DRAWING NO.
C001
C100PLANT OUTFALL PLAN & PROFILE
GENERAL NOTES
C101PLANT OUTFALL SECTIONS & DETAILS
DESCRIPTION
ADELAIDE PCP OUTFALL
STRUCTURE
C003ENVIRONMENTAL PROTECTION
C002GENERAL NOTES
GENERAL NOTES AND CONDITIONS
1. ALL WORK SHALL, MEET THE MINIMUM STANDARDS AND SPECIFICATIONS OF THE CITY OF LONDON ENVIRONMENTAL AND
ENGINEERING DEPARTMENT, THE STANDARD CONTRACT DOCUMENTS FOR MUNICIPAL & PROVINCIAL CONSTRUCTION
PROJECTS, AS ADOPTED BY COUNCIL ON MAY 30, 1994 AND AS AMENDED FROM TIME TO TIME ARE TO BE APPLIED TO THIS
PROJECT, UNLESS OTHERWISE APPROVED BY THE CITY ENGINEER.
2. PRIOR TO COMMENCING CONSTRUCTION, ALL EXISTING UNDERGROUND UTILITIES AND EXISTING SERVICES SHALL BE
LOCATED AND MARKED. ANY UTILITIES OR SERVICES DAMAGED OR DISTURBED DURING CONSTRUCTION SHALL BE
REPAIRED OR REPLACED TO THE SATISFACTION OF THE GOVERNING UTILITY AT THE CONTRACTOR'S EXPENSE. ANY
POLE SUPPORT OR RELOCATION SHALL BE CARRIED OUT BY THE APPROPRIATE AUTHORITY AND NOT THE CONTRACTOR,
BUT ANY COSTS ARE AT THE EXPENSE OF THE CONTRACTOR.
3. A GEOTECHNICAL INVESTIGATION WAS UNDERTAKEN BY GOLDER ASSOCIATES, DATED SEPTEMBER 2013, REPORT No.
12-1132-0098-R01.
4. ALL EXCESS MATERIAL IS TO BE HAULED OFFSITE AND MANAGED AS PER OPSS-180.
5. THE CONTRACTOR SHALL VERIFY ALL OUTLET INFORMATION PRIOR TO COMMENCING CONSTRUCTION AND REPORT ANY
DISCREPANCIES TO THE CONTRACT ADMINISTRATOR.
6. ALL MANHOLES, SANITARY & STORM PDC's, CATCH BASIN OR CATCH BASIN LEADS DAMAGED DURING THE CONSTRUCTION
SHALL BE RESTORED AT THE EXPENSE OF THE CONTRACTOR.
7. THE CONTRACTOR SHALL REMOVE, SALVAGE AND REINSTALL ALL SIGNAGE ETC. IMPACTED BY CONSTRUCTION.
8. ALL EXISTING SURFACE AND UNDERGROUND DRAINAGE SYSTEMS ARE TO BE MAINTAINED DURING CONSTRUCTION.
9. IF AN ELECTRICAL DISTRIBUTION LINE IS ENCOUNTERED DURING CONSTRUCTION ON OR ADJACENT TO THIS SITE , THE
CONTRACTOR SHALL PLACE WARNING SIGNS ON THE POLES SUPPORTING THE CONDUCTORS STATING "DANGER -
OVERHEAD ELECTRICAL WIRES" IN ALL LOCATIONS WHERE PERSONNEL AND CONSTRUCTION VEHICLES MIGHT COME IN
CLOSE PROXIMITY TO THE CONDUCTORS.
OPSD-219.110 LIGHT DUTY SILT FENCE BARRIER
OPSD-219.130 HEAVY DUTY SILT FENCE BARRIER
OPSD-219.180 STRAW BALE FLOW CHECK DAM
OPSD-219.240 DEWATERING TRAP
OPSD-219.260 TURBIDITY CURTAIN
OPSD-220.010 BARRIER FOR TREE PROTECTION
OPSD-401.020 CAST IRON, CIRCULAR FRAME WITH CIRCULAR 745mm COVER FOR
MAINTENANCE HOLES
OPSD-405.020 MAINTENANCE HOLE STEPS, SOLID
OPSD-701.011 PRECAST CONCRETE MAINTENANCE HOLE, 1500mm DIA.
OPSD-701.021 MAINTENANCE HOLE BENCHING AND PIPE OPENING ALTERNATIVES
OPSD-701.040 PRECAST CONCRETE MAINTENANCE HOLE COMPONENTS, 1500mm DIA.,
TRANSITION CONE AND SLABS
OPSD-701.041 PRECAST CONCRETE MAINTENANCE HOLE COMPONENTS, 1500mm DIA., RISER
AND BASES
OPSD-704.010 PRECAST CONCRETE ADJUSTMENT UNITS MAINTENANCE HOLES, CATCH
BASINS AND VALVE CHAMBERS
OPSD-802.010 FLEXIBLE PIPE EMBEDMENT AND BACKFILL, EARTH EXCAVATION
OPSD-802.030 RIGID PIPE BEDDING, COVER AND BACKFILL, TYPE 1 OR 2 SOIL, EARTH
EXCAVATION
OPSD-802.031 RIGID PIPE BEDDING, COVER AND BACKFILL,TYPE 3 SOIL, EARTH EXCAVATION
OPSD-802.032 RIGID PIPE BEDDING, COVER AND BACKFILL, TYPE 4 SOIL, EARTH EXCAVATION
OPSD-804.030 CONCRETE HEADWALL FOR PIPE LESS THAN 900mm DIA.
OPSD-804.040 CONCRETE HEADWALL, FOR SEWER OR CULVERT PIPE OUTLET
OPSD-804.050 GRATING FOR CONCRETE ENDWALL
OPSD-810.010 RIP-RAP TREATMENT FOR SEWER AND CULVERT OUTLETS
OPSD-1006.020 SEWER SERVICE CONNECTIONS FOR FLEXIBLE MAIN PIPE SEWER
THE FOLLOWING OPS DRAWINGS
SHALL BE USED ON THIS PROJECT:
OPSS 180 GENERAL SPECIFICATIONS FOR MANAGEMENT OF EXCESS MATERIALS
OPSS 182 ENVIRONMENTAL PROTECTION FOR CONSTUCTION IN WATERBODIES
AND ON WATERBODY BANKS
OPSS 206 CONSTRUCTION SPECIFICATION FOR GRADING
OPSS 310 HOT MIX ASPHALT
OPSS 401 TRENCHING, BACKFILLING, AND COMPACTING
OPSS 402 EXCAVATING, BACKFILLING, AND COMPACTING FOR MAINTENANCE
HOLES, CATCH BASINS, DITCH INLETS, AND VALVE CHAMBERS
OPSS 404 SUPPORT SYSTEMS
OPSS 407 MAINTENANCE HOLE, CATCH BASIN, DITCH INLET AND VALVE
CHAMBER INSTALLATION
OPSS 410 PIPE INSTALLATION IN OPEN CUT
OPSS 492 SITE RESTORATION FOLLOWING INSTALLATION OF PIPELINES,
UTILITIES, AND ASSOCIATED STRUCTURES
OPSS 501 COMPACTING
OPSS 506 DUST SUPPRESSANTS
OPSS 511 RIP-RAP, ROCK PROTECTION, AND GRANULAR SHEETING
OPSS 517 DEWATERING OR PIPELINE, UTILITY, AND ASSOCIATED STRUCTURE
EXCAVATION
OPSS 518 CONTROL OF WATER FROM DEWATERING OPERATIONS
OPSS 801 THE PROTECTION OF TREES
OPSS 802 TOPSOIL
OPSS 803 SODDING
OPSS 804 SEED AND COVER
OPSS 805 TEMPORARY EROSION CONTROL MEASURES
OPSS 1001 AGGREGATES - GENERAL
OPSS 1002 AGGREGATES - CONCRETE
OPSS 1003 AGGREGATES - HOT MIX ASPHALT
OPSS 1010 AGGREGATES - BASE, SUBBASE, SELECT SUBGRADE AND BACKFILL
MATERIAL
OPSS 1820 CIRCULAR CONCRETE PIPE
OPSS 1850 FRAMES, GRATES, COVERS AND GRATINGS
OPSS 1860 GEOTEXTILES
THE FOLLOWING OPS SPECIFICATIONS
SHALL BE USED ON THIS PROJECT:
ALL DISTURBED AREAS SHALL BE RESTORED AS FOLLOWS:
GRANULAR ACCESS ROAD
-150mm GRANULAR "A" BASE MATERIAL COMPACTED TO 100% SPMDD
-400mm GRANULAR "B" SUB BASE MATERIAL COMPACTED TO 100% SPMDD
ASPHALT PAVEMENT (CITY MAINTENANCE ROAD)
-75mm HL3 SURFACE ASPHALT (97% MARSHALL)
-150mm GRANULAR "A" BASE (98% SPMDD)
-375mm GRANULAR "B" (98% SPMDD)
PAVEMENT RESTORATION
SW-1.0 BEDDING STANDARD FOR GRAVITY PIPE
SPO-1.4A ASPHALT MAINTENANCE ROAD
THE FOLLOWING CITY OF LONDON DRAWINGS
SHALL BE USED ON THIS PROJECT:
10.THE CONTRACTOR SHALL COORDINATE ALL CHANGES IN TRAFFIC MOVEMENT WITH THE ROADS OWNER/OPERATING
AUTHORITY AND SHALL FOLLOW M.T.O. TRAFFIC CONTROL MANUAL (BOOK 7) FOR ROADWAY WORK OPERATION.
