+ All Categories
Home > Documents > Design and Planning of Instrumentation Works

Design and Planning of Instrumentation Works

Date post: 01-Jan-2016
Category:
Upload: min-min-soe
View: 21 times
Download: 0 times
Share this document with a friend
Description:
Design and Planning of Instrumentation Works
Popular Tags:
46
1 Design and Planning of Instrumentation Works AECOM Singapore LIM Chi-Sharn Associate / Principal Engineer (Geotechnical) [email protected] 09 May 2013 Outline 09 May 2013 Page 2 Introduction and Objectives Design of Instrumentation and Monitoring Systems Bored tunnelling Mined tunnelling Deep excavation Planning of Instrumentation and Monitoring Systems Risk Management Information Management Contingency Planning Ensuring Reliability (System Assurance) Challenges
Transcript
Page 1: Design and Planning of Instrumentation Works

1

Design and Planning of Instrumentation Works

AECOM Singapore

LIM Chi-Sharn

Associate / Principal Engineer (Geotechnical)

[email protected]

09 May 2013

Outline

09 May 2013 Page 2

• Introduction and Objectives

•Design of Instrumentation and Monitoring Systems – Bored tunnelling

– Mined tunnelling

– Deep excavation

•Planning of Instrumentation and Monitoring Systems – Risk Management

– Information Management

– Contingency Planning

– Ensuring Reliability (System Assurance)

•Challenges

Page 2: Design and Planning of Instrumentation Works

2

Tunnelling and Excavation causes Ground Movements & Other Changes which are kept Within Acceptable Limits in order to Ensure Safety & Protect Adjacent Structures

09 May 2013 Page 3

What is Instrumentation & Monitoring?

a Surveillance System

Instrumentation is

Monitoring is

at Site

09 May 2013 4

Page 3: Design and Planning of Instrumentation Works

3

Objectives

To Verify Design Assumptions by

Comparing Monitored responses against Predicted Values

To Ensure Safety by Limiting Magnitudes & Restricting Trends of Responses

To Minimize Damage of surrounding Structures & Buried Cables, Pipes etc.

09 May 2013 Page 5

Construction Works as an Engineered System

09 May 2013 Page 6

QUALITY

ability to satisfy requirements

Serviceability

use for purpose and for conditions

Safety

acceptability of risks

Compatibility

acceptability of impacts

Durability

freedom from unanticipated

degradation

• Equipment – reliable

• Processes – clearly defined

• People – clear roles and responsibilities

(Bea, 1994, 2002)

Page 4: Design and Planning of Instrumentation Works

4

Benefits of Instrumentation & Monitoring (from Dunnicliff, 1993)

• Defines initial site conditions such as groundwater, background conditions (temperature, noise, vibration, tides)

• Proof testing (test piles)

• Safety and Risk Management

• Observational approach to design and design verification that is based on data

• Construction control

• Legal protection

• Enhances public relations

09 May 2013 Page 7

What are Monitored?

• Ground Movement – Settlement (& at Depths), Heave (& at Base)

– Lateral Displacement (& along Depths)

• Ground Water – Water Table / Pore Water Pressure

• Structural Forces – Strut/Ground-Anchor Supports, Tunnel Lining

• Structural Deformations – Tilt & Crack Widths of Buildings/Structures

– Utilities; Cables & Pipes

– Profile & Shape of Tunnels

• Vibration and Noise 09 May 2013 Page 8

Page 5: Design and Planning of Instrumentation Works

5

09 May 2013 Page 9

TYPICAL INSTRUMENTATION

Ground Settlement Markers

09 May 2013 Page 10

Page 6: Design and Planning of Instrumentation Works

6

Settlement Plates

09 May 2013 Page 11

Settlement at Depth

(Magnetic Extensometer)

09 May 2013 Page 12

Page 7: Design and Planning of Instrumentation Works

7

Settlement at Depth

(Hydraulic Hook)

09 May 2013 Page 13

Settlement at Depth

(Hook Sensor)

