-15 08:00 AM 17-Feb-15 08:00 PM
1059 IM101193 Removal of bottom support grids, screen mesh 12h 11-Feb-15 02:00 PM 12-Feb-15 02:00 AM
1060 IM101194 Cleaning & Repair & Install of bottom screen mesh, grids 12h 13-Feb-15 08:00 PM 14-Feb-15 08:00 AM
1061 IM101195 Erect Internal Scaffolding 8h 12-Feb-15 02:00 AM 12-Feb-15 10:00 AM
1062 IM101200 Preliminary Inspection 6h 11-Feb-15 08:00 AM 11-Feb-15 02:00 PM
1063 IM101203 N.O.R.M. Survey by I.H. 1h 11-Feb-15 08:00 AM 11-Feb-15 09:00 AM
1064 IM101205 Cleaning & Repair of vessel 30h 12-Feb-15 10:00 AM 13-Feb-15 04:00 PM
1065 IM101207 Remove Internal Scaffolding 4h 13-Feb-15 04:00 PM 13-Feb-15 08:00 PM
1066 IM101210 Instln.of repaired/new (if recom.) bottom meshes and grids 12h 13-Feb-15 08:00 PM 14-Feb-15 08:00 AM
1067 IM101212 Instln.of repaired/new (if recom.) top meshes and grids 12h 17-Feb-15 08:00 AM 17-Feb-15 08:00 PM
1068 IM101215 Final Inspection of bottom mesh & grid after installation 6h 14-Feb-15 08:00 AM 14-Feb-15 02:00 PM
1069 IM101217 Final Inspection of top mesh & grid after installation 6h 17-Feb-15 08:00 PM 18-Feb-15 02:00 AM
1070 IM101220 Side Manway Box-up 6h 14-Feb-15 02:00 PM 14-Feb-15 08:00 PM
1071 IM101225 TSA Painting on Regeneraton Looping Piping 168h 07-Feb-15 06:00 PM 14-Feb-15 06:00 PM
1072 IM101227 Renewal of gaskets & fasteners on regen. piping 120h 12-Feb-15 06:00 PM 17-Feb-15 06:00 PM
1073 IM101228 Reinstall insulations on regen. piping 96h 14-Feb-15 06:00 PM 18-Feb-15 06:00 PM
1074 IM101229 TSA Painting on Vessel 168h 18-Feb-15 08:00 AM 25-Feb-15 08:00 AM
1075 IM101245 Close Work permit 2h 01-Mar-15 08:00 AM 01-Mar-15 10:00 AM
1076 R15E-520-008 RC2-32-520-25-D-501 DRYER - DESICCANT REPLACEMENTR15E-520-008 RC2-32-520-25-D-501 DRYER - DESICCANT REPLACEMENT 192h 24-Jan-15 06:00 AM 01-Feb-15 06:00 AM
1077 SHUTDOWNSHUTDOWN 192h 24-Jan-15 06:00 AM 01-Feb-15 06:00 AM
1078 IM101915 Verify LT&T and Obtain permit 4h 24-Jan-15 06:00 AM 24-Jan-15 10:00 AM
1079 IM101920 Mechanical Isolation & Blinding 8h 24-Jan-15 10:00 AM 24-Jan-15 06:00 PM
1080 IM101925 Top Manway Opening & Screen Mesh 6h 24-Jan-15 06:00 PM 25-Jan-15 12:00 AM
1081 IM101927 Obtain CSE permit 2h 25-Jan-15 12:00 AM 25-Jan-15 02:00 AM
1082 IM101930 Removal of Top Hold down & Support Grids 6h 25-Jan-15 02:00 AM 25-Jan-15 08:00 AM
1083 IM101935 Removal of Dessicants as per approved MOS 48h 25-Jan-15 08:00 AM 27-Jan-15 08:00 AM
1084 IM101937 Open side manway 4h 27-Jan-15 08:00 AM 27-Jan-15 12:00 PM
1085 IM101940 Removal of Bottom Screen Mesh, Hold down & Support Grids 6h 27-Jan-15 08:00 AM 27-Jan-15 02:00 PM
1086 IM101943 Erect Internal Scaffolding 4h 27-Jan-15 02:00 PM 27-Jan-15 06:00 PM
1087 IM101945 Preliminary Inspection 4h 27-Jan-15 06:00 PM 27-Jan-15 10:00 PM
1088 IM101950 Cleaning & Repair in vessel, meshes and grids 18h 27-Jan-15 10:00 PM 28-Jan-15 04:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 17 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1089 IM101953 Final Inspection 4h 28-Jan-15 04:00 PM 28-Jan-15 08:00 PM
1090 IM101955 Removal Internal Scaffolding 4h 28-Jan-15 08:00 PM 29-Jan-15 12:00 AM
1091 IM101957 Installation of bottom meshes and grids 6h 29-Jan-15 12:00 AM 29-Jan-15 06:00 AM
1092 IM101963 Side manyway boxup 4h 29-Jan-15 06:00 AM 29-Jan-15 10:00 AM
1093 IM101965 Loading the Dessicants as per approved MOS 48h 29-Jan-15 10:00 AM 31-Jan-15 10:00 AM
1094 IM101967 Installation of top meshes and grids 6h 31-Jan-15 10:00 AM 31-Jan-15 04:00 PM
1095 IM101970 Final inspection to boxup the vessel 2h 31-Jan-15 04:00 PM 31-Jan-15 06:00 PM
1096 IM101975 Top Manway Box-up 4h 31-Jan-15 06:00 PM 31-Jan-15 10:00 PM
1097 IM101977 De-Blinding & Close work permit 8h 31-Jan-15 10:00 PM 01-Feb-15 06:00 AM
1098 CSE-MDA-D/N17CSE-MDA-D/N17 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1099 R15E-320-003 RC2-32-320-25-D-301B DRYER - DESICCANT REPLACEMENTR15E-320-003 RC2-32-320-25-D-301B DRYER - DESICCANT REPLACEMENT 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1100 SHUTDOWNSHUTDOWN 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1101 IM101265 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM
1102 IM101270 Mechanical Isolation & Blinding 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM
1103 IM101275 Top Manway Opening & screen mesh 6h 07-Feb-15 06:00 PM 08-Feb-15 12:00 AM
1104 IM101280 Removal of Dessicants as per Approved MOS 60h 08-Feb-15 02:00 PM 11-Feb-15 02:00 AM
1105 IM101285 Loading the Dessicants as per Approved MOS 60h 14-Feb-15 08:00 PM 17-Feb-15 08:00 AM
1106 IM101290 Top Manway Box-up 6h 18-Feb-15 02:00 AM 18-Feb-15 08:00 AM
1107 IM101295 De-Blinding 8h 25-Feb-15 08:00 AM 25-Feb-15 04:00 PM
1108 IM101300 Reinstall insulations on vessel 96h 25-Feb-15 08:00 AM 01-Mar-15 08:00 AM
1109 IM101302 Close Work permit 2h 01-Mar-15 08:00 AM 01-Mar-15 10:00 AM
1110 R15E-320-004 RC2-32-320-25-D-301B DRYER - INTERNAL INSPECTION & PAINTINGR15E-320-004 RC2-32-320-25-D-301B DRYER - INTERNAL INSPECTION & PAINTING 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1111 SHUTDOWNSHUTDOWN 532h 07-Feb-15 06:00 AM 01-Mar-15 10:00 AM
1112 IM101335 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM
1113 IM101337 Obtain Confined space permit 2h 08-Feb-15 12:00 AM 08-Feb-15 02:00 AM
1114 IM101339 Removal of top hold down grids 12h 08-Feb-15 02:00 AM 08-Feb-15 02:00 PM
1115 IM101341 Open side manway 6h 11-Feb-15 02:00 AM 11-Feb-15 08:00 AM
1116 IM101343 Cleaning & Repair & Install of top meshes and grids 12h 17-Feb-15 08:00 AM 17-Feb-15 08:00 PM
1117 IM101345 Removal of bottom support grids, screen mesh 12h 11-Feb-15 02:00 PM 12-Feb-15 02:00 AM
1118 IM101349 Cleaning & Repair & Install of bottom screen mesh, grids 12h 13-Feb-15 08:00 PM 14-Feb-15 08:00 AM
1119 IM101351 Erect Internal Scaffolding 8h 12-Feb-15 02:00 AM 12-Feb-15 10:00 AM
1120 IM101353 Preliminary Inspection 6h 11-Feb-15 08:00 AM 11-Feb-15 02:00 PM
1121 IM101357 N.O.R.M. Survey by I.H. 1h 11-Feb-15 08:00 AM 11-Feb-15 09:00 AM
1122 IM101361 Cleaning & Repair of vessel 30h 12-Feb-15 10:00 AM 13-Feb-15 04:00 PM
1123 IM101363 Remove Internal Scaffolding 4h 13-Feb-15 04:00 PM 13-Feb-15 08:00 PM
1124 IM101365 Instln.of repaired/new (if recom.) bottom meshes and grids 12h 13-Feb-15 08:00 PM 14-Feb-15 08:00 AM
1125 IM101367 Instln.of repaired/new (if recom.) top meshes and grids 12h 17-Feb-15 08:00 AM 17-Feb-15 08:00 PM
1126 IM101371 Final Inspection of bottom mesh & grid after installation 6h 14-Feb-15 08:00 AM 14-Feb-15 02:00 PM
1127 IM101373 Final Inspection of top mesh & grid after installation 6h 17-Feb-15 08:00 PM 18-Feb-15 02:00 AM
1128 IM101375 Side Manway Box-up 6h 14-Feb-15 02:00 PM 14-Feb-15 08:00 PM
1129 IM101377 TSA Painting on Regeneraton Looping Piping 168h 07-Feb-15 06:00 PM 14-Feb-15 06:00 PM
1130 IM101379 Renewal of gaskets & fasteners on regen. piping 120h 12-Feb-15 06:00 PM 17-Feb-15 06:00 PM
1131 IM101381 Reinstall insulations on regen. piping 96h 14-Feb-15 06:00 PM 18-Feb-15 06:00 PM
1132 IM101383 TSA Painting on Vessel 168h 18-Feb-15 08:00 AM 25-Feb-15 08:00 AM
1133 IM101385 Close Work permit 2h 01-Mar-15 08:00 AM 01-Mar-15 10:00 AM
1134 CSE-MDA-D/N18CSE-MDA-D/N18 432h 09-Feb-15 06:00 AM 27-Feb-15 06:00 AM
1135 R15E-210-013 RC2-32-210-95-D-221 DRUM - INT, EXT, CUI INSPECTIONR15E-210-013 RC2-32-210-95-D-221 DRUM - INT, EXT, CUI INSPECTION 432h 09-Feb-15 06:00 AM 27-Feb-15 06:00 AM
1136 SHUTDOWNSHUTDOWN 432h 09-Feb-15 06:00 AM 27-Feb-15 06:00 AM
1137 IM100025 Verify LT&T and Obtain permit 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
1138 IM100030 Mechanical Isolation & Blinding 36h 09-Feb-15 12:00 PM 11-Feb-15 12:00 AM
1139 IM100035 Chemical Cleaning Preparations 12h 11-Feb-15 12:00 AM 11-Feb-15 12:00 PM
1140 IM100040 Chemical Cleaning 60h 11-Feb-15 12:00 PM 14-Feb-15 12:00 AM
1141 IM100045 CUI Inspection & Repair 12h 14-Feb-15 12:00 AM 14-Feb-15 12:00 PM
1142 IM100050 Manway Opening & Providing a Ventilation & Lighting 8h 15-Feb-15 02:00 AM 15-Feb-15 10:00 AM
1143 IM100055 Obtain Confined space permit 2h 15-Feb-15 10:00 AM 15-Feb-15 12:00 PM
1144 IM100057 Erect Internal Scaffolding 6h 15-Feb-15 12:00 PM 15-Feb-15 06:00 PM
1145 IM100060 Preliminary Inspection 4h 15-Feb-15 06:00 PM 15-Feb-15 10:00 PM
1146 IM100062 N.O.R.M. Survey by I.H. 1h 15-Feb-15 06:00 PM 15-Feb-15 07:00 PM
1147 IM100065 Cleaning & Repair & Inspect 24h 15-Feb-15 10:00 PM 16-Feb-15 10:00 PM
1148 IM100070 Remove Internal Scaffolding 4h 16-Feb-15 10:00 PM 17-Feb-15 02:00 AM
1149 IM100075 Final Inspection 4h 17-Feb-15 02:00 AM 17-Feb-15 06:00 AM
1150 IM100080 Manway Box-up 4h 17-Feb-15 06:00 AM 17-Feb-15 10:00 AM
1151 IM100085 De-Blinding & Close permit 36h 25-Feb-15 06:00 PM 27-Feb-15 06:00 AM
1152 CSE-INSP-D/N20CSE-INSP-D/N20 206h 12-Feb-15 06:00 AM 20-Feb-15 08:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 18 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1153 R15E-510-029 RC2-32-510-95-D-521 DRUM - INT, EXT, CUI INSPECTIONR15E-510-029 RC2-32-510-95-D-521 DRUM - INT, EXT, CUI INSPECTION 98h 16-Feb-15 06:00 PM 20-Feb-15 08:00 PM
1154 SHUTDOWNSHUTDOWN 98h 16-Feb-15 06:00 PM 20-Feb-15 08:00 PM
1155 IM101715 Verify LT&T and Obtain permit 6h 16-Feb-15 06:00 PM 17-Feb-15 12:00 AM
1156 IM101720 Mechanical Isolation & Blinding 12h 17-Feb-15 12:00 AM 17-Feb-15 12:00 PM
1157 IM101725 Manway Opening & Providing a Ventilation & Lighting 8h 17-Feb-15 12:00 PM 17-Feb-15 08:00 PM
1158 IM101730 CUI Inspection & Repair 18h 17-Feb-15 12:00 PM 18-Feb-15 06:00 AM
1159 IM101735 Obtain Confined space permit 2h 17-Feb-15 08:00 PM 17-Feb-15 10:00 PM
1160 IM101737 Erect Internal Scaffolding 8h 17-Feb-15 10:00 PM 18-Feb-15 06:00 AM
1161 IM101740 Preliminary Inspection 4h 18-Feb-15 06:00 AM 18-Feb-15 10:00 AM
1162 IM101743 N.O.R.M. Survey by I.H. 1h 18-Feb-15 06:00 AM 18-Feb-15 07:00 AM
1163 IM101745 Cleaning & Repair 30h 18-Feb-15 10:00 AM 19-Feb-15 04:00 PM
1164 IM101750 Remove Internal Scaffolding 6h 19-Feb-15 04:00 PM 19-Feb-15 10:00 PM
1165 IM101755 Final Inspection 4h 19-Feb-15 10:00 PM 20-Feb-15 02:00 AM
1166 IM101760 Manway Box-up 6h 20-Feb-15 02:00 AM 20-Feb-15 08:00 AM
1167 IM101765 De-Blinding & Close permit 12h 20-Feb-15 08:00 AM 20-Feb-15 08:00 PM
1168 R15U-020-009 RC2-31-020-95-D-1221 DRUM - INT, EXT, CUI INSPECTIONR15U-020-009 RC2-31-020-95-D-1221 DRUM - INT, EXT, CUI INSPECTION 119h 14-Feb-15 06:00 AM 19-Feb-15 05:00 AM
1169 SHUTDOWNSHUTDOWN 119h 14-Feb-15 06:00 AM 19-Feb-15 05:00 AM
1170 OM100025 Verify LT&T and Obtain permit 4h 14-Feb-15 06:00 AM 14-Feb-15 10:00 AM
1171 OM100030 Mechanical Isolation & Blinding 8h 14-Feb-15 10:00 AM 14-Feb-15 06:00 PM
1172 OM100035 Manway Opening & Providing a Ventilation & Lighting 8h 14-Feb-15 06:00 PM 15-Feb-15 02:00 AM
1173 OM100040 CUI Inspection & Repair 12h 14-Feb-15 06:00 PM 15-Feb-15 06:00 AM
1174 OM100045 Obtain Confined space permit 2h 15-Feb-15 02:00 AM 15-Feb-15 04:00 AM
1175 OM100047 Erect Internal Scaffolding 8h 15-Feb-15 04:00 AM 15-Feb-15 12:00 PM
1176 OM100050 Preliminary Inspection 4h 15-Feb-15 12:00 PM 15-Feb-15 04:00 PM
1177 OM100055 Cleaning & Repair 12h 15-Feb-15 04:00 PM 16-Feb-15 04:00 AM
1178 OM100060 Remove Internal Scaffolding 4h 16-Feb-15 04:00 AM 16-Feb-15 08:00 AM
1179 OM100065 Final Inspection 4h 16-Feb-15 08:00 AM 16-Feb-15 12:00 PM
1180 OM100070 Manway Box-up 4h 18-Feb-15 05:00 PM 18-Feb-15 09:00 PM
1181 OM100075 De-Blinding & Close permit 8h 18-Feb-15 09:00 PM 19-Feb-15 05:00 AM
1182 R15U-024-010 RC2-31-024-95-D-1223 DRUM - INT, EXT, CUI INSPECTIONR15U-024-010 RC2-31-024-95-D-1223 DRUM - INT, EXT, CUI INSPECTION 163h 12-Feb-15 06:00 AM 19-Feb-15 01:00 AM
1183 SHUTDOWNSHUTDOWN 163h 12-Feb-15 06:00 AM 19-Feb-15 01:00 AM
1184 OM100340 Verify LT&T and Obtain permit 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM
1185 OM100345 Mechanical Isolation & Blinding 16h 12-Feb-15 12:00 PM 13-Feb-15 04:00 AM
1186 OM100350 Manway Opening & Providing a Ventilation & Lighting 8h 13-Feb-15 04:00 AM 13-Feb-15 12:00 PM
1187 OM100355 CUI Inspection & Repair 12h 13-Feb-15 12:00 PM 14-Feb-15 12:00 AM
1188 OM100360 Obtain Confined space permit 2h 14-Feb-15 12:00 AM 14-Feb-15 02:00 AM
1189 OM100362 Erect Internal Scaffolding 8h 14-Feb-15 02:00 AM 14-Feb-15 10:00 AM
1190 OM100365 Preliminary Inspection 6h 14-Feb-15 10:00 AM 14-Feb-15 04:00 PM
1191 OM100370 Cleaning & Repair 24h 14-Feb-15 04:00 PM 15-Feb-15 04:00 PM
1192 OM100375 Remove Internal Scaffolding 4h 15-Feb-15 04:00 PM 15-Feb-15 08:00 PM
1193 OM100380 Final Inspection 6h 15-Feb-15 08:00 PM 16-Feb-15 02:00 AM
1194 OM100385 Manway Box-up 6h 16-Feb-15 02:00 AM 16-Feb-15 08:00 AM
1195 OM100390 De-Blinding & Close permit 16h 18-Feb-15 09:00 AM 19-Feb-15 01:00 AM
1196 CSE-INSP-D/N21CSE-INSP-D/N21 77h 27-Feb-15 06:00 AM 02-Mar-15 11:00 AM
1197 R15U-080-004 RC2-31-080-95-D-1290 DRUM - INT, EXT INSPECTIONR15U-080-004 RC2-31-080-95-D-1290 DRUM - INT, EXT INSPECTION 77h 27-Feb-15 06:00 AM 02-Mar-15 11:00 AM
1198 SHUTDOWNSHUTDOWN 77h 27-Feb-15 06:00 AM 02-Mar-15 11:00 AM
1199 OM101440 Verify LT&T and Obtain permit 4h 27-Feb-15 06:00 AM 27-Feb-15 10:00 AM
1200 OM101445 Mechanical Isolation & Blinding 8h 27-Feb-15 10:00 AM 27-Feb-15 06:00 PM
1201 OM101450 Manway Opening, Provide Ventilation & Lighting 8h 27-Feb-15 06:00 PM 28-Feb-15 02:00 AM
1202 OM101455 Obtain Confined space permit 2h 28-Feb-15 02:00 AM 28-Feb-15 04:00 AM
1203 OM101457 Erect Internal Scaffolding 8h 28-Feb-15 04:00 AM 28-Feb-15 12:00 PM
1204 OM101460 Preliminary Inspection 3h 28-Feb-15 12:00 PM 28-Feb-15 03:00 PM
1205 OM101463 N.O.R.M. Survey by I.H. 1h 28-Feb-15 12:00 PM 28-Feb-15 01:00 PM
1206 OM101465 Cleaning, Repair & Inspect 18h 28-Feb-15 03:00 PM 01-Mar-15 09:00 AM
1207 OM101467 Remove Internal Scaffolding 8h 01-Mar-15 09:00 AM 01-Mar-15 05:00 PM
1208 OM101470 Final Inspection 4h 01-Mar-15 05:00 PM 01-Mar-15 09:00 PM
1209 OM101475 Manway Box-up 4h 01-Mar-15 09:00 PM 02-Mar-15 01:00 AM
1210 OM101480 De-Blinding & Close permit 10h 02-Mar-15 01:00 AM 02-Mar-15 11:00 AM
1211 CSE-INSP-D/N23CSE-INSP-D/N23 82h 21-Feb-15 08:00 AM 24-Feb-15 06:00 PM