11.THE CONTRACTOR SHALL NOTE THAT IT IS THEIR RESPONSIBILITY TO PROTECT, SUSTAIN AND ADEQUATELY SUPPORT ALL
EXCAVATION WALLS AND EXISTING UTILITIES AND MAINTAIN THEM IN THEIR ORIGINAL TRENCHES DURING THE WORK AND
MAKE GOOD ANY DAMAGE, WHETHER OR NOT THE TYPE OF SHORING HAS BEEN SPECIFIED.
12.THE CONTRACTOR SHALL COORDINATE WITH THE UTILITY COMPANIES TO FACILITATE UTILITY RELOCATIONS AND SUPPORT
REQUIREMENTS INCLUDING STAMPED DRAWINGS IF REQUIRED BY THE UTILITY.
13.THE CONTRACTOR SHALL CONDUCT ALL HIS OPERATIONS WITHIN THE LIMITS OF THE CONTRACT UNLESS OTHERWISE
DIRECTED BY THE CONTRACT ADMINISTRATOR.
14. THE SETTING OF LINES AND GRADES SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.
15. AN APPROVED SET OF DRAWINGS AND SPECIFICATIONS FOR THE PROJECT MUST REMAIN ON SITE WHILE ANY WORK IS
BEING DONE.
16. ALL EXISTING BOULEVARDS, ROAD SURFACES, ASPHALT DRIVEWAYS AND PLAYGROUND AREAS DISTURBED DURING
CONSTRUCTION SHALL BE RESTORED TO A CONDITION AS GOOD AS THE ORIGINAL OR AS SPECIFIED, WHICHEVER IS THE
MOST STRINGENT.
17. ALL LANDSCAPING INCLUDING DRIVEWAYS, CURBS, RETAINING WALLS, SHRUBS, HEDGES, TREES, ETC. TO BE PRESERVED
AND OR REPLANTED/RECONSTRUCTED TO AS GOOD CONDITION AS EXISTING.
ADELAIDE POLLUTION
CONTROL PLANT
A
D
E
L
A
I
D
E
S
T
R
E
E
T
K
I
P
P
S
L
A
N
E
CONTRACTOR TO KEEP CLEAR
OF SOCCER FIELDS AT ALL
TIMES.
APPROX. SITE LOCATION
ALL EQUIPMENT IS TO STAY
CLEAR OF ASPHALT PATHWAYS
POTENTIAL
STAGING
AREA
S
IT
E
A
C
C
E
S
S
KEY PLAN
PLANT UV CHANNEL TO OUTFALL
SET UP PUMPS HERE.
PROPOSED DISCHARGE LOCATION FOR
TEMP. PUMPING. C/W EROSION CONTROL
MEASURES
TEMP OVERLAND PIPING
ADELAIDE POLLUTION CONTROL PLANT
OUTFALL STRUTURE REPLACMENT
ES 5165-12
GENERAL NOTES
WINTER EROSION CONTROL
IN ORDER TO ENSURE WINTER EROSION CONTROL AND TO MINIMIZE SOIL TRANSPORT, THE FOLLOWING MEASURES WILL
BE IMPLEMENTED:
1. EROSION CONTROL DURING WINTER CONSTRUCTION WILL INCLUDE A PERIMETER SEDIMENT CONTROL FENCE AROUND
ALL WORKING AREAS.
2. INSTALLATION OF SEDIMENT AND WATER CONTROL STRUCTURES (ROCK AND STRAW CHECK DAMS) AT THE EDGE OF
THE RIGHT-OF-WAY WHERE SURFACE WATER SWALES DISCHARGE OR COLLECT.
3. INSTALLATION OF HEAVY DUTY SILT FENCE BARRIER IN THE VICINITY OF ANY WATERCOURSE AS ILLUSTRATED
OPSD-219.130.
4. UNDER FROZEN CONDITIONS, SILT FENCING IS TO BE KEYED IN USING COURSE-GRAINED AGGREGATE MATERIAL; AND,
5. STRAW MULCH APPLICATIONS ARE TO BE ADDED TO EXPOSED TOPSOIL AND SUBSOIL STOCKPILES DURING WINTER TO
MINIMIZE EROSION. (AS ADVISED BY THE CONTRACT ADMINISTRATOR AND ENVIRONMENTAL INSPECTOR).
NOT TO SCALE
200
300
0.75
1.5m
0.30
BACK-FILLING
SAND AND GRAVEL BACKFILL WILL BE USED IF, IN THE OPINION OF THE CONTRACT ADMINISTRATOR, IT IS REQUIRED.
EXCAVATED MATERIAL MAY BE USED FOR BACK-FILL PROVIDED THAT SUCH MATERIALS SUITABLE FOR BACKFILLING IN THE
OPINION OF THE ENGINEER AND GEOTECHNICAL CONSULTANT.
ALL BACKFILLING MATERIAL SHALL BE FREE FROM FOREIGN MATERIALS SUCH AS REFUSE, CINDERS, WOOD, VEGETABLE OR
ORGANIC MATERIAL, BOULDERS, ROCKS, STONES OR OTHER MATERIAL WHICH, IN THE OPINION OF THE ENGINEER, SHOULD
NOT BE USED FOR BACKFILLING.
THE INSPECTOR MAY ORDER THE TRENCH TO BE BACK-FILLED BY HAND FROM THE BOTTOM OF THE TRENCH TO THE
SPRINGLINE OF THE PIPE WITH SAND AND GRAVEL OR OTHER APPROVED MATERIALS IN LAYERS OF 75mm AND COMPACTED
BY MECHANICAL TAMPERING EQUIPMENT. BACKFILLING MATERIAL SHALL BE PLACED IN A TRENCH ON EACH SIDE
SIMULTANEOUSLY.
FROM THE CENTERLINE OF THE PIPE, FITTING OR APPURTENANCES TO A DEPTH OF 0.3m ABOVE THE PIPE, THE TRENCH
SHALL BE BACKFILLED BY HAND OR OTHER METHODS APPROVED BY THE INSPECTOR. THE TYPE OF BACKFILL MATERIAL
SHALL BE SAND, GRAVEL OR APPROVED EXCAVATED MATERIAL. THE CONTRACTOR SHALL TAKE SPECIAL CARE IN PLACING
AND COMPACTING THIS PORTION OF BACKFILLING SO AS TO AVOID DAMAGING OR MOVING THE PIPE.
ZONE 'A' - PIPE BEDDING AS SPECIFIED ON PLAN AND PROFILE DRAWINGS
COMPACTED TO 95% SPMDD IN LAYERS NOT EXCEEDING 150mm, TO
300mm ABOVE PIPE.
ZONE 'B' - SHALL CONSIST OF APPROVED NATIVE MATERIALS OR GRANULAR 'C'
COMPACTED TO 95% SPMDD IN LAYERS NOT EXCEEDING 300mm.
ZONE 'C' - SHALL CONSIST OF APPROVED NATIVE MATERIALS OR GRANULAR 'C'
COMPACTED TO 98% SPMDD IN LAYERS NOT EXCEEDING 300mm UP TO
BOTTOM OF SUBBASE.
ZO
NE
'B
'Z
ON
E 'C
'Z
ON
E 'A
'
TRENCH BACKFILL
(SEE NOTE ABOVE)
COARSE SAND
BEDDING
GEOTEXTILE
(TERRAFIX 270R OR
APPROVED EQUAL)
1/4 Bc 150mm min.
19mm CLEAR STONE
BEDDING
300mm
TRENCH BACKFILL
(SEE NOTE)
COARSE SAND OR
GRANULAR 'A'
150mm min.
GRANULAR 'A'
300mm
N.T.S. N.T.S.
TRENCHING AND PIPE BEDDING
1. TRENCH CONSTRUCTION TO BE IN ACCORDANCE WITH THE LATEST SPECIFICATIONS REGARDING TRENCH WIDTH. (Ont. Reg. 213/91).
2. EXCAVATION WITHIN TYPE 3 SOILS IS TO BE CARRIED OUT USING SIDE SLOPES OF 1:1 FROM THE BOTTOM OF THE EXCAVATION. SIDE SLOPES
OF 1:3 OR FLATTER ARE TO BE USED FOR EXCAVATION IN TYPE 4 SOILS.
3. 19mm CLEAR STONE BEDDING ENCLOSED WITH A SUITABLE GEOTEXTILE (TERRAFIX 270R OR APPROVED EQUAL) TO BE USED WHERE
HYDRAULIC GRADIENT CONDITIONS ARE ANTICIPATED WITH STANDARD BEDDING AS NOTED ON THE PLAN AND PROFILE DRAWINGS BEING
USED IN ALL OTHER AREAS, ALL AS RECOMMENDED BY THE ENGINEER.