09 May 2013 Page 14

Page 8: Design and Planning of Instrumentation Works

8

Deep Leveling Datum

09 May 2013 Page 15

Water Stand Pipe

09 May 2013 Page 16

Page 9: Design and Planning of Instrumentation Works

9

Water Stand Pipe & Piezometer

09 May 2013 Page 17

09 May 2013 Page 18

Page 10: Design and Planning of Instrumentation Works

10

Vibrating Wire Piezometer

09 May 2013 Page 19

Piezometer

09 May 2013 Page 20

Page 11: Design and Planning of Instrumentation Works

11

09 May 2013 Page 21

Push-in Type Piezometer

Building Settlement Markers

For Concrete Surface

For Asphalt Surface

09 May 2013 Page 22

Page 12: Design and Planning of Instrumentation Works

12

Building Settlement Markers

09 May 2013 Page 23

Tilt Meter

09 May 2013 Page 24

Page 13: Design and Planning of Instrumentation Works

13

EL Beam Sensor

09 May 2013 Page 25

EL Beam Sensor As In-Place Inclinometer & for Settlement Profile

09 May 2013 Page 26

Page 14: Design and Planning of Instrumentation Works

14

Convergence Monitoring

09 May 2013 Page 27

Convergence Monitoring

09 May 2013 Page 28

Page 15: Design and Planning of Instrumentation Works

15

Tape Extensometer

09 May 2013 Page 29

Crack Meter

09 May 2013 Page 30

Page 16: Design and Planning of Instrumentation Works

16

09 May 2013 Page 31

09 May 2013 Page 32

Page 17: Design and Planning of Instrumentation Works

17

09 May 2013 Page 33

Strut Load Measurement

09 May 2013 Page 34

Page 18: Design and Planning of Instrumentation Works

18

09 May 2013 Page 35

09 May 2013 Page 36

Page 19: Design and Planning of Instrumentation Works

19

09 May 2013 Page 37

Brillouin optical time domain reflectometry (BOTDR)

Diagram courtesy of ntt.co.jp/news

Distributed strain sensor – BOTDR Average strain over 1m every 20cm Range ~5-10km Resolution 30με (0.003%) Low cost sensors - optical fibre 5 - 25 minutes per measurement Can link or switch between fibres 09 May 2013 Page 38

Page 20: Design and Planning of Instrumentation Works

20

DESIGN

09 May 2013 Page 39

Design Aspects

• Purpose of instrument – What is to be monitored?

• Location of instrument – Where is it to be installed?

• Review levels – What are the safe limits?

• Frequency and duration – When and how often is it to be monitored?

• Contingencies – What should be done when the limits are exceeded, and who should do it?

09 May 2013 Page 40

Page 21: Design and Planning of Instrumentation Works

21

Design Verification – Tunnelling

• Verification of parameters – Water table

– Volume loss

– Ground relaxation

• Comparing predictions with outcomes – Ground movements

– Groundwater changes

– Convergence / radial displacement

• Monitoring at areas of risk – To manage residual design risk, construction risk

09 May 2013 Page 41

Trough Measurements Help to Identify Types of Ground Movement

09 May 2013 42

Page 22: Design and Planning of Instrumentation Works

22

Settlements at Surface Vs at Depth

09 May 2013 43

Monitoring Arrays (Tunnelling)

09 May 2013 Page 44

Page 23: Design and Planning of Instrumentation Works

23

Monitoring Arrays (Tunnelling)

09 May 2013 Page 45

Monitoring Arrays (Tunnelling)

09 May 2013 Page 46

Page 24: Design and Planning of Instrumentation Works

24

Monitoring Arrays (Tunnelling)

09 May 2013 Page 47

Monitoring Arrays (Tunnelling)

09 May 2013 Page 48

Page 25: Design and Planning of Instrumentation Works

25

Interpreted Monitoring Data

09 May 2013 Page 49

• For Both Tunnels, – Min 1 for each drive

– Min. 1 at each soil type encountered

• For 1st tunnel, – Min one at every 100m if clear space <

– Min one at every 25m if clear space < 3m

Convergence Monitoring (Bored Tunnel)

09 May 2013 Page 50

Page 26: Design and Planning of Instrumentation Works

26

• Every 2m from breakout

• 7m from breakout

• Every 20m thereafter 2

m

4m

6m

7m

20

m 0

m

Convergence Monitoring (Cross Passages using SCL)

09 May 2013 Page 51

• Currently Not Monitored at Close Interval

• To Determine Correct Face Pressure with Reference to Ground Water Pressure for Both Slurry and EPBM