1212 R15E-330-008 RC2-32-330-95-D-331 DRUM - INT, EXT INSPECTIONR15E-330-008 RC2-32-330-95-D-331 DRUM - INT, EXT INSPECTION 82h 21-Feb-15 08:00 AM 24-Feb-15 06:00 PM
1213 SHUTDOWNSHUTDOWN 82h 21-Feb-15 08:00 AM 24-Feb-15 06:00 PM
1214 IM101485 Verify LT&T and Obtain permit 6h 21-Feb-15 08:00 AM 21-Feb-15 02:00 PM
1215 IM101490 Mechanical Isolation & Blinding 12h 21-Feb-15 02:00 PM 22-Feb-15 02:00 AM
1216 IM101495 Remove Pump connection, Provide Ventilation & Lighting 8h 22-Feb-15 02:00 AM 22-Feb-15 10:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 19 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1217 IM101500 Obtain Confined space permit 2h 22-Feb-15 10:00 AM 22-Feb-15 12:00 PM
1218 IM101505 Preliminary Inspection 4h 22-Feb-15 12:00 PM 22-Feb-15 04:00 PM
1219 IM101510 Cleaning, Repair & Inspect 30h 22-Feb-15 04:00 PM 23-Feb-15 10:00 PM
1220 IM101515 Final Inspection 4h 23-Feb-15 10:00 PM 24-Feb-15 02:00 AM
1221 IM101520 Fix back Pump connection 4h 24-Feb-15 02:00 AM 24-Feb-15 06:00 AM
1222 IM101525 De-Blinding & Close permit 12h 24-Feb-15 06:00 AM 24-Feb-15 06:00 PM
1223 CSE-INSP-D/N25CSE-INSP-D/N25 78h 22-Feb-15 10:00 PM 26-Feb-15 04:00 AM
1224 R15E-330-007 RC2-32-330-95-D-330 DRUM - INT, EXT INSPECTIONR15E-330-007 RC2-32-330-95-D-330 DRUM - INT, EXT INSPECTION 78h 22-Feb-15 10:00 PM 26-Feb-15 04:00 AM
1225 SHUTDOWNSHUTDOWN 78h 22-Feb-15 10:00 PM 26-Feb-15 04:00 AM
1226 IM101415 Verify LT&T and Obtain permit 6h 22-Feb-15 10:00 PM 23-Feb-15 04:00 AM
1227 IM101420 Mechanical Isolation & Blinding 10h 23-Feb-15 04:00 AM 23-Feb-15 02:00 PM
1228 IM101425 Manway Opening, Provide Ventilation & Lighting 8h 23-Feb-15 02:00 PM 23-Feb-15 10:00 PM
1229 IM101430 Obtain Confined space permit 2h 23-Feb-15 10:00 PM 24-Feb-15 12:00 AM
1230 IM101435 Preliminary Inspection 4h 24-Feb-15 12:00 AM 24-Feb-15 04:00 AM
1231 IM101440 Cleaning & Repair 30h 24-Feb-15 04:00 AM 25-Feb-15 10:00 AM
1232 IM101445 Final Inspection 4h 25-Feb-15 10:00 AM 25-Feb-15 02:00 PM
1233 IM101450 Manway Box-up 4h 25-Feb-15 02:00 PM 25-Feb-15 06:00 PM
1234 IM101455 De-Blinding & Close permit 10h 25-Feb-15 06:00 PM 26-Feb-15 04:00 AM
1235 CSE-INSP-D/N27CSE-INSP-D/N27 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
1236 R15E-310-055 RC2-32-310-95-D-322 DRUM - INT, EXT INSPECTIONR15E-310-055 RC2-32-310-95-D-322 DRUM - INT, EXT INSPECTION 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
1237 SHUTDOWNSHUTDOWN 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
1238 IM100560 Verify LT&T and Obtain permit 6h 07-Feb-15 06:00 AM 07-Feb-15 12:00 PM
1239 IM100565 Mechanical Isolation & Blinding 24h 07-Feb-15 12:00 PM 08-Feb-15 12:00 PM
1240 IM100570 Manway Opening, Provide Ventilation & Lighting 8h 08-Feb-15 12:00 PM 08-Feb-15 08:00 PM
1241 IM100575 Obtain Confined space permit 2h 08-Feb-15 08:00 PM 08-Feb-15 10:00 PM
1242 IM100577 Erect Internal Scaffolding 8h 08-Feb-15 10:00 PM 09-Feb-15 06:00 AM
1243 IM100580 Preliminary Inspection 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
1244 IM100582 N.O.R.M. Survey by I.H. 1h 09-Feb-15 06:00 AM 09-Feb-15 07:00 AM
1245 IM100585 Cleaning & Repair 24h 09-Feb-15 12:00 PM 10-Feb-15 12:00 PM
1246 IM100590 Mist Eliminator Removal and Installation 36h 10-Feb-15 12:00 PM 12-Feb-15 12:00 AM
1247 IM100595 Remove Internal Scaffolding 4h 12-Feb-15 12:00 AM 12-Feb-15 04:00 AM
1248 IM100600 Final Inspection 6h 12-Feb-15 04:00 AM 12-Feb-15 10:00 AM
1249 IM100605 Manway Box-up 6h 12-Feb-15 10:00 AM 12-Feb-15 04:00 PM
1250 IM100610 De-Blinding & Close permit 24h 19-Feb-15 02:00 PM 20-Feb-15 02:00 PM
1251 R15E-310-057 RC2-32-310-95-D-323 DRUM - CLEANING & INSPECTIONR15E-310-057 RC2-32-310-95-D-323 DRUM - CLEANING & INSPECTION 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
1252 SHUTDOWNSHUTDOWN 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
1253 IM100650 Verify LT&T and Obtain permit 6h 07-Feb-15 06:00 AM 07-Feb-15 12:00 PM
1254 IM100655 Mechanical Isolation & Blinding 24h 07-Feb-15 12:00 PM 08-Feb-15 12:00 PM
1255 IM100660 Manway Opening, Provide Ventilation & Lighting 8h 08-Feb-15 08:00 PM 09-Feb-15 04:00 AM
1256 IM100665 Obtain Confined space permit 2h 09-Feb-15 04:00 AM 09-Feb-15 06:00 AM
1257 IM100667 Erect Internal Scaffolding 8h 09-Feb-15 06:00 AM 09-Feb-15 02:00 PM
1258 IM100670 Preliminary Inspection 6h 09-Feb-15 02:00 PM 09-Feb-15 08:00 PM
1259 IM100675 Cleaning & Repair 24h 12-Feb-15 12:00 AM 13-Feb-15 12:00 AM
1260 IM100680 Mist Eliminator Removal and Installation 36h 13-Feb-15 12:00 AM 14-Feb-15 12:00 PM
1261 IM100685 Remove Internal Scaffolding 4h 14-Feb-15 12:00 PM 14-Feb-15 04:00 PM
1262 IM100690 Final Inspection 6h 14-Feb-15 04:00 PM 14-Feb-15 10:00 PM
1263 IM100695 Manway Box-up 6h 14-Feb-15 10:00 PM 15-Feb-15 04:00 AM
1264 IM100700 De-Blinding & Close permit 24h 19-Feb-15 02:00 PM 20-Feb-15 02:00 PM
1265 R15E-310-058 RC2-32-310-95-D-324 DRUM - INT, EXT INSPECTIONR15E-310-058 RC2-32-310-95-D-324 DRUM - INT, EXT INSPECTION 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
1266 SHUTDOWNSHUTDOWN 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
1267 IM100740 Verify LT&T and Obtain permit 6h 07-Feb-15 06:00 AM 07-Feb-15 12:00 PM
1268 IM100745 Mechanical Isolation & Blinding 24h 07-Feb-15 12:00 PM 08-Feb-15 12:00 PM
1269 IM100750 Manway Opening, Provide Ventilation & Lighting 8h 09-Feb-15 04:00 AM 09-Feb-15 12:00 PM
1270 IM100755 Obtain Confined space permit 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM
1271 IM100757 Erect Internal Scaffolding 8h 09-Feb-15 02:00 PM 09-Feb-15 10:00 PM
1272 IM100760 Preliminary Inspection 6h 09-Feb-15 10:00 PM 10-Feb-15 04:00 AM
1273 IM100765 Cleaning & Repair 24h 14-Feb-15 12:00 PM 15-Feb-15 12:00 PM
1274 IM100770 Mist Eliminator Removal and Installation 36h 15-Feb-15 12:00 PM 17-Feb-15 12:00 AM
1275 IM100775 Remove Internal Scaffolding 4h 17-Feb-15 12:00 AM 17-Feb-15 04:00 AM
1276 IM100780 Final Inspection 6h 17-Feb-15 04:00 AM 17-Feb-15 10:00 AM
1277 IM100785 Manway Box-up 6h 17-Feb-15 10:00 AM 17-Feb-15 04:00 PM
1278 IM100790 De-Blinding & Close permit 24h 19-Feb-15 02:00 PM 20-Feb-15 02:00 PM
1279 R15E-310-059 RC2-32-310-95-D-325 DRUM - INT, EXT INSPECTIONR15E-310-059 RC2-32-310-95-D-325 DRUM - INT, EXT INSPECTION 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
1280 SHUTDOWNSHUTDOWN 320h 07-Feb-15 06:00 AM 20-Feb-15 02:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 20 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1281 IM100830 Verify LT&T and Obtain permit 6h 07-Feb-15 06:00 AM 07-Feb-15 12:00 PM
1282 IM100835 Mechanical Isolation & Blinding 18h 07-Feb-15 12:00 PM 08-Feb-15 06:00 AM
1283 IM100840 Manway Opening, Provide Ventilation & Lighting 8h 09-Feb-15 12:00 PM 09-Feb-15 08:00 PM
1284 IM100845 Obtain Confined space permit 2h 09-Feb-15 08:00 PM 09-Feb-15 10:00 PM
1285 IM100847 Erect Internal Scaffolding 8h 09-Feb-15 10:00 PM 10-Feb-15 06:00 AM
1286 IM100850 Preliminary Inspection 4h 10-Feb-15 06:00 AM 10-Feb-15 10:00 AM
1287 IM100852 N.O.R.M. Survey by I.H. 1h 10-Feb-15 06:00 AM 10-Feb-15 07:00 AM
1288 IM100855 Cleaning & Repair 24h 17-Feb-15 12:00 AM 18-Feb-15 12:00 AM
1289 IM100860 Mist Eliminator Removal and Installation 30h 18-Feb-15 12:00 AM 19-Feb-15 06:00 AM
1290 IM100865 Remove Internal Scaffolding 4h 19-Feb-15 06:00 AM 19-Feb-15 10:00 AM
1291 IM100870 Final Inspection 6h 19-Feb-15 10:00 AM 19-Feb-15 04:00 PM
1292 IM100875 Manway Box-up 4h 19-Feb-15 04:00 PM 19-Feb-15 08:00 PM
1293 IM100880 De-Blinding & Close permit 18h 19-Feb-15 08:00 PM 20-Feb-15 02:00 PM
1294 CSE-INSP-D/N28CSE-INSP-D/N28 87h 21-Feb-15 06:00 AM 24-Feb-15 09:00 PM
1295 R15U-025-014 RC2-31-025-95-D-1227 DRUM - INT, EXT INSPECTIONR15U-025-014 RC2-31-025-95-D-1227 DRUM - INT, EXT INSPECTION 87h 21-Feb-15 06:00 AM 24-Feb-15 09:00 PM
1296 SHUTDOWNSHUTDOWN 87h 21-Feb-15 06:00 AM 24-Feb-15 09:00 PM
1297 OM100505 Verify LT&T and Obtain permit 8h 21-Feb-15 06:00 AM 21-Feb-15 02:00 PM
1298 OM100510 Mechanical Isolation & Blinding 24h 21-Feb-15 02:00 PM 22-Feb-15 02:00 PM
1299 OM100515 Manway Opening, Provide Ventilation & Lighting 8h 22-Feb-15 02:00 PM 22-Feb-15 10:00 PM
1300 OM100520 Obtain Confined space permit 2h 22-Feb-15 10:00 PM 23-Feb-15 12:00 AM
1301 OM100522 Erect Internal Scaffolding 8h 23-Feb-15 12:00 AM 23-Feb-15 08:00 AM
1302 OM100525 Preliminary Inspection 4h 23-Feb-15 08:00 AM 23-Feb-15 12:00 PM
1303 OM100530 Cleaning & Repair 18h 23-Feb-15 12:00 PM 24-Feb-15 06:00 AM
1304 OM100535 Remove Internal Scaffolding 4h 24-Feb-15 06:00 AM 24-Feb-15 10:00 AM
1305 OM100540 Final Inspection 4h 24-Feb-15 10:00 AM 24-Feb-15 02:00 PM
1306 OM100545 Manway Box-up 6h 24-Feb-15 02:00 PM 24-Feb-15 08:00 PM
1307 OM100550 De-Blinding & Close permit 1h 24-Feb-15 08:00 PM 24-Feb-15 09:00 PM
1308 CSE-INSP-D/N29CSE-INSP-D/N29 270h 17-Feb-15 06:00 AM 28-Feb-15 12:00 PM
1309 R15E-310-063 RC2-32-310-95-D-327 DRUM - INT, EXT INSPECTIONR15E-310-063 RC2-32-310-95-D-327 DRUM - INT, EXT INSPECTION 270h 17-Feb-15 06:00 AM 28-Feb-15 12:00 PM
1310 SHUTDOWNSHUTDOWN 270h 17-Feb-15 06:00 AM 28-Feb-15 12:00 PM
1311 IM101015 Verify LT&T and Obtain permit 6h 17-Feb-15 06:00 AM 17-Feb-15 12:00 PM
1312 IM101020 Mechanical Isolation & Blinding 18h 17-Feb-15 12:00 PM 18-Feb-15 06:00 AM
1313 IM101025 Manway Opening, Provide Ventilation & Lighting 8h 18-Feb-15 06:00 AM 18-Feb-15 02:00 PM
1314 IM101030 CUI Inspection & Repair 12h 18-Feb-15 06:00 AM 18-Feb-15 06:00 PM
1315 IM101035 Obtain Confined space permit 2h 18-Feb-15 02:00 PM 18-Feb-15 04:00 PM
1316 IM101037 Erect Internal Scaffolding 8h 18-Feb-15 04:00 PM 19-Feb-15 12:00 AM
1317 IM101040 Preliminary Inspection 6h 19-Feb-15 12:00 AM 19-Feb-15 06:00 AM
1318 IM101042 N.O.R.M. Survey by I.H. 1h 19-Feb-15 12:00 AM 19-Feb-15 01:00 AM
1319 IM101045 Cleaning & Repair 24h 19-Feb-15 06:00 AM 20-Feb-15 06:00 AM
1320 IM101050 Cartridges 104Nos Removal & Installation 36h 20-Feb-15 06:00 AM 21-Feb-15 06:00 PM
1321 IM101055 Remove Internal Scaffolding 4h 21-Feb-15 06:00 PM 21-Feb-15 10:00 PM
1322 IM101060 Final Inspection 6h 21-Feb-15 10:00 PM 22-Feb-15 04:00 AM
1323 IM101065 Manway Box-up 6h 22-Feb-15 04:00 AM 22-Feb-15 10:00 AM
1324 IM101070 De-Blinding & Close permit 18h 27-Feb-15 06:00 PM 28-Feb-15 12:00 PM
1325 CSE-INSP-D/N35CSE-INSP-D/N35 292h 12-Feb-15 06:00 AM 24-Feb-15 10:00 AM
1326 R15E-220-019 RC2-32-220-95-D-224 DRUM - INT, EXT, CUI INSPECTIONR15E-220-019 RC2-32-220-95-D-224 DRUM - INT, EXT, CUI INSPECTION 124h 12-Feb-15 06:00 AM 17-Feb-15 10:00 AM
1327 SHUTDOWNSHUTDOWN 124h 12-Feb-15 06:00 AM 17-Feb-15 10:00 AM
1328 IM100275 Verify LT&T and Obtain permit 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM
1329 IM100280 Mechanical Isolation & Blinding 24h 12-Feb-15 12:00 PM 13-Feb-15 12:00 PM
1330 IM100285 Manway Opening, Provide Ventilation & Lighting 8h 13-Feb-15 12:00 PM 13-Feb-15 08:00 PM
1331 IM100290 CUI Inspection & Repair 12h 13-Feb-15 12:00 PM 14-Feb-15 12:00 AM
1332 IM100295 Obtain Confined space permit 2h 13-Feb-15 08:00 PM 13-Feb-15 10:00 PM
1333 IM100297 Erect Internal Scaffolding 8h 13-Feb-15 10:00 PM 14-Feb-15 06:00 AM
1334 IM100300 Preliminary Inspection 4h 14-Feb-15 06:00 AM 14-Feb-15 10:00 AM
1335 IM100305 Cleaning & Repair 36h 14-Feb-15 10:00 AM 15-Feb-15 10:00 PM
1336 IM100310 Remove Internal Scaffolding 4h 15-Feb-15 10:00 PM 16-Feb-15 02:00 AM
1337 IM100315 Final Inspection 4h 16-Feb-15 02:00 AM 16-Feb-15 06:00 AM
1338 IM100320 Manway Box-up 4h 16-Feb-15 06:00 AM 16-Feb-15 10:00 AM
1339 IM100325 De-Blinding & Close permit 24h 16-Feb-15 10:00 AM 17-Feb-15 10:00 AM
1340 R15E-310-052 RC2-32-310-95-D-321 DRUM - INT, EXT, CUI INSPECTIONR15E-310-052 RC2-32-310-95-D-321 DRUM - INT, EXT, CUI INSPECTION 88h 20-Feb-15 06:00 PM 24-Feb-15 10:00 AM
1341 SHUTDOWNSHUTDOWN 88h 20-Feb-15 06:00 PM 24-Feb-15 10:00 AM
1342 IM100470 Verify LT&T and Obtain permit 4h 20-Feb-15 06:00 PM 20-Feb-15 10:00 PM
1343 IM100475 Mechanical Isolation & Blinding 8h 20-Feb-15 10:00 PM 21-Feb-15 06:00 AM
1344 IM100480 Manway Opening, Provide Ventilation & Lighting 8h 21-Feb-15 06:00 AM 21-Feb-15 02:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 21 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1345 IM100485 CUI Inspection & Repair 10h 21-Feb-15 06:00 AM 21-Feb-15 04:00 PM
1346 IM100490 Obtain Confined space permit 2h 21-Feb-15 02:00 PM 21-Feb-15 04:00 PM
1347 IM100492 Erect Internal Scaffolding 6h 21-Feb-15 04:00 PM 21-Feb-15 10:00 PM
1348 IM100495 Preliminary Inspection 3h 21-Feb-15 10:00 PM 22-Feb-15 01:00 AM
1349 IM100497 N.O.R.M. Survey by I.H. 1h 21-Feb-15 10:00 PM 21-Feb-15 11:00 PM
1350 IM100500 Cleaning & Repair 36h 22-Feb-15 01:00 AM 23-Feb-15 01:00 PM
1351 IM100505 Remove Internal Scaffolding 4h 23-Feb-15 01:00 PM 23-Feb-15 05:00 PM
1352 IM100510 Final Inspection 3h 23-Feb-15 05:00 PM 23-Feb-15 08:00 PM
1353 IM100515 Manway Box-up 4h 23-Feb-15 08:00 PM 24-Feb-15 12:00 AM
1354 IM100520 De-Blinding & Close permit 10h 24-Feb-15 12:00 AM 24-Feb-15 10:00 AM
1355 R15E-310-061 RC2-32-310-95-D-326 DRUM - INT, EXT INSPECTIONR15E-310-061 RC2-32-310-95-D-326 DRUM - INT, EXT INSPECTION 142h 16-Feb-15 06:00 AM 22-Feb-15 04:00 AM
1356 SHUTDOWNSHUTDOWN 142h 16-Feb-15 06:00 AM 22-Feb-15 04:00 AM
1357 IM100920 Verify LT&T and Obtain permit 6h 16-Feb-15 06:00 AM 16-Feb-15 12:00 PM
1358 IM100925 Mechanical Isolation & Blinding 18h 16-Feb-15 12:00 PM 17-Feb-15 06:00 AM
1359 IM100930 Manway Opening, Provide Ventilation & Lighting 8h 17-Feb-15 06:00 AM 17-Feb-15 02:00 PM
1360 IM100935 Obtain Confined space permit 2h 17-Feb-15 02:00 PM 17-Feb-15 04:00 PM
1361 IM100937 Erect Internal Scaffolding 8h 17-Feb-15 04:00 PM 18-Feb-15 12:00 AM
1362 IM100940 Preliminary Inspection 6h 18-Feb-15 12:00 AM 18-Feb-15 06:00 AM
1363 IM100945 Cleaning & Repair 24h 18-Feb-15 06:00 AM 19-Feb-15 06:00 AM
1364 IM100950 Mist Eliminator Removal and Installation 36h 19-Feb-15 06:00 AM 20-Feb-15 06:00 PM
1365 IM100955 Remove Internal Scaffolding 4h 20-Feb-15 06:00 PM 20-Feb-15 10:00 PM
1366 IM100960 Final Inspection 6h 20-Feb-15 10:00 PM 21-Feb-15 04:00 AM
1367 IM100965 Manway Box-up 6h 21-Feb-15 04:00 AM 21-Feb-15 10:00 AM