4. PIPE BEDDING AS SPECIFIED ON PLAN AND PROFILE DRAWINGS COMPACTED TO 95% SPMDD IN LAYERS NOT EXCEEDING 150mm, TO 300mm
ABOVE THE PIPE.
5. TRENCH BACKFILL FROM TOP OF PIPE BEDDING TO UNDERSIDE OF GRANULAR "B" SUBBASE SHALL CONSIST OF APPROVED NATIVE
MATERIALS COMPACTED TO 95% SPMDD IN LAYERS NOT EXCEEDING 300mm.
6. PRIOR TO PLACING THE GRANULAR SUBBASE MATERIAL, ALL TOPSOIL, SOFT OR OTHERWISE COMPRESSIBLE MATERIAL MUST BE REMOVED
FROM SUBGRADE AREA AND THE SUBGRADE PROOF ROLLED TO COMPACT ANY LOOSE SURFACE ZONES. ALL EXCAVATED AREAS MUST BE
BACKFILLED WITH APPROVED ON-SITE NATIVE MATERIALS OR IMPORTED GRANULAR PIT-RUN MATERIAL, COMPACTED TO 98% SPMDD
CLASS 'B' BEDDINGSTONE BEDDING
MANHOLE
CATCH BASIN
BELL PEDESTEL
MISC. SIGN
CONIFEROUS TREE
DECIDUOUS TREE
GRAVEL SHOULDER
LEGEND:
ASPHALT RAMP AT DOORWAY
CATCH BASIN MANHOLE
ELECTRICAL PULL BOX
BRUSHLINE
GUY WIRE
VALVE
SANITARY FORCEMAIN MARKER
GAS MARKER
GAS MAIN
UNDERGROUND BELL CABLE
PROPOSED SANITARY FORCEMAIN
WATERMAINS
DITCH INLET CATCHBASIN
MAILBOX
GAS
BTUC
POLE
FENCE LINE
FIRE HYDRANT
NOT TO SCALE
N.T.S.
FERTILIZER
1. APPLY AN ORGANIC 8-32-16 RATIO FERTILIZER AT A RATE OF 380KG/HA AT THE TIME OF
SEEDING (BOTH SEED MIXES). FINAL RATIO AND RATE TO BE CONFIRMED FOLLOWING
SOIL TEST.
BENCHMARK
CITY OF LONDON: V92-9
BRONZE CAP IN CONCRETE: ON ADELAIDE STREET, 300m SOUTH OF THE CENTRELINE OF WINDERMERE
ROAD, 7.0m WEST OF THE CENTRELINE OF ADELAIDE STREET, SET IN THE CONCRETE SIDEWALK ON THE
NORTHWEST SIDE OF THE BRIDGE CARRYING ADELAIDE STREET OVER THE NORTH BRANCH OF THE
THAMES RIVER.
ELEVATION: 245.641 metres
50 X50 WOOD POST STANDARD OR
BETTER OR EQUAL ALTERNATE
STEEL FENCE POST AT 1.8m
CENTERS (MAX.)
50mm X 50mm 14
GA. WIRE FABRIC
FILTER FABRIC MATERIAL
(TEXEL 140 OR APPROVED
ALTERNATE)
50 X50 WOOD POST STANDARD OR
BETTER OR EQUAL ALTERNATE
STEEL FENCE POST AT 1.8m
CENTERS (MAX.)
FILTER FABRIC MATERIAL ON 1500mm WIDE
ROLLS OVERLAYING 50mm X 50mm 14 GA.
WIRE FABRIC ATTACHED WITH STAPLES OR
WIRE RINGS
BACKFILL & COMPACT
THE EXCAVATED SOIL
IN TRENCH AND ON
BOTH SIDES OF THE
FILTER FENCE FABRIC
FOLD & SET FILTER
FABRIC INTO SOIL
BURY BOTTOM OF FILTER MATERIAL IN
200mm X 300mm TRENCH
SEED MIXTURES
CITY OF LONDON NATURALIZATION MIX: SPO-8
SEED AT A RATE OF 100KG/10,000M²
(SPO-8, TABLE 1).
SPECIES INCLUDED AS FOLLOWS:
Orchard Grass 12%
Creeping Red Fescue 13%
Perennial Rye Grass 13%
Double Cut Red Clover 17%
Kentucky Blue Grass 17%
Dutch White Clover
13%
O.S.C. Native Prairie
Meadow Mixture 15%
SEEDING
1. THE CONTRACTOR IS RESPONSIBLE TO ENSURE COVERAGE AND SEED MIX CATCH.
2. THE CONTRACTOR IS TO PROVIDE A WRITTEN GUARANTEE STIPULATING A MINIMUM 80% SEED CATCH. AREAS OF PROPERLY
ESTABLISHED SEED WILL BE ACCEPTED BY THE LANDSCAPE ARCHITECT.
3. SEED APPLICATION IS TO BE UNDERTAKEN IN A CONSISTENT AND THOROUGH FASHION COVERING THE ENTIRE SITE INCLUDING
SHRUB AND TREE AREAS, THROUGH, UNDER AND AROUND THE ENTIRE PERIMETER OF PLANTS.
4. SINGLE DIRECTIONAL SPREADING OF SEED MIX IS NOT ACCEPTABLE.
5. CONTACT THE CONTRACT ADMINISTRATOR PRIOR TO SEEDING TO COORDINATE OPERATIONS.
6. ALL SEEDING AND PLANTING OF DISTURBED AREAS MUST OCCUR IMMEDIATELY UPON COMPLETION OF THE GRADING WORK,
WEATHER PERMITTING. SEEDING OPERATIONS WITH THE SPECIFIED SEED MIXTURE MUST BE COMPLETED BETWEEN SPRING
THAW AND JUNE 15TH.
7. SURFACE TO BE UNIFORMLY CULTIVATED TO A MINIMUM DEPTH OF 100mm AND SHALL NOT HAVE SURFACE STONES GREATER
THAN 25mm DIAMETER.
8. ALL TOPSOIL COMPACTED DURING CONSTRUCTION ACTIVITIES IS TO BE SCARIFIED TO THE SATISFACTION OF THE CONTRACT
ADMINISTRATOR PRIOR TO SEED APPLICATION.
9. ALL AREAS DISTURBED DURING REMOVAL OF SEDIMENT AND EROSION CONTROL MEASURES ARE TO BE SEEDED WITH A HAND
BROADCAST APPLICATION OF THE SPECIFIED SEED MIX.
ADELAIDE POLLUTION CONTROL PLANT
OUTFALL STRUTURE REPLACMENT
ES 5165-12
GENERAL NOTES
ENVIRONMENTAL REQUIREMENTS
2. CONDITIONS OF APPROVAL
1. THE CONTRACTOR AND EACH SUBCONTRACTOR, WHILE PERFORMING THE WORK, SHALL COMPLY WITH
RELEVANT STATUTES, REGULATIONS, BYLAWS AND DIRECTIVES OF LEGISLATIVE AUTHORITIES IN ALL
MATTERS RELATING TO THE PROTECTION OF THE ENVIRONMENT. WITHOUT LIMITING THE GENERALITY OF
THE FOREGOING, THE FOLLOWING LEGISLATION IS CALLED TO THE ATTENTION OF THE CONTRACTOR.
A. FEDERAL
I. CANADIAN ENVIRONMENTAL PROTECTION ACT
II. CANADA WILDLIFE ACT
III. FISHERIES ACT
IV. NAVIGABLE WATERS PROTECTION ACT
V. HAZARDOUS PRODUCTS ACT
VI. TRANSPORTATION OF DANGEROUS GOODS ACT
VII. EXPLOSIVES ACT.
B. ONTARIO
I. ENVIRONMENTAL PROTECTION ACT
II. ONTARIO WATER RESOURCES ACT
III. AGGREGATE RESOURCES ACT
IV. ONTARIO HERITAGE ACT
V. PESTICIDE ACT
VI. LAKES AND RIVERS IMPROVEMENT ACT
VII. WILDERNESS AREAS ACT
VIII. FOREST FIRES PREVENTION ACT
IX. GASOLINE HANDLING ACT
X. HIGHWAY TRAFFIC ACT.
C. LOCAL
I. LOCAL MUNICIPAL BYLAWS E.G., NOISE CONTROL, LICENSING OF TRADES PEOPLE
A. ALL PERMITS, AUTHORIZATIONS AND APPROVALS OBTAINED BY THE CONTRACTOR WILL BE
MADE AVAILABLE ONSITE DURING CONSTRUCTION OR WHEN OBTAINED PRIOR TO SITE
SPECIFIC WORK UNDER APPROVAL PROCEEDING.
B. THE CONTRACTOR SHALL FULLY COMPLY WITH ALL CONDITIONS OF SUCH PERMITS,
AUTHORIZATIONS AND APPROVALS.
3. ENVIRONMENTAL SITE AWARENESS
A. THE CONTRACTOR SHALL MAINTAIN AN AWARENESS OF ENVIRONMENTAL REQUIREMENTS
AND DEVELOPING ISSUES ON SITE.