• To limit Ground settlement

• To avoid Ground heave, slurry spouts and foam spews

• To validate the design of tunnel segment

Monitoring Ground Water Level

09 May 2013 52

Page 27: Design and Planning of Instrumentation Works

27

Examples

09 May 2013 Page 53

Examples

09 May 2013 Page 54

Page 28: Design and Planning of Instrumentation Works

28

Examples

09 May 2013 Page 55

Examples

09 May 2013 Page 56

Page 29: Design and Planning of Instrumentation Works

29

Role in Risk Management – Managing residual design risk and construction risk

• Tunnelling

09 May 2013 Page 57

Before tunnelling

under buildings (esp. with mixed ground)

Start of tunnelling

Cavities are Not Always Fully Grouted

09 May 2013 58

Leca, E. & Domieux, L. (1990)

Page 30: Design and Planning of Instrumentation Works

30

59 09 May 2013

Drawback – Risk of Slurry Path

Subsurface Monitoring – Rod extensometers @ Close Intervals?

Monitoring for unplanned stoppages

09 May 2013 Page 60

Page 31: Design and Planning of Instrumentation Works

31

09 May 2013 Page 61

Design Verification – Excavation

• Verification of parameters – Water table

– Soil properties

• Comparing predictions with outcomes – Ground movements

– Groundwater changes

– Retaining wall deflections

– Strut forces

• Monitoring at areas of design risk – To manage residual design risk

09 May 2013 Page 62

Page 32: Design and Planning of Instrumentation Works

32

Monitoring Arrays - Excavations

09 May 2013 Page 63

Monitoring Arrays - Excavations

09 May 2013 Page 64

Page 33: Design and Planning of Instrumentation Works

33

Examples

09 May 2013 Page 65

Examples

09 May 2013 Page 66

Page 34: Design and Planning of Instrumentation Works

34

Examples

09 May 2013 Page 67

Examples

09 May 2013 Page 68

Page 35: Design and Planning of Instrumentation Works

35

Examples

09 May 2013 Page 69

Interpreted Monitoring Data

• Possible causes – Observed soil profile different from design – no F2 at the East Wall

– Marine clay Cu and Eu lower than adopted at design

09 May 2013 Page 70

Back-Analysis of Unpredicted Sway of a Cut-And-Cover Deep Excavation in

Singapore Marine Clay (Lim et. al. 2011. Proc of ICAGE)

Page 36: Design and Planning of Instrumentation Works

36

Role in Risk Management – Managing residual design risk and construction risk

• Excavations

09 May 2013 Page 71

2D (ok) 3D (??)

The Impact of Geometry on Re-Entrant Corner Behaviour in Deep Excavation Retaining Walls: Two Case Studies from Stage 4 of the Circle Line. (Lim C.S. and Jee Y.Y., 2008, Proc. Of ICDE)

Ensuring Safety and Minimizing Impact – Adjacent Structures

• Comparing predictions with outcomes / safety limits – Ground movements

– Groundwater changes

– Building movements and strains

• Comparing outcomes with legal limits / guidelines – Noise

– Vibration

09 May 2013 Page 72

Page 37: Design and Planning of Instrumentation Works

37

Structure Monitoring

09 May 2013 Page 73

09 May 2013 Page 74

Page 38: Design and Planning of Instrumentation Works

38

Structure Monitoring

09 May 2013 Page 75

Structure Monitoring

09 May 2013 Page 76

Page 39: Design and Planning of Instrumentation Works

39

Effects of tunnelling on pile foundations

Base

Load

Shaft

Friction

Volume Loss

Volume Loss

F

F

B

B

W

W = F + B

Tunnel volume loss

causes base load B to

reduce, pile settles

and shaft friction F

increases

(slide from Mair, 2009)

09 May 2013 Page 77

-50

-40

-30

-20

-10

0

settlm

ents

(mm

)

4

-1

-6

-11

-16

-21

dep

thb

elo

wre

f.le

vel(

m)

-30 -20 -10 0 10

-30 -20 -10 0 10

distance from tunnel (m)

piles tunnel

pile

settlement

surface

settlement

Bored tunnelling below full scale pile trials in the Second Heinenoordtunnel site (Kaalberg et al, 2005)

Zone A

Zone C

Zone B

30o

45o

(slide from Mair, 2009)