1368 IM100970 De-Blinding & Close permit 18h 21-Feb-15 10:00 AM 22-Feb-15 04:00 AM
1369 CUI-DRUM-D36CUI-DRUM-D36 252h 06-Feb-15 06:00 AM 26-Feb-15 06:00 PM
1370 R15E-500-007 RC2-32-500-95-D-525 DRUM - CUI INSPECTIONR15E-500-007 RC2-32-500-95-D-525 DRUM - CUI INSPECTION 20h 06-Feb-15 06:00 AM 07-Feb-15 02:00 PM
1371 SHUTDOWNSHUTDOWN 20h 06-Feb-15 06:00 AM 07-Feb-15 02:00 PM
1372 IM101665 Obtain Permit 2h 06-Feb-15 06:00 AM 06-Feb-15 08:00 AM
1373 IM101670 CUI Inspection & Repair 16h 06-Feb-15 08:00 AM 07-Feb-15 12:00 PM
1374 IM101672 Final Inspection 2h 07-Feb-15 12:00 PM 07-Feb-15 02:00 PM
1375 R15E-520-024 RC2-32-520-95-D-523A DRUM - EXT, CUI INSPECTIONR15E-520-024 RC2-32-520-95-D-523A DRUM - EXT, CUI INSPECTION 28h 07-Feb-15 12:00 PM 09-Feb-15 04:00 PM
1376 SHUTDOWNSHUTDOWN 28h 07-Feb-15 12:00 PM 09-Feb-15 04:00 PM
1377 IM102015 Obtain Permit 2h 07-Feb-15 12:00 PM 07-Feb-15 02:00 PM
1378 IM102020 CUI Inspection & Repair 24h 07-Feb-15 02:00 PM 09-Feb-15 02:00 PM
1379 IM102022 Final Inspection 2h 09-Feb-15 02:00 PM 09-Feb-15 04:00 PM
1380 R15E-520-025 RC2-32-520-95-D-523B DRUM - EXT, CUI INSPECTIONR15E-520-025 RC2-32-520-95-D-523B DRUM - EXT, CUI INSPECTION 28h 09-Feb-15 02:00 PM 11-Feb-15 06:00 PM
1381 SHUTDOWNSHUTDOWN 28h 09-Feb-15 02:00 PM 11-Feb-15 06:00 PM
1382 IM102060 Obtain Permit 2h 09-Feb-15 02:00 PM 09-Feb-15 04:00 PM
1383 IM102065 CUI Inspection & Repair 24h 09-Feb-15 04:00 PM 11-Feb-15 04:00 PM
1384 IM102067 Final Inspection 2h 11-Feb-15 04:00 PM 11-Feb-15 06:00 PM
1385 R15E-810-053 RC2-32-810-95-D-823 DRUM - EXT, CUI INSPECTIONR15E-810-053 RC2-32-810-95-D-823 DRUM - EXT, CUI INSPECTION 34h 22-Feb-15 06:00 AM 24-Feb-15 04:00 PM
1386 SHUTDOWNSHUTDOWN 34h 22-Feb-15 06:00 AM 24-Feb-15 04:00 PM
1387 IM102515 Obtain Permit 2h 22-Feb-15 06:00 AM 22-Feb-15 08:00 AM
1388 IM102520 CUI Inspection & Repair 30h 22-Feb-15 08:00 AM 24-Feb-15 02:00 PM
1389 IM102522 Final Inspection 2h 24-Feb-15 02:00 PM 24-Feb-15 04:00 PM
1390 R15E-820-027 RC2-32-820-95-D-824 DRUM - EXT, CUI INSPECTIONR15E-820-027 RC2-32-820-95-D-824 DRUM - EXT, CUI INSPECTION 28h 24-Feb-15 02:00 PM 26-Feb-15 06:00 PM
1391 SHUTDOWNSHUTDOWN 28h 24-Feb-15 02:00 PM 26-Feb-15 06:00 PM
1392 IM102560 Obtain Permit 2h 24-Feb-15 02:00 PM 24-Feb-15 04:00 PM
1393 IM102565 CUI Inspection & Repair 24h 24-Feb-15 04:00 PM 26-Feb-15 04:00 PM
1394 IM102567 Final Inspection 2h 26-Feb-15 04:00 PM 26-Feb-15 06:00 PM
1395 FILTERFILTER 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1396 CSE-MDA-D/N17CSE-MDA-D/N17 136h 12-Feb-15 04:00 PM 18-Feb-15 08:00 AM
1397 R15U-022-001 RC2-31-022-35-F-1202 FILTER - MEDIA REPLACEMENTR15U-022-001 RC2-31-022-35-F-1202 FILTER - MEDIA REPLACEMENT 136h 12-Feb-15 04:00 PM 18-Feb-15 08:00 AM
1398 SHUTDOWNSHUTDOWN 136h 12-Feb-15 04:00 PM 18-Feb-15 08:00 AM
1399 OM106310 Verify LT&T & Obtain Permit 4h 12-Feb-15 04:00 PM 12-Feb-15 08:00 PM
1400 OM106312 Mechanical isolation & blinding 8h 12-Feb-15 08:00 PM 13-Feb-15 04:00 AM
1401 OM106315 Open Top Manway 6h 13-Feb-15 04:00 AM 13-Feb-15 10:00 AM
1402 OM106317 Provide ventilation & lighting 2h 13-Feb-15 10:00 AM 13-Feb-15 12:00 PM
1403 OM106320 Obtain Confined space permit 2h 13-Feb-15 12:00 PM 13-Feb-15 02:00 PM
1404 OM106325 Removal of Media 12h 13-Feb-15 02:00 PM 14-Feb-15 02:00 AM
1405 OM106330 Load new Media 8h 17-Feb-15 08:00 AM 17-Feb-15 04:00 PM
1406 OM106335 Final Inspection before boxup 4h 17-Feb-15 04:00 PM 17-Feb-15 08:00 PM
1407 OM106340 Manway Box-up 4h 17-Feb-15 08:00 PM 18-Feb-15 12:00 AM
1408 OM106345 De-Blinding & Close work permit 8h 18-Feb-15 12:00 AM 18-Feb-15 08:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 22 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1409 R15U-022-002 RC2-31-022-35-F-1202 FILTER - INT, EXT INSPECTIONR15U-022-002 RC2-31-022-35-F-1202 FILTER - INT, EXT INSPECTION 136h 12-Feb-15 04:00 PM 18-Feb-15 08:00 AM
1410 SHUTDOWNSHUTDOWN 136h 12-Feb-15 04:00 PM 18-Feb-15 08:00 AM
1411 OM106230 Verify LT&T & Obtain Permit 4h 12-Feb-15 04:00 PM 12-Feb-15 08:00 PM
1412 OM106240 Open Manway 8h 13-Feb-15 04:00 AM 13-Feb-15 12:00 PM
1413 OM106245 Obtain Confined space permit 2h 13-Feb-15 12:00 PM 13-Feb-15 02:00 PM
1414 OM106250 Preliminary Inspection 4h 14-Feb-15 02:00 AM 14-Feb-15 06:00 AM
1415 OM106255 Erect Internal Scaffolding 4h 14-Feb-15 06:00 AM 14-Feb-15 10:00 AM
1416 OM106260 Cleaning & Repair 12h 14-Feb-15 10:00 AM 14-Feb-15 10:00 PM
1417 OM106265 Renew Mushroom Strainers 8h 14-Feb-15 10:00 PM 15-Feb-15 06:00 AM
1418 OM106270 Final Inspection after renew strainer 4h 15-Feb-15 06:00 AM 15-Feb-15 10:00 AM
1419 OM106275 Remove Internal Scaffolding 4h 15-Feb-15 10:00 AM 15-Feb-15 02:00 PM
1420 OM106280 Manway Box-up 4h 17-Feb-15 08:00 PM 18-Feb-15 12:00 AM
1421 OM106285 De-Blinding & Close work permit 8h 18-Feb-15 12:00 AM 18-Feb-15 08:00 AM
1422 BLN-STR-D/N61BLN-STR-D/N61 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1423 R15E-310-013 RC2-32-310-35-F-301 INT, EXT CLEANING & INSPECTIONR15E-310-013 RC2-32-310-35-F-301 INT, EXT CLEANING & INSPECTION 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1424 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1425 IM115240 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
1426 IM115245 Drop spool with strainer & Fix end blind 18h 07-Feb-15 08:00 AM 08-Feb-15 02:00 AM
1427 IM115250 Shift strainer to cleaning area 2h 08-Feb-15 02:00 AM 08-Feb-15 04:00 AM
1428 IM115255 Clean, Inspect & Repair as per ERG 24h 08-Feb-15 04:00 AM 09-Feb-15 04:00 AM
1429 IM115260 Shift strainer to job site 2h 09-Feb-15 04:00 AM 09-Feb-15 06:00 AM
1430 IM115265 Drop end blind, Fix spool with strainer & close PTW 18h 01-Mar-15 04:00 AM 01-Mar-15 10:00 PM
1431 R15E-310-016 RC2-32-310-35-F-310 INT, EXT CLEANING & INSPECTIONR15E-310-016 RC2-32-310-35-F-310 INT, EXT CLEANING & INSPECTION 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1432 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1433 IM115420 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
1434 IM115425 Drop spool with strainer & Fix end blind 12h 07-Feb-15 08:00 AM 07-Feb-15 08:00 PM
1435 IM115430 Shift strainer to cleaning area 2h 07-Feb-15 08:00 PM 07-Feb-15 10:00 PM
1436 IM115435 Clean, Inspect & Repair as per ERG 24h 07-Feb-15 10:00 PM 08-Feb-15 10:00 PM
1437 IM115440 Shift strainer to job site 2h 08-Feb-15 10:00 PM 09-Feb-15 12:00 AM
1438 IM115445 Drop end blind, Fix spool with strainer & close PTW 12h 01-Mar-15 10:00 AM 01-Mar-15 10:00 PM
1439 R15E-310-017 RC2-32-310-35-F-311 INT, EXT CLEANING & INSPECTIONR15E-310-017 RC2-32-310-35-F-311 INT, EXT CLEANING & INSPECTION 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1440 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1441 IM115480 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
1442 IM115485 Drop spool with strainer & Fix end blind 12h 07-Feb-15 08:00 AM 07-Feb-15 08:00 PM
1443 IM115490 Shift strainer to cleaning area 2h 07-Feb-15 08:00 PM 07-Feb-15 10:00 PM
1444 IM115495 Clean, Inspect & Repair as per ERG 24h 07-Feb-15 10:00 PM 08-Feb-15 10:00 PM
1445 IM115500 Shift strainer to job site 2h 08-Feb-15 10:00 PM 09-Feb-15 12:00 AM
1446 IM115505 Drop end blind, Fix spool with strainer & close PTW 12h 01-Mar-15 10:00 AM 01-Mar-15 10:00 PM
1447 R15E-320-005 RC2-32-320-35-F-312 FILTER - CLEANING, INSPECTION & CATRIDGE REPL.R15E-320-005 RC2-32-320-35-F-312 FILTER - CLEANING, INSPECTION & CATRIDGE REPL. 74h 12-Feb-15 06:00 AM 15-Feb-15 08:00 AM
1448 SHUTDOWNSHUTDOWN 74h 12-Feb-15 06:00 AM 15-Feb-15 08:00 AM
1449 IM115535 Verify LT&T and Obtain PTW 2h 12-Feb-15 06:00 AM 12-Feb-15 08:00 AM
1450 IM115540 Drop top spool & blind as per blindlist 10h 12-Feb-15 08:00 AM 12-Feb-15 06:00 PM
1451 IM115545 Open top dish head & manhole 8h 12-Feb-15 06:00 PM 13-Feb-15 02:00 AM
1452 IM115550 Obtain CSE permit 2h 13-Feb-15 02:00 AM 13-Feb-15 04:00 AM
1453 IM115555 Clean, Inspect & Repair as per ERG 18h 13-Feb-15 04:00 AM 13-Feb-15 10:00 PM
1454 IM115560 Replace all filter cadridges 12h 13-Feb-15 10:00 PM 14-Feb-15 10:00 AM
1455 IM115565 Fix back top dish head & manhole 12h 14-Feb-15 10:00 AM 14-Feb-15 10:00 PM
1456 IM115570 De-Blind, Fix back top spool & close PTW 10h 14-Feb-15 10:00 PM 15-Feb-15 08:00 AM
1457 R15E-820-067 RC2-32-820-16-C-802 ERC SUCTION STRAINER - INT, EXT INSPECTIONR15E-820-067 RC2-32-820-16-C-802 ERC SUCTION STRAINER - INT, EXT INSPECTION 412h 10-Feb-15 06:00 AM 27-Feb-15 10:00 AM
1458 SHUTDOWNSHUTDOWN 412h 10-Feb-15 06:00 AM 27-Feb-15 10:00 AM
1459 IM115660 Verify LT&T and Obtain PTW 2h 10-Feb-15 06:00 AM 10-Feb-15 08:00 AM
1460 IM115665 Drop spool with strainer & Fix end blind 18h 10-Feb-15 08:00 AM 11-Feb-15 02:00 AM
1461 IM115670 Shift strainers to cleaning area 2h 11-Feb-15 02:00 AM 11-Feb-15 04:00 AM
1462 IM115675 Clean, Inspect & Repair as per ERG 24h 11-Feb-15 04:00 AM 12-Feb-15 04:00 AM
1463 IM115680 Shift strainers to job site 2h 12-Feb-15 04:00 AM 12-Feb-15 06:00 AM
1464 IM115685 Drop end blind, Fix spool with strainer & close PTW 18h 26-Feb-15 04:00 PM 27-Feb-15 10:00 AM
1465 BLN-STR-D/N62BLN-STR-D/N62 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1466 R15E-310-014 RC2-32-310-35-F-308 INT, EXT CLEANING & INSPECTIONR15E-310-014 RC2-32-310-35-F-308 INT, EXT CLEANING & INSPECTION 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1467 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1468 IM115300 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
1469 IM115305 Drop spool with strainer & Fix end blind 18h 07-Feb-15 08:00 AM 08-Feb-15 02:00 AM
1470 IM115310 Shift strainer to cleaning area 2h 08-Feb-15 02:00 AM 08-Feb-15 04:00 AM
1471 IM115315 Clean, Inspect & Repair as per ERG 24h 08-Feb-15 04:00 AM 09-Feb-15 04:00 AM
1472 IM115320 Shift strainer to job site 2h 09-Feb-15 04:00 AM 09-Feb-15 06:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 23 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1473 IM115325 Drop end blind, Fix spool with strainer & close PTW 18h 01-Mar-15 04:00 AM 01-Mar-15 10:00 PM
1474 R15E-310-015 RC2-32-310-35-F-309 INT, EXT CLEANING & INSPECTIONR15E-310-015 RC2-32-310-35-F-309 INT, EXT CLEANING & INSPECTION 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1475 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1476 IM115360 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
1477 IM115365 Drop spool with strainer & Fix end blind 18h 07-Feb-15 08:00 AM 08-Feb-15 02:00 AM
1478 IM115370 Shift strainer to cleaning area 2h 08-Feb-15 02:00 AM 08-Feb-15 04:00 AM
1479 IM115375 Clean, Inspect & Repair as per ERG 24h 08-Feb-15 04:00 AM 09-Feb-15 04:00 AM
1480 IM115380 Shift strainer to job site 2h 09-Feb-15 04:00 AM 09-Feb-15 06:00 AM
1481 IM115385 Drop end blind & Fix strainer with spool 18h 01-Mar-15 04:00 AM 01-Mar-15 10:00 PM
1482 R15E-810-099 RC2-32-810-16-C-801 PRC SUCTION STRAINER - INT, EXT INSPECTIONR15E-810-099 RC2-32-810-16-C-801 PRC SUCTION STRAINER - INT, EXT INSPECTION 440h 09-Feb-15 06:00 AM 27-Feb-15 02:00 PM
1483 SHUTDOWNSHUTDOWN 440h 09-Feb-15 06:00 AM 27-Feb-15 02:00 PM
1484 IM115600 Verify LT&T and Obtain PTW 2h 09-Feb-15 06:00 AM 09-Feb-15 08:00 AM
1485 IM115605 Drop spool with strainer & Fix end blind 24h 09-Feb-15 08:00 AM 10-Feb-15 08:00 AM
1486 IM115610 Shift strainer to cleaning area 2h 10-Feb-15 08:00 AM 10-Feb-15 10:00 AM
1487 IM115615 Clean, Inspect & Repair as per ERG 48h 10-Feb-15 10:00 AM 12-Feb-15 10:00 AM
1488 IM115620 Shift strainer to job site 2h 12-Feb-15 10:00 AM 12-Feb-15 12:00 PM
1489 IM115625 Drop end blind & Fix strainer with spool 24h 26-Feb-15 02:00 PM 27-Feb-15 02:00 PM
1490 PIPING-MECH-D65PIPING-MECH-D65 98h 16-Feb-15 08:00 AM 24-Feb-15 10:00 AM
1491 R15U-097-009 RC2-32-151-35-F-225 ETHANE FILTER - I/L & O/L VALVES SERVICINGR15U-097-009 RC2-32-151-35-F-225 ETHANE FILTER - I/L & O/L VALVES SERVICING 98h 16-Feb-15 08:00 AM 24-Feb-15 10:00 AM
1492 SHUTDOWNSHUTDOWN 98h 16-Feb-15 08:00 AM 24-Feb-15 10:00 AM
1493 OM105500 Verify LT&T and Obtain PTW 2h 16-Feb-15 08:00 AM 16-Feb-15 10:00 AM
1494 OM105505 Blinding as per blindlist. 3h 16-Feb-15 10:00 AM 16-Feb-15 01:00 PM
1495 OM105510 Drop I/L, O/L valves & provide end blinds 12h 16-Feb-15 01:00 PM 17-Feb-15 01:00 PM
1496 OM105515 Shift removed valves to valve shop for servicing 4h 17-Feb-15 01:00 PM 17-Feb-15 05:00 PM
1497 OM105520 Servicing of valve 48h 17-Feb-15 05:00 PM 21-Feb-15 05:00 PM
1498 OM105525 Shift the serviced valves from valve shop 3h 21-Feb-15 05:00 PM 22-Feb-15 08:00 AM
1499 OM105530 Remove end blinds & install the valves 12h 23-Feb-15 07:00 AM 24-Feb-15 07:00 AM
1500 OM105535 De-Blinding & close PTW 3h 24-Feb-15 07:00 AM 24-Feb-15 10:00 AM
1501 TWR D/N116TWR D/N116 268h 09-Feb-15 06:00 AM 20-Feb-15 10:00 AM
1502 R15E-210-024 TWR-32-0171 - PROVISION OF DUAL FILTER AT P-203A/B D/CR15E-210-024 TWR-32-0171 - PROVISION OF DUAL FILTER AT P-203A/B D/C 268h 09-Feb-15 06:00 AM 20-Feb-15 10:00 AM
1503 SHUTDOWNSHUTDOWN 268h 09-Feb-15 06:00 AM 20-Feb-15 10:00 AM
1504 IP100115 LT&T and PTW 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM
1505 IP100120 Insulation removal 12h 10-Feb-15 10:00 AM 10-Feb-15 10:00 PM
1506 IP100125 Marking on existing lines as per approved isometric drawings 8h 10-Feb-15 10:00 PM 11-Feb-15 06:00 AM
1507 IP100130 Cold cutting of the existing lines at tie in points 16h 11-Feb-15 06:00 AM 11-Feb-15 10:00 PM
1508 IP100135 Allignment and fittup of tie in points 24h 11-Feb-15 02:00 PM 12-Feb-15 02:00 PM
1509 IP100140 Inspection of fittup 4h 12-Feb-15 02:00 PM 12-Feb-15 06:00 PM
1510 IP100145 Complete welding of tie in points 48h 12-Feb-15 06:00 PM 14-Feb-15 06:00 PM
1511 IP100150 NDT of all welded tie in joints 16h 14-Feb-15 02:00 PM 15-Feb-15 06:00 AM
1512 IP100155 Hydrotesting 24h 15-Feb-15 06:00 AM 16-Feb-15 06:00 AM
1513 IP100160 Deblinding & reinstatment 12h 16-Feb-15 06:00 AM 16-Feb-15 06:00 PM
1514 IP100165 Paint application to all joints 36h 16-Feb-15 06:00 PM 18-Feb-15 06:00 AM
1515 IP100170 Insulation installation 36h 18-Feb-15 06:00 AM 19-Feb-15 06:00 PM
1516 IP100175 PSSR 4h 19-Feb-15 06:00 PM 19-Feb-15 10:00 PM
1517 IP100180 System blinding 24h 09-Feb-15 10:00 AM 10-Feb-15 10:00 AM