B. THE CONTRACTOR'S ENVIRONMENTAL COORDINATOR IN CONSULTATION WITH THE
CONTRACT ADMINISTRATOR SHALL HOLD FORMAL ENVIRONMENTAL ORIENTATION
MEETINGS INVOLVING KEY SITE PERSONNEL.
C. THE CONTRACTOR SHALL HAVE AN ENVIRONMENTAL COMPONENT AT ITS WEEKLY
WORK-GROUP TOOLBOX MEETINGS INVOLVING ALL WORKERS.
D. ORIENTATION MEETINGS WITH MEMBERS OF THE SITE TEAM SHALL BE HELD AT THE START
OF THE WORK (AT THE TIME OF MOBILIZATION) AND WHEN NEW STAFF JOIN THE
WORKFORCE. ENVIRONMENTAL REVIEW MEETINGS WITH THE SITE TEAM SHALL ALSO BE
HELD AT OTHER KEY TIMES THROUGHOUT THE WORK PRIOR TO STARTING SIGNIFICANT
NEW TASKS.
E. THE CONTRACTOR SHALL REVIEW THE ENVIRONMENTAL CONTENT OF ITS ORIENTATION, AS
WELL AS REVIEW TOOLBOX MEETINGS WITH THE CONTRACT ADMINISTRATOR.
F. THE CONTRACTOR SHALL PROVIDE MINUTES OF ITS ORIENTATION, REVIEW AND TOOLBOX
MEETINGS TO ALL ATTENDEES AND THE CONTRACT ADMINISTRATOR. EACH ATTENDEE
SHALL BE REQUIRED TO SIGN AN ATTENDANCE LIST WHICH INCLUDES A POINT FORM
SUMMARY OF THE MEETING CONTENT.
4. HAZARDOUS SUBSTANCES
A. THE CONTRACTOR SHALL MAKE ITSELF FULLY AWARE OF ALL FEDERAL AND
PROVINCIAL LEGISLATION AND RESTRICTIONS ON THE STORAGE AND USE OF
CERTAIN PRODUCTS OR MATERIALS CONSIDERED HARMFUL TO THE ENVIRONMENT
OR PERSONS AND SHALL COMPLY WITH ALL APPLICABLE REGULATIONS AND
GUIDELINES.
B. THE CONTRACTOR SHALL REQUIRE ITS MANUFACTURERS OR SUPPLIERS TO
PROVIDE CURRENT MATERIAL SAFETY DATA SHEETS (MSDS) FOR ALL SUCH
PRODUCTS AND SHALL COMPLY WITH ALL REQUIREMENTS OF THE WORKPLACE
HAZARDOUS MATERIALS INFORMATION SYSTEM (WHMIS) REGULATIONS.
C. THE CONTRACTOR SHALL PROMPTLY PROVIDE THE CONTRACT ADMINISTRATOR
WITH COPIES OF ALL MSDS RELATING TO ALL HAZARDOUS SUBSTANCES BROUGHT
TO THE PROJECT SITE.
5. WATER MANAGEMENT
A. THE CONTRACTOR SHALL MAKE ITSELF FULLY AWARE OF WATER LEVEL, WATER
FLOW AND WEATHER CONDITIONS IN AND AFFECTING THE WORK AND SHALL
ALLOW FOR ALL EFFECTS THAT ANY SUCH CONDITIONS MIGHT HAVE ON THE
WORK.
B. THE CONTRACTOR SHALL COMPLY WITH ANY PERMIT TO TAKE WATER
REQUIREMENTS OF THE ONTARIO WATER RESOURCES ACT IN CONNECTION WITH
ITS OPERATIONS.
6. WASTE MANAGEMENT
A. THE CONTRACTOR SHALL DISPOSE OF ALL WASTES GENERATED ON SITE AND SHALL BE
RESPONSIBLE FOR ALL PERMITS AND APPROVALS REQUIRED FOR WASTE DISPOSAL. FOR
RECYCLED MATERIALS AND FOR DISPOSAL OF HAZARDOUS, SUBJECT AND CONTAMINATED
WASTES, THE CONTRACTOR SHALL PROVIDE PROOF OF RECYCLING AND/OR DISPOSAL
DOCUMENTATION TO THE CONTRACT ADMINISTRATOR.
B. THE CONTRACTOR SHALL PROVIDE INFORMATION ON QUANTITIES OF PRINCIPAL PRODUCTS
BROUGHT TO SITE AND QUANTITIES OF LIKE PRODUCTS REUSED, RECYCLED AND WASTED IN
THE PROCESS OF USING THESE PRODUCTS. THE CONTRACTOR SHALL ALSO PROVIDE
INFORMATION ON QUANTITIES OF WASTES ARISING FROM DEMOLITION AND CONCRETE
REMOVALS AND CORRESPONDING QUANTITIES REUSED, RECYCLED AND WASTED.
C. WASTE TYPES ANTICIPATED AT THE WORK SITE INCLUDE SANITARY SEWAGE, DOMESTIC
GARBAGE, CONSTRUCTION GARBAGE, CONCRETE AND CEMENT GROUT WASTES, IRON AND
STEEL WASTES, GRANULAR MATERIALS WASTES, SMALL ELECTRICAL FIXTURES, WARE, FORM
WORK AND FALSE WORK WASTES, OPERATING FLUID WASTES FROM VEHICLES AND
CONSTRUCTION EQUIPMENT AND COLLECTED SEDIMENT. DISPOSAL OF THESE AND OTHER
WASTES SHALL BE AS INDICATED IN THIS SECTION. THE CONTRACTOR SHALL RECYCLE
WASTES WHERE POSSIBLE.
D. SANITARY SEWAGE SHALL BE COLLECTED IN PORTABLE TOILET FACILITIES. WASTE SHALL BE
DISPOSED OF AT A LICENSED DISPOSAL LOCATION BY A LICENSED HAULER. WASTE SHALL BE
REMOVED ON A REGULAR BASIS CONSISTENT WITH HEALTH AND SAFETY REQUIREMENTS.
E. THE CONTRACTOR SHALL MINIMIZE THE VOLUMES OF DOMESTIC AND CONSTRUCTION
GARBAGE PRODUCED ON SITE. AN MOE-APPROVED LOCAL LANDFILL SHALL BE USED FOR
DISPOSAL OF DOMESTIC AND CONSTRUCTION GARBAGE. WASTE STORAGE BINS WITH LIDS
SHALL BE PROVIDED BY THE CONTRACTOR AND USED ON SITE FOR COLLECTION AND
TEMPORARY STORAGE OF DOMESTIC GARBAGE. THE CONTRACTOR SHALL ENSURE THAT
WASTES ARE DEPOSITED IN DESIGNATED BINS AND THAT THE SITE IS KEPT IN A CLEAN AND
TIDY CONDITION. WASTE SHALL BE REMOVED ON A REGULAR BASIS TO AVOID
ACCUMULATION ON SITE. ALL ELECTRICAL FIXTURES, WIRING AND OTHER WASTE TYPES,
IMPRACTICAL TO RECYCLE DUE TO ANTICIPATED SMALL VOLUME WILL BE TREATED AS
CONSTRUCTION GARBAGE.
G. THE CONCRETE WASHOUT BASIN AND SURROUNDING AREA SHALL BE STORED UPON
COMPLETION OF THE WORK. LOOSE OR EXPOSED CONCRETE REINFORCING STEEL OR IRON
AND OTHER STEEL WASTES SHALL BE RECYCLED BY THE CONTRACTOR. THE CONTRACTOR
SHALL COLLECT THE RECYCLE METAL WASTES ARISING ON SITE. PREFERENCE SHALL BE
GIVEN TO CONSTRUCTIVE REUSE OF UNCONTAMINATED GRANULAR MATERIAL NO LONGER
REQUIRED FOR PROJECT.
H. QUANTITIES OF CONSTRUCTION LUMBER AND WOOD PRODUCTS WASTED DURING
CONSTRUCTION SHALL BE MINIMIZED. EVERY REASONABLE EFFORT SHALL BE MADE TO
REUSE WASTE OR SURPLUS WOOD. WASTE WOOD THAT CANNOT BE REUSED OR GIVEN
AWAY SHALL BE DISPOSED OF AT AN MOE-APPROVED LOCAL LANDFILL SITE.
I. OPERATING FLUID WASTES ARISING ON SITE FROM VEHICLES AND CONSTRUCTION
EQUIPMENT SHALL BE COLLECTED IN SUITABLE CONTAINERS WITH TIGHT SEALING LIDS AND
SHALL BE REMOVED FROM SITE FOR RECYCLING OR DISPOSAL AS HAZARDOUS WASTE.
J. WASTES SHALL BE PROPERLY LABELED ACCORDING TO WHMIS REGULATIONS.
UNCONTAMINATED COLLECTED AND EXCAVATED SEDIMENT SHALL BE REMOVED FROM THE
SITE FOR DISPOSAL AS INERT FILL OR AS CONSTRUCTION GARBAGE. COLLECTED AND
EXCAVATED SEDIMENT CONTAMINATED, OR SUSPECTED TO BE CONTAMINATED BY
ENVIRONMENTALLY HARMFUL SUBSTANCES SHALL BE REMOVED FROM SITE. THE CRITERIA,
PROCEDURES, TERMS AND CONDITIONS FOR DISPOSAL OF CONTAMINATED SEDIMENT
SHALL BE THOSE SET OUT IN CURRENT MOE REGULATIONS AND GUIDELINES. HAZARDOUS,
SUBJECT AND CONTAMINATED SOLID AND LIQUID WASTES SHALL BE DISPOSED OF OFF SITE
USING LICENSED DISPOSAL AGENTS AND HAULERS. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR REGISTRATION OF ALL HAZARDOUS, SUBJECT AND CONTAMINATED
WASTES UNDER REGULATION 347 OF THE ONTARIO ENVIRONMENTAL PROTECTION ACT.