09 May 2013 Page 78

• Piles in Zone A settle > ground surface

• Piles in Zone B settle ~ ground surface

• Piles in Zone C settle < ground surface

• Field trials : wooden and concrete piles above two 8.3m OD tunnels

• End-bearing piles, shaft friction very low

• Volume losses

– 1st tunnel : 1~2%

– 2nd tunnel : 0.75%

• 0.5D was considered to be safe distance between pile toe and tunnel

Page 40: Design and Planning of Instrumentation Works

40

Structure Monitoring (Real Time)

09 May 2013 Page 79

09 May 2013 Page 80

Structure Monitoring (Real Time)

Page 41: Design and Planning of Instrumentation Works

41

Design Role of the Qualified Person for Geotechnical Aspects of GBWs

09 May 2013 Page 81

(Building Control Regulations)

09 May 2013 Page 82

PLANNING (For the construction phase)

Page 42: Design and Planning of Instrumentation Works

42

Supervision Role of the Qualified Person for Geotechnical Aspects of GBWs

• Tunnels

09 May 2013 Page 83

(8th Schedule, Part II, Building Control Regulations)

Supervision Role of the Qualified Person for Geotechnical Aspects of GBWs

• Deep excavations

09 May 2013 Page 84

(8th Schedule, Part II, Building Control Regulations)

Page 43: Design and Planning of Instrumentation Works

43

Construction Works as an Engineered System

09 May 2013 Page 85

QUALITY

ability to satisfy requirements

Serviceability

use for purpose and for conditions

Safety

acceptability of risks

Compatibility

acceptability of impacts

Durability

freedom from unanticipated

degradation

• Equipment – reliable

• Processes – clearly defined

• People – clear roles and responsibilities

(Bea, 1994, 2002)

Monitoring Works as an Engineered System

09 May 2013 Page 86

QUALITY

ability to satisfy requirements

Serviceability

use for purpose and for conditions

Safety

acceptability of risks

Compatibility

acceptability of impacts

Durability

freedom from unanticipated

degradation

• Equipment – reliable

• Processes – clearly defined

• People – clear roles and responsibilities

(Bea, 1994, 2002)

Page 44: Design and Planning of Instrumentation Works

44

Role in Risk Management

Safety & Design RISKS are Managed

by

Setting Limits on Each Response

&

Comparing Monitored Responses

Against these Set Limits

09 May 2013 Page 87

Land Transportation Excellence Awards 2011

Best Innovation Partner

4 Key plan with instrumentation locations

2 Trend graphically visible

1 X-axis annotated with dates

5 Table readings against Review Levels

3 Activity against trend

09 May 2013 Page 97

FORM

IS

FUNCTION

Interpreting monitoring data – key information required

Page 45: Design and Planning of Instrumentation Works

45

• Sufficient & Correct Instrumentation

• Proper Installation & Establishment of Initial Readings

• Monitoring Schedule Updated Regularly &

Strictly Adhered To

• Readings Taken by Competent Technicians

• Proper Data Deduction & Verification

• Daily Results into Summary Format

09 May 2013 98

Instrumentation & Monitoring Quality Plan (1 of 2)

Instrumentation & Monitoring Quality Plan (2 of 2)

• Daily Trend Watch

• Daily Check on Results Vs Review Levels

• Weekly Reports with Tables, Trend Plots

• Regular Meetings among Key Personnel

• Full Participation of QP(S) & PE

• Increased Monitoring at High Risk Area

• Increased Monitoring at High Activity Area

• Prompt Replacement of Damaged Instruments

• Calibration of Tools as per Schedule

• Manual checks of automated real-time monitoring

09 May 2013 99

Page 46: Design and Planning of Instrumentation Works

46

Challenges of Instrumentation & Monitoring

– Key responses of ground and structures are monitored

– Correct type of instrumentation is used

– Review Levels are set for each instrumentation

– Monitoring frequency matched with site activities

– Prompt processing of monitored data

– Graphical outputs to visualized trends

– Responses are tracked against Review Levels

– Regular review of monitored readings with key personnel

– Continuous training of personnel involved

Timely Interpretation

Voluminous Data

Monitor and Analyze trend Graphical output

Relate to

construction

activities Tracking

against

Predicted Levels

09 May 2013 Page 100

THANK YOU

09 May 2013


Recommended