1518 IP100185 System deblinding 12h 19-Feb-15 10:00 PM 20-Feb-15 10:00 AM
1519 IP103375 Installation of Instruments 8h 16-Feb-15 06:00 AM 16-Feb-15 02:00 PM
1520 IP103380 Connection of instument tubing and cable termination 30h 16-Feb-15 02:00 PM 17-Feb-15 08:00 PM
1521 IP103385 Calibration / Leak test 10h 17-Feb-15 08:00 PM 18-Feb-15 06:00 AM
1522 IP103390 Loop test / Function test 12h 18-Feb-15 06:00 AM 18-Feb-15 06:00 PM
1523 SUMPSUMP 64h 14-Feb-15 09:00 AM 17-Feb-15 01:00 AM
1524 CSE-INSP-D/N30CSE-INSP-D/N30 64h 14-Feb-15 09:00 AM 17-Feb-15 01:00 AM
1525 R15U-022-006 RC2-31-022-95-S-1228 SUMP - INT INSPECTIONR15U-022-006 RC2-31-022-95-S-1228 SUMP - INT INSPECTION 64h 14-Feb-15 09:00 AM 17-Feb-15 01:00 AM
1526 SHUTDOWNSHUTDOWN 64h 14-Feb-15 09:00 AM 17-Feb-15 01:00 AM
1527 OM100105 Verify LT&T and Obtain permit 4h 14-Feb-15 09:00 AM 14-Feb-15 01:00 PM
1528 OM100110 Mechanical Isolation & Blinding 8h 14-Feb-15 01:00 PM 14-Feb-15 09:00 PM
1529 OM100115 Clean the Sump with Super Sucker/ Manual 8h 14-Feb-15 09:00 PM 15-Feb-15 05:00 AM
1530 OM100117 Obtain CSE permit 2h 15-Feb-15 05:00 AM 15-Feb-15 07:00 AM
1531 OM100120 Erect Internal Scaffolding 8h 15-Feb-15 07:00 AM 15-Feb-15 03:00 PM
1532 OM100125 Preliminary Inspection 4h 15-Feb-15 03:00 PM 15-Feb-15 07:00 PM
1533 OM100130 Cleaning & Repair 12h 15-Feb-15 07:00 PM 16-Feb-15 07:00 AM
1534 OM100135 Remove Internal Scaffolding 4h 16-Feb-15 07:00 AM 16-Feb-15 11:00 AM
1535 OM100140 Final Inspection 4h 16-Feb-15 11:00 AM 16-Feb-15 03:00 PM
1536 OM100145 De-Blinding & Close permit 10h 16-Feb-15 03:00 PM 17-Feb-15 01:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 24 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1537 TANKTANK 604h 07-Feb-15 06:00 AM 04-Mar-15 10:00 AM
1538 CSE-INSP-D/N21CSE-INSP-D/N21 388h 11-Feb-15 06:00 AM 27-Feb-15 10:00 AM
1539 R15U-080-005 RC2-31-080-95-TK-341 TANK - INT, EXT INSPECTIONR15U-080-005 RC2-31-080-95-TK-341 TANK - INT, EXT INSPECTION 388h 11-Feb-15 06:00 AM 27-Feb-15 10:00 AM
1540 SHUTDOWNSHUTDOWN 388h 11-Feb-15 06:00 AM 27-Feb-15 10:00 AM
1541 OM101520 Verify LT&T and Obtain permit 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM
1542 OM101525 Mechanical Isolation & Blinding 12h 11-Feb-15 10:00 AM 11-Feb-15 10:00 PM
1543 OM101530 Manway Opening & Provide Ventilation & Lighting 8h 11-Feb-15 10:00 PM 12-Feb-15 06:00 AM
1544 OM101535 CUI Inspection & Repair 24h 11-Feb-15 10:00 PM 12-Feb-15 10:00 PM
1545 OM101540 Obtain Confined space permit 2h 12-Feb-15 06:00 AM 12-Feb-15 08:00 AM
1546 OM101542 Erect Internal Scaffolding 18h 12-Feb-15 08:00 AM 13-Feb-15 02:00 AM
1547 OM101545 Preliminary Inspection 6h 13-Feb-15 02:00 AM 13-Feb-15 08:00 AM
1548 OM101550 Cleaning, Repair & Inspect 300h 13-Feb-15 08:00 AM 25-Feb-15 08:00 PM
1549 OM101555 Remove Internal Scaffolding 12h 25-Feb-15 08:00 PM 26-Feb-15 08:00 AM
1550 OM101560 Final Inspection 6h 26-Feb-15 08:00 AM 26-Feb-15 02:00 PM
1551 OM101565 Manway Box-up 8h 26-Feb-15 02:00 PM 26-Feb-15 10:00 PM
1552 OM101570 De-Blinding & Close permit 12h 26-Feb-15 10:00 PM 27-Feb-15 10:00 AM
1553 CSE-INSP-D/N26CSE-INSP-D/N26 57h 16-Feb-15 06:00 AM 18-Feb-15 03:00 PM
1554 R15U-022-007 RC2-31-022-95-TK-1263 TANK - INT, EXT INSPECTIONR15U-022-007 RC2-31-022-95-TK-1263 TANK - INT, EXT INSPECTION 57h 16-Feb-15 06:00 AM 18-Feb-15 03:00 PM
1555 SHUTDOWNSHUTDOWN 57h 16-Feb-15 06:00 AM 18-Feb-15 03:00 PM
1556 OM100175 Verify LT&T and Obtain permit 4h 16-Feb-15 06:00 AM 16-Feb-15 10:00 AM
1557 OM100180 Mechanical Isolation & Blinding 6h 16-Feb-15 10:00 AM 16-Feb-15 04:00 PM
1558 OM100185 Manway Opening, Provide Ventilation & Lighting 6h 16-Feb-15 04:00 PM 16-Feb-15 10:00 PM
1559 OM100190 Obtain Confined space permit 2h 16-Feb-15 10:00 PM 17-Feb-15 12:00 AM
1560 OM100192 Erect Internal Scaffolding 6h 17-Feb-15 12:00 AM 17-Feb-15 06:00 AM
1561 OM100195 Preliminary Inspection 3h 17-Feb-15 06:00 AM 17-Feb-15 09:00 AM
1562 OM100200 Cleaning, Repair & Inspect 12h 17-Feb-15 09:00 AM 17-Feb-15 09:00 PM
1563 OM100205 Remove Internal Scaffolding 4h 17-Feb-15 09:00 PM 18-Feb-15 01:00 AM
1564 OM100210 Final Inspection 3h 18-Feb-15 01:00 AM 18-Feb-15 04:00 AM
1565 OM100215 Manway Box-up 3h 18-Feb-15 04:00 AM 18-Feb-15 07:00 AM
1566 OM100220 De-Blinding & Close permit 8h 18-Feb-15 07:00 AM 18-Feb-15 03:00 PM
1567 R15U-022-008 RC2-31-022-95-TK-1264 TANK - INT, EXT INSPECTIONR15U-022-008 RC2-31-022-95-TK-1264 TANK - INT, EXT INSPECTION 57h 16-Feb-15 06:00 AM 18-Feb-15 03:00 PM
1568 SHUTDOWNSHUTDOWN 57h 16-Feb-15 06:00 AM 18-Feb-15 03:00 PM
1569 OM100255 Verify LT&T and Obtain permit 4h 16-Feb-15 06:00 AM 16-Feb-15 10:00 AM
1570 OM100260 Mechanical Isolation & Blinding 6h 16-Feb-15 10:00 AM 16-Feb-15 04:00 PM
1571 OM100265 Manway Opening, Provide Ventilation & Lighting 6h 16-Feb-15 04:00 PM 16-Feb-15 10:00 PM
1572 OM100270 Obtain Confined space permit 2h 16-Feb-15 10:00 PM 17-Feb-15 12:00 AM
1573 OM100272 Erect Internal Scaffolding 6h 17-Feb-15 12:00 AM 17-Feb-15 06:00 AM
1574 OM100275 Preliminary Inspection 3h 17-Feb-15 06:00 AM 17-Feb-15 09:00 AM
1575 OM100280 Cleaning & Repair 12h 17-Feb-15 09:00 AM 17-Feb-15 09:00 PM
1576 OM100285 Remove Internal Scaffolding 4h 17-Feb-15 09:00 PM 18-Feb-15 01:00 AM
1577 OM100290 Final Inspection 3h 18-Feb-15 01:00 AM 18-Feb-15 04:00 AM
1578 OM100295 Manway Box-up 3h 18-Feb-15 04:00 AM 18-Feb-15 07:00 AM
1579 OM100300 De-Blinding & Close permit 8h 18-Feb-15 07:00 AM 18-Feb-15 03:00 PM
1580 CSE-INSP-D/N29CSE-INSP-D/N29 154h 11-Feb-15 06:00 AM 17-Feb-15 04:00 PM
1581 R15U-075-008 RC2-31-075-95-TK-1148 TANK - INT, EXT INSPECTIONR15U-075-008 RC2-31-075-95-TK-1148 TANK - INT, EXT INSPECTION 154h 11-Feb-15 06:00 AM 17-Feb-15 04:00 PM
1582 SHUTDOWNSHUTDOWN 154h 11-Feb-15 06:00 AM 17-Feb-15 04:00 PM
1583 OM101365 Verify LT&T and Obtain permit 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM
1584 OM101370 Mechanical Isolation & Blinding 8h 11-Feb-15 10:00 AM 11-Feb-15 06:00 PM
1585 OM101375 Manway Opening, Provide Ventilation & Lighting 8h 11-Feb-15 06:00 PM 12-Feb-15 02:00 AM
1586 OM101380 Obtain Confined space permit 2h 12-Feb-15 02:00 AM 12-Feb-15 04:00 AM
1587 OM101382 Erect Internal Scaffolding 24h 12-Feb-15 04:00 AM 13-Feb-15 04:00 AM
1588 OM101385 Preliminary Inspection 6h 13-Feb-15 04:00 AM 13-Feb-15 10:00 AM
1589 OM101390 Cleaning & Repair 60h 13-Feb-15 10:00 AM 15-Feb-15 10:00 PM
1590 OM101395 Remove Internal Scaffolding 18h 15-Feb-15 10:00 PM 16-Feb-15 04:00 PM
1591 OM101400 Final Inspection 6h 16-Feb-15 04:00 PM 16-Feb-15 10:00 PM
1592 OM101405 Manway Box-up 8h 16-Feb-15 10:00 PM 17-Feb-15 06:00 AM
1593 OM101410 De-Blinding & Close permit 10h 17-Feb-15 06:00 AM 17-Feb-15 04:00 PM
1594 CSE-INSP-D/N30CSE-INSP-D/N30 462h 09-Feb-15 06:00 AM 28-Feb-15 12:00 PM
1595 R15U-060-007 RC2-31-060-95-TK-1213 TANK - INT, EXT INSPECTIONR15U-060-007 RC2-31-060-95-TK-1213 TANK - INT, EXT INSPECTION 55h 12-Feb-15 06:00 AM 14-Feb-15 01:00 PM
1596 SHUTDOWNSHUTDOWN 55h 12-Feb-15 06:00 AM 14-Feb-15 01:00 PM
1597 OM100755 Verify LT&T and Obtain permit 4h 12-Feb-15 06:00 AM 12-Feb-15 10:00 AM
1598 OM100760 Mechanical Isolation & Blinding 6h 12-Feb-15 10:00 AM 12-Feb-15 04:00 PM
1599 OM100765 Manway Opening, Provide Ventilation & Lighting 6h 12-Feb-15 04:00 PM 12-Feb-15 10:00 PM
1600 OM100770 Obtain Confined space permit 2h 12-Feb-15 10:00 PM 13-Feb-15 12:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 25 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1601 OM100772 Erect Internal Scaffolding 4h 13-Feb-15 12:00 AM 13-Feb-15 04:00 AM
1602 OM100775 Preliminary Inspection 3h 13-Feb-15 04:00 AM 13-Feb-15 07:00 AM
1603 OM100780 Cleaning & Repair 12h 13-Feb-15 07:00 AM 13-Feb-15 07:00 PM
1604 OM100785 Remove Internal Scaffolding 4h 13-Feb-15 07:00 PM 13-Feb-15 11:00 PM
1605 OM100790 Final Inspection 3h 13-Feb-15 11:00 PM 14-Feb-15 02:00 AM
1606 OM100795 Manway Box-up 3h 14-Feb-15 02:00 AM 14-Feb-15 05:00 AM
1607 OM100800 De-Blinding & Close permit 8h 14-Feb-15 05:00 AM 14-Feb-15 01:00 PM
1608 R15U-075-006 RC2-31-075-95-TK-1144 TANK - INT, EXT INSPECTIONR15U-075-006 RC2-31-075-95-TK-1144 TANK - INT, EXT INSPECTION 462h 09-Feb-15 06:00 AM 28-Feb-15 12:00 PM
1609 SHUTDOWNSHUTDOWN 462h 09-Feb-15 06:00 AM 28-Feb-15 12:00 PM
1610 OM101215 Verify LT&T and Obtain permit 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM
1611 OM101220 Mechanical Isolation & Blinding 8h 09-Feb-15 10:00 AM 09-Feb-15 06:00 PM
1612 OM101225 Manway Opening, Provide Ventilation & Lighting 12h 09-Feb-15 06:00 PM 10-Feb-15 06:00 AM
1613 OM101230 Obtain Confined space permit 2h 10-Feb-15 06:00 AM 10-Feb-15 08:00 AM
1614 OM101232 Erect Internal Scaffolding 24h 10-Feb-15 08:00 AM 11-Feb-15 08:00 AM
1615 OM101235 Preliminary Inspection 6h 11-Feb-15 08:00 AM 11-Feb-15 02:00 PM
1616 OM101240 Cleaning & Repair 360h 11-Feb-15 02:00 PM 26-Feb-15 02:00 PM
1617 OM101245 Remove Internal Scaffolding 18h 26-Feb-15 02:00 PM 27-Feb-15 08:00 AM
1618 OM101250 Final Inspection 6h 27-Feb-15 08:00 AM 27-Feb-15 02:00 PM
1619 OM101255 Manway Box-up 12h 27-Feb-15 02:00 PM 28-Feb-15 02:00 AM
1620 OM101260 De-Blinding & Close permit 10h 28-Feb-15 02:00 AM 28-Feb-15 12:00 PM
1621 CSE-INSP-D/N31CSE-INSP-D/N31 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1622 R15U-074-002 RC2-31-074-95-TK-1152 TANK - INT, EXT INSPECTION & REPAIRR15U-074-002 RC2-31-074-95-TK-1152 TANK - INT, EXT INSPECTION & REPAIR 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1623 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1624 OM101135 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM
1625 OM101140 Mechanical Isolation & Blinding 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM
1626 OM101145 Manway Opening, Provide Ventilation & Lighting 12h 07-Feb-15 06:00 PM 08-Feb-15 06:00 AM
1627 OM101150 Obtain Confined space permit 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM
1628 OM101152 Erect Internal Scaffolding 24h 08-Feb-15 08:00 AM 09-Feb-15 08:00 AM
1629 OM101155 Preliminary Inspection 12h 09-Feb-15 08:00 AM 09-Feb-15 08:00 PM
1630 OM101160 Cleaning & Repair 120h 09-Feb-15 08:00 PM 14-Feb-15 08:00 PM
1631 OM101162 Dismantle Existing Primary & Secondary Seals 72h 12-Feb-15 08:00 PM 15-Feb-15 08:00 PM
1632 OM101165 Renew the Primary & Secondary Seals 168h 15-Feb-15 08:00 PM 22-Feb-15 08:00 PM
1633 OM101170 Remove Internal Scaffolding 18h 22-Feb-15 08:00 PM 23-Feb-15 02:00 PM
1634 OM101175 Final Inspection 8h 23-Feb-15 02:00 PM 23-Feb-15 10:00 PM
1635 OM101180 Side Manway Box-up 12h 23-Feb-15 10:00 PM 24-Feb-15 10:00 AM
1636 OM101182 Leak checking of seal by floatation (water) 72h 24-Feb-15 10:00 AM 27-Feb-15 10:00 AM
1637 OM101185 Draining & Pre-commissioning 48h 27-Feb-15 10:00 AM 01-Mar-15 10:00 AM
1638 OM101187 De-Blinding & Close permit 12h 01-Mar-15 10:00 AM 01-Mar-15 10:00 PM
1639 CSE-INSP-D/N32CSE-INSP-D/N32 532h 10-Feb-15 06:00 AM 04-Mar-15 10:00 AM
1640 R15U-060-006 RC2-31-060-95-TK-1212 TANK - INT, EXT INSPECTIONR15U-060-006 RC2-31-060-95-TK-1212 TANK - INT, EXT INSPECTION 55h 02-Mar-15 03:00 AM 04-Mar-15 10:00 AM
1641 SHUTDOWNSHUTDOWN 55h 02-Mar-15 03:00 AM 04-Mar-15 10:00 AM
1642 OM100670 Verify LT&T and Obtain permit 4h 02-Mar-15 03:00 AM 02-Mar-15 07:00 AM
1643 OM100675 Mechanical Isolation & Blinding 6h 02-Mar-15 07:00 AM 02-Mar-15 01:00 PM
1644 OM100680 Manway Opening, Provide Ventilation & Lighting 6h 02-Mar-15 01:00 PM 02-Mar-15 07:00 PM
1645 OM100685 Obtain Confined space permit 2h 02-Mar-15 07:00 PM 02-Mar-15 09:00 PM
1646 OM100687 Erect Internal Scaffolding 4h 02-Mar-15 09:00 PM 03-Mar-15 01:00 AM
1647 OM100690 Preliminary Inspection 3h 03-Mar-15 01:00 AM 03-Mar-15 04:00 AM
1648 OM100695 Cleaning & Repair 12h 03-Mar-15 04:00 AM 03-Mar-15 04:00 PM
1649 OM100700 Remove Internal Scaffolding 4h 03-Mar-15 04:00 PM 03-Mar-15 08:00 PM
1650 OM100705 Final Inspection 3h 03-Mar-15 08:00 PM 03-Mar-15 11:00 PM
1651 OM100710 Manway Box-up 3h 03-Mar-15 11:00 PM 04-Mar-15 02:00 AM
1652 OM100715 De-Blinding & Close permit 8h 04-Mar-15 02:00 AM 04-Mar-15 10:00 AM
1653 R15U-060-008 RC2-31-060-95-TK-1244 TANK - INT, EXT INSPECTIONR15U-060-008 RC2-31-060-95-TK-1244 TANK - INT, EXT INSPECTION 468h 10-Feb-15 06:00 AM 01-Mar-15 06:00 PM
1654 SHUTDOWNSHUTDOWN 468h 10-Feb-15 06:00 AM 01-Mar-15 06:00 PM
1655 OM100835 Verify LT&T and Obtain permit 6h 10-Feb-15 06:00 AM 10-Feb-15 12:00 PM
1656 OM100840 Mechanical Isolation & Blinding 10h 10-Feb-15 12:00 PM 10-Feb-15 10:00 PM
1657 OM100845 Manway Opening, Provide Ventilation & Lighting 12h 10-Feb-15 10:00 PM 11-Feb-15 10:00 AM
1658 OM100850 Obtain Confined space permit 2h 11-Feb-15 10:00 AM 11-Feb-15 12:00 PM
1659 OM100852 Erect Internal Scaffolding 24h 11-Feb-15 12:00 PM 12-Feb-15 12:00 PM
1660 OM100855 Preliminary Inspection 6h 12-Feb-15 12:00 PM 12-Feb-15 06:00 PM
1661 OM100857 N.O.R.M. Survey by I.H. 1h 12-Feb-15 12:00 PM 12-Feb-15 01:00 PM
1662 OM100860 Cleaning & Repair 360h 12-Feb-15 06:00 PM 27-Feb-15 06:00 PM
1663 OM100865 Remove Internal Scaffolding 18h 27-Feb-15 06:00 PM 28-Feb-15 12:00 PM
1664 OM100870 Final Inspection 6h 28-Feb-15 12:00 PM 28-Feb-15 06:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 26 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1665 OM100875 Manway Box-up 12h 28-Feb-15 06:00 PM 01-Mar-15 06:00 AM
1666 OM100880 De-Blinding & Close permit 12h 01-Mar-15 06:00 AM 01-Mar-15 06:00 PM
1667 R15U-060-013 RC2-31-060-95-TK-1248 TANK - INSPECTION & REPAIR WORKR15U-060-013 RC2-31-060-95-TK-1248 TANK - INSPECTION & REPAIR WORK 77h 27-Feb-15 06:00 PM 02-Mar-15 11:00 PM
1668 SHUTDOWNSHUTDOWN 77h 27-Feb-15 06:00 PM 02-Mar-15 11:00 PM
1669 OM100910 Verify LT&T and Obtain permit 6h 27-Feb-15 06:00 PM 28-Feb-15 12:00 AM
1670 OM100915 Mechanical Isolation & Blinding 8h 28-Feb-15 12:00 AM 28-Feb-15 08:00 AM
1671 OM100920 Manway Opening, Provide Ventilation & Lighting 6h 28-Feb-15 08:00 AM 28-Feb-15 02:00 PM
1672 OM100925 Obtain Confined space permit 2h 28-Feb-15 02:00 PM 28-Feb-15 04:00 PM
1673 OM100927 Erect Internal Scaffolding 8h 28-Feb-15 04:00 PM 01-Mar-15 12:00 AM
1674 OM100930 Preliminary Inspection 3h 01-Mar-15 12:00 AM 01-Mar-15 03:00 AM