WASTES SHALL BE PROPERLY STORED AND LABELED ACCORDING TO WHMIS REGULATIONS.
K. THERE SHALL BE NO OPEN OR BURNING WASTE, ETC., ON SITE. THE CONTRACTOR SHALL
PROVIDE FIRE EXTINGUISHERS FOR ALL MECHANICAL EQUIPMENT.
7. SURFACE WATER QUALITY PROTECTION
A. THE CONTRACTOR SHALL ENSURE THAT NO SEDIMENTS, WASTE SUBSTANCES OR MATERIALS
RESULTING FROM WORK ACTIVITIES ENTER THE MUNICIPAL DRAINS.
B. THE CONTRACTOR SHALL UNDERTAKE ALL WATER QUALITY MONITORING, SAMPLING AND
TESTING NECESSARY TO DETERMINE AND /OR CONFIRM TO THE SATISFACTION OF THE
CONTRACT ADMINISTRATOR THE EFFECTS OF THE WORK ON THE QUALITY OF THE WATER IN
WATERCOURSES AND WATER BODIES ADJOINING OR AFFECTED BY THE WORK.
C. THE CONTRACTOR SHALL VISUALLY MONITOR WATER QUALITY WITH RESPECT TO
BACKGROUND AND PROJECT-RELATED SEDIMENT LOADING ON A DAILY BASIS AND SHALL
RECORD THESE OBSERVATIONS IN A WATER QUALITY LOG. VISUAL MONITORING SHALL BE IN
THE FORM OF AN ONGOING VISUAL AWARENESS ON THE PART OF THE WORK CREW OF THE
EFFECTS OF THE WORK ON WATER QUALITY, WITH SUMMARY OBSERVATIONS, INCLUDING
WATER ELEVATIONS, BEING RECORDED DAILY IN THE LOG. PARTICULAR ATTENTION SHALL BE
PAID TO MONITORING DURING GROUTING OPERATIONS. WHERE RELEASES OF SEDIMENT
BECOME EVIDENT, THE CONTRACT ADMINISTRATOR MAY REQUIRE PERIODIC WATER
SAMPLING AND TESTING TO DETERMINE ACTUAL TOTAL SUSPENDED SOLIDS (TSS) LEVELS
AND/OR TO SUPPORT AND CONFIRM VISUAL WATER QUALITY OBSERVATIONS.
D. ALL WORK AFFECTING ANY WATERCOURSE OR WATER BODY SHALL CEASE UPON A SPILL OF
SEDIMENT TO A RECEIVING WATERCOURSE OF WATER BODY. A SPILL OF SEDIMENT IS
DEFINED AS A RELEASE OF SEDIMENT TO A RECEIVING WATERCOURSE OR WATER BODY
SUCH THAT THE LEVEL OF SEDIMENT IS INCREASED BY MORE THAT 15MG/L (TSS) ABOVE THE
BACKGROUND LEVEL AT THE POINT OF DISCHARGE. THE CONTRACTOR MAY INITIALLY
ASSESS THE LEVEL OF SUSPENDED SOLIDS BY VISUAL OBSERVATION AND SUBSEQUENTLY
CONFIRM THESE OBSERVATIONS BY SAMPLING AND TESTING. THE RULING OF THE CONTRACT
ADMINISTRATOR ON THE VISUALLY ASSESSED LEVEL OF IN-WATER SEDIMENT CONSTITUTING
A SPILL SHALL BE BINDING IN THE ABSENCE OF THE RESULTS OF TESTS CONDUCTED AT THE
TIME OF DISCOVERY OF A POTENTIAL SPILL. ALL NECESSARY MEASURES SHALL BE TAKEN BY
THE CONTRACTOR TO STOP THE RELEASE. THE CONTRACT ADMINISTRATOR WILL NOT ALLOW
WORK TO RESUME ON THE TASK WHICH RESULTED IN THE RELEASE UNTIL THE SITE
OPERATIONS OF THE CONTRACTOR HAVE BEEN REVIEWED AND PROCEDURES ACCEPTABLE
TO THE CONTRACT ADMINISTRATOR FOR CONTINUING THE WORK ON THE PARTICULAR TASK
HAVE BEEN ESTABLISHED.
E. THE CONTRACTOR SHALL PROVIDE UPDATED COPIES OF ITS WATER QUALITY LOG, AND THE
RESULTS OF ALL WATER QUALITY TESTING UNDERTAKEN TO THE CONTRACT ADMINISTRATOR
AT THE WEEKLY PROGRESS MEETINGS.
F. THE CONTRACTOR SHALL PREVENT GROUT MATERIALS FROM ENTERING WATERCOURSE OR
WATER BODIES.
G. THE CONTRACTOR SHALL REPORT TO THE CONTRACT ADMINISTRATOR WITHOUT DELAY ALL
OBSERVED RELEASE OF SEDIMENT TO AN ADJOINING WATERCOURSE OR WATER BODY UPON
THEIR DISCOVERY AND SHALL IMMEDIATELY TAKE MEASURES TO EFFECTIVELY STOP SUCH
RELEASES AND PREVENT THE OCCURRENCE OF A SEDIMENT SPILL. ALL SPILLS OF SEDIMENT
SHALL BE DEALT WITH AND REPORTED AS REQUIRED BY THE SPILL REPORTING
REQUIREMENTS IN THIS SPECIFICATION AND AS REQUIRED BY REGULATION.
H. ACCIDENTAL CHEMICAL OR EQUIPMENT OPERATING FLUID SPILLS WHICH MAY ENTER A
WATER BODY SHALL BE CLEANED UP IMMEDIATELY BY THE CONTRACTOR AND REPORTED AS
REQUIRED AS DETAILED IN THIS SPECIFICATION AND AS REQUIRED BY REGULATION.
8. SEDIMENT, EROSION AND DUST CONTROL
A. THE CONTRACTOR. SHALL BE RESPONSIBLE FOR SEDIMENT, EROSION AND DUST
CONTROL ON THE SITE BOTH ON LAND AND WATERCOURSES AND WATER BODIES
ADJOINING AND/OR AFFECTED BY THE WORK. THE CONTRACTOR SHALL PROVIDE AND
MAINTAIN ALL SEDIMENT, EROSION AND DUST CONTROL INSTALLATIONS AS REQUIRED
BY SITE CONDITIONS AND/OR AS REQUIRED FROM TIME TO TIME BY THE CONTRACT
ADMINISTRATOR.
B. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE DESIGN, OPERATION AND
MAINTENANCE OF ALL SEDIMENT, EROSION AND DUST CONTROL FACILITIES TO MEET
THE REQUIREMENTS OF THE CONTRACT, REGULATIONS AND APPROVALS GRANTED
FOR THIS PROJECT SPECIFIED. THE CONTRACTOR SHALL REVIEW ITS DESIGNS AND
PLANS FOR SEDIMENT CONTROL WITH THE CONTRACT ADMINISTRATOR AT THE START
OF THE WORK AND PRIOR TO CRITICAL STAGES OF THE WORK AS IT PROGRESSES.
C. CONTAINMENT, SETTLING AND/OR DIRECT FILTERING TECHNIQUES SHALL BE USED TO
CONTROL SUSPENDED SOLIDS IN ALL SITE DISCHARGE WATER AND RUNOFF AND TO
CONTAIN WORK AREA SEDIMENT RELEASES IN WATER, AS NECESSARY TO MEET THE
WATER QUALITY REQUIREMENTS AS DETAILED IN THIS SPECIFICATION. TURBID WATER
IN PUMP DISCHARGES SHALL BE PASSED THROUGH FILTER SOCKS OR BAGS AS THE
PRIMARY SEDIMENT RETENTION SYSTEM FOR DEWATERING PUMP DISCHARGES.
D. THE CONTRACTOR SHALL TAKE MEASURES TO ENSURE THAT A STABLE BASE, NOT
PRONE TO EROSION, IS PROVIDED AT ALL TIMES IN LAY DOWN, WORK AND OTHER
AREAS WHICH ARE OR BECOME, PRONE TO DISTURBANCE. EROSION AND SEDIMENT
CONTROL MEASURES SUCH AS SILT FENCES AND STRAW BALE BARRIERS SHALL BE
USED IN DRAINAGE AND RUNOFF AREAS ON LAND AND WITHOUT DEWATERING AREAS
AS REQUIRED BY SITE CONDITIONS.
