+ All Categories
Home > Documents > Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated...

Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated...

Date post: 07-Oct-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
53
Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. Kennedy/Jenks Consultants Calvin Huey, P.E. San Francisco Public Utilities Commission Sam Young, P.E. San Francisco Public Utilities Commission October 2, 2013
Transcript
Page 1: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Design and Construction of an

11 MG Treated Water Reservoir

under Challenging Seismic

Conditions

Deborah C. Cohen, P.E. – Kennedy/Jenks ConsultantsCalvin Huey, P.E. – San Francisco Public Utilities CommissionSam Young, P.E. – San Francisco Public Utilities Commission

October 2, 2013

Page 2: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Presentation Outline

Project Overview

Harry Tracy Water Treatment Plant (HTWTP) Long Term Improvements Project (LTIP)

Design Elements

Seismic design criteria

Soil nail, MSE and soldier pile walls

11 MG Treated Water Reservoir

Construction

Construction sequencing

Lessons learned during construction

Page 3: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

OVERVIEW OF HTWTP

PROJECT

Page 4: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

SFPUC Hetch Hetchy Water System

Page 5: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

HTWTP Facts

Built in 1972 and expanded in 1988 / 1992

Direct filtration plant

Rated capacity: 140 MGD

Sustainable capacity: 90 MGD

Average Flow: 20 - 40 MGD

Plant challenges

San Andreas Fault

Raw water quality

Site limitations

Page 6: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Project Objectives

Delivery Reliability

LOS Goal300 MGD with any source out of

service

Design Criteria: HTWTP

Reliably treat raw water of typical

water quality at a sustained flow

rate of 140 MGD for 60 days

Seismic Reliability

LOS Goal229 MGD within 24 hours and 300

MGD within 30 days of seismic

event

Design Criteria: HTWTP

Sustain limited damage following

Maximum Credible Earthquake on

San Andreas Fault and deliver 140

MGD within 24 hours after event

Page 7: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Project Overview

Region Peninsula

Project No. CUW 36701

Contract No. WD-2596

Contract Amount $174,197,000

Notice-to-Proceed March 16, 2011

Contract Time November 29, 2014 (1355 CD S.C.)

February 27, 2015 (1445 CD F.C.)

Page 8: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Project Map

Page 9: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

DESIGN ELEMENTS

Page 10: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Seismic Design Criteria

Importance Factor: 1.5 for critical facilities

BSE-2 (Basic Safety Earthquake-2) per ASCE 41

2,475 year return period earthquake

2% occurrence in 50 years

Maximum Credible Earthquake of 7.9

Building Code regulates a return period of 475 years

Therefore higher acceleration (150% higher) required for design calculations

Concern for failure dictates replacement of existing 8 and 6.5 MG reservoirs with new 11 MG reservoir at new location

Page 11: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Earthwork Required to Support New

TWR

Cut and fill areas required to create flat surface for TWR

Soil nail and soldier pile walls

Designed to support cut face uphill of TWR

Mechanically stabilized earth (MSE) wall

Designed to support fill area downhill of TWR

Separates reservoir from main plant access road

Page 12: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Earthwork Required to Support New

TWR, cont.

Page 13: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Soil Nail Retaining Wall

Length: ~700 feet long

Height: 20 to 65 feet tall

Anchored by ~1,000 soil nails

Length of nails: 25 to 70 feet long

Diameter of nails: 1.375”

Required 6 to 8” diameter drilled holes

4” perforated horizontal drain pipes

10’ o.c. horizontal and 5’ o.c. vertical

Reduce pressure of non-drained condition

Page 14: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Design Drawing for Soil Nail Wall

Page 15: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Design Drawing for Soil Nail Wall

Page 16: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Mechanically Stabilized Earth (MSE)

Wall

Two tiers - upper and lower walls

Precast concrete facing panels

5’ by 5’ face area

Architectural detailing

Galvanized steel reinforcing strips

Anchor panels causing soil to behave monolithically

29.5’ long for bottom wall

19’ long for top wall

Spacing between strips determined by manufacturer

Page 17: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Design Drawing for MSE Wall

Page 18: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

TWR - Process Flow

Page 19: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

Page 20: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Piles, Pile Caps, and Foundation

800+ Piles

HP-14 x 117 (14”x14” area; 117 weight per foot)

Depth: 12 to 61 feet

Depth based on the depth of bedrock

Bedrock varied 40’ throughout footprint of TWR

Pile-caps to connect piles to floor slab

Foundation

2’-3” thick slab

Page 21: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Design Drawing of TWR

Page 22: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

TWR Inner Wall

To contain operational storage reservoir (8 MG)