1675 OM100935 Cleaning & Repair 24h 01-Mar-15 03:00 AM 02-Mar-15 03:00 AM
1676 OM100940 Remove Internal Scaffolding 4h 02-Mar-15 03:00 AM 02-Mar-15 07:00 AM
1677 OM100945 Final Inspection 3h 02-Mar-15 07:00 AM 02-Mar-15 10:00 AM
1678 OM100950 Manway Box-up 3h 02-Mar-15 10:00 AM 02-Mar-15 01:00 PM
1679 OM100955 De-Blinding & Close permit 10h 02-Mar-15 01:00 PM 02-Mar-15 11:00 PM
1680 CSE-INSP-D/N33CSE-INSP-D/N33 154h 11-Feb-15 06:00 AM 17-Feb-15 04:00 PM
1681 R15U-075-007 RC2-31-075-95-TK-1147 TANK - INT, EXT INSPECTIONR15U-075-007 RC2-31-075-95-TK-1147 TANK - INT, EXT INSPECTION 154h 11-Feb-15 06:00 AM 17-Feb-15 04:00 PM
1682 SHUTDOWNSHUTDOWN 154h 11-Feb-15 06:00 AM 17-Feb-15 04:00 PM
1683 OM101290 Verify LT&T and Obtain permit 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM
1684 OM101295 Mechanical Isolation & Blinding 8h 11-Feb-15 10:00 AM 11-Feb-15 06:00 PM
1685 OM101300 Manway Opening, Provide Ventilation & Lighting 8h 11-Feb-15 06:00 PM 12-Feb-15 02:00 AM
1686 OM101305 Obtain Confined space permit 2h 12-Feb-15 02:00 AM 12-Feb-15 04:00 AM
1687 OM101307 Erect Internal Scaffolding 24h 12-Feb-15 04:00 AM 13-Feb-15 04:00 AM
1688 OM101310 Preliminary Inspection 6h 13-Feb-15 04:00 AM 13-Feb-15 10:00 AM
1689 OM101315 Cleaning & Repair 60h 13-Feb-15 10:00 AM 15-Feb-15 10:00 PM
1690 OM101320 Remove Internal Scaffolding 18h 15-Feb-15 10:00 PM 16-Feb-15 04:00 PM
1691 OM101325 Final Inspection 6h 16-Feb-15 04:00 PM 16-Feb-15 10:00 PM
1692 OM101330 Manway Box-up 8h 16-Feb-15 10:00 PM 17-Feb-15 06:00 AM
1693 OM101335 De-Blinding & Close Work permit 10h 17-Feb-15 06:00 AM 17-Feb-15 04:00 PM
1694 CSE-INSP-D/N34CSE-INSP-D/N34 432h 12-Feb-15 06:00 AM 02-Mar-15 06:00 AM
1695 R15U-071-015 RC2-31-071-95-TK-1140 TANK - INT, EXT INSPECTION & REPAIRR15U-071-015 RC2-31-071-95-TK-1140 TANK - INT, EXT INSPECTION & REPAIR 432h 12-Feb-15 06:00 AM 02-Mar-15 06:00 AM
1696 SHUTDOWNSHUTDOWN 432h 12-Feb-15 06:00 AM 02-Mar-15 06:00 AM
1697 OM100985 Verify LT&T and Obtain permit 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM
1698 OM100990 Mechanical Isolation & Blinding 12h 12-Feb-15 12:00 PM 13-Feb-15 12:00 AM
1699 OM100995 Manway Opening, Provide Ventilation & Lighting 8h 13-Feb-15 12:00 AM 13-Feb-15 08:00 AM
1700 OM101000 Obtain Confined space permit 4h 13-Feb-15 08:00 AM 13-Feb-15 12:00 PM
1701 OM101002 Erect Internal Scaffolding 36h 13-Feb-15 12:00 PM 15-Feb-15 12:00 AM
1702 OM101005 Preliminary Inspection 6h 15-Feb-15 12:00 AM 15-Feb-15 06:00 AM
1703 OM101007 N.O.R.M. Survey by I.H. 1h 15-Feb-15 12:00 AM 15-Feb-15 01:00 AM
1704 OM101010 Cleaning & Repair 312h 15-Feb-15 06:00 AM 28-Feb-15 06:00 AM
1705 OM101015 Remove Internal Scaffolding 24h 28-Feb-15 06:00 AM 01-Mar-15 06:00 AM
1706 OM101020 Final Inspection 6h 01-Mar-15 06:00 AM 01-Mar-15 12:00 PM
1707 OM101025 Manway Box-up 6h 01-Mar-15 12:00 PM 01-Mar-15 06:00 PM
1708 OM101030 De-Blinding & Close permit 12h 01-Mar-15 06:00 PM 02-Mar-15 06:00 AM
1709 MISC-MECH-D/N59MISC-MECH-D/N59 72h 21-Feb-15 08:00 AM 24-Feb-15 08:00 AM
1710 R15U-060-019 RC2-31-060-95-TK-1249 TANK - SCUM BOX INTERNAL REPAIRR15U-060-019 RC2-31-060-95-TK-1249 TANK - SCUM BOX INTERNAL REPAIR 72h 21-Feb-15 08:00 AM 24-Feb-15 08:00 AM
1711 SHUTDOWNSHUTDOWN 72h 21-Feb-15 08:00 AM 24-Feb-15 08:00 AM
1712 OM101825 Verify LT&T and Obtain permit 2h 21-Feb-15 08:00 AM 21-Feb-15 10:00 AM
1713 OM101830 Mechanical Isolation & Blinding 8h 21-Feb-15 10:00 AM 21-Feb-15 06:00 PM
1714 OM101835 Providing a Ventilation & Lighting 6h 21-Feb-15 06:00 PM 22-Feb-15 12:00 AM
1715 OM101840 Obtain Confined space permit 4h 22-Feb-15 12:00 AM 22-Feb-15 04:00 AM
1716 OM101843 Erect Internal Scaffolding 6h 22-Feb-15 04:00 AM 22-Feb-15 10:00 AM
1717 OM101845 Preliminary Inspection 4h 22-Feb-15 10:00 AM 22-Feb-15 02:00 PM
1718 OM101850 Cleaning & Repair 24h 22-Feb-15 02:00 PM 23-Feb-15 02:00 PM
1719 OM101855 Remove Internal Scaffolding 6h 23-Feb-15 02:00 PM 23-Feb-15 08:00 PM
1720 OM101860 Final Inspection 4h 23-Feb-15 08:00 PM 24-Feb-15 12:00 AM
1721 OM101865 De-Blinding & Close PTW 8h 24-Feb-15 12:00 AM 24-Feb-15 08:00 AM
1722 TWR D/N114TWR D/N114 310h 10-Feb-15 06:00 AM 23-Feb-15 04:00 AM
1723 R15U-060-012 TWR-31-0189 - TK-1244 MODIFICATIONSR15U-060-012 TWR-31-0189 - TK-1244 MODIFICATIONS 310h 10-Feb-15 06:00 AM 23-Feb-15 04:00 AM
1724 SHUTDOWNSHUTDOWN 310h 10-Feb-15 06:00 AM 23-Feb-15 04:00 AM
1725 OP100365 LT&T AND PTW 4h 10-Feb-15 06:00 AM 10-Feb-15 10:00 AM
1726 OP100370 Marking on tank 12h 11-Feb-15 10:00 AM 11-Feb-15 10:00 PM
1727 OP100375 Cutting on existing tank sheet 24h 11-Feb-15 10:00 PM 12-Feb-15 10:00 PM
1728 OP100380 Allignment & fittup of new tank sheet 20h 12-Feb-15 10:00 PM 13-Feb-15 06:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 27 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1729 OP100385 Inspection of fittup 10h 13-Feb-15 06:00 PM 14-Feb-15 04:00 AM
1730 OP100390 Complete welding of tie in points 36h 14-Feb-15 04:00 AM 15-Feb-15 04:00 PM
1731 OP100395 NDT of all welded tie in joints 16h 15-Feb-15 04:00 PM 16-Feb-15 08:00 AM
1732 OP100400 Welding of 21 Nos. of stoppers inside the tank. 72h 16-Feb-15 08:00 AM 19-Feb-15 08:00 AM
1733 OP100405 Paint application to all joints 72h 19-Feb-15 08:00 AM 22-Feb-15 08:00 AM
1734 OP100410 PSSR 8h 22-Feb-15 08:00 AM 22-Feb-15 04:00 PM
1735 OP100415 System blinding 24h 10-Feb-15 10:00 AM 11-Feb-15 10:00 AM
1736 OP100420 System deblinding 12h 22-Feb-15 04:00 PM 23-Feb-15 04:00 AM
1737 TOWERTOWER 708h 06-Feb-15 06:00 AM 07-Mar-15 06:00 PM
1738 CSE-MDA-D/N18CSE-MDA-D/N18 432h 09-Feb-15 06:00 AM 27-Feb-15 06:00 AM
1739 R15E-210-018 RC2-32-210-95-T-201 QT - CHEMICAL CLEANINGR15E-210-018 RC2-32-210-95-T-201 QT - CHEMICAL CLEANING 114h 09-Feb-15 06:00 AM 14-Feb-15 12:00 AM
1740 SHUTDOWNSHUTDOWN 114h 09-Feb-15 06:00 AM 14-Feb-15 12:00 AM
1741 IM100125 Verify LT&T and Obtain permit 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
1742 IM100130 Mechanical Isolation & Blinding 36h 09-Feb-15 12:00 PM 11-Feb-15 12:00 AM
1743 IM100135 Chemical Cleaning Preparations 12h 11-Feb-15 12:00 AM 11-Feb-15 12:00 PM
1744 IM100140 Chemical Cleaning & Close permit 60h 11-Feb-15 12:00 PM 14-Feb-15 12:00 AM
1745 R15E-210-019 RC2-32-210-95-T-201 QT - INSPECTION & PACKING REPLACEMENTR15E-210-019 RC2-32-210-95-T-201 QT - INSPECTION & PACKING REPLACEMENT 432h 09-Feb-15 06:00 AM 27-Feb-15 06:00 AM
1746 SHUTDOWNSHUTDOWN 432h 09-Feb-15 06:00 AM 27-Feb-15 06:00 AM
1747 IM100180 Verify LT&T and Obtain permit 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
1748 IM100185 Mechanical Isolation & Blinding 36h 09-Feb-15 12:00 PM 11-Feb-15 12:00 AM
1749 IM100190 Manway Opening & Providing a Ventilation & Lighting 12h 14-Feb-15 12:00 AM 14-Feb-15 12:00 PM
1750 IM100195 Obtain Confined space permit 2h 14-Feb-15 12:00 PM 14-Feb-15 02:00 PM
1751 IM100197 Erect Internal Scaffolding 6h 14-Feb-15 02:00 PM 14-Feb-15 08:00 PM
1752 IM100200 Preliminary Inspection 6h 14-Feb-15 08:00 PM 15-Feb-15 02:00 AM
1753 IM100203 N.O.R.M. Survey by I.H. 1h 14-Feb-15 08:00 PM 14-Feb-15 09:00 PM
1754 IM100205 Packing Removal 72h 15-Feb-15 02:00 AM 18-Feb-15 02:00 AM
1755 IM100210 Cleaning & Repair & Trays replacement if any 144h 18-Feb-15 02:00 AM 24-Feb-15 02:00 AM
1756 IM100212 Remove Internal Scaffolding 6h 24-Feb-15 02:00 AM 24-Feb-15 08:00 AM
1757 IM100220 Final Inspection 6h 25-Feb-15 08:00 AM 25-Feb-15 02:00 PM
1758 IM100225 Manway Box-up 4h 25-Feb-15 02:00 PM 25-Feb-15 06:00 PM
1759 IM100230 De-Blinding & Close permit 36h 25-Feb-15 06:00 PM 27-Feb-15 06:00 AM
1760 CSE-REF-D/N19CSE-REF-D/N19 636h 09-Feb-15 06:00 AM 07-Mar-15 06:00 PM
1761 R15U-050-003 RC2-31-050-36-C-1224 THERMAL OXIDISER INSPECTION & REFRACTORY REPAIRR15U-050-003 RC2-31-050-36-C-1224 THERMAL OXIDISER INSPECTION & REFRACTORY REPAIR 636h 09-Feb-15 06:00 AM 07-Mar-15 06:00 PM
1762 SHUTDOWNSHUTDOWN 636h 09-Feb-15 06:00 AM 07-Mar-15 06:00 PM
1763 OM100585 Verify LT&T and Obtain permit 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM
1764 OM100590 Mechanical Isolation & Blinding 8h 09-Feb-15 10:00 AM 09-Feb-15 06:00 PM
1765 OM100595 Stack Manway Opening, Provide Ventilation & Lighting 8h 09-Feb-15 06:00 PM 10-Feb-15 02:00 AM
1766 OM100600 Obtain Confined space permit 2h 10-Feb-15 02:00 AM 10-Feb-15 04:00 AM
1767 OM100602 Erect Internal Scaffolding 8h 10-Feb-15 04:00 AM 10-Feb-15 12:00 PM
1768 OM100605 Preliminary Inspection 4h 10-Feb-15 12:00 PM 10-Feb-15 04:00 PM
1769 OM100610 Cleaning, Refractory Repair, Installation in Bottom & Above Segments 576h 10-Feb-15 04:00 PM 06-Mar-15 04:00 PM
1770 OM100615 Remove Internal Scaffolding 8h 06-Mar-15 04:00 PM 07-Mar-15 12:00 AM
1771 OM100620 Final Inspection 6h 07-Mar-15 12:00 AM 07-Mar-15 06:00 AM
1772 OM100625 Manway Box-up 4h 07-Mar-15 06:00 AM 07-Mar-15 10:00 AM
1773 OM100630 De-Blinding & Close permit 8h 07-Mar-15 10:00 AM 07-Mar-15 06:00 PM
1774 CSE-INSP-D/N22CSE-INSP-D/N22 270h 06-Feb-15 06:00 AM 17-Feb-15 12:00 PM
1775 R15E-510-035 RC2-32-510-95-T-501 TOWER - INT, EXT, CUI INSPECTIONR15E-510-035 RC2-32-510-95-T-501 TOWER - INT, EXT, CUI INSPECTION 270h 06-Feb-15 06:00 AM 17-Feb-15 12:00 PM
1776 SHUTDOWNSHUTDOWN 270h 06-Feb-15 06:00 AM 17-Feb-15 12:00 PM
1777 IM101810 Verify LT&T and Obtain permit 6h 06-Feb-15 06:00 AM 06-Feb-15 12:00 PM
1778 IM101815 Mechanical Isolation & Blinding 18h 06-Feb-15 12:00 PM 07-Feb-15 06:00 AM
1779 IM101820 Manway Opening, Provide Ventilation & Lighting 12h 07-Feb-15 06:00 AM 07-Feb-15 06:00 PM
1780 IM101825 CUI Inspection & Repair 48h 07-Feb-15 06:00 AM 09-Feb-15 06:00 AM
1781 IM101830 Obtain Confined space permit 8h 07-Feb-15 06:00 PM 08-Feb-15 02:00 AM
1782 IM101832 Erect Internal Scaffolding 2h 08-Feb-15 02:00 AM 08-Feb-15 04:00 AM
1783 IM101835 Preliminary Inspection 12h 08-Feb-15 04:00 AM 08-Feb-15 04:00 PM
1784 IM101840 Cleaning, Repair & Inspect 36h 08-Feb-15 04:00 PM 10-Feb-15 04:00 AM
1785 IM101845 Trays Manways 41Nos Opening, Repair & Boxup 168h 08-Feb-15 04:00 PM 15-Feb-15 04:00 PM
1786 IM101850 Remove Internal Scaffolding 4h 15-Feb-15 04:00 PM 15-Feb-15 08:00 PM
1787 IM101855 Final Inspection 12h 15-Feb-15 08:00 PM 16-Feb-15 08:00 AM
1788 IM101860 Manway Box-up 10h 16-Feb-15 08:00 AM 16-Feb-15 06:00 PM
1789 IM101865 De-Blinding & Close permit 18h 16-Feb-15 06:00 PM 17-Feb-15 12:00 PM
1790 R15E-510-036 RC2-32-510-95-T-501 TOWER - INSPN. & EVALUATION. OF POLYMER BUILD-UPR15E-510-036 RC2-32-510-95-T-501 TOWER - INSPN. & EVALUATION. OF POLYMER BUILD-UP 20h 08-Feb-15 06:00 AM 09-Feb-15 02:00 AM
1791 SHUTDOWNSHUTDOWN 20h 08-Feb-15 06:00 AM 09-Feb-15 02:00 AM
1792 IM101887 Obtain Confined space permit 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 28 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1793 IM101890 Inspect - Polymer Build up 4h 08-Feb-15 08:00 AM 08-Feb-15 12:00 PM
1794 IM101895 Carryout repair as per recommendations 12h 08-Feb-15 12:00 PM 09-Feb-15 12:00 AM
1795 IM101997 Close permit 2h 09-Feb-15 12:00 AM 09-Feb-15 02:00 AM
1796 CSE-INSP-D/N23CSE-INSP-D/N23 288h 09-Feb-15 06:00 AM 21-Feb-15 06:00 AM
1797 R15E-220-021 RC2-32-220-95-T-202 TOWER - INT, EXT, CUI INSPECTIONR15E-220-021 RC2-32-220-95-T-202 TOWER - INT, EXT, CUI INSPECTION 288h 09-Feb-15 06:00 AM 21-Feb-15 06:00 AM
1798 SHUTDOWNSHUTDOWN 288h 09-Feb-15 06:00 AM 21-Feb-15 06:00 AM
1799 IM100370 Verify LT&T and Obtain permit 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
1800 IM100375 Mechanical Isolation & Blinding 12h 09-Feb-15 12:00 PM 10-Feb-15 12:00 AM
1801 IM100380 Manway Opening, Provide Ventilation & Lighting 8h 10-Feb-15 12:00 AM 10-Feb-15 08:00 AM
1802 IM100385 CUI Inspection & Repair 24h 10-Feb-15 12:00 AM 11-Feb-15 12:00 AM
1803 IM100390 Obtain Confined space permit 2h 10-Feb-15 08:00 AM 10-Feb-15 10:00 AM
1804 IM100392 Erect Internal Scaffolding 8h 10-Feb-15 10:00 AM 10-Feb-15 06:00 PM
1805 IM100395 Preliminary Inspection 6h 10-Feb-15 06:00 PM 11-Feb-15 12:00 AM
1806 IM100397 N.O.R.M. Survey by I.H. 1h 10-Feb-15 06:00 PM 10-Feb-15 07:00 PM
1807 IM100400 Cleaning, Repair & Inspect 24h 11-Feb-15 12:00 AM 12-Feb-15 12:00 AM
1808 IM100405 Trays 12Nos Removal & Installation 192h 12-Feb-15 12:00 AM 20-Feb-15 12:00 AM
1809 IM100410 Remove Internal Scaffolding 4h 20-Feb-15 12:00 AM 20-Feb-15 04:00 AM
1810 IM100415 Final Inspection 8h 20-Feb-15 04:00 AM 20-Feb-15 12:00 PM
1811 IM100420 Manway Box-up 6h 20-Feb-15 12:00 PM 20-Feb-15 06:00 PM
1812 IM100425 De-Blinding & Close permit 12h 20-Feb-15 06:00 PM 21-Feb-15 06:00 AM
1813 CSE-INSP-D/N24CSE-INSP-D/N24 450h 06-Feb-15 06:00 AM 25-Feb-15 12:00 AM
1814 R15E-520-031 RC2-32-520-95-T-502 TOWER - INSPN. & EVALUATION FOR OIL & FOULINGR15E-520-031 RC2-32-520-95-T-502 TOWER - INSPN. & EVALUATION FOR OIL & FOULING 24h 10-Feb-15 08:00 PM 11-Feb-15 08:00 PM
1815 SHUTDOWNSHUTDOWN 24h 10-Feb-15 08:00 PM 11-Feb-15 08:00 PM
1816 IM102190 Inspect - Oil Fouling 6h 10-Feb-15 08:00 PM 11-Feb-15 02:00 AM
1817 IM102195 Carrout repair as per recommendations 18h 11-Feb-15 02:00 AM 11-Feb-15 08:00 PM
1818 R15E-520-034 RC2-32-520-95-T-502 TOWER - INT, EXT, CUI INSPECTIONR15E-520-034 RC2-32-520-95-T-502 TOWER - INT, EXT, CUI INSPECTION 450h 06-Feb-15 06:00 AM 25-Feb-15 12:00 AM
1819 SHUTDOWNSHUTDOWN 450h 06-Feb-15 06:00 AM 25-Feb-15 12:00 AM
1820 IM102110 Verify LT&T and Obtain permit 12h 06-Feb-15 06:00 AM 06-Feb-15 06:00 PM
1821 IM102115 Mechanical Isolation & Blinding 72h 06-Feb-15 06:00 PM 09-Feb-15 06:00 PM
1822 IM102120 Manway Opening, Provide Ventilation & Lighting 12h 09-Feb-15 06:00 PM 10-Feb-15 06:00 AM
1823 IM102125 CUI Inspection & Repair 48h 09-Feb-15 06:00 PM 11-Feb-15 06:00 PM
1824 IM102130 Obtain Confined space permit 2h 10-Feb-15 06:00 AM 10-Feb-15 08:00 AM
1825 IM102132 Erect Internal Scaffolding 12h 10-Feb-15 08:00 AM 10-Feb-15 08:00 PM
1826 IM102135 Preliminary Inspection 8h 10-Feb-15 08:00 PM 11-Feb-15 04:00 AM
1827 IM102137 N.O.R.M. Survey by I.H. 1h 10-Feb-15 08:00 PM 10-Feb-15 09:00 PM
1828 IM102140 Cleaning, Repair & Inspect 144h 11-Feb-15 04:00 AM 17-Feb-15 04:00 AM
1829 IM102145 Trays 145Nos Manways Opening & Box up 96h 17-Feb-15 04:00 AM 21-Feb-15 04:00 AM