E. THE CONTRACTOR SHALL INSTALL SILT FENCES, SILT CURTAINS AND OTHER SEDIMENT
CONTROL STRUCTURES. SILT FENCES SHALL BE INSTALLED AROUND THE LAY DOWN
AREA PRIOR TO COMMENCEMENT OF CONSTRUCTION ACTIVITIES AND MOBILIZATION OF
EQUIPMENT AND MATERIALS.
H. ALL STOCKPILES SHALL BE PROTECTED AGAINST EROSION.
I. DUSTS SHALL BE CONTROLLED FOR THE DURATION OF THE WORK.
J. REGULAR MECHANICAL SWEEPING, ENVIRONMENTALLY ACCEPTABLE DUST SUPPRESSANTS
AND/OR WATER SHALL BE USED AS NECESSARY TO CONTROL DUST ON THE ACCESS ROAD
AND IN LAY DOWN AND WORK AREAS.
K. OILS SHALL NOT BE USED FOR DUST CONTROL.
L. THE CONTRACTOR SHALL NOT USE CHEMICAL DUST SUPPRESSANTS.
9. SPILL CONTINGENCY PLANNING
A. THE CONTRACTOR SHALL ENDEAVOR AT ALL TIMES THROUGHOUT THE WORK TO
PREVENT SPILLS, AND PROVIDE IN THE EVENT OF A SPILL, THE BEST RESPONSE
WITHIN THE SHORTEST POSSIBLE TIME.
B. ENVIRONMENTAL LEGISLATION WITH RESPECT TO SPILLS TREATS SEDIMENT
RELEASES TO WATER AS SPILLS DETRIMENTAL TO THE NATURAL ENVIRONMENT.
SEDIMENT RELEASES TO A WATERCOURSE OR WATER BODY ARE THEREFORE
INCLUDED IN THE SAME CATEGORY AS SPILLS OF POLLUTANTS.
C. THE CONTRACTOR SHALL DESIGNATE AN EMERGENCY RESPONSE COORDINATOR
(ERC) FROM SUITABLY QUALIFIED MEMBER OF ITS SITE WORKFORCE. THE
CONTRACTOR SHALL SUBMIT THE NAME OF THE ERC FOR REVIEW AND
CONCURRENCE.
D. ABSORBENT BOOMS SHALL ALSO BE PROVIDED AND KEPT READILY AVAILABLE AT
NEAR\QC WATER WORK AREAS FOR LOCAL DEPLOYMENT AS A PRECAUTIONARY
MEASURE.
E. ABSORBENT MATERIAL SHALL BE ON HAND AT ALL WORK AREAS, AT EQUIPMENT
STORAGE OR PARKING AREAS AND AT ALL REFUELING LOCATIONS AS A MEANS OF
CONTAINING AND SOAKING UP ANY SPILL SUBSTANCE BEFORE IT REACHES THE
GROUNDWATER TABLE OR OPEN WATER.
F. UNLESS OTHERWISE APPROVED BY THE CONTRACT ADMINISTRATOR, DRIP AND SPILL
TRAYS SHALL BE CONSTRUCTED ON METAL OR RIGID MOLDED PLASTIC. DRIP AND
SPILL TRAYS SHALL BE EFFECTIVELY OF ON-PIECE CONSTRUCTION, HAVE NO LEAKS
AND SHALL NOT BE READILY DEFORMABLE.
G. EMPTY OPEN-HEAD DRUMS WITH SEALABLE LIDS SHALL BE PROVIDED ON SITE FOR
PREDISPOSAL STORAGE OF SPILLABLE SUBSTANCES AND FOR DISPOSAL OF USED
ABSORBENTS, CONTAMINATED SOIL, ETC. A MINIMUM OF FOUR 205-L NOMINAL SIZE
DISPOSAL DRUMS SHALL BE PROVIDED AND SUITABLY LOCATED ON SITE.
H. THE CONTRACTOR SHALL PROVIDE A MINIMUM OF TWO COMPLETE SPILL KITS TO BE
LOCATED IN THE PRINCIPAL WORK AREAS. THE EXACT LOCATION OF ANY SPILL KIT
WITHIN A WORK AREA MAY VARY BUT A KIT SHALL ALWAYS BE LOCATED IN CLOSE
PROXIMITY TO THE ACTUAL WORK ZONE AND SHALL BE READILY ACCESSIBLE.
I. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REPORTING SPILLS. ALL SPILLS SHALL
BE REPORTED TO THE CONTRACT ADMINISTRATOR IMMEDIATELY FOLLOWING THEIR
DISCOVERY AND ATTENTION TO IMMEDIATE SAFETY AND CONTAINMENT CONCERNS.
ALL SPILLS TO THE NATURAL ENVIRONMENT SHALL BE REPORTED TO THE CONTRACT
ADMINISTRATOR AND THE MOE (SPILLS ACTION CENTRE 1-800-268-6060) AND OTHER
EXTERNAL AGENCIES.
J. THE CONTRACTOR SHALL SUBMIT WRITTEN SPILL NOTIFICATION REPORTS TO THE
CONTRACT ADMINISTRATOR WITHIN NOT MORE THAN 2 WORKING DAYS AFTER THE
DISCOVERY OF A SPILL.
K. ALL SPILLS TO THE NATURAL ENVIRONMENT RESULTING FROM ACTION OR INACTION
ON THE PART OF THE CONTRACTOR OR ITS SUBCONTRACTORS SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR. ALL TESTING REQUIRED BY THE
CONTRACTOR, THE CONTRACT ADMINISTRATOR OR MNR IN CONNECTION WITH A SPILL
SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.
I. EXCESS GROUT AND OTHER LIQUID WASTE PRODUCTS SHALL BE DIRECTED TO
SECURE CONTAINMENT FACILITIES FOR SUBSEQUENT REMOVAL AND DISPOSAL IN
ACCORDANCE WITH CURRENT ENVIRONMENTAL REQUIREMENTS.
10. CONSTRUCTION LAY DOWN, PARKING, ACCESS AND WORK AREAS
A. LAY DOWN AREAS HAVE BEEN IDENTIFIED AND DESIGNATED FOR USE BY THE
CONTRACTOR, AS SHOWN ON THE DRAWINGS. MATERIALS AND EQUIPMENT
STORAGE, PARKING AND SITE OFFICE FACILITIES WILL BE RESTRICTED TO THE AREA
DEVELOPED AS A LAY DOWN AREA.
B. THE CONTRACTOR SHALL PREPARE, DEVELOP AND MAINTAIN LAY DOWN, PARKING
ACCESS, WORK AND STAGING AREAS AS REQUIRED TO EXECUTE THE WORK. THERE
SHALL BE NO CLEARING OR CUTTING OF TREES OR SHRUBS EXCEPT AS ALLOWED BY
THE CONTRACT ADMINISTRATOR. THERE SHALL BE NO STRIPPING OF EXISTING
SURFICIAL SOILS AND MATERIALS ON SITE EXCEPT AS REQUIRED FOR THE
PROVISION OF AN EXCESS CONCRETE/TRUCK MIXER WASHINGS DISPOSAL BASIN.
C. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE SECURITY OF ALL WORK AND
ACCESS AREAS ADJOINING AREAS OPEN TO THE PUBLIC AND SHALL AT ALL TIMES
PREVENT PUBLIC ACCESS TO THE WORK.
D. THE SECURITY OF THE PROPERTY OF THE CONTRACTOR ON SITE SHALL BE ENTIRELY
THE RESPONSIBILITY OF THE CONTRACTOR. INSTALLATION OF TEMPORARY
SECURITY FACILITIES SHALL BE AT THE DISCRETION OF THE CONTRACTOR AND
SUCH FACILITIES SHALL BE REMOVED ON COMPLETION OF THE WORK.
E. LAY DOWN, PARKING, WORK AND ACCESS AREAS SHALL BE CLEANED OF ALL
CONSTRUCTION MATERIALS AND DEBRIS AND SHALL BE RESTORED BY THE
CONTRACTOR UPON COMPLETION.
11. WORK NEAR WATER
A. THE CONTRACTOR IS PROHIBITED FROM WORKING WITHIN THE RIVER WITHOUT OBTAINING
APPROVAL FROM THE MNR EITHER DIRECTLY OR THROUGH THE LOCAL GOVERNING AUTHORITY.
WORKING INCLUDES BUT IS NOT LIMITED TO THE PLACEMENT OF PERMANENT OR TEMPORARY
STRUCTURES, TRAVERSING THROUGH THIS AREA WITH EQUIPMENT OR MATERIAL, DEPOSITING ANY
MATERIAL WITHIN THE RIVER.
B. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO FULLY FAMILIARIZE ITSELF WITH WATER LEVEL
AND FLOW CONDITIONS IN THE MUNICIPAL DRAINS AND TO ANTICIPATE THE EFFECTS THAT ANY
WATER LEVELS AND FLOWS MAY HAVE ON THE WORK.
C. THE CONTRACTOR SHALL MEET THE WATER QUALITY PROTECTION REQUIREMENTS AND THE
EROSION AND SEDIMENT CONTROL REQUIREMENTS OF THIS SPECIFICATION AND ALL APPLICABLE
REGULATIONS. TURBID WATER SHALL NOT BE DIRECTLY DISCHARGED TO THE LAKE OR RIVER.