Cast-in-place concrete wall

No prestressed reinforcement

Vertical post-tensioning tendons

Tapered wall

12” at top to 34” at bottom

Thickness at bottom required to withstand:

Hydrostatic pressure (water load 50’ of head)

Hydrodynamic (seismic) pressures

More cost effective to reduce mass of tank

Page 23: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

TWR Outer Wall

To contain chlorine contact raceway (3 MG)

Strand-wound circular prestressed concrete tank

Cast-in-place concrete core

12” thick at top, tapered to 18” at bottom

Vertical post-tensioning tendons

Circular prestressed reinforcement

Design provided schedule of wraps for each layer

4 layers of strands wrapped around the tanks

1.5” thick shotcrete layer between wraps

Page 24: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Design Drawing of TWR

Page 25: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

TWR Wall Connections

Connections to floor slab and to roof slab

Designed as unrestrained conditions

Allows tank to expand and contract when filling or draining the tank

Seismic cable connections

Transfer seismic load of the wall to the foundation

Prevents sliding of the tank off the foundation

Page 26: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Roof and Columns

Roof designed as two-way slab

Rebar resists bending stresses in each directions

Reduces required thickness of concrete in roof

More complicated design than one-way slab, but more cost effective

Columns

88 columns

30” diameter circular columns

Page 27: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

CONSTRUCTION

Page 28: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Construction Sequencing

Completed to date:

Earthwork, including cut and fill areas

Construct soil nail, soldier pile and MSE walls

Installed piles and pile-caps

Placed buried pipelines

Installed leak detection system

Constructed grade beams and foundation slab in

quadrants

Poured inner and outer walls concurrently (in

progress)

Page 29: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

TWR AREA – PRE-CONSTRUCTION

Page 30: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

EXCAVATION AND SOIL NAIL WALL (SEPTEMBER 2011)

Page 31: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

EXCAVATION AND TEST PILES (MARCH 2012)

Page 32: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Soil Nail Wall

Page 33: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Soil Nail Wall

Page 34: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

MSE Wall

Page 35: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Buried Pipelines

BURIED PIPELINE INSTALLATION (JUNE 2012)

Page 36: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Buried Pipelines

96” TW MANIFOLD PIPING SYSTEM

Page 37: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

PILE INSTALLATION (SEPTEMBER 2012)

Page 38: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

CONCRETE MUDSLAB (DECEMBER 2012)

Page 39: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

ENDURAFLEX COATING (JANUARY 2013)

Page 40: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

CLASS II PERMEABLE & LEAK DETECTION SYSTEM (FEBRUARY 2013)

Page 41: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

QUADRANT FORMWORK / REBAR / SEISMIC CABLES (MARCH 2013)

Page 42: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

2/4 QUADRANT CONCRETE POURS (APRIL 2013)

Page 43: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

COMPLETED QUADRANT CONCRETE POURS (MAY 2013)

Page 44: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

OUTER WALL CONCRETE & FORMWORK (JUNE 2013)

Page 45: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

OUTER WALL CONCRETE & FORMWORK (JULY 2013)

Page 46: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

TWR INNER AND OUTER WALLS (AUGUST 2013)

Page 47: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Construction Sequencing, cont.

To be completed:

Construct columns and contactor effluent box

Install roof

Prestress outer wall

Perform leak test

Place coating on inner and outer walls

Perform tracer study

Page 48: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Lessons Learned – Soil Nail Wall

Tall wall with high seismic loading resulted in extremely long soil nails with tight spacing.

Issue:

Potential for conflict between adjacent soil nails and drain lines.

Solution:

Require staking out/surveying of the soil nail alignment above and behind the wall to align drilling equipment.

Page 49: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Lessons Learned – Soil Nail Wall

Page 50: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Lessons Learned - TWR

Contractor developed two full-scale mock-ups of:

Seismic cables between foundation and walls

Reinforcement of outer wall

Purpose

Verify construction will follow design intent

Coordinate reinforcing in the wall and footing with seismic cables and rebar couplers

Page 51: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

MOCK UP OF FOUNDATION REBARS AND SEISMIC CABLES

Page 52: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

11 MG Treated Water Reservoir

MOCK UP OF OUTER WALL

Page 53: Design and Construction of an 11 MG Treated Water ......Design and Construction of an 11 MG Treated Water Reservoir under Challenging Seismic Conditions Deborah C. Cohen, P.E. –Kennedy/Jenks

Questions?

Deborah C. Cohen, P.E. - Kennedy/Jenks Consultants

[email protected]

(415) 243-2528

Calvin Huey, P.E. – SFPUC

[email protected]

(415) 554-3189

Sam Young, P.E. – SFPUC

[email protected]

(415) 551-4651


Recommended