1830 IM102150 Remove Internal Scaffolding 6h 21-Feb-15 04:00 AM 21-Feb-15 10:00 AM
1831 IM102155 Final Inspection 8h 21-Feb-15 10:00 AM 21-Feb-15 06:00 PM
1832 IM102160 Manway Box-up 6h 21-Feb-15 06:00 PM 22-Feb-15 12:00 AM
1833 IM102165 De-Blinding & Close permit 72h 22-Feb-15 12:00 AM 25-Feb-15 12:00 AM
1834 CSE-INSP-D/N25CSE-INSP-D/N25 362h 08-Feb-15 06:00 AM 23-Feb-15 08:00 AM
1835 R15E-330-014 RC2-32-330-95-T-301 TOWER - INT, EXT, CUI INSPECTIONR15E-330-014 RC2-32-330-95-T-301 TOWER - INT, EXT, CUI INSPECTION 362h 08-Feb-15 06:00 AM 23-Feb-15 08:00 AM
1836 SHUTDOWNSHUTDOWN 362h 08-Feb-15 06:00 AM 23-Feb-15 08:00 AM
1837 IM101565 Verify LT&T and Obtain permit 6h 08-Feb-15 06:00 AM 08-Feb-15 12:00 PM
1838 IM101570 Mechanical Isolation & Blinding 12h 08-Feb-15 12:00 PM 09-Feb-15 12:00 AM
1839 IM101575 Manway Opening, Provide Ventilation & Lighting 12h 09-Feb-15 12:00 AM 09-Feb-15 12:00 PM
1840 IM101580 CUI Inspection & Repair 24h 09-Feb-15 12:00 AM 10-Feb-15 12:00 AM
1841 IM101585 Obtain Confined space permit 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM
1842 IM101587 Erect Internal Scaffolding 8h 09-Feb-15 02:00 PM 09-Feb-15 10:00 PM
1843 IM101590 Preliminary Inspection 6h 09-Feb-15 10:00 PM 10-Feb-15 04:00 AM
1844 IM101595 37 Trays Manways opening, Cleaning, Repair & Manway Box up 60h 10-Feb-15 04:00 AM 12-Feb-15 04:00 PM
1845 IM101600 Strong Acid Chimney Tray & One Tray below that Removal & Installation 174h 12-Feb-15 04:00 PM 19-Feb-15 10:00 PM
1846 IM101605 Leak Testing both Stong & Weak Acid Chimney Trays 48h 19-Feb-15 10:00 PM 21-Feb-15 10:00 PM
1847 IM101610 Remove Internal Scaffolding 6h 21-Feb-15 10:00 PM 22-Feb-15 04:00 AM
1848 IM101615 Final Inspection 8h 22-Feb-15 04:00 AM 22-Feb-15 12:00 PM
1849 IM101620 Manway Box-up 8h 22-Feb-15 12:00 PM 22-Feb-15 08:00 PM
1850 IM101625 De-Blinding & Close permit 12h 22-Feb-15 08:00 PM 23-Feb-15 08:00 AM
1851 CSE-INSP-D/N26CSE-INSP-D/N26 260h 07-Feb-15 06:00 AM 18-Feb-15 02:00 AM
1852 R15E-610-010 RC2-32-610-95-T-601 TOWER - INSPN. & EVALUATION FOR POLYMER BUILDUPR15E-610-010 RC2-32-610-95-T-601 TOWER - INSPN. & EVALUATION FOR POLYMER BUILDUP 16h 09-Feb-15 06:00 AM 09-Feb-15 10:00 PM
1853 SHUTDOWNSHUTDOWN 16h 09-Feb-15 06:00 AM 09-Feb-15 10:00 PM
1854 IM102300 Inspect - Polymer Build up 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM
1855 IM102305 Carrout repair as per recommendations 12h 09-Feb-15 10:00 AM 09-Feb-15 10:00 PM
1856 R15E-610-011 RC2-32-610-95-T-601 TOWER - INT, EXT, CUI INSPECTIONR15E-610-011 RC2-32-610-95-T-601 TOWER - INT, EXT, CUI INSPECTION 260h 07-Feb-15 06:00 AM 18-Feb-15 02:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 29 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1857 SHUTDOWNSHUTDOWN 260h 07-Feb-15 06:00 AM 18-Feb-15 02:00 AM
1858 IM102220 Verify LT&T and Obtain permit 8h 07-Feb-15 06:00 AM 07-Feb-15 02:00 PM
1859 IM102225 Mechanical Isolation & Blinding 18h 07-Feb-15 02:00 PM 08-Feb-15 08:00 AM
1860 IM102230 Manway Opening, Provide Ventilation & Lighting 12h 08-Feb-15 08:00 AM 08-Feb-15 08:00 PM
1861 IM102235 CUI Inspection & Repair 48h 08-Feb-15 08:00 AM 10-Feb-15 08:00 AM
1862 IM102240 Obtain Confined space permit 2h 08-Feb-15 08:00 PM 08-Feb-15 10:00 PM
1863 IM102242 Erect Internal Scaffolding 8h 08-Feb-15 10:00 PM 09-Feb-15 06:00 AM
1864 IM102245 Preliminary Inspection 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM
1865 IM102250 Cleaning & Repair 96h 09-Feb-15 12:00 PM 13-Feb-15 12:00 PM
1866 IM102255 Trays 44Nos Manways Opening & Box up 72h 13-Feb-15 12:00 PM 16-Feb-15 12:00 PM
1867 IM102260 Remove Internal Scaffolding 6h 16-Feb-15 12:00 PM 16-Feb-15 06:00 PM
1868 IM102265 Final Inspection 6h 16-Feb-15 06:00 PM 17-Feb-15 12:00 AM
1869 IM102270 Manway Box-up 8h 17-Feb-15 12:00 AM 17-Feb-15 08:00 AM
1870 IM102275 De-Blinding & Close permit 18h 17-Feb-15 08:00 AM 18-Feb-15 02:00 AM
1871 CUI-DRUM-D36CUI-DRUM-D36 124h 11-Feb-15 04:00 PM 22-Feb-15 08:00 AM
1872 R15E-620-027 RC2-32-620-95-T-602 TOWER - CUI INSPECTIONR15E-620-027 RC2-32-620-95-T-602 TOWER - CUI INSPECTION 28h 19-Feb-15 04:00 PM 22-Feb-15 08:00 AM
1873 SHUTDOWNSHUTDOWN 28h 19-Feb-15 04:00 PM 22-Feb-15 08:00 AM
1874 IM102325 Obtain Permit 2h 19-Feb-15 04:00 PM 19-Feb-15 06:00 PM
1875 IM102330 CUI Inspection & Repair 24h 20-Feb-15 06:00 AM 21-Feb-15 06:00 PM
1876 IM102332 Final Inspection 2h 22-Feb-15 06:00 AM 22-Feb-15 08:00 AM
1877 R15E-710-044 RC2-32-710-95-T-701 TOWER - CUI INSPECTIONR15E-710-044 RC2-32-710-95-T-701 TOWER - CUI INSPECTION 50h 11-Feb-15 04:00 PM 15-Feb-15 06:00 PM
1878 SHUTDOWNSHUTDOWN 50h 11-Feb-15 04:00 PM 15-Feb-15 06:00 PM
1879 IM102435 Obtain permit 6h 11-Feb-15 04:00 PM 12-Feb-15 10:00 AM
1880 IM102450 CUI Inspection & Repair 36h 12-Feb-15 10:00 AM 15-Feb-15 10:00 AM
1881 IM102465 Final Inspection 8h 15-Feb-15 10:00 AM 15-Feb-15 06:00 PM
1882 TWR D/N99TWR D/N99 77h 19-Feb-15 02:00 AM 22-Feb-15 07:00 AM
1883 R15E-330-016 TWR-32-0163 - CIRCULATING CAUSTIC FLOW METERSR15E-330-016 TWR-32-0163 - CIRCULATING CAUSTIC FLOW METERS 77h 19-Feb-15 02:00 AM 22-Feb-15 07:00 AM
1884 SHUTDOWNSHUTDOWN 77h 19-Feb-15 02:00 AM 22-Feb-15 07:00 AM
1885 IP101115 LT&T and PTW 4h 19-Feb-15 10:00 PM 20-Feb-15 02:00 AM
1886 IP101120 PSSR 5h 21-Feb-15 06:00 PM 21-Feb-15 11:00 PM
1887 IP101125 Replacement of 02 Nos. of 8" flow meter 12h 20-Feb-15 06:00 AM 20-Feb-15 06:00 PM
1888 IP101130 System blinding 24h 19-Feb-15 02:00 AM 20-Feb-15 02:00 AM
1889 IP101135 System deblinding 8h 21-Feb-15 11:00 PM 22-Feb-15 07:00 AM
1890 IP103320 Removal of Cable Connections 4h 20-Feb-15 02:00 AM 20-Feb-15 06:00 AM
1891 IP103325 Cable Glanding and Termination 8h 20-Feb-15 06:00 PM 21-Feb-15 02:00 AM
1892 IP103330 Calibration / Leak test / Function Tes t 16h 21-Feb-15 02:00 AM 21-Feb-15 06:00 PM
1893 TWR D/N100TWR D/N100 262h 15-Feb-15 06:00 AM 26-Feb-15 04:00 AM
1894 R15E-420-012 TWR-32-0200 - DEMETHANIZER IMPROVEMENT PROJECTR15E-420-012 TWR-32-0200 - DEMETHANIZER IMPROVEMENT PROJECT 262h 15-Feb-15 06:00 AM 26-Feb-15 04:00 AM
1895 SHUTDOWNSHUTDOWN 262h 15-Feb-15 06:00 AM 26-Feb-15 04:00 AM
1896 IP101385 LT&T and PTW 4h 15-Feb-15 06:00 AM 15-Feb-15 10:00 AM
1897 IP101390 Insulation removal 12h 16-Feb-15 10:00 AM 16-Feb-15 10:00 PM
1898 IP101395 Marking on existing lines as per approved isometric drawings 16h 16-Feb-15 10:00 PM 17-Feb-15 02:00 PM
1899 IP101400 Cold cutting of the existing lines at tie in points 24h 17-Feb-15 06:00 AM 18-Feb-15 06:00 AM
1900 IP101405 Allignment and fittup of tie in points 24h 17-Feb-15 10:00 PM 18-Feb-15 10:00 PM
1901 IP101410 Inspection of fittup 12h 18-Feb-15 02:00 PM 19-Feb-15 02:00 AM
1902 IP101415 Complete welding of tie in points 48h 18-Feb-15 02:00 AM 20-Feb-15 02:00 AM
1903 IP101420 NDT of all welded tie in joints 16h 19-Feb-15 10:00 PM 20-Feb-15 02:00 PM
1904 IP101425 Hydrotesting 24h 21-Feb-15 06:00 AM 22-Feb-15 06:00 AM
1905 IP101430 Deblinding & reinstatment 12h 23-Feb-15 06:00 PM 24-Feb-15 06:00 AM
1906 IP101435 Paint application to all joints 16h 24-Feb-15 06:00 AM 24-Feb-15 10:00 PM
1907 IP101440 Insulation installation 8h 24-Feb-15 10:00 PM 25-Feb-15 06:00 AM
1908 IP101445 PSSR 10h 25-Feb-15 06:00 AM 25-Feb-15 04:00 PM
1909 IP101450 Erection & welding of pipe supports 16h 20-Feb-15 02:00 PM 21-Feb-15 06:00 AM
1910 IP101455 Hot tapping 36h 22-Feb-15 06:00 AM 23-Feb-15 06:00 PM
1911 IP101460 System blinding 24h 15-Feb-15 10:00 AM 16-Feb-15 10:00 AM
1912 IP101465 System deblinding 12h 25-Feb-15 04:00 PM 26-Feb-15 04:00 AM
1913 IP103260 Installation of Instruments 12h 22-Feb-15 06:00 AM 22-Feb-15 06:00 PM
1914 IP103265 Connection of instument tubing and cable termination 24h 22-Feb-15 06:00 PM 23-Feb-15 06:00 PM
1915 IP103270 Calibration / Leak test 14h 23-Feb-15 06:00 PM 24-Feb-15 08:00 AM
1916 IP103275 Loop test / Function test 16h 24-Feb-15 08:00 AM 25-Feb-15 12:00 AM
1917 ROTATING EQUIPMENTROTATING EQUIPMENT 616h 04-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1918 ROT-CGC-MP-D/N53ROT-CGC-MP-D/N53 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1919 R15E-310-119 RC2-32-310-16-CC-301B CGC MP COMPRESSOR - MAJOR O/HR15E-310-119 RC2-32-310-16-CC-301B CGC MP COMPRESSOR - MAJOR O/H 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1920 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 30 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1921 IM116670 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
1922 IM116675 Blinding as per blindlist 24h 07-Feb-15 08:00 AM 08-Feb-15 08:00 AM
1923 IM116680 Remove necessary pipes & inst. lines 10h 08-Feb-15 08:00 AM 08-Feb-15 06:00 PM
1924 IM116685 Remove coupling guard - Turbine to MP 4h 08-Feb-15 08:00 AM 08-Feb-15 12:00 PM
1925 IM116690 Check & Record Turbine to MP alignment 4h 08-Feb-15 12:00 PM 08-Feb-15 04:00 PM
1926 IM116695 Remove coupling spacer - Turbine to MP 6h 08-Feb-15 04:00 PM 08-Feb-15 10:00 PM
1927 IM116700 Remove coupling guard - MP to LP 4h 08-Feb-15 10:00 PM 09-Feb-15 02:00 AM
1928 IM116705 Check & Record MP to LP alignment 4h 09-Feb-15 02:00 AM 09-Feb-15 06:00 AM
1929 IM116710 Remove coupling spacer - MP to LP 8h 09-Feb-15 06:00 AM 09-Feb-15 02:00 PM
1930 IM116715 Record measurements on NDE & DE 4h 09-Feb-15 02:00 PM 09-Feb-15 06:00 PM
1931 IM116720 Lock rotor & Remove coupling hub @ MP-NDE 4h 09-Feb-15 06:00 PM 09-Feb-15 10:00 PM
1932 IM116725 Open DE bearing top half housing 4h 09-Feb-15 10:00 PM 10-Feb-15 02:00 AM
1933 IM116730 Measure & record the DE bearing clearance 4h 10-Feb-15 02:00 AM 10-Feb-15 06:00 AM
1934 IM116735 Install shipping bearings at DE 4h 10-Feb-15 06:00 AM 10-Feb-15 10:00 AM
1935 IM116740 Open NDE bearing top half housing 4h 10-Feb-15 02:00 AM 10-Feb-15 06:00 AM
1936 IM116745 Measure & record the NDE bearing clearance 4h 10-Feb-15 06:00 AM 10-Feb-15 10:00 AM
1937 IM116750 Install shipping bearings at NDE 4h 10-Feb-15 10:00 AM 10-Feb-15 02:00 PM
1938 IM116755 Remove lock nut & thrust disk 4h 10-Feb-15 02:00 PM 10-Feb-15 06:00 PM
1939 IM116760 Disassemble MP-NDE Dry gas seal/Sealing system from housing 4h 10-Feb-15 06:00 PM 10-Feb-15 10:00 PM
1940 IM116765 Install MP-NDE rotor seal support unit 4h 10-Feb-15 10:00 PM 11-Feb-15 02:00 AM
1941 IM116770 Remove coupling hub @ MP-DE 4h 11-Feb-15 02:00 AM 11-Feb-15 06:00 AM
1942 IM116775 Disassemble MP-DE Dry gas seal/Sealing system from housing 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM
1943 IM116780 Install MP-DE rotor seal support unit 4h 11-Feb-15 10:00 AM 11-Feb-15 02:00 PM
1944 IM116785 Remove injection nozzles 6h 10-Feb-15 02:00 AM 10-Feb-15 08:00 AM
1945 IM116790 Remove all casing bolts 18h 11-Feb-15 02:00 PM 12-Feb-15 08:00 AM
1946 IM116795 Remove & Shift upper casing 6h 12-Feb-15 08:00 AM 12-Feb-15 02:00 PM
1947 IM116800 Remove casing top inserts 12h 12-Feb-15 02:00 PM 13-Feb-15 02:00 AM
1948 IM116805 Remove rotor & Place on support stand 6h 13-Feb-15 02:00 AM 13-Feb-15 08:00 AM
1949 IM116810 Remove casing inserts from lower casing 12h 13-Feb-15 08:00 AM 13-Feb-15 08:00 PM
1950 IM116815 Shift casing inserts to blasting area 24h 13-Feb-15 08:00 PM 14-Feb-15 08:00 PM
1951 IM116820 Glass bead blasting of casing inserts 36h 14-Feb-15 08:00 PM 16-Feb-15 08:00 AM
1952 IM116825 Cleaning of casing & rotor 24h 13-Feb-15 08:00 PM 14-Feb-15 08:00 PM
1953 IM116830 Cleaning of suction lines & injn. nozzle 24h 10-Feb-15 08:00 AM 11-Feb-15 08:00 AM
1954 IM116835 Inspect lower, upper casing & accessories 24h 16-Feb-15 08:00 AM 17-Feb-15 08:00 AM
1955 IM116840 Inspect all casing bolts 24h 17-Feb-15 08:00 AM 18-Feb-15 08:00 AM
1956 IM116845 Shift casing inserts to job site 24h 17-Feb-15 08:00 AM 18-Feb-15 08:00 AM
1957 IM116850 Install casing inserts into lower casing 8h 18-Feb-15 08:00 AM 18-Feb-15 04:00 PM
1958 IM116855 Lift rotor & Position in to the compressor casing 8h 18-Feb-15 04:00 PM 19-Feb-15 12:00 AM
1959 IM116860 Record the neccessary clearances 6h 19-Feb-15 12:00 AM 19-Feb-15 06:00 AM
1960 IM116865 Install casing inserts into upper casing 8h 19-Feb-15 06:00 AM 19-Feb-15 02:00 PM
1961 IM116870 Lift & Install upper casing 12h 19-Feb-15 02:00 PM 20-Feb-15 02:00 AM
1962 IM116875 Tight casing bolts as per procedure 12h 20-Feb-15 02:00 AM 20-Feb-15 02:00 PM
1963 IM116880 Measure & record rotor free float 4h 20-Feb-15 02:00 PM 20-Feb-15 06:00 PM
1964 IM116885 Install all injection nozzle 8h 20-Feb-15 06:00 PM 21-Feb-15 02:00 AM
1965 IM116890 Install MP-NDE Dry gas seal/Sealing system 6h 21-Feb-15 02:00 AM 21-Feb-15 08:00 AM
1966 IM116895 Assemble NDE thrust disk & lock the disk 4h 21-Feb-15 08:00 AM 21-Feb-15 12:00 PM
1967 IM116900 Assemble thrust brg. case with thrust pads 4h 21-Feb-15 12:00 PM 21-Feb-15 04:00 PM
1968 IM116905 Install NDE coupling hub & Provide lock nut 4h 21-Feb-15 04:00 PM 21-Feb-15 08:00 PM
1969 IM116910 Install DE Dry gas seal/Sealing system 6h 21-Feb-15 08:00 PM 22-Feb-15 02:00 AM
1970 IM116915 Install DE coupling hub & Provide lock nut 4h 22-Feb-15 02:00 AM 22-Feb-15 06:00 AM
1971 IM116920 Remove shipping brg. @ DE & Install journal brgs. 6h 22-Feb-15 06:00 AM 22-Feb-15 12:00 PM
1972 IM116925 Remove shipping brg. @ NDE & Install journal/thrust brgs. 6h 22-Feb-15 12:00 PM 22-Feb-15 06:00 PM
1973 IM116930 Record the neccessary clearances 4h 22-Feb-15 06:00 PM 22-Feb-15 10:00 PM
1974 IM116935 Install DE/NDE bearing housing top half 6h 22-Feb-15 10:00 PM 23-Feb-15 04:00 AM
1975 IM116940 Install coupling spacer - MP to LP 4h 24-Feb-15 12:00 AM 24-Feb-15 04:00 AM
1976 IM116945 Perform alignment on MP-LP by LASER/Dial 12h 24-Feb-15 04:00 AM 24-Feb-15 04:00 PM
1977 IM116950 Install back MP-LP lower/upper half of coupling guard 4h 24-Feb-15 04:00 PM 24-Feb-15 08:00 PM
1978 IM116955 Fix back instrument connections 8h 24-Feb-15 08:00 PM 25-Feb-15 04:00 AM
1979 IM116960 Fix back auxiliary pipings 12h 25-Feb-15 04:00 AM 25-Feb-15 04:00 PM
1980 IM116965 Carryout De-Blinding & Close PTW 24h 28-Feb-15 10:00 PM 01-Mar-15 10:00 PM