D. ANY DEWATERING, WATER CONTAINMENT, SETTLING AND/OR FILTERING AND DRAINAGE FACILITIES
SET UP IN WORK AREAS SHALL BE REMOVED IN THEIR ENTIRETY UPON COMPLETION OF THE WORK.
COLLECTED AND EXCAVATED SEDIMENTS SHALL BE CAREFULLY REMOVED FOR DISPOSAL
REQUIREMENTS IN ACCORDANCE WITH THIS SPECIFICATION AND ALL APPLICABLE REGULATIONS.
E. WHERE GEOTEXTILES AND PLASTIC GEOMEMBRANES ARE USED, THEY SHALL BE REMOVED IN THEIR
ENTIRETY ON COMPLETION AND DISPOSED OF AT AN APPROVED LOCAL LANDFILL. GEOTEXTILE
CONTAINING CONTAMINATED SEDIMENT SHALL BE DISPOSED OF IN ACCORDANCE WITH THIS
SPECIFICATION AND ALL APPLICABLE REGULATIONS.
12. LIQUID STORAGE, REFUELING AND EQUIPMENT OPERATION
A. ON-SITE BULK FUEL STORAGE TANKS AND BULK STORAGE FOR OTHER ENVIRONMENTALLY HAZARDOUS
LIQUIDS SHALL BE LOCATED AT LEAST 30 M AWAY FROM THE RIVER, WITHIN DYKES OR EQUIVALENT
SECONDARY CONTAINMENT ON FLAT GROUND IN THE LAY DOWN AREA.
B. CONTAINMENT IN LIQUID STORAGE AREAS SHALL BE SUCH AS TO CONTAIN THE TOTAL VOLUME STORED
PLUS PRECIPITATION. A MINIMUM SECONDARY STORAGE CAPACITY EQUIVALENT TO 110% OF THE
VOLUME OF STORED LIQUIDS SHALL BE PROVIDED.
C. THE CONTRACTOR SHALL REGULARLY CHECK ALL SPILL CONTAINMENT FACILITIES FOR PRECIPITATION
AND SPILLED SUBSTANCE AND MAINTAIN THESE FACILITIES IN A CLEAN AND SERVICEABLE CONDITION,
REGULARLY REMOVING PRECIPITATION TO MAINTAIN THE SECONDARY STORAGE VOLUME. WHERE
EFFECTIVE, SECONDARY CONTAINMENT CANNOT OTHERWISE BE ACHIEVED, PROTECTION AGAINST
SEEPAGE SHALL BE PROVIDED BY THE USE OF IMPERMEABLE LINERS.
D. FUEL AND OTHER LIQUIDS REQUIRED FOR THE WORK SHALL NOT BE TRANSPORTED TO AND/OR
TEMPORARILY STORED IN THE WORK AREA IN QUANTITIES OF MORE THAN 30 M AWAY FROM A
WATERCOURSE OR WATER BODY AND WITHIN SECURE SECONDARY CONTAINMENT OF AN APPROPRIATE
SIZE. SECURE SECONDARY CONTAINMENT AS SPECIFIED ABOVE SHALL BE PROVIDED THROUGHOUT ALL
THE TRANSPORTATION AND TEMPORARY WORK AREA STORAGE.
E. SMALL CONTAINERS OF FUEL AND OTHER CHEMICAL PRODUCTS SHALL HAVE SECURE SECONDARY
CONTAINMENT AND SHALL BE PROTECTED AT ALL TIMES FROM ACCIDENTAL SPILLAGE.
F. ABSORBENT MATERIALS SHALL BE ON HAND AT ALL LIQUID STORAGE AREAS, WHETHER FOR LARGE OR
SMALL VOLUMES, AS A MEANS OF CONTAINING OR SOAKING UP ERRANT SPILLS.
G. EMPTY OPEN-HEAD DRUMS WITH SEALABLE LIDS SHALL BE ON HAND FOR PRE-DISPOSAL STORAGE OF
SPILLED SUBSTANCES; SUFFICIENT DRUMS SHALL BE AVAILABLE TO ACCOMMODATE STORED AND
IN-SERVICE VOLUMES OF SPILLABLE SUBSTANCES.
H. REFUELING SHALL BE UNDERTAKEN AS FOLLOWS:
I. MOBILE HIGHWAY VEHICLES SHALL BE REFUELED OFF SITE.
II. EQUIPMENT WHICH IS NOT READILY MOBILE MAY BE REFUELED AT THE WORK SITE LOCATION AS
FAR AS POSSIBLE FROM OPEN WATER OR WATERCOURSES. DRIP TRAYS SHALL BE USED AND
ABSORBENT MATERIALS SHALL BE IMMEDIATELY ON HAND FOR USE IN PREVENTING A SPILL.
III. WHEN ENGAGED IN REFUELING, WORKERS SHALL HAVE WITH THEM A SUPPLY OF ABSORBENT
MATERIAL AND DRIP TRAYS AS REQUIRED TO MEET ALL NEEDS IN CONTAINING AND/OR SOAKING
UP ALL SPILLS DURING REFUELING OPERATION.
I. EQUIPMENT OPERATION SHALL BE UNDERTAKEN FOLLOWING THESE PROCEDURES:
I. EQUIPMENT WORKING NEAR WATER SHALL BE CLEANED AND SERVICED AS NECESSARY TO
PREVENT DEPOSITION OF SOILS, OIL, GREASE, COOLANT, FUEL AND ANY OTHER CONTAINMENT.
II. STATIONARY EQUIPMENT OPERATION NEAR OPEN WATER OR IN DEWATERED AREAS SHALL BE
EQUIPPED WITH DRIP TRAYS TO CONTAIN ANY FUEL, OIL, COOLANT OR GREASE LEAKAGE.
EQUIPMENT DRIP TRAYS SHALL BE OF A SUFFICIENT SIZE TO EFFECTIVELY PROTECT FROM ALL
POTENTIAL DRIPS OR SPILLS THE PLAN AREA BENEATH EACH PIECE OF EQUIPMENT FOR WHICH
PROTECTION IS PROVIDED. DRIP TRAYS FOR CONCRETE PUMPS, GROUT PUMPS AND GROUT
RESERVOIRS SHALL BE CAPABLE OF CONTAINING ALL ACCIDENTAL SPILLS/LEAKAGE DURING
OPERATION AND HOSE CONNECTION.
III. TRUCK AND EQUIPMENT WASHING INVOLVING THE REMOVAL OF COLLECTED DIRT, GREASE, OIL
AND OTHER CONTAINMENTS IS NOT PERMITTED ON SITE. CONCRETE MIXERS, CEMENT GROUT
MIXERS AND ASSOCIATED EQUIPMENT SHALL BE WASHED OUT SUCH THAT ALL CONCRETE AND
CEMENT GROUT WASHINGS ARE DISCHARGED INTO THE EXCESS CONCRETE DISPOSAL BASIN IN
THE LAY DOWN AREA.
IV. NO EQUIPMENT SHALL BE WASHED IN OR NEAR OPEN WATER OR WATERCOURSES.
V. ALL EQUIPMENT SHALL BE IN GOOD CONDITION AND MEET APPLICABLE STATUTORY
REQUIREMENTS FOR SERVICEABILITY AND EXHAUST EMISSIONS. EXHAUST SYSTEMS SHALL
FUNCTION IN A MANNER TO CONTROL EXHAUST NOISE WITHIN ACCEPTABLE REGULATED LEVELS.
VI. MAJOR REPAIRS TO EQUIPMENT WILL NOT BE PERMITTED AT THE WORK SITE. ROUTINE
EQUIPMENT SERVICING OF A MINOR NATURE WILL BE ALLOWED ON SITE WITH THE PROVISION
THAT DRIP/SPILL TRAYS BE USED TO CONTROL ONGROUND SPILLAGE OF FUELS, OILS, COOLANTS
AND GREASE.
J. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY AND ALL CLEANUP OF CONTAMINATION RESULTING
FORM ITS OPERATIONS.
K. CONTAMINATED GRANULAR MATERIALS AND OTHER CONTAMINATED SOILS SHALL BE CAREFULLY
EXCAVATED AND SHALL BE DISPOSED OF ACCORDING TO MOE REGULATIONS AND GUIDELINES. THESE
MATERIALS MAY BE CLASSIFIED AS HAZARDOUS WASTE.
I. SOILS AND SIMILAR MATERIALS CONTAMINATED BY EQUIPMENT OPERATING FLUIDS SHALL BE REMOVED
FROM SITE AND DISPOSED OF IN ACCORDANCE WITH THIS SPECIFICATION AND ALL APPLICABLE
REGULATIONS.
13. CONSTRUCTION NOISE CONTROL
A. UNLESS AS DETAILED` AS. A SEPARATE ITEM IN THE "SCHEDULE OF ITEMS AND
PRICES" IN THE FORM OF TENDER SECTION AND SUBSEQUENTLY DESCRIBED
UNDER ANOTHER SECTION WITHIN THE SPECIFICATIONS, NO SEPARATE PAYMENT
WILL BE MADE FOR THE PROVISION OF ALL LABOUR, MATERIALS, PLANT AND
EQUIPMENT TO COMPLY WITH THE ENVIRONMENTAL REQUIREMENTS OF THIS
SECTION OF THE SPECIFICATIONS. FULL COMPENSATION FOR COMPLYING WITH
ALL THE REQUIREMENTS OF THIS SECTION SHALL BE DEEMED TO BE INCLUDED IN
THE PAYMENTS FOR THE WORK TO WHICH THESE REQUIREMENTS ARE RELATED.
B. CONSTRUCTION SAFETY (OHSA REQUIREMENTS) AND LOCAL MUNICIPAL BYLAWS
SHALL PROVIDE THE REGULATORY BASIS FOR NOISE CONTROL AND HEARING
PROTECTION. NOISE BYLAWS OR FORMAL EXEMPTION THEREOF SHALL BE USED IN
SETTING HOURS OF WORK LIMITATIONS.
F. UNLESS DETAILED OTHERWISE IN THE CONTRACT DRAWINGS OR SPECIFICATION, THE
SILT FENCE AND FILTERING SYSTEM DESIGN SHALL CONFORM TO THE FOLLOWING
SPECIFICATIONS:
I. SILT FENCE DESIGN SHALL BE BY CONTRACTOR. "SNOW"FENCING LINED WITH
FILTER FABRIC SHALL BE ATTACHED TO POSTS SECURELY SET IN THE GROUND.
SILT FENCE FILTER FABRIC SHALL BE TERRAFIX 270 R SYNTHETIC FIBRE FABRIC
OR EQUIVALENT APPROVED BY THE CONTRACT ADMINISTRATOR.
II. FILTER MATERIAL FOR USE AS FILTER SOCKS OR BAGS ON DEWATERING PUMP
DISCHARGE HOSES OR FOR USE IN SETTLING BASIN OVERFLOW WEIRS SHALL BE
COMPRISED OF TERRAFIX 370 RS SYNTHETIC FIBRE FABRIC OR APPROVED
EQUIVALENT. FILTER SOCKS AND FILTER BAGS SHALL HAVE A MINIMUM SURFACE
FILTERING AREA OF NOT LESS THAN 80 TIMES THE CROSS-SECTIONAL AREA OF
THE DISCHARGE HOSE TO WHICH THEY ARE ATTACHED.
III. CLOGGED, RUPTURED OR OTHERWISE INEFFECTIVE FILTER SOCKS AND FILTER
BAGS SHALL BE REPLACED WITHOUT DELAY TO MAINTAIN THE SERVICEABILITY OF
DEWATERING PUMP DISCHARGE FILTERING SYSTEMS.
G. A VISUAL INSPECTION OF THE SEDIMENT, EROSION AND DUST CONTROL MEASURES
SHALL BE COMPLETED DAILY AND REPAIRS TO ANY DAMAGES TO BE COMPLETED
IMMEDIATELY UPON IDENTIFICATION.
F. ALL EXCESS WET CONCRETE, EXCESS CEMENT GROUT TRUCK MIXER WASHINGS SHALL BE
DISPOSED OF IN A WASHOUT BASIN TO BE DEVELOPED BY THE CONTRACTOR IN THE LAY
DOWN AREA AWAY FROM THE RIVER AT THE SITE. THE PROPOSED DESIGN OF THE EXCESS
WET CONCRETE WASHOUT BASIN SHALL BE SUBMITTED TO THE CONTRACT ADMINISTRATOR
FOR APPROVAL. THE BASIN SHALL BE FORMED BY SUBSTANTIAL BERMS OF IMPORTED SAND
AND MATERIAL EXCAVATED FOR THE BASIN SHALL BE USED TO FORM A BERM AROUND THE
BASIN OR STOCKPILED FOR FUTURE USE IN RESTORATION. HARDENED EXCESS CONCRETE,
CEMENT GROUT AND UNCONTAMINATED WASHINGS IN A DISPOSAL BASIN SHALL BE
REMOVED FOR DISPOSAL AS CONCRETE RUBBLE IF THE CAPACITY FOR THE BASIN IS
REACHED BEFORE COMPLETION OF THE WORK.
ADELAIDE POLLUTION CONTROL PLANT
OUTFALL STRUTURE REPLACMENT
ES 5165-12
ENVIRONMENTAL PROTECTION
THAMES RIVER
ADELAIDE POLLUTION CONTROL PLANT
OUTFALL STRUTURE REPLACEMENT
ES 5165-12
PLANT OUTFALL
PLAN & PROFILE
ADELAIDE PCP OUTFALL SEWER-PLAN
SECTION A-A
(SEE DRAWING C100)
CONSIDERATIONS FOR STAGING OPERATIONS
THIS INFORMATION IS BEING PROVIDED AS A GUIDE FOR THE CONTRACTOR TO ASSIST THEM IN PREPARING THE
CONSTRUCTION STAGING PLAN FOR THIS PROJECT.
1. THE CITY OF LONDON OPERATIONS CAN TEMPORARILY HOLD FLOW BACK AT THE PLANT FOR APPROXIMATELY 6 HOURS
TO ASSIST WITH THE INSTALLATION OF THE HEADWALL. THIS WORK NEEDS TO BE COORDINATED WITH THE CITY PLANT
OPERATION STAFF AT LEAST 72 HOURS IN ADVANCE OF THE WORK. THE WORK MAY BE DELAYED OR POSTPONED AT ANY
TIME DUE TO FORECASTED WEATHER AND ANTICIPATED PLANT FLOWS. THE CONTRACTOR MAY EXPLORE THE OPTION TO
WORK AFTER HOURS OR ON WEEKENDS TO FURTHER EXTEND THE POSSIBLE SHUTDOWN TIME OF THE OUTLET PIPE.
THIS WILL HAVE TO BE DISCUSSED IN DETAIL WITH THE CITY OPERATIONS STAFF.
2. IF THE CONTRACTOR ANTICIPATES REQUIRING A LONGER SHUT DOWN THAN 6 HOURS TO COMPLETE THE INSTALLATION
OF THE HEADWALL STRUCTURE TEMPORARY PIPING & PUMPING CAN BE USED TO DIVERT FLOW FROM THE EXISTING UV
CHANNEL AT THE PLANT TO A NEAR BY DITCH ( REFER TO DRAWING C001) THIS MAY INCREASE THE LENGTH OF THE
SHUTDOWN. IF TEMPORARY PUMPING IS USED THE CONTRACTOR WILL BE RESPONSIBLE FOR ALL SEDIMENT AND
EROSION CONTROL MEASURES AND DISSIPATING THE FLOW PRIOR TO ENTERING THE DITCH TO ENSURE NO WASH OUTS
OCCUR. REFER TO THE SPECIAL PROVISION ITEM M10 FOR FURTHER INFORMATION ON TEMPORARY PUMPING.
3. THE CONTRACTOR SHOULD PREPARE AS MUCH OF THE EXCAVATION, RIP RAP/CONCRETE MAT AND ARMOUR STONE AS
POSSIBLE PRIOR TO THE INSTALLATION OF THE HEADWALL. THE CONTRACTOR SHOULD ANTICIPATE TEMPORARILY
SUPPORTING THE OUTFALL PIPE IF REQUIRED.
4. THE CONTRACTOR SHOULD ALSO ANTICIPATE FLOWS IN THE OUTLET PIPING THAT CAN NOT BE HELD BACK DUE TO
STORM SEWERS THAT MAY TIE INTO THE PIPING BETWEEN THE POLLUTION CONTROL PLANT UV CHANNEL AND THE
EXISTING HEADWALL STRUCTURE. AN ADDITIONAL PLUG IN THE 900mm OUTLET PIPE MAY BE REQUIRED.
5. THE TYPICAL LEVEL OF THE RIVER IS ABOVE THE INVERT OF THE OUTLET PIPE AND CAN RANGE FROM 200mmTO FULL
SUBMERGENCE DEPENDING ON THE FLOWS IN THE RIVER. THIS WORK SHOULD BE SCHEDULED DURING LOW FLOW
CONDITIONS .THE CONTRACTOR WILL NEED TO PROVIDE A TEMPORARY PLUG IN THE PIPE TO PREVENT FLOW FROM
TRAVELING THROUGH THE PIPE AND INTO THE EXCAVATION.
6. A PERMIT TO TAKE WATER HAS BEEN APPLIED FOR TO ALLOW FOR TEMPORARY PUMPING AT THE HEADWALL LOCATION
TO CONTEND WITH GROUND WATER ISSUES.
7. GIVEN THAT THE NEW LOCATION OF THE HEADWALL IS SET BACK FROM THE EXISTING RIVERBANK CONSIDERATION
SHOULD BE GIVEN TO LEAVING THE EXISTING BANK IN PLACE WHILE INSTALLING THE HEADWALL. ONCE THE HEADWALL IS
IN PLACE THE EXISTING EMBANKMENT COULD THEN BE REMOVED WITHIN THE NEW CHANNEL, AND FINAL CHANNEL
RESTORATION/CONSTRUCTION COMPLETED AT THAT TIME.
ADELAIDE POLLUTION CONTROL PLANT
OUTFALL STRUTURE REPLACEMENT
ES 5165-12
PLANT OUTFALL
DETAILS & SECTIONS