1981 ROT-CGC-LP-D/N54ROT-CGC-LP-D/N54 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1982 R15E-310-011 RC2-32-310-16-CC-301A CGC LP COMPRESSOR - MAJOR O/HR15E-310-011 RC2-32-310-16-CC-301A CGC LP COMPRESSOR - MAJOR O/H 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1983 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
1984 IM117025 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 31 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
1985 IM117030 Blinding as per blindlist (R15E-310-119) 24h 07-Feb-15 08:00 AM 08-Feb-15 08:00 AM
1986 IM117035 Remove necessary pipes & inst. lines 24h 08-Feb-15 08:00 AM 09-Feb-15 08:00 AM
1987 IM117040 Remove coupling guard - LP to HP 4h 08-Feb-15 08:00 AM 08-Feb-15 12:00 PM
1988 IM117045 Check & Record LP to HP alignment 4h 08-Feb-15 12:00 PM 08-Feb-15 04:00 PM
1989 IM117050 Remove coupling spacer - LP to HP 4h 08-Feb-15 04:00 PM 08-Feb-15 08:00 PM
1990 IM117055 Record measurements on LP-NDE & DE 4h 08-Feb-15 08:00 PM 09-Feb-15 12:00 AM
1991 IM117060 Open DE bearing top half housing 4h 09-Feb-15 12:00 AM 09-Feb-15 04:00 AM
1992 IM117065 Measure & record the DE bearing clearance 4h 09-Feb-15 04:00 AM 09-Feb-15 08:00 AM
1993 IM117070 Remove journal brg. @ DE & Install shipping brg. 4h 09-Feb-15 08:00 AM 09-Feb-15 12:00 PM
1994 IM117075 Lock rotor & Remove coupling hub @ LP-NDE 4h 09-Feb-15 12:00 PM 09-Feb-15 04:00 PM
1995 IM117080 Open NDE bearing top half housing 4h 09-Feb-15 04:00 PM 09-Feb-15 08:00 PM
1996 IM117085 Measure & record the NDE bearing clearance 4h 09-Feb-15 08:00 PM 10-Feb-15 12:00 AM
1997 IM117090 Remove journal brg. @ NDE & Install shipping brg. 4h 10-Feb-15 12:00 AM 10-Feb-15 04:00 AM
1998 IM117095 Remove coupling hub at LP-NDE 4h 10-Feb-15 04:00 AM 10-Feb-15 08:00 AM
1999 IM117100 Remove lock nut & thrust disk 4h 10-Feb-15 08:00 AM 10-Feb-15 12:00 PM
2000 IM117105 Disassemble LP-NDE Dry gas seal/Sealing system from housing 4h 10-Feb-15 12:00 PM 10-Feb-15 04:00 PM
2001 IM117110 Install LP-NDE rotor seal support unit 4h 10-Feb-15 04:00 PM 10-Feb-15 08:00 PM
2002 IM117115 Disassemble LP-DE Dry gas seal/Sealing system from housing 4h 10-Feb-15 08:00 PM 11-Feb-15 12:00 AM
2003 IM117120 Install LP-DE rotor seal support unit 4h 11-Feb-15 12:00 AM 11-Feb-15 04:00 AM
2004 IM117125 Remove injection nozzles 8h 11-Feb-15 04:00 AM 11-Feb-15 12:00 PM
2005 IM117130 Remove all LP casing bolts 18h 11-Feb-15 12:00 PM 12-Feb-15 06:00 AM
2006 IM117135 Remove & Shift upper casing 8h 12-Feb-15 06:00 AM 12-Feb-15 02:00 PM
2007 IM117140 Remove LP casing top inserts 12h 12-Feb-15 02:00 PM 13-Feb-15 02:00 AM
2008 IM117145 Remove rotor & Place on support stand 8h 13-Feb-15 02:00 AM 13-Feb-15 10:00 AM
2009 IM117150 Remove casing inserts from lower casing 12h 13-Feb-15 10:00 AM 13-Feb-15 10:00 PM
2010 IM117155 Shift casing inserts to blasting area 24h 13-Feb-15 10:00 PM 14-Feb-15 10:00 PM
2011 IM117160 Glass bead blasting of casing inserts 48h 14-Feb-15 10:00 PM 16-Feb-15 10:00 PM
2012 IM117165 Cleaning of casing & rotor 48h 13-Feb-15 10:00 AM 15-Feb-15 10:00 AM
2013 IM117170 Cleaning of suction lines & injn. nozzle 8h 11-Feb-15 12:00 PM 11-Feb-15 08:00 PM
2014 IM117175 Inspect lower, upper casing & acce. 24h 15-Feb-15 10:00 AM 16-Feb-15 10:00 AM
2015 IM117180 Inspect all casing bolts 24h 16-Feb-15 10:00 AM 17-Feb-15 10:00 AM
2016 IM117185 Shift casing inserts to job site 24h 16-Feb-15 10:00 PM 17-Feb-15 10:00 PM
2017 IM117190 Install casing inserts into lower casing 8h 17-Feb-15 10:00 PM 18-Feb-15 06:00 AM
2018 IM117195 Lift rotor & Position in to the compressor casing 8h 18-Feb-15 06:00 AM 18-Feb-15 02:00 PM
2019 IM117200 Record the neccessary clearances 8h 18-Feb-15 02:00 PM 18-Feb-15 10:00 PM
2020 IM117205 Install casing inserts into upper casing 8h 18-Feb-15 10:00 PM 19-Feb-15 06:00 AM
2021 IM117210 Lift & Install upper casing 12h 19-Feb-15 06:00 AM 19-Feb-15 06:00 PM
2022 IM117215 Tight casing bolts as per procedure 12h 19-Feb-15 06:00 PM 20-Feb-15 06:00 AM
2023 IM117220 Measure & record rotor free float 4h 20-Feb-15 06:00 AM 20-Feb-15 10:00 AM
2024 IM117225 Install all injection nozzle 8h 20-Feb-15 10:00 AM 20-Feb-15 06:00 PM
2025 IM117230 Install LP-NDE Dry gas seal/Sealing system 8h 20-Feb-15 06:00 PM 21-Feb-15 02:00 AM
2026 IM117235 Assemble NDE thrust disk & lock the disk 8h 21-Feb-15 02:00 AM 21-Feb-15 10:00 AM
2027 IM117240 Assemble thrust brg. case with thrust pads 4h 21-Feb-15 10:00 AM 21-Feb-15 02:00 PM
2028 IM117245 Install NDE coupling hub & Provide lock nut 4h 21-Feb-15 02:00 PM 21-Feb-15 06:00 PM
2029 IM117250 Install DE Dry gas seal/Sealing system 8h 21-Feb-15 06:00 PM 22-Feb-15 02:00 AM
2030 IM117255 Install DE coupling hub & Provide lock nut 4h 22-Feb-15 02:00 AM 22-Feb-15 06:00 AM
2031 IM117260 Remove shipping brg. @ DE & Install journal brgs. 8h 22-Feb-15 06:00 AM 22-Feb-15 02:00 PM
2032 IM117265 Remove shipping brg. @ NDE & Install journal/thrust brgs. 8h 22-Feb-15 02:00 PM 22-Feb-15 10:00 PM
2033 IM117270 Record the neccessary clearances 4h 22-Feb-15 10:00 PM 23-Feb-15 02:00 AM
2034 IM117275 Install DE/NDE bearing housing top half 6h 23-Feb-15 02:00 AM 23-Feb-15 08:00 AM
2035 IM117280 Install coupling spacer MP-LP 4h 24-Feb-15 12:00 AM 24-Feb-15 04:00 AM
2036 IM117285 Perform alignment on MP-LP by LASER/Dial 12h 24-Feb-15 04:00 AM 24-Feb-15 04:00 PM
2037 IM117290 Install back MP-LP lower/upper half of coupling guard 4h 24-Feb-15 04:00 PM 24-Feb-15 08:00 PM
2038 IM117295 Fix back instrument connections 8h 24-Feb-15 08:00 PM 25-Feb-15 04:00 AM
2039 IM117300 Fix back auxiliary pipings 8h 25-Feb-15 04:00 AM 25-Feb-15 12:00 PM
2040 IM117305 Carryout De-Blinding (R15E-310-119) & Close PTW 24h 28-Feb-15 10:00 PM 01-Mar-15 10:00 PM
2041 ROT-CGC-HP-D/N55ROT-CGC-HP-D/N55 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
2042 R15E-310-012 RC2-32-310-16-CC-301C CGC HP COMPRESSOR - MAJOR O/HR15E-310-012 RC2-32-310-16-CC-301C CGC HP COMPRESSOR - MAJOR O/H 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
2043 SHUTDOWNSHUTDOWN 544h 07-Feb-15 06:00 AM 01-Mar-15 10:00 PM
2044 IM117360 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
2045 IM117365 Blinding as per blindlist (R15E-310-119) 24h 07-Feb-15 08:00 AM 08-Feb-15 08:00 AM
2046 IM117370 Remove necessary pipes & inst. lines 10h 08-Feb-15 08:00 AM 08-Feb-15 06:00 PM
2047 IM117375 Open DE bearing top half housing 8h 08-Feb-15 08:00 AM 08-Feb-15 04:00 PM
2048 IM117380 Remove journal brg. @ DE & Install shipping brg. 8h 08-Feb-15 04:00 PM 09-Feb-15 12:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 32 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
2049 IM117385 Open NDE bearing top half housing 8h 09-Feb-15 12:00 AM 09-Feb-15 08:00 AM
2050 IM117390 Remove journal brg. @ NDE & Install shipping brg. 4h 09-Feb-15 08:00 AM 09-Feb-15 12:00 PM
2051 IM117395 Measure & record the NDE bearing clearance 8h 09-Feb-15 12:00 PM 09-Feb-15 08:00 PM
2052 IM117400 Remove lock nut & thrust disk 4h 09-Feb-15 08:00 PM 10-Feb-15 12:00 AM
2053 IM117405 Disassemble HP-NDE Dry gas seal/Sealing system from housing 4h 10-Feb-15 12:00 AM 10-Feb-15 04:00 AM
2054 IM117410 Install HP-NDE rotor seal support unit 4h 10-Feb-15 04:00 AM 10-Feb-15 08:00 AM
2055 IM117415 Remove coupling hub at HP-DE 4h 10-Feb-15 08:00 AM 10-Feb-15 12:00 PM
2056 IM117420 Disassemble HP-DE Dry gas seal/Sealing system from housing 4h 10-Feb-15 12:00 PM 10-Feb-15 04:00 PM
2057 IM117425 Install HP-DE rotor seal support unit 4h 10-Feb-15 04:00 PM 10-Feb-15 08:00 PM
2058 IM117430 Remove injection nozzles 10h 10-Feb-15 08:00 PM 11-Feb-15 06:00 AM
2059 IM117435 Remove HP casing bolts 12h 11-Feb-15 06:00 AM 11-Feb-15 06:00 PM
2060 IM117440 Install bundle pulling arrangement 12h 11-Feb-15 06:00 PM 12-Feb-15 06:00 AM
2061 IM117445 Pullout Bundle 12h 12-Feb-15 06:00 AM 12-Feb-15 06:00 PM
2062 IM117450 Dismantle bundle 18h 12-Feb-15 06:00 PM 13-Feb-15 12:00 PM
2063 IM117455 Remove rotor & Place on support stand 6h 13-Feb-15 12:00 PM 13-Feb-15 06:00 PM
2064 IM117460 Shift casing inserts to blasting area 24h 13-Feb-15 06:00 PM 14-Feb-15 06:00 PM
2065 IM117465 Glass bead blasting of casing inserts 48h 14-Feb-15 06:00 PM 16-Feb-15 06:00 PM
2066 IM117470 Shift casing inserts to job site 24h 16-Feb-15 06:00 PM 17-Feb-15 06:00 PM
2067 IM117475 Clean HP parts & casing 48h 17-Feb-15 06:00 PM 19-Feb-15 06:00 PM
2068 IM117480 Cleaning of suction lines & injn. nozzle 8h 11-Feb-15 06:00 AM 11-Feb-15 02:00 PM
2069 IM117485 Assemble bundle with new rotor 36h 13-Feb-15 06:00 PM 15-Feb-15 06:00 AM
2070 IM117490 Inspect HP Casing & accessories 24h 19-Feb-15 06:00 PM 20-Feb-15 06:00 PM
2071 IM117495 Inspect all casing bolts 24h 20-Feb-15 06:00 PM 21-Feb-15 06:00 PM
2072 IM117500 Insert HP barrel into compressor casing 24h 15-Feb-15 06:00 AM 16-Feb-15 06:00 AM
2073 IM117505 Record the neccessary clearances 4h 16-Feb-15 06:00 AM 16-Feb-15 10:00 AM
2074 IM117510 Install casing cover 8h 16-Feb-15 10:00 AM 16-Feb-15 06:00 PM
2075 IM117515 Tight casing bolts as per procedure 8h 16-Feb-15 06:00 PM 17-Feb-15 02:00 AM
2076 IM117520 Measure & record rotor free float 4h 17-Feb-15 02:00 AM 17-Feb-15 06:00 AM
2077 IM117525 Install all injection nozzle 8h 17-Feb-15 06:00 AM 17-Feb-15 02:00 PM
2078 IM117530 Install NDE Dry gas seal/Sealing system 8h 17-Feb-15 02:00 PM 17-Feb-15 10:00 PM
2079 IM117535 Assemble NDE thrust disk & lock the disk 4h 17-Feb-15 10:00 PM 18-Feb-15 02:00 AM
2080 IM117540 Remove shipping brg. @ NDE & Install journal brgs. 8h 18-Feb-15 02:00 AM 18-Feb-15 10:00 AM
2081 IM117545 Install DE Dry gas seal/Sealing system 8h 18-Feb-15 10:00 AM 18-Feb-15 06:00 PM
2082 IM117550 Install DE coupling hub & Provide lock nut 8h 18-Feb-15 06:00 PM 19-Feb-15 02:00 AM
2083 IM117555 Remove shipping brg. @ DE & Install journal brgs. 8h 19-Feb-15 02:00 AM 19-Feb-15 10:00 AM
2084 IM117560 Record the neccessary clearances 4h 19-Feb-15 10:00 AM 19-Feb-15 02:00 PM
2085 IM117565 Install DE/NDE bearing housing top half 8h 19-Feb-15 02:00 PM 19-Feb-15 10:00 PM
2086 IM117570 Install coupling spacer LP-HP 4h 24-Feb-15 04:00 PM 24-Feb-15 08:00 PM
2087 IM117575 Perform alignment on LP-HP by LASER/Dial 12h 24-Feb-15 08:00 PM 25-Feb-15 08:00 AM
2088 IM117580 Install back LP-HP lower/upper half of coupling guard 6h 25-Feb-15 08:00 AM 25-Feb-15 02:00 PM
2089 IM117585 Replace seal gas filter elements 4h 25-Feb-15 02:00 PM 25-Feb-15 06:00 PM
2090 IM117590 Fix back instrument connections 8h 25-Feb-15 06:00 PM 26-Feb-15 02:00 AM
2091 IM117595 Fix back auxiliary pipings 12h 26-Feb-15 02:00 AM 26-Feb-15 02:00 PM
2092 IM117600 Carryout De-Blinding (R15E-310-119) & Close PTW 24h 28-Feb-15 10:00 PM 01-Mar-15 10:00 PM
2093 ROT-CGC-ST-D/N56ROT-CGC-ST-D/N56 520h 08-Feb-15 06:00 AM 01-Mar-15 10:00 PM
2094 R15E-310-039 RC2-32-310-43-X-1338 CGC BARRING GEAR SERVICER15E-310-039 RC2-32-310-43-X-1338 CGC BARRING GEAR SERVICE 28h 11-Feb-15 06:00 AM 12-Feb-15 10:00 AM
2095 SHUTDOWNSHUTDOWN 28h 11-Feb-15 06:00 AM 12-Feb-15 10:00 AM
2096 IM117810 Verify LT&T and Obtain PTW 2h 11-Feb-15 06:00 AM 11-Feb-15 08:00 AM
2097 IM117815 Remove barring gear assembly 10h 11-Feb-15 08:00 AM 11-Feb-15 06:00 PM
2098 IM117820 Inspect barring gear assembly 4h 11-Feb-15 06:00 PM 11-Feb-15 10:00 PM
2099 IM117825 Flush & Check barring gear oil system 6h 11-Feb-15 10:00 PM 12-Feb-15 04:00 AM
2100 IM117830 Check jacking oil pump 6h 12-Feb-15 04:00 AM 12-Feb-15 10:00 AM
2101 R15E-310-044 RC2-32-310-84-ST-301 CGC ST - MINOR O/H, BEARINGS & SEAL REPL.R15E-310-044 RC2-32-310-84-ST-301 CGC ST - MINOR O/H, BEARINGS & SEAL REPL. 520h 08-Feb-15 06:00 AM 01-Mar-15 10:00 PM
2102 SHUTDOWNSHUTDOWN 520h 08-Feb-15 06:00 AM 01-Mar-15 10:00 PM
2103 IM117652 Verify LT&T and Obtain PTW 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM
2104 IM117655 Blinding as per blindlist 24h 08-Feb-15 08:00 AM 09-Feb-15 08:00 AM
2105 IM117657 Remove all connections, Drop ESV's & provide blind 16h 08-Feb-15 08:00 AM 09-Feb-15 12:00 AM
2106 IM117659 Remove ESV's strainer 6h 08-Feb-15 08:00 AM 08-Feb-15 02:00 PM
2107 IM117661 Inspect ESV strainer 6h 08-Feb-15 02:00 PM 08-Feb-15 08:00 PM
2108 IM117663 Remove necessary pipes & inst. lines 12h 09-Feb-15 08:00 AM 09-Feb-15 08:00 PM
2109 IM117665 Remove NDE brg. housing top cover 4h 09-Feb-15 08:00 AM 09-Feb-15 12:00 PM
2110 IM117667 Remove NDE brg. housing 4h 09-Feb-15 12:00 PM 09-Feb-15 04:00 PM
2111 IM117669 Inspect NDE journal & thrust brg. 4h 09-Feb-15 04:00 PM 09-Feb-15 08:00 PM
2112 IM117671 Fix back NDE brg. housing 4h 09-Feb-15 08:00 PM 10-Feb-15 12:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 33 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
2113 IM117673 Remove DE brg. housing 4h 09-Feb-15 04:00 PM 09-Feb-15 08:00 PM
2114 IM117675 Inspect DE journal & thrust brg. 4h 09-Feb-15 08:00 PM 10-Feb-15 12:00 AM
2115 IM117677 Fix back DE brg. housing 4h 10-Feb-15 12:00 AM 10-Feb-15 04:00 AM
2116 IM117679 Inspect seal rings 8h 10-Feb-15 04:00 AM 10-Feb-15 12:00 PM
2117 IM117681 Check bypass & b.fly valves 6h 10-Feb-15 12:00 PM 10-Feb-15 06:00 PM
2118 IM117685 Replace parts of valves, if reqd. 6h 10-Feb-15 06:00 PM 11-Feb-15 12:00 AM
2119 IM117690 Check & Inspect extraction, bleed S/O valves 12h 11-Feb-15 12:00 AM 11-Feb-15 12:00 PM
2120 IM117695 Clean & Inspect Double servo cylinder 12h 11-Feb-15 12:00 PM 12-Feb-15 12:00 AM
2121 IM117700 Clean & Inspect the Pilot valves 12h 12-Feb-15 12:00 AM 12-Feb-15 12:00 PM
2122 IM117705 Clean & Inspect the Operating cylinder 12h 12-Feb-15 12:00 PM 13-Feb-15 12:00 AM
2123 IM117710 Clean & Inspect pinion/wheel gear brg. 12h 13-Feb-15 12:00 AM 13-Feb-15 12:00 PM
2124 IM117713 Clean & Inspect governing valve links, bushes 12h 13-Feb-15 12:00 PM 14-Feb-15 12:00 AM
2125 IM117715 Recharge nitrogen for accumulator, if reqd. 8h 14-Feb-15 12:00 AM 14-Feb-15 08:00 AM
2126 IM117717 Fix back auxiliary pipings 8h 14-Feb-15 12:00 AM 14-Feb-15 08:00 AM
2127 IM117719 Fix back instrument connections 8h 14-Feb-15 08:00 AM 14-Feb-15 04:00 PM
2128 IM117720 Fix back insulation, wherever removed at ST 8h 14-Feb-15 04:00 PM 15-Feb-15 12:00 AM
2129 IM117721 Provide steam blow-out tool & Fix piping 12h 23-Feb-15 04:00 PM 24-Feb-15 04:00 AM
2130 IM117723 Carryout steam blow-out 24h 26-Feb-15 04:00 AM 27-Feb-15 04:00 AM
2131 IM117725 Remove piping & steam blow-out tool 8h 27-Feb-15 04:00 AM 27-Feb-15 12:00 PM
2132 IM117727 Fix back ESV strainer 4h 27-Feb-15 12:00 PM 27-Feb-15 04:00 PM
2133 IM117730 Reinstall ESV & provide all necessary connections 12h 27-Feb-15 12:00 PM 28-Feb-15 12:00 AM
2134 IM117733 Fix back insulation on ESV'S 2h 28-Feb-15 12:00 AM 28-Feb-15 02:00 AM
2135 IM117735 Remove scaffolding from ESV's 6h 28-Feb-15 02:00 AM 28-Feb-15 08:00 AM
2136 IM117737 Install Coupling spacer - Turbine to MP 8h 23-Feb-15 04:00 AM 23-Feb-15 12:00 PM
2137 IM117740 Perform alignment on Turbine-MP by LASER/Dial 12h 23-Feb-15 12:00 PM 24-Feb-15 12:00 AM
2138 IM117742 De-couple - Turbine to MP for OST check 6h 24-Feb-15 12:00 AM 24-Feb-15 06:00 AM
2139 IM117744 Partial LT&T & Perform OST 12h 28-Feb-15 12:00 AM 28-Feb-15 12:00 PM
2140 IM117746 Couple - Turbine to MP 6h 28-Feb-15 12:00 PM 28-Feb-15 06:00 PM
2141 IM117748 Install coupling guard 4h 28-Feb-15 06:00 PM 28-Feb-15 10:00 PM
2142 IM117765 Carryout De-Blinding & Close PTW 24h 28-Feb-15 10:00 PM 01-Mar-15 10:00 PM
2143 ROT-PRC-ST-D57ROT-PRC-ST-D57 440h 09-Feb-15 06:00 AM 27-Feb-15 02:00 PM
2144 R15E-810-002 RC2-32-810-16-C-801 PRC - REPLACEMENT OF CORRODED BRG. HSG. BOLTSR15E-810-002 RC2-32-810-16-C-801 PRC - REPLACEMENT OF CORRODED BRG. HSG. BOLTS 18h 13-Feb-15 06:00 AM 14-Feb-15 12:00 PM
2145 SHUTDOWNSHUTDOWN 18h 13-Feb-15 06:00 AM 14-Feb-15 12:00 PM
2146 IM116310 Verify LT&T and Obtain PTW 2h 13-Feb-15 06:00 AM 13-Feb-15 08:00 AM
2147 IM116315 Replace bearing housing corroded bolts 12h 13-Feb-15 08:00 AM 14-Feb-15 08:00 AM
2148 IM116320 Remove scaffolding & Close PTW 4h 14-Feb-15 08:00 AM 14-Feb-15 12:00 PM
2149 R15E-810-039 RC2-32-810-84-ST-801 PRC ST - MINOR O/H (BRG. INSPN/ REPL.)R15E-810-039 RC2-32-810-84-ST-801 PRC ST - MINOR O/H (BRG. INSPN/ REPL.) 440h 09-Feb-15 06:00 AM 27-Feb-15 02:00 PM
2150 SHUTDOWNSHUTDOWN 440h 09-Feb-15 06:00 AM 27-Feb-15 02:00 PM
2151 IM116115 Verify LT&T and Obtain PTW 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM
2152 IM116120 Blinding as per blindlist 24h 09-Feb-15 10:00 AM 10-Feb-15 10:00 AM
2153 IM116125 Remove insulation from turbine 6h 09-Feb-15 10:00 AM 09-Feb-15 04:00 PM
2154 IM116130 Remove necessary pipes & inst. lines 8h 10-Feb-15 10:00 AM 10-Feb-15 06:00 PM
2155 IM116135 Remove coupling guard 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM
2156 IM116140 Record torque meter gap & alignment reading 8h 11-Feb-15 10:00 AM 11-Feb-15 06:00 PM
2157 IM116145 Remove coupling spacer 4h 12-Feb-15 06:00 AM 12-Feb-15 10:00 AM
2158 IM116150 Measure the DBSE and float 4h 12-Feb-15 10:00 AM 12-Feb-15 02:00 PM
2159 IM116155 DE bearing housing removal 6h 12-Feb-15 02:00 PM 13-Feb-15 08:00 AM
2160 IM116160 DE journal bearing inspection 4h 13-Feb-15 08:00 AM 13-Feb-15 12:00 PM
2161 IM116162 DE - Inspect RDT, vibration probes, if required replace it 4h 13-Feb-15 12:00 PM 13-Feb-15 04:00 PM
2162 IM116165 Fix back DE bearing housing 6h 13-Feb-15 04:00 PM 14-Feb-15 10:00 AM
2163 IM116170 NDE bearing housing removal 6h 14-Feb-15 10:00 AM 14-Feb-15 04:00 PM
2164 IM116175 NDE journal & thrust bearing inspection 4h 14-Feb-15 04:00 PM 15-Feb-15 08:00 AM
2165 IM116180 NDE - Inspect RDT, vibration probes, if required replace it 4h 15-Feb-15 08:00 AM 15-Feb-15 12:00 PM
2166 IM116185 Fix back NDE bearing housing 6h 15-Feb-15 12:00 PM 15-Feb-15 06:00 PM
2167 IM116187 Barring gear unit removal & inspection 8h 16-Feb-15 06:00 AM 16-Feb-15 02:00 PM
2168 IM116190 Fix back the barring gear unit 8h 16-Feb-15 02:00 PM 17-Feb-15 10:00 AM
2169 IM116195 Removal of ESV 8h 17-Feb-15 10:00 AM 17-Feb-15 06:00 PM
2170 IM116200 Blind both ends of ESV flanges 6h 18-Feb-15 06:00 AM 18-Feb-15 12:00 PM
2171 IM116205 Disassamble & Inspection of ESV 8h 18-Feb-15 12:00 PM 19-Feb-15 08:00 AM
2172 IM116210 Check, Clean & Replace the strainer if reqd. 4h 19-Feb-15 08:00 AM 19-Feb-15 12:00 PM
2173 IM116215 Inspect - Condition of ESV 4h 19-Feb-15 12:00 PM 19-Feb-15 04:00 PM
2174 IM116220 Assemble ESV 12h 19-Feb-15 04:00 PM 20-Feb-15 04:00 PM
2175 IM116225 Remove end blinds from ESV 4h 20-Feb-15 04:00 PM 21-Feb-15 08:00 AM
2176 IM116230 Reinstall ESV 6h 21-Feb-15 08:00 AM 21-Feb-15 02:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 34 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
2177 IM116235 Clean & Inspect governing valves links & bushes 8h 21-Feb-15 02:00 PM 22-Feb-15 10:00 AM
2178 IM116240 Recharge nitrogen for accumulator, if reqd. 4h 21-Feb-15 02:00 PM 21-Feb-15 06:00 PM
2179 IM116245 Connect all lube oil piping's & acce. 6h 22-Feb-15 10:00 AM 22-Feb-15 04:00 PM
2180 IM116250 Fix back instrument lines 6h 22-Feb-15 04:00 PM 23-Feb-15 10:00 AM
2181 IM116260 Check & replace oil soaked insulation 8h 23-Feb-15 10:00 AM 23-Feb-15 06:00 PM
2182 IM116265 Carryout all instrument function test 12h 24-Feb-15 06:00 AM 24-Feb-15 06:00 PM
2183 IM116270 Partial LT&T & Carryout OST of turbine 12h 25-Feb-15 06:00 AM 25-Feb-15 06:00 PM
2184 IM116275 Fix back coupling spacer 4h 26-Feb-15 06:00 AM 26-Feb-15 10:00 AM
2185 IM116280 Fix back coupling guard 4h 26-Feb-15 10:00 AM 26-Feb-15 02:00 PM
2186 IM116283 Carryout De-Blinding & Close PTW 24h 26-Feb-15 02:00 PM 27-Feb-15 02:00 PM
2187 ROT-ERC-ST-D58ROT-ERC-ST-D58 556h 04-Feb-15 06:00 AM 27-Feb-15 10:00 AM
2188 R15E-310-010 RC2-32-310-16-C-302A N2 BOOSTER COMPRESSOR - MAJOR O/HR15E-310-010 RC2-32-310-16-C-302A N2 BOOSTER COMPRESSOR - MAJOR O/H 48h 04-Feb-15 06:00 AM 07-Feb-15 06:00 PM
2189 SHUTDOWNSHUTDOWN 48h 04-Feb-15 06:00 AM 07-Feb-15 06:00 PM
2190 IM115885 Verify LT&T and Obtain PTW 2h 04-Feb-15 06:00 AM 04-Feb-15 08:00 AM
2191 IM115890 Blinding as per blindlist 2h 04-Feb-15 08:00 AM 04-Feb-15 10:00 AM
2192 IM115895 Remove necessary pipes & inst. lines 2h 04-Feb-15 10:00 AM 04-Feb-15 12:00 PM
2193 IM115900 Remove foundation bolt & lift the skit 4h 04-Feb-15 12:00 PM 04-Feb-15 04:00 PM
2194 IM115905 Shift the skit to workshop 1h 04-Feb-15 04:00 PM 04-Feb-15 05:00 PM
2195 IM115910 Disassemble the drive unit 2h 04-Feb-15 05:00 PM 05-Feb-15 07:00 AM
2196 IM115915 Disassemble the valve/piston assembly 2h 05-Feb-15 07:00 AM 05-Feb-15 09:00 AM
2197 IM115920 Disassemble crankcase assembly 2h 05-Feb-15 09:00 AM 05-Feb-15 11:00 AM
2198 IM115925 Clean & Inspect all parts 2h 05-Feb-15 11:00 AM 05-Feb-15 01:00 PM
2199 IM115930 Repair or Replace, if reqd. 2h 05-Feb-15 01:00 PM 05-Feb-15 03:00 PM
2200 IM115935 Assemble crankcase assembly 2h 05-Feb-15 03:00 PM 05-Feb-15 05:00 PM
2201 IM115940 Assemble the valve/piston assembly 2h 05-Feb-15 05:00 PM 06-Feb-15 07:00 AM
2202 IM115945 Assemble the drive unit 2h 06-Feb-15 07:00 AM 06-Feb-15 09:00 AM
2203 IM115950 Shift the skit to job site 1h 06-Feb-15 09:00 AM 06-Feb-15 10:00 AM
2204 IM115955 Fix back the skit 4h 06-Feb-15 10:00 AM 06-Feb-15 02:00 PM
2205 IM115960 Clean & Check cooler/ NRV/ relief valve 4h 06-Feb-15 02:00 PM 06-Feb-15 06:00 PM
2206 IM115965 Fix back all pipes & inst. lines 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
2207 IM115970 Carrryout De-Blinding 2h 07-Feb-15 08:00 AM 07-Feb-15 10:00 AM
2208 IM115975 Performance check for compressor & close PTW 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM
2209 R15E-310-120 RC2-32-310-16-C-302B N2 BOOSTER COMPRESSOR - MAJOR O/HR15E-310-120 RC2-32-310-16-C-302B N2 BOOSTER COMPRESSOR - MAJOR O/H 48h 04-Feb-15 06:00 AM 07-Feb-15 06:00 PM
2210 SHUTDOWNSHUTDOWN 48h 04-Feb-15 06:00 AM 07-Feb-15 06:00 PM
2211 IM115995 Verify LT&T and Obtain PTW 2h 04-Feb-15 06:00 AM 04-Feb-15 08:00 AM
2212 IM116000 Blinding as per blindlist 2h 04-Feb-15 08:00 AM 04-Feb-15 10:00 AM
2213 IM116005 Remove necessary pipes & inst. lines 2h 04-Feb-15 10:00 AM 04-Feb-15 12:00 PM
2214 IM116010 Remove foundation bolt & lift the skit 4h 04-Feb-15 12:00 PM 04-Feb-15 04:00 PM
2215 IM116015 Shift the skit to workshop 1h 04-Feb-15 04:00 PM 04-Feb-15 05:00 PM
2216 IM116020 Disassemble the drive unit 2h 04-Feb-15 05:00 PM 05-Feb-15 07:00 AM
2217 IM116025 Disassemble the valve/piston assembly 2h 05-Feb-15 07:00 AM 05-Feb-15 09:00 AM
2218 IM116030 Disassemble crankcase assembly 2h 05-Feb-15 09:00 AM 05-Feb-15 11:00 AM
2219 IM116035 Clean & Inspect all parts 2h 05-Feb-15 11:00 AM 05-Feb-15 01:00 PM
2220 IM116040 Repair or Replace, if reqd. 2h 05-Feb-15 01:00 PM 05-Feb-15 03:00 PM
2221 IM116045 Assemble crankcase assembly 2h 05-Feb-15 03:00 PM 05-Feb-15 05:00 PM
2222 IM116050 Assemble the valve/piston assembly 2h 05-Feb-15 05:00 PM 06-Feb-15 07:00 AM
2223 IM116055 Assemble the drive unit 2h 06-Feb-15 07:00 AM 06-Feb-15 09:00 AM
2224 IM116060 Shift the skit to job site 1h 06-Feb-15 09:00 AM 06-Feb-15 10:00 AM
2225 IM116065 Fix back the skit 4h 06-Feb-15 10:00 AM 06-Feb-15 02:00 PM
2226 IM116070 Clean & Check cooler/ NRV/ relief valve 4h 06-Feb-15 02:00 PM 06-Feb-15 06:00 PM
2227 IM116075 Fix back all pipes & inst. lines 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM
2228 IM116080 Carrryout De-Blinding 2h 07-Feb-15 08:00 AM 07-Feb-15 10:00 AM
2229 IM116085 Performance check for compressor & close PTW 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM
2230 R15E-820-002 RC2-32-820-16-C-802 ERC - REPLACEMENT OF CORRODED BRG. HSG. BOLTSR15E-820-002 RC2-32-820-16-C-802 ERC - REPLACEMENT OF CORRODED BRG. HSG. BOLTS 18h 12-Feb-15 06:00 AM 13-Feb-15 12:00 PM
2231 SHUTDOWNSHUTDOWN 18h 12-Feb-15 06:00 AM 13-Feb-15 12:00 PM
2232 IM116535 Verify LT&T and Obtain PTW 2h 12-Feb-15 06:00 AM 12-Feb-15 08:00 AM
2233 IM116540 Replace bearing housing corroded bolts 12h 12-Feb-15 08:00 AM 13-Feb-15 08:00 AM
2234 IM116545 Remove scaffolding & Close PTW 4h 13-Feb-15 08:00 AM 13-Feb-15 12:00 PM
2235 R15E-820-025 RC2-32-820-84-ST-802 ERC ST - MINOR O/H (BRG. INSPN/ REPL.)R15E-820-025 RC2-32-820-84-ST-802 ERC ST - MINOR O/H (BRG. INSPN/ REPL.) 412h 10-Feb-15 06:00 AM 27-Feb-15 10:00 AM
2236 SHUTDOWNSHUTDOWN 412h 10-Feb-15 06:00 AM 27-Feb-15 10:00 AM
2237 IM116350 Verify LT&T and Obtain PTW 4h 10-Feb-15 06:00 AM 10-Feb-15 10:00 AM
2238 IM116355 Blinding as per blindlist 24h 10-Feb-15 10:00 AM 11-Feb-15 10:00 AM
2239 IM116360 Remove insulation from turbine 6h 10-Feb-15 10:00 AM 10-Feb-15 04:00 PM
2240 IM116365 Remove necessary pipes & inst. lines 6h 11-Feb-15 10:00 AM 11-Feb-15 04:00 PM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 35 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.
© Oracle Corporation
# Activity ID Activity Name Original Duration Start Finish
2241 IM116370 Remove coupling guard 2h 11-Feb-15 04:00 PM 11-Feb-15 06:00 PM
2242 IM116375 Record torque meter gap & alignment reading 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM
2243 IM116380 Remove coupling spacer 2h 12-Feb-15 12:00 PM 12-Feb-15 02:00 PM
2244 IM116385 Measure the DBSE and float 4h 12-Feb-15 02:00 PM 12-Feb-15 06:00 PM
2245 IM116390 DE bearing housing removal 4h 13-Feb-15 06:00 AM 13-Feb-15 10:00 AM
2246 IM116395 DE journal bearing inspection 4h 13-Feb-15 10:00 AM 13-Feb-15 02:00 PM
2247 IM116397 DE - Inspect RDT, vibration probes, if required replace it 4h 13-Feb-15 02:00 PM 13-Feb-15 06:00 PM
2248 IM116400 Fix back DE bearing housing 4h 14-Feb-15 06:00 AM 14-Feb-15 10:00 AM
2249 IM116405 NDE bearing housing removal 4h 14-Feb-15 10:00 AM 14-Feb-15 02:00 PM
2250 IM116410 NDE journal & thrust bearing inspection 4h 14-Feb-15 02:00 PM 14-Feb-15 06:00 PM
2251 IM116412 NDE - Inspect RDT, vibration probes, if required replace it 4h 15-Feb-15 06:00 AM 15-Feb-15 10:00 AM
2252 IM116415 Fix back NDE bearing housing 4h 15-Feb-15 10:00 AM 15-Feb-15 02:00 PM
2253 IM116420 Removal of ESV 8h 15-Feb-15 02:00 PM 16-Feb-15 10:00 AM
2254 IM116425 Blind both ends of ESV flanges 6h 16-Feb-15 10:00 AM 16-Feb-15 04:00 PM
2255 IM116430 Disassamble & Inspection of ESV 12h 16-Feb-15 04:00 PM 17-Feb-15 04:00 PM
2256 IM116435 Check, Clean & Replace the strainer if reqd. 6h 17-Feb-15 04:00 PM 18-Feb-15 10:00 AM
2257 IM116440 Inspect - Condition of ESV 6h 18-Feb-15 10:00 AM 18-Feb-15 04:00 PM
2258 IM116445 Assemble ESV 12h 18-Feb-15 04:00 PM 19-Feb-15 04:00 PM
2259 IM116450 Remove end blinds from ESV 6h 19-Feb-15 04:00 PM 20-Feb-15 10:00 AM
2260 IM116455 Reinstall ESV 8h 20-Feb-15 10:00 AM 20-Feb-15 06:00 PM
2261 IM116460 Clean & Inspect governing valves links & bushes 8h 21-Feb-15 06:00 AM 21-Feb-15 02:00 PM
2262 IM116465 Recharge nitrogen for accumulator 4h 21-Feb-15 02:00 PM 21-Feb-15 06:00 PM
2263 IM116470 Connect all lube oil piping's & acce. 8h 21-Feb-15 02:00 PM 22-Feb-15 10:00 AM
2264 IM116475 Fix back instrument lines 4h 22-Feb-15 10:00 AM 22-Feb-15 02:00 PM
2265 IM116485 Fix back insulation 12h 22-Feb-15 02:00 PM 23-Feb-15 02:00 PM
2266 IM116490 Carryout all instrument function test 12h 23-Feb-15 02:00 PM 24-Feb-15 02:00 PM
2267 IM116495 Partial LT&T & Carryout OST of turbine 12h 24-Feb-15 02:00 PM 25-Feb-15 02:00 PM
2268 IM116500 Fix back coupling spacer 4h 25-Feb-15 02:00 PM 25-Feb-15 06:00 PM
2269 IM116505 Fix back coupling guard 4h 26-Feb-15 06:00 AM 26-Feb-15 10:00 AM
2270 IM116507 Carryout De-Blinding & Close PTW 24h 26-Feb-15 10:00 AM 27-Feb-15 10:00 AM
2271 PIPING-MECH-D68PIPING-MECH-D68 28h 12-Feb-15 04:00 PM 15-Feb-15 08:00 AM
2272 R15E-310-045 RC2-32-310-84-ST-301 CGC ST - ATTENDING FLANGE LEAKR15E-310-045 RC2-32-310-84-ST-301 CGC ST - ATTENDING FLANGE LEAK 28h 12-Feb-15 04:00 PM 15-Feb-15 08:00 AM
2273 SHUTDOWNSHUTDOWN 28h 12-Feb-15 04:00 PM 15-Feb-15 08:00 AM
2274 IM117855 Verify LT&T and Obtain PTW 2h 12-Feb-15 04:00 PM 12-Feb-15 06:00 PM
2275 IM117860 Open flanges & Clean flange faces 12h 13-Feb-15 06:00 AM 13-Feb-15 06:00 PM
2276 IM117865 Repair / Renew gaskets & Boxup flanges 12h 14-Feb-15 06:00 AM 14-Feb-15 06:00 PM
2277 IM117867 Close PTW 2h 15-Feb-15 06:00 AM 15-Feb-15 08:00 AM
Sat S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri Sat S M T W T Fri S S M T W Thr Fri Sat S M T W Thr
Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08
RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - DETAIL 01-Jan-15 05:30 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 36 of 36 TASK filters: DUMMY, DUMMY1, DUMMY2.